CN109632482A - A kind of building rod piece pullout tests grip device - Google Patents
A kind of building rod piece pullout tests grip device Download PDFInfo
- Publication number
- CN109632482A CN109632482A CN201811576963.0A CN201811576963A CN109632482A CN 109632482 A CN109632482 A CN 109632482A CN 201811576963 A CN201811576963 A CN 201811576963A CN 109632482 A CN109632482 A CN 109632482A
- Authority
- CN
- China
- Prior art keywords
- rod piece
- pedestal
- building rod
- clamping piece
- holding holes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01N—INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
- G01N3/00—Investigating strength properties of solid materials by application of mechanical stress
- G01N3/08—Investigating strength properties of solid materials by application of mechanical stress by applying steady tensile or compressive forces
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D33/00—Testing foundations or foundation structures
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01N—INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
- G01N3/00—Investigating strength properties of solid materials by application of mechanical stress
- G01N3/02—Details
- G01N3/04—Chucks
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01N—INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
- G01N2203/00—Investigating strength properties of solid materials by application of mechanical stress
- G01N2203/0014—Type of force applied
- G01N2203/0016—Tensile or compressive
- G01N2203/0017—Tensile
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01N—INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
- G01N2203/00—Investigating strength properties of solid materials by application of mechanical stress
- G01N2203/02—Details not specific for a particular testing method
- G01N2203/04—Chucks, fixtures, jaws, holders or anvils
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Biochemistry (AREA)
- Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Pathology (AREA)
- Chemical & Material Sciences (AREA)
- Immunology (AREA)
- General Physics & Mathematics (AREA)
- Analytical Chemistry (AREA)
- General Health & Medical Sciences (AREA)
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
Abstract
The present invention relates to architectural engineering detection technique field, more specifically, it relates to a kind of building rod piece pullout tests grip device, its key points of the technical solution are that: a kind of building rod piece pullout tests grip device, including pedestal and clamping piece;Pedestal has the pilot hole through both ends;Clamping piece has the holding holes through both ends, and the aperture of holding holes is adjustable;Clamping piece is for being assemblied in the pilot hole of pedestal, with the building rod piece by holding holes clamping across pilot hole;Wherein, pedestal can opposing gripping members so that the aperture of holding holes is become smaller, to clamp building rod piece to clamping piece applied force when pedestal is mobile to side for opposing gripping members along the centerline direction activity of pilot hole.The technical solution provided according to the present invention, pedestal can drive clamping piece drawing building rod piece together, can be measured by stroke of the measuring device to building rod piece, detect at the construction field (site) to the pullout tests of building rod piece so as to realize.
Description
Technical field
The present invention relates to architectural engineering detection technique field, in particular to a kind of building rod piece pullout tests grip device.
Background technique
It is existing in construction, it is often necessary to the building rod piece of construction site, for example, foundation anchor or prestressing force it is pre-
Tubulation stake carries out pullout tests detection, to guarantee the safe application performance of building rod piece.
However, at the construction field (site), since the building rod piece such as foundation anchor or prestressing force prefabricated tubular pile has installed fixation, nothing
Method is removed from construction site transports the special pullout tests detection of laboratory progress back, therefore need to be fixed to having installed at the construction field (site)
It builds rod piece and carries out pullout tests detection, however the grip device in the prior art without corresponding live pullout tests detection, therefore
Urgent need is designed and a kind of can be gripped at the construction field (site) to carry out pullout tests inspection to having installed fixed building rod piece
The grip device of survey.
Summary of the invention
In view of this, the present invention provides a kind of building rod piece pullout tests grip device, main purpose is can
It grips at the construction field (site) to having installed fixed building rod piece, to carry out pullout tests detection to building rod piece.
In order to achieve the above objectives, present invention generally provides following technical solutions:
The embodiment of the present invention provides a kind of building rod piece pullout tests grip device, including pedestal and clamping piece;
The pedestal has the pilot hole through both ends;
The clamping piece has the holding holes through both ends, and the aperture of the holding holes is adjustable;
The clamping piece is for being assemblied in the pilot hole of the pedestal, to be clamped by the holding holes across the pilot hole
Building rod piece;
Wherein, the pedestal can the relatively described clamping piece along the pilot hole centerline direction activity, the pedestal be used for phase
To the clamping piece applied force when mobile to side to the clamping piece, the aperture of the holding holes is set to become smaller, described in clamping
Build rod piece.
