CN109657366A - A kind of pier top swivel bridges rotating device method for analog construction based on BIM - Google Patents

A kind of pier top swivel bridges rotating device method for analog construction based on BIM Download PDF

Info

Publication number
CN109657366A
CN109657366A CN201811580893.6A CN201811580893A CN109657366A CN 109657366 A CN109657366 A CN 109657366A CN 201811580893 A CN201811580893 A CN 201811580893A CN 109657366 A CN109657366 A CN 109657366A
Authority
CN
China
Prior art keywords
animation
construction
rotating device
file
animation collection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811580893.6A
Other languages
Chinese (zh)
Inventor
公彦良
刘彬
田小路
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority to CN201811580893.6A priority Critical patent/CN109657366A/en
Publication of CN109657366A publication Critical patent/CN109657366A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T13/00Animation
    • G06T13/203D [Three Dimensional] animation

Abstract

The present invention relates to a kind of method for analog construction, specifically a kind of pier top swivel bridges rotating device method for analog construction based on BIM, the following steps are included: establishing race's type file of BIM model component, race's file of bridge pier, rotating device and the segment beam body 0# is established using Revit software;It establishes the item file of BIM model component and builds threedimensional model, established using Revit software using pier top rotary body device installation model as the item file of title;Fabrication and installation three-dimensional simulation animation establishes bridge pier, rotating device, the segment beam body 0# multi-stage simulation construction animation file using Navisworks software;Carry out arrangement and method for construction formulation and training of confiding a technological secret.The present invention can be come out abstract, complicated bridge pier top body rotation rotating device installation process with threedimensional model animation form simulation and carry out project study and exchange of technology, construction personnel is set to intuitively understand construction object, step and requirement, to improve construction accuracy and precision, it avoids mistake from causing to do over again, improves construction efficiency.

