CN109653103A - 悬臂拼装钢筋笼结构 - Google Patents
悬臂拼装钢筋笼结构 Download PDFInfo
- Publication number
- CN109653103A CN109653103A CN201811394149.7A CN201811394149A CN109653103A CN 109653103 A CN109653103 A CN 109653103A CN 201811394149 A CN201811394149 A CN 201811394149A CN 109653103 A CN109653103 A CN 109653103A
- Authority
- CN
- China
- Prior art keywords
- reinforcing bar
- beam section
- box beam
- beam reinforcing
- block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/10—Cantilevered erection
- E01D21/105—Balanced cantilevered erection
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及一种悬臂拼装钢筋笼结构,属于桥梁工程领域。本发明是将箱梁钢筋在工厂或预制场内绑扎成型,之后用运输车辆或船舶运送至预施工节段正下方,再用桥上起吊装置将箱梁钢筋提升至设计位置。箱梁钢筋就位后,移动模板并调整模板,将箱梁钢筋放置于模板上,纵向钢筋与已经浇筑节段钢筋连接;最后安装预应力管道及内模,浇筑混凝土,张拉预应力钢筋。本发明将钢筋绑扎的大部分工作转化为地面工作,减少了高空作业,提高了施工安全;有利于常规机械的使用,提高了机械化程度;提高了工作环境的舒适性;减小了天气对工期的影响;减少了防护成本;缩短了施工工期;同时采用预制场预制箱梁钢筋的方式提高了质量,方便了验收。
Description
技术领域
本发明涉及一种悬臂拼装钢筋笼结构,属于桥梁工程领域。
背景技术
连续刚构桥及连续梁桥是大跨径桥梁建设中常用的一种结构体系,其主要的施工方法为悬臂浇筑法。悬臂浇筑法指的是在桥墩两侧设置工作平台,平衡地逐段向跨中悬臂浇筑水泥混凝土梁体,并逐段施加预应力的施工方法。悬臂浇筑法主要设备是一对能行走的挂篮,挂篮在已经张拉锚固并与墩身连成整体的梁段上移动,绑扎钢筋、立模、浇筑混凝土、施预应力都在其上进行。完成本段施工后,挂篮对称向前各移动一节段,进行下一对梁段施工,循序前行,直至悬臂梁段浇筑完成。
常规的悬臂浇筑施工工艺为:桥墩施工完成后,在墩顶侧面设置扇形托架,在墩顶及托架上架立模板、绑扎钢筋及浇筑0#块梁段;在0#块梁段顶部拼装挂篮;在挂篮上安装1#块梁段模板;绑扎1#块梁段钢筋;安装预应力管道;浇筑1#块梁段混凝土;养护混凝土;张拉1#块梁段预应力钢筋;挂篮前移;同样方法施工后续梁段。
常规的悬臂浇筑施工工艺中钢筋绑扎占用的工期较长,操作工人多,操作空间狭窄,且属高空作业,危险性较高。
发明内容
本发明所要解决的技术问题是:提供一种悬臂拼装钢筋笼结构,可以缩短施工工期,提高施工安全。
为解决上述技术问题本发明所采用的技术方案是:悬臂拼装钢筋笼结构,包括如下步骤:
一、常规工艺施工桥墩及0#块梁段;
二、在0#块梁段顶部拼装挂篮及提升装置纵梁;
三、在工厂或预制场利用长线法或者短线法绑扎箱梁钢筋;
四、利用运输工具将1#块梁段的箱梁钢筋运送至1#块梁段正下方;
五、利用提升装置将箱梁钢筋安放就位;
六、纵向移动挂篮至1#块梁段处;移动模板并调整模板,将箱梁钢筋放置于模板上;
七、将1#块梁段的箱梁钢筋与0#块梁段的相应纵向钢筋连接;
八、安装预应力管道及内模;
九、浇筑混凝土并养护;
十、张拉预应力钢筋;
十一、前移提升装置纵梁,提升2#块梁段的箱梁钢筋;
十二、重复上述步骤,直至全桥合拢。
本发明的有益效果是:将钢筋绑扎的大部分工作转化为地面工作,减少了高空作业,提高了施工安全;有利于常规机械的使用,提高了机械化程度;提高了工作环境的舒适性;减小了天气对工期的影响;减少了防护成本;缩短了施工工期;同时采用预制场预制箱梁钢筋的方式提高了质量,方便了验收。