Clamping piece is arranged to facilitate because holding holes run through the both ends of clamping piece by using above-mentioned technical proposal
On fixed building rod piece has been installed;Again because when pedestal opposing gripping members are mobile to side can to clamping piece applied force,
The aperture of holding holes is set to become smaller, clamping piece clamps building rod piece by holding holes, when applied force further to pedestal, due to building
It builds rod piece and fixation has been installed, pedestal can drive clamping piece drawing building rod piece together, can be by measuring device to construction rod
The stroke of part measures, and detects at the construction field (site) to the pullout tests of building rod piece so as to realize.
The present invention is further arranged to: the clamping piece includes more than two split blocks, is all had on each split block
Half bore;
Half bore cooperation on each split block, surrounds the holding holes;
Wherein, at least one split block and the pilot hole are cooperated by inclined surface, and the pedestal is used for the relatively described clamping piece
The aperture of the holding holes is set to become smaller, to clamp the split block applied force by the inclined surface when mobile to side
State building rod piece.
In the above-mentioned technical solutions, cooperated by the inclined surface between pilot hole on split block and pedestal, when pedestal is opposite
When clamping piece is mobile to side, the power towards holding holes centerline direction can be applied to split block, it is preferred that the application
Power and holding holes central axis, keep split block mobile to the centerline direction of holding holes, to make the aperture of holding holes
Become smaller, and then plays the purpose for clamping building rod piece.
The present invention is further arranged to: the pilot hole is taper type hole, and the split block is used for and the pilot hole
The face of cooperation has the outer shape consistent with the taper type hole.
In the above-mentioned technical solutions, taper type hole has the effect of facilitating processing and installation.
The present invention is further arranged to: having screw thread on the hole wall of the holding holes.
In the above-mentioned technical solutions, screw thread primarily serves the effect for increasing the frictional resistance of holding holes hole wall, improves clamping
The clamping force of hole clamping construction rod part.
The present invention is further arranged to: the pedestal has opposite first end and second end, and the pilot hole is from described
First end is through to the second end, to form the first opening in the first end;
To the clamping piece applied force when pedestal is used for mobile to second end side relative to the clamping piece, make the holding holes
Aperture become smaller, to clamp the building rod piece;
Wherein, the clamping piece is used for the first opening of the non-bulging pilot hole when the pedestal is mobile to second end side.
Make by using above-mentioned technical proposal when the first end applied force of external drive mechanism such as jack pair pedestal
When pedestal opposing gripping members are mobile to second end side, since clamping piece will not protrude the first opening of pilot hole, thus clamping piece
Will not the work of external drive mechanism such as jack to the first open side interfere.
The present invention is further arranged to: building rod piece pullout tests grip device, further includes that lid is located at first opening
On push plate, the push plate is equipped with for the via hole that passes through of building rod piece;
The push plate is used to drive the pedestal to move together when being pushed by external force.
By using above-mentioned technical proposal, push plate can be plate, and forced area is relatively large, facilitates external drive motor
Structure such as jack pair its pushed.
The present invention is further arranged to: the push plate is fixedly connected with the pedestal, and the push plate is equipped with handle.
By using above-mentioned technical proposal, convenient working personnel carry or mobile building rod piece pullout tests folder of the invention
Has device.
The present invention is further arranged to: building rod piece pullout tests grip device further includes for driving the pedestal opposite
The clamping piece driving mechanism mobile to the side.
By using above-mentioned technical proposal, there is labor-saving technical effect.
The present invention is further arranged to: when the building rod piece pullout tests grip device includes push plate, the driving
Mechanism includes jack, to make the push plate drive the pedestal with respect to institute by push plate applied force described in the jack pair
It is mobile to the side to state clamping piece.
In the above-mentioned technical solutions, jack is commercially available part, obtains and implement more convenient.
The present invention is further arranged to: the building rod piece is basic anchor pole or prestressing force prefabricated tubular pile.