Description

A kind of pier top swivel bridges rotating device method for analog construction based on BIM
Technical field
The present invention relates to a kind of method for analog construction, specifically a kind of pier top swivel bridges rotating device construction based on BIM Analogy method.
Background technique
In the science of bridge building across existing railway, highway, it can be reduced using erection by swing construction to existing line operation Influence.Pier top erection by swing is one of Bridge Rotation Construction Technique common methods.Bridge pier top body rotation construction technology is more, required precision Can the installation of flexural pivot even more turn the key that go on smoothly in height, especially rotating device.Traditional way is filled in rotation It sets in flexural pivot installation, most of construction personnel is completed under conditions of two-dimentional drawing, due to flexural pivot material object Structure does not recognize intuitively, is easy to appear deviation to the not vivid understanding of installation process, influences installation quality and construction Progress.
Present invention aim to address the above problems, provide one kind by flexural pivot installation steps, technology in rotating device The key contents such as parameter, process conditions, in such a way that BIM technology carries out three-dimensional visualization expression and construction simulation, for optimization Design parameter and the arrangement and method for construction for formulating science provide intuitive condition, and construction personnel is made to understand work progress, image in advance Understand design idea, grasp construction point, to reach the target for guaranteeing precision, smoothly completing installation.
Summary of the invention
The purpose of the present invention is to provide a kind of pier top swivel bridges rotating device method for analog construction based on BIM, with solution Certainly the problems mentioned above in the background art.
To achieve the above object, the invention provides the following technical scheme:
A kind of pier top swivel bridges rotating device method for analog construction based on BIM, comprising the following steps:
1) race's type file of BIM model component, is established
According to construction drawing, race's file of bridge pier, rotating device and the segment beam body 0# is established using Revit software;
2) item file of BIM model component, is established, and builds threedimensional model
According to construction drawing, established using Revit software using pier top rotary body device installation model as the item file of title;
3), fabrication and installation three-dimensional simulation animation
Bridge pier, rotating device, the segment beam body 0# multi-stage simulation construction animation file are established using Navisworks software;
4) arrangement and method for construction formulation and training of confiding a technological secret, are carried out
Three-dimensional visualization model is relied on to carry out arrangement and method for construction formulation, by the video file of the construction simulation of substep production to pipe Reason and construction personnel carry out training of telling somebody what one's real intentions are, and audio-visual-materials are dealt into every management and constructor by internet, wechat group, QQ groups Member's mobile phone terminal, convenient for checking at any time, guiding construction.
Further embodiment: the race's type file for establishing BIM model component is further comprising the steps of:
1-1), the other same clan, race and same clan's type are determined;
1-2), race's type file is made, race's type file includes pier shaft sectional dimension, the height, chamfer radius of component, ball The parameters such as spherical radius, steel plate thickness, plan radius, the height of hinge and the height of spherical hinge holder, form fashioned iron at width The technical parameter information of size.
Further scheme: race's file include the reinforcing bar same clan not, the bridge pier pier shaft same clan not, the bridge pier pallet same clan Not, the segment the beam body 0# same clan is other and the serial same clan of rotating device is other.
Further scheme: the rotating device series same clan does not include spherical hinge holder, slideway bracket, lower flexural pivot, cunning Block, upper flexural pivot, steel pile casting, connecting plate, pin shaft and bolt.
Further scheme: the item file for establishing BIM model component, and build threedimensional model, further include with Lower step:
2-1), absolute altitude, axis net order are applied in item file, are longitudinally established line midline, left line, right line, are laterally built Vertical pier line, then establishes pier cap bottom absolute altitude, tray bottom absolute altitude, pier top absolute altitude, bottom elevation, back absolute altitude, to form structure Part locating framework;
2-2), race's file of the bridge pier of step 1) production, rotating device, the segment beam body 0# is loaded into item file;