附图说明
图1是本发明的施工示意图;
图2是图1的A-A视图;
图中标记:1-桥墩中心线、2-挂篮、3-挂篮轨道、4-提升装置纵梁、5-卷扬机、6-提升钢丝绳、7-箱梁钢筋、8-底模板、9-前下横梁、10-后下横梁、11-外模、12-内模、13-已张拉箱梁节段、14-相邻已张拉箱梁节段、15-箱梁、16-枕木。
具体实施方式
下面结合附图及实施例对本发明作进一步说明。
如图1和图2所示,本发明包括如下步骤:
一、常规工艺施工桥墩及0#块梁段:桥墩施工完成后,在墩顶侧面设置扇形托架,在墩顶及托架上架立模板、绑扎钢筋及浇筑0#块梁段;
二、在0#块梁段顶部拼装挂篮及提升装置纵梁;
三、在工厂或预制场利用长线法或者短线法绑扎箱梁钢筋;
四、利用运输工具将1#块梁段的箱梁钢筋运送至1#块梁段正下方;运输工具通常采用车辆或船舶的方式;
五、利用提升装置将箱梁钢筋安放就位;提升装置可采用卷扬机;
六、纵向移动挂篮至1#块梁段处;移动模板并调整模板,将箱梁钢筋放置于模板上;
七、将1#块梁段的箱梁钢筋与0#块梁段的相应纵向钢筋连接;钢筋绑扎牢固,应保证钢筋在浇筑过程中不发生移位,从而保证纵向钢筋连接顺利。
八、安装预应力管道及内模;
九、浇筑混凝土并养护;
十、张拉预应力钢筋;
十一、前移提升装置纵梁,提升2#块梁段的箱梁钢筋;
十二、重复上述步骤,直至全桥合拢。
Claims (1)
1.悬臂拼装钢筋笼结构,其特征在于,包括如下步骤:
一、常规工艺施工桥墩及0#块梁段;
二、在0#块梁段顶部拼装挂篮及提升装置纵梁;
三、在工厂或预制场利用长线法或者短线法绑扎箱梁钢筋;
四、利用运输工具将1#块梁段的箱梁钢筋运送至1#块梁段正下方;
五、利用提升装置将箱梁钢筋安放就位;
六、纵向移动挂篮至1#块梁段处;移动模板并调整模板,将箱梁钢筋放置于模板上;
七、将1#块梁段的箱梁钢筋与0#块梁段的相应纵向钢筋连接;
八、安装预应力管道及内模;
九、浇筑混凝土并养护;
十、张拉预应力钢筋;
十一、前移提升装置纵梁,提升2#块梁段的箱梁钢筋;
十二、重复上述步骤,直至全桥合拢。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811394149.7A CN109653103A (zh) | 2018-11-21 | 2018-11-21 | 悬臂拼装钢筋笼结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811394149.7A CN109653103A (zh) | 2018-11-21 | 2018-11-21 | 悬臂拼装钢筋笼结构 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109653103A true CN109653103A (zh) | 2019-04-19 |
Family
ID=66112298
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811394149.7A Pending CN109653103A (zh) | 2018-11-21 | 2018-11-21 | 悬臂拼装钢筋笼结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109653103A (zh) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102174796A (zh) * | 2011-04-06 | 2011-09-07 | 湖南中铁五新钢模有限责任公司 | 一种主桁下置式悬浇施工挂篮 |
CN102199916A (zh) * | 2011-04-12 | 2011-09-28 | 中铁三局集团有限公司 | 用于桥梁悬臂浇筑施工的挂篮及施工方法 |
CN102747677A (zh) * | 2012-07-27 | 2012-10-24 | 中铁三局集团有限公司 | 一种桥梁及其施工方法 |