By above-mentioned technical proposal, a kind of building rod piece pullout tests grip device of the present invention at least has below beneficial to effect
Fruit:
In the technical solution provided by the present invention, because holding holes run through the both ends of clamping piece, clamping piece is arranged to facilitate
On fixed building rod piece has been installed;Again because when pedestal opposing gripping members are mobile to side can to clamping piece applied force,
The aperture of holding holes is set to become smaller, clamping piece clamps building rod piece by holding holes, when applied force further to pedestal, due to building
It builds rod piece and fixation has been installed, pedestal can drive clamping piece drawing building rod piece together, can be by measuring device to construction rod
The stroke of part measures, and detects at the construction field (site) to the pullout tests of building rod piece so as to realize.
The above description is only an overview of the technical scheme of the present invention, in order to better understand the technical means of the present invention,
And can be implemented in accordance with the contents of the specification, the following is a detailed description of the preferred embodiments of the present invention and the accompanying drawings.
Detailed description of the invention
Fig. 1 is a kind of building rod piece pullout tests grip device clamping building rod piece that one embodiment of the invention provides
Structural schematic diagram;
Fig. 2 is the first visual angle of both pedestal and clamping piece of a kind of grip device that one embodiment of the invention provides assembly
Cross section view;
Fig. 3 is the second visual angle of both pedestal and clamping piece of a kind of grip device that one embodiment of the invention provides assembly
Cross section view.
Appended drawing reference: 1, pedestal;2, clamping piece;3, push plate;4, jack;10, pilot hole;11, first end;12, second
End;20, holding holes;21, split block;101, the first opening;102, inclined surface;100, rod piece pullout tests grip device is built;
200, rod piece is built.
Specific embodiment
It is of the invention to reach the technical means and efficacy that predetermined goal of the invention is taken further to illustrate, below in conjunction with
Specific embodiment, structure, feature and its effect applied according to the present invention is described in detail such as in attached drawing and preferred embodiment
Afterwards.In the following description, what different " embodiment " or " embodiment " referred to is not necessarily the same embodiment.In addition, one or more
Special characteristic, structure or feature in a embodiment can be combined by any suitable form.
As depicted in figs. 1 and 2, a kind of building rod piece pullout tests grip device that one embodiment of the present of invention proposes
100 comprising pedestal 1 and clamping piece 2.Pedestal 1 has the pilot hole 10 through both ends.Clamping piece 2 has the folder through both ends
Hold hole 20.The aperture of holding holes 20 is adjustable.Clamping piece 2 is for being assemblied in the pilot hole 10 of pedestal 1, to be pressed from both sides by holding holes 20
Hold the building rod piece 200 across pilot hole 10.Wherein, pedestal 1 can opposing gripping members 2 along pilot hole 10 centerline direction activity
(i.e. arrow a direction in Fig. 2) makes to press from both sides to 2 applied force of clamping piece when pedestal 1 is mobile to side for opposing gripping members 2
The aperture for holding hole 20 becomes smaller, and builds rod piece 200 to clamp.
In the technical solution of above-mentioned offer, since holding holes 20 run through the both ends of clamping piece 2, thus even if building rod piece
200 such as foundation anchors or prestressing force prefabricated tubular pile fix at the construction field (site) by installation, and clamping piece 2 can also be set in construction rod
On part 200, and pass through the clamping building rod piece 200 of holding holes 20.It again because can be with when 1 opposing gripping members 2 of pedestal are mobile to side
To 2 applied force of clamping piece, the aperture of holding holes 20 is made to become smaller, clamping piece 2 clamps building rod piece 200 by holding holes 20.When right
When 1 further applied force of pedestal, since building rod piece 200 has installed fixation, pedestal 1 can drive clamping piece 2, and drawing is built together
Rod piece 200 is built, can be measured by amount of tension of the measuring device to building rod piece 200, it is existing in construction so as to realize
The pullout tests of building rod piece 200 are detected field.