2-3), according to bridge rotating device construction sequencing, using placement member order, by rotating device and beam body 0# Segment is placed on the corresponding absolute altitude of locating framework, on axis, forms whole threedimensional model;
2-4), it is built in item file after completing threedimensional model, inspection model, simulates installation process, pass through tune The mode of whole element type parameter carries out the optimization and adjustment of mount scheme.
Further scheme: the mode that race's file is loaded into includes primary is all loaded into or according to modelling sequence It is loaded into respectively.
Further scheme: the fabrication and installation three-dimensional simulation animation, further comprising the steps of:
3-1), Navisworks Manage software is opened, the item file established in step 2) is loaded into this It in Navisworks Manage, clicks and saves order, file is saved with pier top rotary body device installation model form;
3-2), check installation model in pel positional relationship, using scaling, rotation, hide etc. tools inspection pel and Positional relationship between pel;
3-3), construction process simulation animation is made, is protected in the pier top rotary body device installation model form that step 3-1) is defined It deposits the impact of file midpoint and opens animator tool, click addition scene and define scene title.
Further scheme: the production construction process simulation animation is further comprising the steps of:
3-3-1), animation collection animation is made, according to construction content production series animation collection, chooses whole figures in selection tree Member adds animation collection in the scene of definition and defines entitled first animation collection, it is transparent then to click the first animation collection of change Command icon is spent, the transparency of the first animation collection is adjusted to 100% transparent, with construction simulation original state, then clicks and catches Crucial frame ordering is caught, original state key frame is generated in scale sequence, traveling time tuning drive gear to subsequent time is caught again Key frame is caught, the first animation collection is completed, the first animation collection is made of two key frames;
Straight Ramp bridge pier pel is chosen in selection tree, add animation collection again in same scene and defines entitled the Two animation collection click down arrows and adjust the second animation collection position, and different animation collection sequences is made to meet construction process, click the Then two animation collection, adjustment time tuning drive gear to the second animation collection end are clicked and capture key frame, the second animation collection is generated Then first frame clicks the second animation collection transparency command icon of change, the transparency of the second animation collection is adjusted to 50% thoroughly It is bright, the second animation collection color commands icon of change is then clicked, its designated color, adjustment time pointer to certain position, point are given Capture key frame is hit, the second frame of the animation collection is generated.Then the second animation collection transparency command icon of change is clicked, by second The transparency of animation collection is adjusted to 0% transparent, adjustment time pointer to next position, clicks and captures key frame, and it is dynamic to generate this The third frame of album completes the second animation collection.
3-3-2), it makes viewpoint animation: adding a camera in same scene and define title, camera is used for basis Cartoon making needs, and amplification is reduced or rotates viewpoint, and at the time of with the first animation collection and corresponding the second animation collection end frame Key frame is captured on axis, and the first animation collection and the second animation collection is cooperated to form construction process animation;
3-3-3), it makes section animation: adding a section in same scene and define title, in step 3-3-1) After completing with step 3-3-2), section animation is started from, section animation is used to demonstrate the internal structure of component, adjusts view At front, the left side or above, in viewpoint toolbar selection enable subdivision, enable subdivision toolbar in, select a plane, Alignment front, traveling time pointer to step 3-3-2) viewpoint animation end third frame are clicked and capture third frame, and it is dynamic to generate section The starting keyframe of picture, traveling time pointer to future time are moved forward and backward profile position profile control view, capture first and close Key frame generates the second key frame of section animation, completes section animation.
Compared with prior art, the beneficial effects of the present invention are:
The present invention is based on the pier top swivel bridges rotating device method for analog construction of BIM, can be abstract, complicated bridge pier Top swivel rotating device installation process is come out with threedimensional model animation form simulation carries out project study and exchange of technology, makes Construction personnel intuitively understands construction object, step and requirement and avoids mistake from causing to return to improve construction accuracy and precision Work improves construction efficiency.
Detailed description of the invention
Fig. 1 is that the present invention is based on the flow diagrams of the pier top swivel bridges rotating device method for analog construction of BIM.
Specific embodiment
Technical solution of the present invention is described in more detail With reference to embodiment.
Embodiment 1
In the embodiment of the present invention, a kind of pier top swivel bridges rotating device method for analog construction based on BIM, including following step It is rapid:
1), BIM model component race document creation: according to construction drawing, using Revit software establish bridge pier, rotating device, Race's file of the segment beam body 0# associated components;
Race's file includes the technical parameter information of component, by establishing reference plane or line of reference, and will using alignment command Threedimensional model carries out technical parameter association, and implementation model is information-based and parameterizes.During simulating installation, it can pass through The mode of adjustment member type parameter carries out the optimization and adjustment of mount scheme.
The race's type file for establishing BIM model component is further comprising the steps of:
1-1), the other same clan, race and same clan's type are determined;
1-2), race's type file is made, race's type file includes pier shaft sectional dimension, the height, chamfer radius of component, ball The parameters such as spherical radius, steel plate thickness, plan radius, the height of hinge and the height of spherical hinge holder, form fashioned iron at width The technical parameter information of size.
2) it, BIM model item document creation: according to construction drawing, is established using Revit software with pier top rotary body device peace Die-filling type is the item file of title.
2-1), absolute altitude, axis net order are applied in item file, are longitudinally established line midline, left line, right line, are laterally built Vertical pier line.Then pier cap bottom absolute altitude, tray bottom absolute altitude, pier top absolute altitude, bottom elevation, back absolute altitude are established, to form structure Part locating framework.
2-2), the bridge pier, rotating device, the segment beam body 0# isofamily file of step 1) production are loaded into item file, it is related Race's file once can be all loaded into, and can also be loaded into respectively according to modelling sequence;
2-3), it constructs sequencing according to bridge rotating device, using placement member order, successively by bridge pier same clan type, Spherical hinge holder same clan type, slideway bracket same clan type, lower flexural pivot same clan type, slideway same clan Xing Deng rotating device same clan type, bridge 0 Segment same clan type is placed on the corresponding absolute altitude of locating framework, on axis, forms whole threedimensional model.
3), fabrication and installation flowsheeting video: bridge pier, rotating device, beam body 0# are established using Navisworks software and is saved Section multi-stage simulation construction animation file;
3-1), Navisworks Manage software is opened, is added the item file established in step 2) using additional command It is downloaded in this Navisworks Manage, clicks and save order, save text in the form of pier top rotary body device installation model .nwf Part.
3-2), check installation model in pel positional relationship, using scaling, rotation, hide etc. tools inspection pel and Positional relationship between pel.
3-3), construction process simulation animation is made, in the pier top rotary body device installation model .nwf text that step 3-1) is defined Animator tool is opened in the impact of part midpoint, is clicked addition scene and is defined scene title, for example title may be defined as scene 1- zongtiliuchengjieshao。
It is further comprising the steps of to make construction process simulation animation:
3-3-1), animation collection animation is made: according to construction content production series animation collection.Whole figures are chosen in selection tree Member adds in the scene of definition and animation collection and defines entitled first animation collection, then clicks change animation collection is transparent and drag out a miserable existence Icon is enabled, the transparency of the first animation collection is adjusted to 100% transparent, with construction simulation original state, then clicks to capture and close Key frame ordering, generates original state key frame in scale sequence, and traveling time tuning drive gear to subsequent time captures close again Key frame completes the first animation collection, and the first animation collection is made of two key frames, the duration of two key frames, according to simulation Demonstration needs to determine.