CN107905124A (zh) * | 2017-11-30 | 2018-04-13 | 中铁二十局集团有限公司 | 一种对称式刚构连续梁施工工艺 |
-
2018
- 2018-11-21 CN CN201811394149.7A patent/CN109653103A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102174796A (zh) * | 2011-04-06 | 2011-09-07 | 湖南中铁五新钢模有限责任公司 | 一种主桁下置式悬浇施工挂篮 |
CN102199916A (zh) * | 2011-04-12 | 2011-09-28 | 中铁三局集团有限公司 | 用于桥梁悬臂浇筑施工的挂篮及施工方法 |
CN102747677A (zh) * | 2012-07-27 | 2012-10-24 | 中铁三局集团有限公司 | 一种桥梁及其施工方法 |
CN107905124A (zh) * | 2017-11-30 | 2018-04-13 | 中铁二十局集团有限公司 | 一种对称式刚构连续梁施工工艺 |
Non-Patent Citations (2)
Title |
---|
建筑施工手册编写组: "《建筑施工手册》", 31 January 1999, 中国建筑工业出版社 * |
龙振华等: "《施工技术》", 28 February 2015, 华中科技大学出版社 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106758737B (zh) | 横向预应力全宽钢筋混凝土桥面板钢板组合梁的桥位安装施工方法 | |
CN101476291B (zh) | 一种节段拼装简支箱梁移动膺架施工方法 | |
CN102146658B (zh) | 局部不组合的悬索桥钢-混凝土组合桥面系及其施工方法 | |
CN101424073A (zh) | 整孔预制的钢-混凝土组合连续箱梁的桥面板与钢梁的二次结合方法 | |
CN101748682A (zh) | 采用波形钢腹板的钢-混凝土叠合板组合梁及其施工方法 | |
CN104929034A (zh) | 一种模块化钢-混快速施工小箱梁桥及其施工方法 | |
CN101781878B (zh) | 独塔无背索斜拉桥主塔整体提升模板及其提升施工方法 | |
CN206512581U (zh) | 横向预应力全宽钢筋混凝土桥面板钢板组合梁 | |
CN105804395B (zh) | 基于整体式定型模板的楼梯一次连续浇筑成型施工方法 | |
CN107584650A (zh) | 采用自行式流水作业的桥梁预制装置及其方法 | |
CN106120855B (zh) | 一种地铁明挖车站拱形无柱结构及其施工工法 | |
CN103470040A (zh) | 一种叠合楼板与梁的拼接方法 | |
CN201172797Y (zh) | 便捷式移动模架造桥机 | |
CN110700105B (zh) | 高墩墩柱与系梁同步施工方法及所用模板 | |
CN209144661U (zh) | 用于桥梁施工的模架 | |
CN109267491B (zh) | 一种移动模架及其施工方法 | |
CN111254836A (zh) | 山区大跨径钢混组合梁现场拼装及架桥机架设施工方法 | |
CN107806019A (zh) | 大跨度悬索桥门型索塔施工方法 | |
CN113370384A (zh) | 固定液压模板移动台车工装及t梁预制施工工艺 | |
CN108396630A (zh) | 带湿接缝横桥向连接的预制混凝土大箱梁结构 | |
CN209227836U (zh) | 装配式混凝土结构墙-柱全钢键连接结构 | |
CN107386246A (zh) | 一种船闸闸室墙移动模架施工方法 | |
CN209114299U (zh) | 一种单箱多室箱梁桥 | |
CN109653103A (zh) | 悬臂拼装钢筋笼结构 | |
CN110055905A (zh) | 一种新型装配式圬工拱体的加固方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190419 |