To 2 applied force of clamping piece when in order to realize that aforementioned 1 opposing gripping members 2 of pedestal are mobile to side, make holding holes 20
The purpose that aperture becomes smaller, the present invention also provides the following technical solutions: as shown in Figures 2 and 3, clamping piece 2 above-mentioned can wrap
Include more than two split blocks 21, all have half bore on each split block 21, the half bore can for 1/2 hole, 1/3 hole, 1/4 hole or
1/5 etc..Wherein, the half bore cooperation on each split block 21 can surround holding holes 20 above-mentioned.At least one above-mentioned split block
21 are cooperated with the pilot hole 10 on pedestal 1 by inclined surface 102, which can be plane or curved surface etc..Pedestal 1 is used
The aperture of holding holes 20 is set to become smaller 21 applied force of split block by inclined surface 102 when opposing gripping members 2 are mobile to side,
Rod piece 200 is built to clamp.
In the examples described above, cooperated by the inclined surface 102 between pilot hole 10 on split block 21 and pedestal 1, when pedestal 1
When opposing gripping members 2 are mobile to side, the power towards 20 centerline direction of holding holes can be applied to split block 21, preferably
, the power of the application and the central axis of holding holes 20 keep split block 21 mobile to the centerline direction of holding holes 20, thus
So that the aperture of holding holes 20 is become smaller, and then plays the purpose for clamping building rod piece 200.
At one specifically using in example, as shown in Figures 2 and 3, pilot hole 10 above-mentioned can be taper type hole.Point
The face for cooperating with pilot hole 10 of body block 21 has the outer shape consistent with taper type hole.Wherein, taper type hole has
There is the effect for facilitating processing and installation.
Further, as shown in Figures 2 and 3, it can have screw thread on the hole wall in aforesaid clip hole 20, which mainly rises
To the effect for the frictional resistance for increasing 20 hole wall of holding holes, the clamping force of the clamping building rod piece 200 of holding holes 20 is improved.Certainly,
In order to increase the frictional resistance of 20 hole wall of holding holes, can also on the hole wall of holding holes 20 salient point or concave point etc., and pass through
The mode that screw thread is arranged increases the frictional resistance of 20 hole wall of holding holes, primarily to facilitating processing.
As shown in Fig. 2, pedestal 1 above-mentioned has opposite first end 11 and second end 12.Pilot hole 10 is from first end 11
It is through to second end 12, to form the first opening 101 in first end 11.Pedestal 1 is used for opposing gripping members 2 to 12 sidesway of second end
To 2 applied force of clamping piece when dynamic, the aperture of holding holes 20 is made to become smaller, builds rod piece 200 to clamp.Wherein, clamping piece 2 is used for
First opening 101 of the pedestal 1 to 12 side of second end non-bulging pilot hole 10 when mobile.
By above-mentioned setting, when external drive mechanism such as jack 4 is to 11 applied force of first end of pedestal 1, make seat
When 1 opposing gripping members 2 of body are mobile to 12 side of second end, since clamping piece 2 will not protrude the first opening 101 of pilot hole 10, from
And clamping piece 2 will not interfere the work of the external drive mechanism such as jack 4 of the first 101 sides of opening.
As shown in Figure 1, building rod piece pullout tests grip device 100 of the invention can also include push plate 3.Push plate 3 is covered
It is located in the first opening 101.Push plate 3 is equipped with the via hole passed through for building rod piece 200.When push plate 3 is used to be pushed by external force
Pedestal 1 is driven to move together.In this example, push plate 3 can be plate, and forced area is relatively large, facilitates external drive
Mechanism such as jack 4 pushes it.
Above-mentioned push plate 3 is fixedly connected with pedestal 1.Push plate 3 is equipped with handle, is carried with convenient working personnel or moves this
The building rod piece pullout tests grip device 100 of invention.
Further, as shown in Figure 1, building rod piece pullout tests grip device 100 of the invention can also include being used for
The driving mechanism that 1 opposing gripping members 2 of pedestal are mobile to side is driven, which may include jack 4, by very heavy
4 pairs of 3 applied forces of push plate are pushed up, push plate 3 is made to drive 1 opposing gripping members 2 of pedestal mobile to side, to resist to building rod piece 200
Pull out testing inspection.
What needs to be explained here is that: in the absence of conflict, those skilled in the art can according to the actual situation by
Relevant technical characteristic is combined with each other in above-mentioned each example, to reach corresponding technical effect, particularly for various combined situations
It will not repeat them here.