Straight Ramp bridge pier pel is chosen in selection tree, add animation collection again in same scene and defines entitled the Two animation collection click down arrows and adjust animation collection position, so that different animation collection sequences is met construction process, it is dynamic to click second Then album, adjustment time tuning drive gear to the first animation collection end are clicked and capture key frame, the first of the second animation collection is generated Frame, then clicks change animation collection transparency command icon, the transparency of the second animation collection is adjusted to 50% transparent, then point Change animation collection color commands icon is hit, specifies a kind of color (if fixed respectively to pel when modeling in Revit to it The different color of justice can then not have to the color for changing animation collection again), adjustment time pointer to certain position, click catches Key frame is caught, the second frame of the animation collection is generated, change animation collection transparency command icon is then clicked, by the second animation collection Transparency is adjusted to 0% transparent, adjustment time pointer to next position, clicks and captures key frame, generates the 3rd of the animation collection Frame completes the second animation collection.
The step of with production animation collection 1-2zhipo, establishes the animation collection of other pels in remaining construction content respectively.
Step 3-3-2): production viewpoint animation: adding a camera in same scene and define title, such as: phase Machine 1-zongtijieshao.Camera is used for according to cartoon making needs, and amplification is reduced or rotation viewpoint, and with corresponding first Key frame is captured at the time of animation collection and the second animation collection end frame correspond on axis, cooperates the first animation collection and the second animation collection shape At construction process animation, increase the visual effect of construction simulation animation.
Step 3-3-3): production section animation: adding a section in same scene and define title, such as: it cuts open Face 1-zongtijieshao.In step 3-3-1) and step 3-3-2) complete after, start from section animation, section animation For demonstrating the internal structure of component, adjustment view is at front, the left side or above, and selection enables subdivision in viewpoint toolbar, In enabling subdivision toolbar, a plane, alignment front, traveling time pointer to step 3-3-2) viewpoint animation end are selected Frame is clicked and captures key frame, and the starting keyframe of section animation is generated.Traveling time pointer to future time, cut open by back-and-forth motion Face position profile control view captures key frame, generates the 2nd key frame of section animation, completes section animation.Section animation can To need to make according to demonstration comprising several key frames.
Step 4): arrangement and method for construction formulation and training of confiding a technological secret are carried out: three-dimensional visualization model is relied on to carry out arrangement and method for construction It formulates, the video file of the construction simulation of substep production is subjected to training of telling somebody what one's real intentions are to management and construction personnel.
The present invention is based on the pier top swivel bridges rotating device method for analog construction of BIM, can be abstract, complicated bridge pier Top swivel rotating device installation process is come out with threedimensional model animation form simulation carries out project study and exchange of technology, makes Construction personnel intuitively understands construction object, step and requirement and avoids mistake from causing to return to improve construction accuracy and precision Work improves construction efficiency.
Embodiment 2
A kind of pier top swivel bridges rotating device method for analog construction based on BIM, the embodiment of the present invention is the base of embodiment 1 The further restriction carried out on plinth.
Further, it is preferable that race's file include the reinforcing bar same clan not, the bridge pier pier shaft same clan not, the bridge pier pallet same clan not, The segment the beam body 0# same clan is not and the rotating device series same clan is other;The rotating device series same clan does not include spherical hinge holder, slideway Bracket, lower flexural pivot, sliding block, upper flexural pivot, steel pile casting, connecting plate, pin shaft and bolt.
Better embodiment of the invention is explained in detail above, but the present invention is not limited to above-mentioned embodiment party Formula within the knowledge of one of ordinary skill in the art can also be without departing from the purpose of the present invention Various changes can be made.

Claims (8)

1. a kind of pier top swivel bridges rotating device method for analog construction based on BIM, which comprises the following steps:
1) race's type file of BIM model component, is established
According to construction drawing, race's file of bridge pier, rotating device and the segment beam body 0# is established using Revit software;
2) item file of BIM model component, is established, and builds threedimensional model
According to construction drawing, established using Revit software using pier top rotary body device installation model as the item file of title;
3), fabrication and installation three-dimensional simulation animation
Bridge pier, rotating device, the segment beam body 0# multi-stage simulation construction animation file are established using Navisworks software;
4) arrangement and method for construction formulation and training of confiding a technological secret, are carried out
Rely on three-dimensional visualization model carry out arrangement and method for construction formulation, by substep production construction simulation video file to management and Construction personnel carries out training of telling somebody what one's real intentions are, and audio-visual-materials are dealt into every management and construction personnel's hand by internet, wechat group, QQ groups Machine terminal, convenient for checking at any time, guiding construction.
2. a kind of pier top swivel bridges rotating device method for analog construction based on BIM according to claim 1, feature exist In the race's type file for establishing BIM model component is further comprising the steps of:
1-1), the other same clan, race and same clan's type are determined;
1-2), race's type file is made, race's type file includes pier shaft sectional dimension, the height, chamfer radius of component, flexural pivot The parameters such as spherical radius, steel plate thickness, plan radius, height and the height of spherical hinge holder, width, the size for forming fashioned iron Technical parameter information.
3. a kind of pier top swivel bridges rotating device method for analog construction based on BIM according to claim 1, feature exist In, race's file include the reinforcing bar same clan not, the bridge pier pier shaft same clan not, the bridge pier pallet same clan not, the segment the beam body 0# same clan not and The rotating device series same clan is other.
4. a kind of pier top swivel bridges rotating device method for analog construction based on BIM according to claim 3, feature exist In the rotating device series same clan does not include spherical hinge holder, slideway bracket, lower flexural pivot, sliding block, upper flexural pivot, steel pile casting, connection Plate, pin shaft and bolt.
5. a kind of pier top swivel bridges rotating device method for analog construction based on BIM according to claim 1, feature exist In, the item file for establishing BIM model component, and threedimensional model is built, it is further comprising the steps of:
2-1), absolute altitude, axis net order are applied in item file, are longitudinally established line midline, left line, right line, are laterally established pier Number line, then establishes pier cap bottom absolute altitude, tray bottom absolute altitude, pier top absolute altitude, bottom elevation, back absolute altitude, so that it is fixed to form component Position skeleton;
2-2), race's file of the bridge pier of step 1) production, rotating device, the segment beam body 0# is loaded into item file;
2-3), according to bridge rotating device construction sequencing, using placement member order, by rotating device and the segment beam body 0# It is placed on the corresponding absolute altitude of locating framework, on axis, forms whole threedimensional model;
2-4), it is built in item file after completing threedimensional model, inspection model, installation process is simulated, by adjusting structure The mode of part type parameter carries out the optimization and adjustment of mount scheme.
6. a kind of pier top swivel bridges rotating device method for analog construction based on BIM according to claim 5, feature exist In the mode that race's file is loaded into includes primary all loadings or is loaded into respectively according to modelling sequence.
7. a kind of pier top swivel bridges rotating device method for analog construction based on BIM according to claim 1, feature exist In the fabrication and installation three-dimensional simulation animation is further comprising the steps of:
3-1), Navisworks Manage software is opened, the item file established in step 2) is loaded into this Navisworks It in Manage, clicks and saves order, file is saved with pier top rotary body device installation model form;
3-2), the positional relationship for checking pel in installation model, using scaling, rotation, hide tools check pel and pel it Between positional relationship;
3-3), construction process simulation animation is made, saves text in the pier top rotary body device installation model form that step 3-1) is defined Animator tool is opened in the impact of part midpoint, is clicked addition scene and is defined scene title.
8. a kind of pier top swivel bridges rotating device method for analog construction based on BIM according to claim 7, feature exist In the production construction process simulation animation is further comprising the steps of:
3-3-1), animation collection animation is made, according to construction content production series animation collection, chooses whole pels in selection tree, It is added in the scene of definition and animation collection and defines entitled first animation collection, then clicked change the first animation collection is transparent and drag out a miserable existence Icon is enabled, the transparency of the first animation collection is adjusted to 100% transparent, with construction simulation original state, then clicks to capture and close Key frame ordering, generates original state key frame in scale sequence, and traveling time tuning drive gear to subsequent time captures close again Key frame, completes the first animation collection, and the first animation collection is made of two key frames;
Straight Ramp bridge pier pel is chosen in selection tree, add animation collection again in same scene and defines entitled second is dynamic Album clicks down arrows and adjusts the second animation collection position, so that different animation collection sequences is met construction process, it is dynamic to click second Then album, adjustment time tuning drive gear to the second animation collection end are clicked and capture key frame, the first of the second animation collection is generated Frame, then clicks the second animation collection transparency command icon of change, the transparency of the second animation collection is adjusted to 50% transparent, so The second animation collection color commands icon of change is clicked afterwards, gives its designated color, and adjustment time pointer to certain position is clicked and captured Key frame generates the second frame of the animation collection, the second animation collection transparency command icon of change is then clicked, by the second animation collection Transparency be adjusted to 0% transparent, adjustment time pointer to next position, click and capture key frame, generate the animation collection Third frame completes the second animation collection.
3-3-2), it makes viewpoint animation: adding a camera in same scene and define title, camera is used for according to animation Production needs, and amplification is reduced or rotates viewpoint, and at the time of with the first animation collection and corresponding the second animation collection end frame on axis Key frame is captured, the first animation collection and the second animation collection is cooperated to form construction process animation;
3-3-3), it makes section animation: adding a section in same scene and define title, in step 3-3-1) and step Rapid 3-3-2) complete after, start from section animation, section animation is used to demonstrate the internal structure of component, adjusts view at preceding Face, the left side or above, selection enables subdivision in viewpoint toolbar, in enabling subdivision toolbar, selects a plane, is aligned Front, traveling time pointer to step 3-3-2) viewpoint animation end third frame are clicked and capture third frame, and section animation is generated Starting keyframe, traveling time pointer to future time are moved forward and backward profile position profile control view, and it is crucial to capture first Frame generates the second key frame of section animation, completes section animation.
CN201811580893.6A 2018-12-24 2018-12-24 A kind of pier top swivel bridges rotating device method for analog construction based on BIM Pending CN109657366A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811580893.6A CN109657366A (en) 2018-12-24 2018-12-24 A kind of pier top swivel bridges rotating device method for analog construction based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811580893.6A CN109657366A (en) 2018-12-24 2018-12-24 A kind of pier top swivel bridges rotating device method for analog construction based on BIM