The above is only a preferred embodiment of the present invention, protection scope of the present invention is not limited merely to above-mentioned implementation
Example, all technical solutions belonged under thinking of the present invention all belong to the scope of protection of the present invention.It should be pointed out that for the art
Those of ordinary skill for, several improvements and modifications without departing from the principles of the present invention, these improvements and modifications
It should be regarded as protection scope of the present invention.
Claims (10)
1. a kind of building rod piece pullout tests grip device, which is characterized in that including pedestal (1) and clamping piece (2);
The pedestal (1) has the pilot hole (10) through both ends;
The clamping piece (2) has the holding holes (20) through both ends, and the aperture of the holding holes (20) is adjustable;
The clamping piece (2) is used to be assemblied in the pilot hole (10) of the pedestal (1), to be clamped by the holding holes (20)
Across the building rod piece (200) of the pilot hole (10);
Wherein, the pedestal (1) can the relatively described clamping piece (2) along the pilot hole (10) centerline direction activity, it is described
To the clamping piece (2) applied force when pedestal (1) is used for mobile to side relative to the clamping piece (2), make the holding holes
(20) aperture becomes smaller, to clamp the building rod piece (200).
2. a kind of building rod piece pullout tests grip device according to claim 1, which is characterized in that
The clamping piece (2) includes more than two split blocks (21), all has half bore on each split block (21);
Half bore cooperation on each split block (21), surrounds the holding holes (20);
Wherein, at least one split block (21) and the pilot hole (10) are cooperated by inclined surface (102), and the pedestal (1) is used
Institute is made to the split block (21) applied force by the inclined surface (102) when moving relative to the clamping piece (2) to side
The aperture for stating holding holes (20) becomes smaller, to clamp the building rod piece (200).
3. a kind of building rod piece pullout tests grip device according to claim 2, which is characterized in that
The pilot hole (10) is taper type hole, and the face for cooperating with the pilot hole (10) of the split block (21) has
The outer shape consistent with the taper type hole.
4. a kind of building rod piece pullout tests grip device according to any one of claim 1 to 3, which is characterized in that
There is screw thread on the hole wall of the holding holes (20).
5. a kind of building rod piece pullout tests grip device according to any one of claim 1 to 3, which is characterized in that
The pedestal (1) has opposite first end (11) and second end (12), and the pilot hole (10) is from the first end
(11) second end (12) are through to, to form the first opening (101) in the first end (11);
The pedestal (1) applies the clamping piece (2) when being used for mobile to second end (12) side relative to the clamping piece (2)
Power makes the aperture of the holding holes (20) become smaller, to clamp the building rod piece (200);
Wherein, the clamping piece (2) is used for the non-bulging pilot hole when the pedestal (1) is mobile to second end (12) side
(10) the first opening (101).
6. a kind of building rod piece pullout tests grip device according to claim 5, which is characterized in that further include that lid is located at
Push plate (3) in first opening (101), the push plate (3) are equipped with the via hole passed through for building rod piece (200);
The push plate (3) is used to drive the pedestal (1) to move together when being pushed by external force.
7. a kind of building rod piece pullout tests grip device according to claim 6, which is characterized in that
The push plate (3) is fixedly connected with the pedestal (1), and the push plate (3) is equipped with handle.
8. existing according to claim 1 to a kind of building rod piece pullout tests grip device, feature described in any one of 3,6,7
In further including the driving mechanism for driving the pedestal (1) mobile relative to the clamping piece (2) side Xiang Suoshu.
9. a kind of building rod piece pullout tests grip device according to claim 8, which is characterized in that
When the building rod piece pullout tests grip device includes push plate (3), the driving mechanism includes jack (4), with
By the jack (4) to the push plate (3) applied force, the push plate (3) is made to drive the relatively described clamping of pedestal (1)
Part (2) side Xiang Suoshu is mobile.