Publications (1)

Publication Number Publication Date
CN109657366A true CN109657366A (en) 2019-04-19

Family

ID=66116342

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811580893.6A Pending CN109657366A (en) 2018-12-24 2018-12-24 A kind of pier top swivel bridges rotating device method for analog construction based on BIM

Country Status (1)

Country Link
CN (1) CN109657366A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110674551A (en) * 2019-09-25 2020-01-10 中国建筑第二工程局有限公司 Simulation system and method for mounting bracket on nuclear power steel lining
CN110700114A (en) * 2019-11-19 2020-01-17 中建交通建设集团有限公司 Lower bearing platform structure of spherical surface flat hinge of large swivel bridge and construction method thereof
CN110714416A (en) * 2019-10-25 2020-01-21 中国一冶集团有限公司 BIM-based temporary consolidation construction structure and method for large cantilever bridge body
CN110820580A (en) * 2019-11-18 2020-02-21 广州揽睿路桥设计有限公司 Bridge rotation construction three-dimensional linear control technology based on BIM technology
CN111021265A (en) * 2020-01-16 2020-04-17 中铁十九局集团第一工程有限公司 BIM technology-based railway large-span continuous beam swivel construction control method
CN111310271A (en) * 2020-03-04 2020-06-19 青岛理工大学 BIM (building information modeling) standardized modeling method for high-speed railway swivel bridge
CN111739129A (en) * 2020-06-09 2020-10-02 广联达科技股份有限公司 Method and device for adding key frames in simulated animation
CN111877184A (en) * 2020-08-05 2020-11-03 中铁二十二局集团有限公司 Railway continuous beam swivel construction method based on BIM
CN112231646A (en) * 2020-12-11 2021-01-15 北京本源云建科技有限公司 Family file protection method based on Revit software
CN113239517A (en) * 2021-04-14 2021-08-10 中亿丰建设集团股份有限公司 S-shaped runner horizontal axial flow pump installation method based on Revit simulation
CN113821855A (en) * 2021-09-17 2021-12-21 中铁六局集团有限公司 BIM-based gantry crane construction simulation method, device and medium
CN115953510A (en) * 2022-12-28 2023-04-11 华东交通大学 Construction simulation animation manufacturing method for iron-involved swivel bridge

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120310602A1 (en) * 2011-06-03 2012-12-06 Walter P. Moore and Associates, Inc. Facilities Management System
CN107862105A (en) * 2017-09-30 2018-03-30 山东聊建集团有限公司 The method confided a technological secret based on BIM to component working procedure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120310602A1 (en) * 2011-06-03 2012-12-06 Walter P. Moore and Associates, Inc. Facilities Management System
CN107862105A (en) * 2017-09-30 2018-03-30 山东聊建集团有限公司 The method confided a technological secret based on BIM to component working procedure

Non-Patent Citations (7)