10. special according to claim 1 to a kind of building rod piece pullout tests grip device described in any one of 3,6,7,9
Sign is,
The building rod piece (200) is basic anchor pole or prestressing force prefabricated tubular pile.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811576963.0A CN109632482A (en) | 2018-12-23 | 2018-12-23 | A kind of building rod piece pullout tests grip device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811576963.0A CN109632482A (en) | 2018-12-23 | 2018-12-23 | A kind of building rod piece pullout tests grip device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109632482A true CN109632482A (en) | 2019-04-16 |
Family
ID=66076608
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811576963.0A Pending CN109632482A (en) | 2018-12-23 | 2018-12-23 | A kind of building rod piece pullout tests grip device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109632482A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110553776A (en) * | 2019-09-12 | 2019-12-10 | 苏州热工研究院有限公司 | Clamp of pipeline support hanger force measuring device and pipeline support hanger force measuring device |
CN114575274A (en) * | 2020-11-29 | 2022-06-03 | 中铁十二局集团有限公司 | Roadbed sound barrier foundation embedded bolt anti-pulling structure and test method |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2090529U (en) * | 1991-01-22 | 1991-12-11 | 陕西省建筑科学研究设计院 | Instrument for investigating antiwithdrawing force of mud jacking anchor bolt |
US5515294A (en) * | 1994-06-10 | 1996-05-07 | L & P Property Management Company | Method and apparatus for testing coiled materials |
KR20010074286A (en) * | 2001-05-04 | 2001-08-04 | 박지원 | Fatigue testing machine by using a tubular linear servo motor |
CN2663974Y (en) * | 2003-12-26 | 2004-12-15 | 山西晋城无烟煤矿业集团有限责任公司 | Full-length drawing experimental bench for anchor rod |
CN201355329Y (en) * | 2009-02-20 | 2009-12-02 | 深圳市市政工程总公司 | Pullout test fixture on rebar bonding site |
CN202101909U (en) * | 2011-07-06 | 2012-01-04 | 湖南科技大学 | Anchor rod drawing force lossless dynamic detecting device |
CN202119674U (en) * | 2011-06-29 | 2012-01-18 | 葛洲坝集团试验检测有限公司 | Fan-shaped drawing clamp for anchor rod |
CN103471918A (en) * | 2013-09-18 | 2013-12-25 | 山东科技大学 | Anchor rod engineering stress simulation experimental device |
CN203396646U (en) * | 2013-06-19 | 2014-01-15 | 上海市质量监督检验技术研究院 | Anchor rod pulling tester |
CN204575480U (en) * | 2015-04-29 | 2015-08-19 | 济南大学 | A kind of multi-direction movement artificial hip joint frictional wear experimental device |
CN105699191A (en) * | 2016-04-14 | 2016-06-22 | 北京智博联科技股份有限公司 | Mechanical anchor tension meter |
CN105699192A (en) * | 2016-03-14 | 2016-06-22 | 安徽省建筑科学研究设计院 | Pull-out test device of glass fiber rib anti-floating anchor and test method of pull-out test device |
CN207318248U (en) * | 2017-10-30 | 2018-05-04 | 湖北陆诚建设工程质量检测有限公司 | The pulling test strength detection supplementary structure and detection device of a kind of post-install |
CN207456946U (en) * | 2017-09-14 | 2018-06-05 | 深圳百勤建设工程有限公司 | A kind of device for anchor pole pullout tests |
CN207672636U (en) * | 2017-12-29 | 2018-07-31 | 邯郸市绿园建筑工程检测有限公司 | Anti-float anchor rod vertically pulling-resistant experimental rig |
-
2018
- 2018-12-23 CN CN201811576963.0A patent/CN109632482A/en active Pending
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2090529U (en) * | 1991-01-22 | 1991-12-11 | 陕西省建筑科学研究设计院 | Instrument for investigating antiwithdrawing force of mud jacking anchor bolt |
US5515294A (en) * | 1994-06-10 | 1996-05-07 | L & P Property Management Company | Method and apparatus for testing coiled materials |
KR20010074286A (en) * | 2001-05-04 | 2001-08-04 | 박지원 | Fatigue testing machine by using a tubular linear servo motor |
CN2663974Y (en) * | 2003-12-26 | 2004-12-15 | 山西晋城无烟煤矿业集团有限责任公司 | Full-length drawing experimental bench for anchor rod |
CN201355329Y (en) * | 2009-02-20 | 2009-12-02 | 深圳市市政工程总公司 | Pullout test fixture on rebar bonding site |
CN202119674U (en) * | 2011-06-29 | 2012-01-18 | 葛洲坝集团试验检测有限公司 | Fan-shaped drawing clamp for anchor rod |
CN202101909U (en) * | 2011-07-06 | 2012-01-04 | 湖南科技大学 | Anchor rod drawing force lossless dynamic detecting device |
CN203396646U (en) * | 2013-06-19 | 2014-01-15 | 上海市质量监督检验技术研究院 | Anchor rod pulling tester |
CN103471918A (en) * | 2013-09-18 | 2013-12-25 | 山东科技大学 | Anchor rod engineering stress simulation experimental device |
CN204575480U (en) * | 2015-04-29 | 2015-08-19 | 济南大学 | A kind of multi-direction movement artificial hip joint frictional wear experimental device |
CN105699192A (en) * | 2016-03-14 | 2016-06-22 | 安徽省建筑科学研究设计院 | Pull-out test device of glass fiber rib anti-floating anchor and test method of pull-out test device |
CN105699191A (en) * | 2016-04-14 | 2016-06-22 | 北京智博联科技股份有限公司 | Mechanical anchor tension meter |
CN207456946U (en) * | 2017-09-14 | 2018-06-05 | 深圳百勤建设工程有限公司 | A kind of device for anchor pole pullout tests |
CN207318248U (en) * | 2017-10-30 | 2018-05-04 | 湖北陆诚建设工程质量检测有限公司 | The pulling test strength detection supplementary structure and detection device of a kind of post-install |
CN207672636U (en) * | 2017-12-29 | 2018-07-31 | 邯郸市绿园建筑工程检测有限公司 | Anti-float anchor rod vertically pulling-resistant experimental rig |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110553776A (en) * | 2019-09-12 | 2019-12-10 | 苏州热工研究院有限公司 | Clamp of pipeline support hanger force measuring device and pipeline support hanger force measuring device |
CN114575274A (en) * | 2020-11-29 | 2022-06-03 | 中铁十二局集团有限公司 | Roadbed sound barrier foundation embedded bolt anti-pulling structure and test method |
CN114575274B (en) * | 2020-11-29 | 2023-11-24 | 中铁十二局集团有限公司 | Roadbed sound barrier foundation embedded bolt pulling-resistant structure and test method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109632482A (en) | A kind of building rod piece pullout tests grip device | |
EP0177980A2 (en) | Apparatus for stretching, loosening, and fixing a wire member | |
CN202735159U (en) | Detecting clamp for high strength bolt fastener load-guarantee | |
CN104020043A (en) | Tool clamp for testing low-temperature mechanical tensile properties of fiber reinforced composite material | |
CN103175733B (en) | Direct tensile test jag of incompressible material | |
CN103398896A (en) | Horizontal online tension tester | |
US10060459B2 (en) | Removable blind fastener for narrow apertures | |
CN104655486B (en) | Tubular test sample constant-deformation stress corrosion testing clamp | |
CN110142706A (en) | A kind of tubing test fixture | |
CN212287359U (en) | Dedicated clamping device of elevator wire rope inspection | |
CN105798654A (en) | Clamp for columnar work-pieces | |
CN218330941U (en) | Clamp for electromagnetic loading dynamic tensile test | |
US8425157B1 (en) | Clamp for pile driving | |
CN107884284B (en) | Elevator material shear resistance detection equipment | |
US6199828B1 (en) | Linear spreader | |
CN209961618U (en) | Low-temperature embrittlement performance testing machine | |
CN204705545U (en) | Cable checkout equipment fixture | |
CN212181748U (en) | Biaxial synchronous stretching experiment teaching device | |
CN106638724B (en) | Hydraulic jack rising strain hammering test device | |
RU156880U1 (en) | DEVICE FOR TESTING WELDED POINT COMPOUNDS FOR RIP | |
CN212331060U (en) | A snatch mechanism for concrete compression test block | |
CN203919313U (en) | Quick loading and unloading clamp between stationary pipes for a kind of concrete blinding | |
CN214952670U (en) | Simple device for civil engineering structure detection | |
CN210439344U (en) | Anchor rod clamp | |
CN214334308U (en) | Geotechnical sampling detection device for civil engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190416 |
|
RJ01 | Rejection of invention patent application after publication |