* Cited by examiner, † Cited by third party
Title
侯佳伟等: "Naviswork2018从入门到精通教程", 中国电力出版社, pages: 66 - 76 *
周强;: "BIM在铁路桥梁施工阶段中的应用", no. 20 *
姚刚;岳文峰;杨阳;张爱莉;: "基于BIM的框架结构三维虚拟建模实验设计", no. 03, pages 91 - 95 *
赵佳云;: "张呼高速铁路连续梁桥墩顶水平转体施工技术", no. 05, pages 73 - 76 *
陈交;: "基于BIM技术的桥梁工程设计的应用", no. 31 *
马杭州: "基于MIDAS-ANSYS的曲线梁桥转体施工虚拟仿真及BIM技术应用研究", pages 69 - 92 *
黄国庆: "基于BIM技术的大跨度钢结构施工管理应用研究", pages 69 - 92 *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110674551A (en) * 2019-09-25 2020-01-10 中国建筑第二工程局有限公司 Simulation system and method for mounting bracket on nuclear power steel lining
CN110714416A (en) * 2019-10-25 2020-01-21 中国一冶集团有限公司 BIM-based temporary consolidation construction structure and method for large cantilever bridge body
CN110820580A (en) * 2019-11-18 2020-02-21 广州揽睿路桥设计有限公司 Bridge rotation construction three-dimensional linear control technology based on BIM technology
CN110820580B (en) * 2019-11-18 2021-04-27 广州揽睿路桥设计有限公司 Bridge rotation construction three-dimensional linear control technology based on BIM technology
CN110700114A (en) * 2019-11-19 2020-01-17 中建交通建设集团有限公司 Lower bearing platform structure of spherical surface flat hinge of large swivel bridge and construction method thereof
CN110700114B (en) * 2019-11-19 2021-02-02 中建交通建设集团有限公司 Construction method of lower bearing platform structure of spherical flat hinge of large swivel bridge
CN111021265A (en) * 2020-01-16 2020-04-17 中铁十九局集团第一工程有限公司 BIM technology-based railway large-span continuous beam swivel construction control method
CN111310271A (en) * 2020-03-04 2020-06-19 青岛理工大学 BIM (building information modeling) standardized modeling method for high-speed railway swivel bridge
CN111739129B (en) * 2020-06-09 2024-04-12 广联达科技股份有限公司 Keyframe adding method and device in simulated animation
CN111739129A (en) * 2020-06-09 2020-10-02 广联达科技股份有限公司 Method and device for adding key frames in simulated animation
CN111877184A (en) * 2020-08-05 2020-11-03 中铁二十二局集团有限公司 Railway continuous beam swivel construction method based on BIM
CN112231646A (en) * 2020-12-11 2021-01-15 北京本源云建科技有限公司 Family file protection method based on Revit software
CN113239517A (en) * 2021-04-14 2021-08-10 中亿丰建设集团股份有限公司 S-shaped runner horizontal axial flow pump installation method based on Revit simulation
CN113821855A (en) * 2021-09-17 2021-12-21 中铁六局集团有限公司 BIM-based gantry crane construction simulation method, device and medium
CN113821855B (en) * 2021-09-17 2024-04-30 中铁六局集团有限公司 Portal crane construction simulation method, device and medium based on BIM
CN115953510A (en) * 2022-12-28 2023-04-11 华东交通大学 Construction simulation animation manufacturing method for iron-involved swivel bridge
CN115953510B (en) * 2022-12-28 2023-08-01 华东交通大学 Construction simulation animation production method of iron-related swivel bridge

Similar Documents

Publication Publication Date Title
CN109657366A (en) A kind of pier top swivel bridges rotating device method for analog construction based on BIM
CN105069827B (en) A method of video transition is handled using threedimensional model
CN107690672A (en) Training data generation method, generating means and its image, semantic dividing method
CN106652049A (en) Full-professional design delivery method for building based on augmented reality technology of mobile terminal
US11170536B2 (en) Systems and methods for home improvement visualization
CN103838437A (en) Touch positioning control method based on projection image
CN108537890A (en) A kind of panoramic pictures mobile terminal methods of exhibiting of fusion BIM modelings and outdoor scene modeling
US9176662B2 (en) Systems and methods for simulating the effects of liquids on a camera lens
CN107862105A (en) The method confided a technological secret based on BIM to component working procedure
CN105719248B (en) A kind of real-time Facial metamorphosis method and its system
EP3438937A1 (en) Method for integrating photographic images and bim data
CN112232761A (en) Infrastructure application system and method
CN110209864B (en) Network platform system for three-dimensional model measurement, ruler changing, labeling and re-modeling
CN107424202A (en) Extensive three-dimensional colony's performance animation concurrent rendering method based on PBRT
CN111113414B (en) Robot three-dimensional space scale prompting method and system based on screen identification
CN109816744B (en) Neural network-based two-dimensional special effect picture generation method and device
CN115953510A (en) Construction simulation animation manufacturing method for iron-involved swivel bridge
CN114299205A (en) Expression animation production method and device, storage medium and computer equipment
Tingdahl et al. Arc3d: A public web service that turns photos into 3d models
Gimeno et al. An occlusion-aware AR authoring tool for assembly and repair tasks
CN107516341A (en) Architectural wind environment method for visualizing based on AR
CN102930582A (en) Animation production method based on game engine
CN100410031C (en) Equipment and mthod of industrial robot possessing ability of recognizing color image
CN114581287B (en) Data processing method and device
CN116595619B (en) BIM-based virtual template design system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination