CN109629664B - basement construction method based on assembled resin concrete drainage ditch - Google Patents
basement construction method based on assembled resin concrete drainage ditch Download PDFInfo
- Publication number
- CN109629664B CN109629664B CN201811651316.1A CN201811651316A CN109629664B CN 109629664 B CN109629664 B CN 109629664B CN 201811651316 A CN201811651316 A CN 201811651316A CN 109629664 B CN109629664 B CN 109629664B
- Authority
- CN
- China
- Prior art keywords
- drainage ditch
- groove body
- section
- groove
- basement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/0007—Base structures; Cellars
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/08—Restraining of underground water by employing open ditches arranged below the level of the water
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Electromagnetism (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
the invention discloses a basement construction method based on an assembled resin concrete drainage ditch, which comprises the following steps: firstly, excavating a foundation pit; secondly, constructing a valve plate foundation and a bearing structure; thirdly, base layer treatment; fourthly, drainage ditch construction: the drainage ditch is an assembled resin concrete drainage ditch which is processed and formed in advance; fifthly, constructing a concrete surface layer; and step two, after the construction of the bearing structure in the constructed basement is completed, constructing the top plate of the constructed basement. The method has the advantages of simple steps, reasonable design, simple and convenient construction and good use effect, the prefabricated drainage ditch is assembled on the construction site by adopting a plurality of drainage ditch segments which are processed and formed in advance, the construction quality of the prefabricated drainage ditch can be effectively improved, the outer side walls of the left side and the right side of the prefabricated drainage ditch are rectangular waveform side walls, the integrity and the stability of the prefabricated drainage ditch can be effectively improved, the integral construction efficiency of the basement with the drainage ditch can be effectively improved, the site construction is simple and convenient, and the construction period can be effectively shortened.
Description
Technical Field
the invention belongs to the technical field of basement construction, and particularly relates to a basement construction method based on an assembled resin concrete drainage ditch.
Background
the basement is that the height of the floor of a room lower than the ground level of the outdoor exceeds one half of the net height of the room, such as an underground garage, an underground warehouse, an underground movable room and the like. The multi-storey and high-rise buildings need deeper foundations, and in order to utilize the height, a basement is built under the bottom floor of the building, so that the use area is increased, soil backfilling of the center of the building is omitted, and the building is economical. The basement generally comprises roof, bottom plate, side wall, stair, door and window, light production well etc..
drainage gutters are typically provided in the underground chamber. At present, a cast-in-place drainage ditch is mostly adopted in a basement drainage ditch, when the traditional cast-in-place drainage ditch is constructed, a plurality of processes such as formwork erecting and concrete pouring are needed, the labor force usage amount is large, the construction period is long, the construction quality of the cast-in-place drainage ditch cannot be effectively guaranteed, the cast-in-place drainage ditch formed by construction has more defects, and the problems of formwork expansion, slurry leakage and the like easily occur. In addition, because the external corner of the groove and tongue of the drainage ditch is a concrete member, the edge and corner of the groove and tongue are easily damaged under the condition of long-term traffic of vehicles, machinery and the like in the use process, and the service life of the drainage ditch is influenced.
Disclosure of Invention
the invention aims to solve the technical problems in the prior art, and provides a basement construction method based on an assembled resin concrete drainage ditch, which has the advantages of simple steps, reasonable design, simple and convenient construction and good use effect.
In order to solve the technical problems, the invention adopts the technical scheme that: a basement construction method based on an assembly type resin concrete drainage ditch is characterized by comprising the following steps:
Step one, excavation of a foundation pit: excavating a foundation pit of the constructed basement from top to bottom;
the constructed basement is supported on a raft foundation and comprises a top plate and a bearing structure supported between the raft foundation and the top plate, wherein the top plate, the bearing structure and the raft foundation are all of cast-in-place reinforced concrete structures, the raft foundation and the top plate are horizontally arranged, and the top plate is positioned right above the raft foundation; the bearing structures comprise a plurality of vertical bearing structures distributed along the contour line of the raft foundation;
Step two, raft foundation and bearing structure construction: constructing a raft foundation and the bearing structure of the constructed basement respectively;
Step three, basic layer treatment: performing backfill construction on the raft foundation in the step two to obtain a constructed backfill layer;
step four, drainage ditch construction: constructing the drainage ditches in the constructed underground chamber on the backfill layer in the step three according to the number of the drainage ditches arranged in the constructed underground chamber and the arrangement positions of the drainage ditches which are designed in advance; all drainage ditches in the constructed underground chamber have the same structure and the same construction method, and each drainage ditch is an assembled resin concrete drainage ditch;
the prefabricated drainage ditch comprises a prefabricated drainage ditch formed by connecting a plurality of ditch body basic sections arranged from front to back and a plurality of ditch body thickened sections arranged from front to back, wherein the inner bottom surface of the prefabricated drainage ditch and the inner walls of the left side and the right side of the prefabricated drainage ditch are planes; the groove body basic sections and the groove body thickened sections are arranged in a staggered mode, and every two adjacent groove body thickened sections are connected through one groove body basic section; the cross sections of the groove body basic section and the groove body thickened section are both in a concave shape, and the cross section structures and the sizes of the inner grooves of the groove body basic section and the groove body thickened section are the same; the groove body basic section and the groove body thickened section are respectively formed by connecting a groove body bottom plate and a left groove body side plate and a right groove body side plate which are symmetrically arranged above two sides of the groove body bottom plate, the two groove body side plates are arranged in parallel and are both vertically arranged with the groove body bottom plate; the groove body bottom plate is horizontally arranged, and the inner side wall and the outer side wall of the groove body side plate are vertical surfaces; the height of the groove body side plate in the groove body basic section and the groove body thickened section is the same, the plate thickness of the groove body side plate in the groove body basic section is smaller than that of the groove body side plate in the groove body thickened section, and the plate thickness of the groove body bottom plate in the groove body basic section is smaller than that of the groove body bottom plate in the groove body thickened section; the outer side walls of the left side and the right side of the prefabricated drainage ditch are rectangular waveform side walls;
The prefabricated drainage ditch is formed by splicing a plurality of drainage ditch segments arranged from front to back, the drainage ditch segments are resin concrete drainage ditch segments formed by pouring resin concrete in advance, and the drainage ditch segments are arranged on the same straight line; the front adjacent drainage ditch segment and the rear adjacent drainage ditch segment are in socket joint connection; one of the plurality of drain segments that is positioned on a forwardmost side is a front end segment, one of the plurality of drain segments that is positioned on a rearwardmost side is a rear end segment, a front end face of the front end segment and a rear end face of the rear end segment are both vertical surfaces, and drain segments of the prefabricated drain that are positioned between the front end segment and the rear end segment are both socket segments; one end of the socket segment is a bell mouth, the other end of the socket segment is a spigot which can be inserted into the bell mouth, the rear end of the front end segment is the bell mouth or the spigot, and the front end of the rear end segment is the spigot or the bell mouth; each drainage ditch segment is provided with two right angle steel angles, the two right angle steel angles are symmetrically distributed on the upper parts of the left side and the right side of the drainage ditch segment, and the two right angle steel angles are distributed on the same plane and are distributed along the length direction of the prefabricated drainage ditch; one side of the right angle steel is a horizontal side fixed at the upper part of the groove body side plate, the other side of the right angle steel is a vertical side positioned above the outer side of the horizontal side, the inner side wall of the horizontal side is flush with the inner side wall of the groove body side plate, and the outer side wall of the vertical side is flush with the outer side wall of the groove body side plate in the groove body basic section or positioned inside the outer side wall of the groove body side plate in the groove body basic section;
the joint between two adjacent drainage ditch segments in the front and the back is the position of one thickened ditch section, and the thickened ditch sections positioned at the joint between two adjacent drainage ditch segments in the front and the back in the plurality of thickened ditch sections are all connected ditch sections; each groove body connecting section is formed by splicing a socket connecting section with the socket and a socket connecting section with the socket which can be inserted into the socket;
In the third step, the upper surface of the backfill layer is not higher than the top surface of the ditch body side plate;
when any drainage ditch in the constructed underground chamber is constructed, the process is as follows:
Step 401, excavating a foundation trench: according to the pre-designed layout position of the drainage ditch currently constructed, a base groove for installing the drainage ditch currently constructed is dug on the backfill layer in the third step, wherein the base groove is a groove arranged along the length direction of the drainage ditch currently constructed;
Step 402, drain assembly: splicing a plurality of drainage ditch segments of the drainage ditch which is processed and formed in advance into a whole from front to back along the length direction of the drainage ditch which is constructed currently, and finishing the assembly process of the drainage ditch which is constructed currently;
Step five, concrete surface layer construction: after all drainage ditches in the constructed underground chamber are constructed, a concrete surface layer is poured on the backfill layer;
in the fourth step, the top surface of the vertical edge is flush with the upper surface of the concrete surface layer, the concrete surface layer is poured on the outer side of the right-angle steel, and the vertical edge is a side template for pouring the concrete surface layer;
After the construction of the bearing structure in the basement constructed in the second step is completed, constructing a top plate of the basement constructed; the top plate is horizontally arranged and supported on the bearing structure; the top plate is a cast-in-place reinforced concrete plate.
The basement construction method based on the assembled resin concrete drainage ditch is characterized by comprising the following steps of: after the foundation trench is excavated in the step 401, a layer of lime soil cushion layer is paved at the bottom of the inner side of the excavated foundation trench, and the assembled resin concrete drainage ditch is supported on the lime soil cushion layer.
the basement construction method based on the assembled resin concrete drainage ditch is characterized by comprising the following steps of: in the step 401, the cross section of the base groove is in an isosceles trapezoid shape, the width of the base groove is gradually reduced from top to bottom, and the width of the bottom of the base groove is larger than the width of the thickened section of the groove body;
after the drainage ditch is assembled in step 402 and before the concrete surface layer is constructed in step five, backfilling construction needs to be performed on a gap between the currently constructed drainage ditch and the foundation trench in which the drainage ditch is located.
The basement construction method based on the assembled resin concrete drainage ditch is characterized by comprising the following steps of: in the fourth step, the front end and the rear end of the prefabricated drainage ditch are both thickened ditch body sections;
Every the escape canal all is located two between the vertical bearing structure, every the front and back end in escape canal all with one vertical bearing structure's inside wall is hugged closely.
The basement construction method based on the assembled resin concrete drainage ditch is characterized by comprising the following steps of: in the fourth step, outer side connecting steel bars are welded and fixed on the outer side walls of the vertical edges in the right angle steel, and the outer side connecting steel bars are horizontally arranged; the outer connecting steel bars positioned above the left side of the prefabricated drainage ditch are left steel bars, the outer connecting steel bars positioned above the right side of the prefabricated drainage ditch are right steel bars, and the left steel bars and the right steel bars are symmetrically distributed;
the left side reinforcing bar with the quantity of right side reinforcing bar is a plurality of and its equipartition locates on the same horizontal plane, the left side reinforcing bar with the right side reinforcing bar all is fixed in the concrete surface layer.
The basement construction method based on the assembled resin concrete drainage ditch is characterized by comprising the following steps of: in the fourth step, a socket with a concave cross section is formed on the socket, and a plug which is inserted into the socket and has a concave cross section is arranged on the socket; the slots and the plugs are horizontally arranged;
the plug is a horizontal plug inserted into the slot from front to back, the width of the plug is gradually reduced from front to back, the inner side wall of the plug is the inner side wall of the side plate of the groove body, the bottom surface of the inner side of the plug is the upper surface of the bottom plate of the groove body, the outer side walls of the left side and the right side of the plug are inclined surfaces which are gradually inclined inwards from front to back, and the bottom surface of the outer side of the plug is an inclined surface which is gradually inclined downwards from front to back; the width of the front end of the plug is larger than that of the inner wall groove, and the width of the rear end of the plug is smaller than that of the groove body thickened section; the length of the plug is 35 mm-45 mm;
The width of the slot is gradually reduced from front to back, the outer side wall of the slot is the outer side wall of the side plate of the groove body, the outer bottom surface of the slot is the bottom surface of the bottom plate of the groove body, the inner side walls of the left side and the right side of the slot are inclined planes which are gradually inclined inwards from front to back, and the inner bottom surface of the slot is an inclined plane which is gradually inclined upwards from front to back.
The basement construction method based on the assembled resin concrete drainage ditch is characterized by comprising the following steps of: in the fourth step, a socket with a concave cross section is formed on the socket, and a plug which is inserted into the socket and has a concave cross section is arranged on the socket; the slots and the plugs are horizontally arranged;
The joint between two adjacent drainage ditch sections in the front and the back is provided with a water swelling water stop strip, the joint of the two water swelling water stop strips is hermetically connected through sealant, and the water swelling water stop strip is a concave water stop strip;
each plug is positioned at the front side of the slot in which the plug is inserted;
The front end face and the rear end face of the plug are vertical faces, and the front end face and the rear end face of the slot are vertical faces;
The rear end surface of the plug and the rear end surface of the slot are both provided with a water stop strip placing groove for placing a water-swelling water stop strip, and the water stop strip placing groove is a concave groove;
the rear end of the socket section is a spigot, the front end of the socket section is a socket, the rear end of the front end section is a spigot, and the front end of the rear end section is a socket;
When the drainage ditch is assembled in the step 402, according to the arrangement positions of a plurality of drainage ditch segments in the drainage ditch under construction, the drainage ditch segments are spliced one by one from back to front, and the process is as follows:
Step 4021, rear end section installation: horizontally placing the rear end section of the currently constructed drainage ditch on the inner side of the rear end of the base groove, and tightly attaching the rear end of the currently constructed drainage ditch to the vertical bearing structure positioned on the rear side of the currently constructed drainage ditch;
Step 4022, splicing the next drainage ditch segment: fixing a water swelling water stop strip in a water stop strip placement groove at the rear end of the next spliced drainage ditch segment in the currently constructed drainage ditch, horizontally placing the currently spliced drainage ditch segment in the base groove, horizontally pushing the currently spliced drainage ditch segment from front to back, inserting the socket at the rear end of the currently spliced drainage ditch segment into the socket at the front end of the drainage ditch segment at the rear side of the currently spliced drainage ditch segment, and tightly clamping the water swelling water stop strip between the currently spliced drainage ditch segment and the drainage ditch segment at the rear side of the currently spliced drainage ditch segment;
and 4023, repeating the step 4022 one or more times until the splicing process of all drainage ditch segments in the currently constructed drainage ditch is completed, and obtaining the assembled resin concrete drainage ditch.
The basement construction method based on the assembled resin concrete drainage ditch is characterized by comprising the following steps of: sealing grooves for filling the sealant are formed in the rear end faces of the plug and the slot, are concave grooves and are located above the water stop strip placing groove; the sealing grooves on the plug and the slot and the water stop strip placing groove are separated by a concave-shaped check strip;
The sealing groove on the plug is distributed along the inner contour line at the rear end of the plug and is communicated with the inner groove, and the sealing groove on the slot is distributed along the inner contour line at the rear end of the slot and is communicated with the inner groove;
two sealing grooves at the connecting part between two adjacent drainage ditch sections at the front and the back are spliced to form a sealant filling seam;
the joint between two adjacent drainage ditch segments at the front and the back is a splicing seam, a joint sealing structure is arranged on the inner side of the splicing seam, the joint sealing structure is positioned on the inner side of the sealant filling seam, and the joint sealing structure is in a concave shape and is arranged along the length direction of the splicing seam; the joint sealing structure comprises glass fiber gridding cloth paved on the inner wall of the prefabricated drainage ditch and a polyurethane coating formed by a layer of polyurethane coating uniformly coated on the glass fiber gridding cloth;
after the concrete surface layer construction is finished in the step five, sealant caulking construction needs to be carried out on the sealant filling joints between two adjacent drainage ditch sections in the front and back of the fabricated resin concrete drainage ditch; when sealant caulking construction is carried out on the sealant filling joints between the front and rear adjacent drainage ditch segments, the sealant filling joints are uniformly filled with sealant and the sealant is tightly filled;
The adjacent two in front and back between the escape canal segment the sealed glue is filled the seam and is carried out sealed gluey caulking construction back, still need adjacent two in front and back the seam inboard between the escape canal segment is provided with seam seal structure.
The basement construction method based on the assembled resin concrete drainage ditch is characterized by comprising the following steps of: the top plate is a basement top plate;
The basement roof is internally provided with a plurality of concealed pipes and a plurality of junction boxes, the concealed pipes are threading pipes which are pre-embedded in the basement roof, each threading pipe is connected with one junction box through one wire pipe connecting section, the threading pipes are electric wire pipes, the threading pipes are connected with the wire pipe connecting sections connected with the threading pipes through connecting joints, and each threading pipe is coaxially arranged with the wire pipe connecting sections and the connecting joints connected with the threading pipes; the wire pipe connecting sections are wire pipe sections with inner ends inserted into the pipeline holes in the junction boxes and outer ends connected with the threading pipes, each wire pipe connecting section is welded and fixed with the junction box inserted into the wire pipe connecting section into a whole, each wire pipe connecting section and a connecting joint connected with the outer end of the wire pipe connecting section form a wire pipe connecting section with a joint, and each junction box and all the wire pipe connecting sections with joints, into which the inner ends are inserted, are assembled into an assembled wire pipe junction box;
before the basement top plate is constructed, determining the number of assembled type wire pipe junction boxes to be arranged in the basement top plate, the number of connected sections of connected wire pipes on each assembled type wire pipe junction box and the arrangement positions of the connected sections of the connected wire pipes according to the number of pre-designed junction boxes to be buried in the basement top plate, the number of connected wire pipes on each junction box and the arrangement positions of the wire pipes, wherein the number of the assembled type wire pipe junction boxes is the same as the number of the junction boxes; then, according to the determined number of the assembled wire tube junction boxes, the number of the wire tube connecting sections with joints connected on each assembled wire tube junction box and the arrangement positions of the wire tube connecting sections with joints, respectively assembling all the assembled wire tube junction boxes to be arranged in the top plate of the basement in a processing field to obtain all the assembled wire tube junction boxes which are assembled and formed;
When the basement roof is constructed, the method comprises the following steps:
step A1, formwork support: erecting a forming template for constructing the basement top plate;
The forming template comprises a bottom template and a side template, wherein the bottom template is horizontally arranged, and the side template is arranged above the bottom template;
Step A2, binding a reinforcement cage: binding a reinforcement cage arranged in the top plate of the basement to obtain the reinforcement cage formed by binding;
step A3, arranging the assembled wire tube junction box and the threading tube: uniformly distributing all assembled wire tube junction boxes which are assembled in advance and all wire tubes which are required to be distributed in the basement top plate in the forming template in the step A1 according to the number of the pre-designed junction boxes which need to be embedded in the basement top plate and the distribution positions of the junction boxes, the number of the pre-designed wire tubes which need to be embedded in the basement top plate and the distribution positions of the junction boxes connected with the wire tubes, and the distribution positions of the wire tubes which need to be distributed in the basement top plate, and connecting each wire tube with the wire tube connecting section connected with the wire tube connecting section through a connecting joint;
step A4, pouring concrete: and carrying out concrete pouring on the basement top plate to obtain the constructed and molded basement top plate.
the basement construction method based on the assembled resin concrete drainage ditch is characterized by comprising the following steps of: when all the assembled wire tube junction boxes needing to be distributed in the top plate of the basement are assembled in a processing field respectively, the assembling methods of all the assembled wire tube junction boxes are the same;
when any assembled wire tube junction box is assembled, a wire tube is fed into a junction box adjusting mold for assembly;
the threading pipe inlet junction box adjusting die comprises a base plate, a vertical sleeve, a vertical limiting rod, an insertion length limiting part and a wire pipe supporting rod, wherein the base plate is horizontally arranged, the vertical sleeve is fixed on the base plate, the vertical limiting rod is fixed on the base plate and is positioned in the vertical sleeve, the insertion length limiting part is used for limiting the insertion length of a wire pipe connecting section horizontally inserted into the junction box, the wire pipe supporting rod is used for horizontally supporting the wire pipe connecting section and limiting the placement position of the wire pipe connecting section, and the vertical limiting rod is arranged on the central axis of the vertical sleeve; each wire tube connecting section is uniformly distributed on one wire tube supporting rod, and each wire tube connecting section is distributed along the central axis of the distributed wire tube supporting rod; the number of the wire tube supporting rods is the same as that of the wire tube connecting sections which are horizontally inserted into the junction box, the wire tube supporting rods are horizontally arranged, the inner ends of the wire tube supporting rods are fixed to the upper portion of the vertical sleeve, the structures and the sizes of the wire tube supporting rods are the same, and the wire tube supporting rods are located on the same horizontal plane; the wire tube supporting rod is provided with a wire releasing groove for horizontally placing one wire tube connecting section, and the wire releasing groove is opposite to a pipeline hole which is formed in the junction box and used for inserting the wire tube connecting section placed in the wire releasing groove;
the insertion length limiting part is positioned in the vertical sleeve; the insertion length limiting part comprises a limiting sleeve coaxially sleeved on the vertical limiting rod from top to bottom, a horizontal limiting plate fixed on the limiting sleeve and a wire pipe limiting plate arranged on the horizontal limiting plate, and the limiting sleeve is vertically arranged; the horizontal limiting plate is positioned right above the limiting sleeve and is vertically arranged with the limiting sleeve, and the horizontal limiting plate is positioned below the wire laying groove; the spool limiting plate is the vertical limiting plate that lays perpendicularly with horizontal limiting plate, the quantity of spool limiting plate is the same with the quantity of spool branch, every the inboard equipartition of spool branch is equipped with one and carries out spacing spool limiting plate to the inner of the spool linkage segment that places on this spool branch.
Compared with the prior art, the invention has the following advantages:
1. The method has the advantages of simple steps, reasonable design, simple and convenient construction and good use effect.
2. The adopted prefabricated drainage ditch has the advantages of simple structure, reasonable design and lower investment cost.
3. The drainage ditch is prefabricated in a factory, the forming quality can be effectively guaranteed, the concrete quality of the drainage ditch can be effectively guaranteed, the structural compactness is good, and the flatness is high; the construction site only needs to be assembled, a plurality of working procedures such as formwork erecting, pouring, formwork removing and the like are not needed, labor and time are saved, the construction is safe and reliable, the construction period can be effectively shortened, and the construction efficiency is improved. Meanwhile, the discharge amount of building garbage can be effectively reduced, the appearance quality of the concrete surface of the drainage ditch can be effectively improved, and the drainage ditch is of an assembled structure and is high in popularization value.
3. The construction is simple and convenient and excellent in use effect, and after the foundation trench excavation was accomplished, only need with a plurality of escape canal segments assemble one by one in proper order can to adopt the socket joint to connect between two adjacent escape canal segments, can effectively ensure the straightness of escape canal and the tightness of interface between two adjacent escape canal segments. The invention can effectively solve the problems of various working procedures, more quality defects, higher construction cost and low construction efficiency in the traditional cast-in-place drainage ditch construction, and simultaneously adopts the right-angle steel to ensure that the edge edges and corners of the drainage ditch are clear, complete and beautiful, and have high impact resistance, compression resistance and bending strength, thereby greatly improving the engineering technical characteristics, meeting various requirements on the construction process and fundamentally ensuring the construction quality and efficiency. Meanwhile, the angle steel is directly and simply fixed. From the above, the present invention has the following advantages: the drainage ditch is cast by resin concrete, so that the impact resistance, compression resistance and bending strength are high, the thickness is reduced, the weight of the component is light, and the transportation and installation are convenient; second, the process is simple, saves the time limit for a project: the assembled resin concrete drainage ditch is prefabricated in a factory in advance and is directly installed after being transported to the site, so that the time for on-site formwork erecting, concrete pouring, formwork dismantling and the like of the cast-in-place drainage ditch is reduced, the workload is reduced, and the construction period is saved; thirdly, the quality is easy to guarantee, the construction is convenient, the component quality is easy to guarantee, the edge and the edge are clear, complete and attractive, and the component size is almost free of deviation; compared with the quality problems of mold expansion, slurry leakage, corner damage and the like which often occur in a cast-in-place drainage ditch, the quality problems are greatly improved; fourthly, energy conservation and environmental protection are realized, the drainage ditch is manufactured in a factory, and the pouring concrete excess material is easy to recycle; fifthly, the field construction efficiency is high, the construction method changes the traditional drainage ditch construction method, and adopts the construction process of factory prefabrication and field assembly, so that the work efficiency can be effectively improved, the construction period is shortened, and the manufacturing cost is reduced; sixth, construction is easy and simple to handle, has reduced the construction degree of difficulty, has improved work efficiency and quality, and once one time merit is rateed highly, has improved the efficiency of construction, has reduced cost of maintenance, has advantages such as suitability, security, flexibility, high efficiency, economic nature, environmental protection nature, has good economic benefits and social, has good popularization and application prospect.
5. The drainage ditch has wide application range and can be effectively applied to the construction of drainage ditches such as basements, garages and the like of general projects.
6. the construction is simple and convenient and the efficiency of construction is high, construction period is short, can effectively improve the efficiency of construction and the construction quality of taking the ditch basement, adopt a plurality of processing fashioned escape canal segments in advance to assemble prefabricated escape canal at the job site, can effectively improve the construction quality of prefabricated escape canal, the left and right sides lateral wall of prefabricated escape canal is the rectangular waveform lateral wall simultaneously, can effectively improve the wholeness and the steadiness of prefabricated escape canal, and the site operation is simple and convenient, can effectively improve the efficiency of construction, shorten construction period.
7. The adjusting die for the threading pipe into the junction box is simple in structure, reasonable in design and low in investment cost.
8. the threading pipe is arranged in the junction box adjusting die, so that the processing and manufacturing cost is low, the processing and manufacturing are simple and convenient, and the threading pipe can be repeatedly used.
9. The assembly method of the assembled wire tube junction box is simple, reasonable in design, simple and convenient in construction and good in using effect, and the wire tube is pre-assembled in the junction box adjusting die. During actual assembly, the length limiting part is used for limiting the insertion length of the threading pipe entering the junction box through inserting the threading pipe into the junction box adjusting die, meanwhile, the threading pipe is horizontally supported and guided through the pipe supporting rod, the position accuracy of the threading pipe entering the junction box can be effectively guaranteed, the length of the threading pipe entering the junction box can be guaranteed, the welding connection quality of the threading pipe and the junction box can be guaranteed, labor and time are saved, and the adjusting process of the threading pipe entering the junction box can be simply, conveniently and quickly completed. Adopt assembled spool terminal box can effectively ensure the connection quality between wiring magazine and the interior threading pipe that its portion wore to establish, and can guarantee the position accuracy of wiring magazine and the threading pipe that the wiring magazine wore to establish and lay violently flat vertical, simultaneously can effectively reduce or even stop terminal box positional deviation great, threading pipe slope or distortion scheduling problem, can effectively improve the efficiency of construction, and make construction quality effectively guarantee, can effectively improve the construction quality and the efficiency of construction of the electric dark piping of basement roof (be the threading pipe), the construction qualification rate that makes the electric dark piping of basement roof (be the threading pipe) reaches more than 95%. Therefore, the quality of the construction molding assembly type wire tube junction box can be effectively ensured. Therefore, the assembled wire tube junction box limits the insertion length of the wire passing tube entering the junction box through the insertion length limiting part, and simultaneously carries out horizontal supporting and guiding on the wire passing tube through the wire tube supporting rod, so that the position accuracy of the wire passing tube entering the junction box can be effectively ensured, the length of the wire passing tube entering the junction box can be ensured to ensure the welding connection quality of the wire passing tube and the junction box, labor and time are saved, the adjusting process of the wire passing tube entering the junction box can be simply, conveniently and quickly completed, and the assembling process of the assembled wire tube junction box can be simply, conveniently and quickly completed with high quality.
10. the construction method of the wiring box and the threading pipe in the top plate is simple and convenient, the construction is rapid, the using effect is good, labor and time are saved, the construction efficiency is high, the realization is convenient, only the assembled wiring box and the threading pipe which are assembled in advance are needed to be assembled, and when the top plate is constructed on the construction site actually, only the assembled wiring box and the threading pipe which are assembled in advance are needed to be arranged in the forming template, and each threading pipe is connected with the wiring pipe connecting section through the connecting joint, so that the construction efficiency can be greatly improved, the connecting quality of the concealed piping and the wiring cassette can be effectively ensured, and the economic benefit and the social benefit are obvious.
11. The construction is simple and convenient, the work progress is easily controlled and the efficiency of construction is high, construction period is short, construction quality can effectively be guaranteed simultaneously, through improving the structure and the construction process of basement escape canal and the construction process of secret piping and wiring magazine in the basement roof, can improve the efficiency of construction of basement by a wide margin to can effectively improve construction quality, the spreading value is very big.
in conclusion, the method has the advantages of simple steps, reasonable design, simplicity and convenience in construction and good use effect, the prefabricated drainage ditch is assembled on the construction site by adopting the plurality of prefabricated drainage ditch segments, the construction quality of the prefabricated drainage ditch can be effectively improved, the outer side walls of the left side and the right side of the prefabricated drainage ditch are rectangular waveform side walls, the integrity and the stability of the prefabricated drainage ditch can be effectively improved, the integral construction efficiency of the basement with the drainage ditch can be effectively improved, the site construction is simple and convenient, and the construction period can be effectively shortened.
the technical solution of the present invention is further described in detail by the accompanying drawings and embodiments.
Drawings
FIG. 1 is a schematic view of a prefabricated drain according to the present invention.
3 fig. 32 3 is 3 a 3 sectional 3 view 3 taken 3 along 3 line 3 a 3- 3 a 3 of 3 fig. 31 3. 3
Fig. 3 is a sectional view taken along line B-B of fig. 1.
Fig. 4 is a schematic structural diagram of the socket of the present invention.
fig. 5 is a schematic structural view of the socket of the present invention.
Fig. 6 is a schematic view of the construction of the junction between two adjacent drain segments according to the invention.
Figure 7 is a schematic view of the assembly between two adjacent drain segments according to the invention.
FIG. 8 is a schematic view showing a construction state in which the prefabricated drain according to the present invention is placed in the foundation trench.
Fig. 9 is a schematic view showing a construction state after the prefabricated drain according to the present invention is assembled and the construction of the concrete surface layer is completed.
FIG. 10 is a schematic view of the deployment position of the inboard seal of the seam of the present invention.
FIG. 11 is a flow chart of a construction method of the present invention.
fig. 12 is a schematic structural diagram of the present invention.
Fig. 13 is a schematic view of the assembly structure of the present invention.
FIG. 14 is a schematic view of the deployment position of the junction box with vertical sleeves and conduit struts of the present invention.
fig. 15 is a schematic structural view of the assembled wire tube junction box of the present invention.
description of reference numerals:
1-a trench body base section; 2-groove body thickening section; 3-gutter segment;
4-right angle steel; 6-concrete surface course; 7, connecting reinforcing steel bars at the outer side;
8, a slot; 9-a plug; 10-water swelling water stop strip;
11-water stop strip placing groove; 12-sealing glue; 13-a seal groove;
15-connecting steel bars at the bottom; 16-digging a groove; 17-lime soil cushion layer.
18-inside sealing structure of seam; 21-base plate; 22-a vertical sleeve;
23-vertical stop lever; 24-a limit sleeve; 25-a junction box;
26-a threading pipe; 27-horizontal limiting plate; 28-line pipe limiting plate;
29-spool support; 30-connecting a joint; 31-fastening bolts;
32-vertical spacing sleeve; 33-reinforcing plate.
Detailed Description
as shown in fig. 11, the basement construction method based on the fabricated resin concrete drainage ditch comprises the following steps:
step one, excavation of a foundation pit: excavating a foundation pit of the constructed basement from top to bottom;
The constructed basement is supported on a raft foundation and comprises a top plate and a bearing structure supported between the raft foundation and the top plate, wherein the top plate, the bearing structure and the raft foundation are all of cast-in-place reinforced concrete structures, the raft foundation and the top plate are horizontally arranged, and the top plate is positioned right above the raft foundation; the bearing structures comprise a plurality of vertical bearing structures distributed along the contour line of the raft foundation, and are shown in detail in fig. 8 and 9;
step two, raft foundation and bearing structure construction: constructing a raft foundation and the bearing structure of the constructed basement respectively;
when the raft foundation and the bearing structure are constructed, underground chamber foundation and bearing structure construction methods well known to those skilled in the art are adopted;
Step three, basic layer treatment: performing backfill construction on the raft foundation in the second step to obtain a constructed backfill layer, which is detailed in fig. 8 and 9;
Wherein, the backfill construction is a basement backfill construction method known by the technical personnel in the field;
Step four, drainage ditch construction: constructing the drainage ditches in the constructed underground chamber on the backfill layer in the step three according to the number of the drainage ditches arranged in the constructed underground chamber and the arrangement positions of the drainage ditches which are designed in advance; all drainage ditches in the constructed underground chamber have the same structure and the same construction method, and each drainage ditch is an assembled resin concrete drainage ditch;
As shown in fig. 1, 2 and 3, the fabricated resin concrete drainage ditch comprises a prefabricated drainage ditch formed by connecting a plurality of ditch body basic sections 1 arranged from front to back and a plurality of ditch body thickened sections 2 arranged from front to back, wherein the inner bottom surface and the inner walls at the left and right sides of the prefabricated drainage ditch are both flat; the groove body basic sections 1 and the groove body thickened sections 2 are arranged in a staggered mode, and every two adjacent groove body thickened sections 2 are connected through one groove body basic section 1; the cross sections of the groove body basic section 1 and the groove body thickened section 2 are both in a concave shape, and the cross section structures and the sizes of the inner grooves of the groove body basic section and the groove body thickened section are the same; the groove body basic section 1 and the groove body thickened section 2 are respectively formed by connecting a groove body bottom plate and a left groove body side plate and a right groove body side plate which are symmetrically arranged above two sides of the groove body bottom plate, the two groove body side plates are arranged in parallel and are both vertically arranged with the groove body bottom plate; the groove body bottom plate is horizontally arranged, and the inner side wall and the outer side wall of the groove body side plate are vertical surfaces; the height of the groove body side plate in the groove body basic section 1 and the groove body thickened section 2 is the same, the plate thickness of the groove body side plate in the groove body basic section 1 is smaller than that of the groove body side plate in the groove body thickened section 2, and the plate thickness of the groove body bottom plate in the groove body basic section 1 is smaller than that of the groove body bottom plate in the groove body thickened section 2; the outer side walls of the left side and the right side of the prefabricated drainage ditch are rectangular waveform side walls;
with reference to fig. 4, 5, 6 and 7, the prefabricated drain is formed by splicing a plurality of drain segments 3 arranged from front to back, the drain segments 3 are resin concrete drain segments formed by casting resin concrete in advance, and the plurality of drain segments 3 are arranged on the same straight line; the front and the rear adjacent drainage ditch segments 3 are connected in a socket manner; one of the drain segments 3 located at the foremost side of the plurality of drain segments 3 is a front end segment, one of the drain segments 3 located at the rearmost side of the plurality of drain segments 3 is a rear end segment, a front end surface of the front end segment and a rear end surface of the rear end segment are both vertical surfaces, and the drain segments 3 located between the front end segment and the rear end segment in the prefabricated drain are both socket segments; one end of the socket segment is a bell mouth, the other end of the socket segment is a spigot which can be inserted into the bell mouth, the rear end of the front end segment is the bell mouth or the spigot, and the front end of the rear end segment is the spigot or the bell mouth; each drainage ditch section 3 is provided with two right angle steel angles 4, the two right angle steel angles 4 are symmetrically arranged at the upper parts of the left side and the right side of the drainage ditch section 3, and the two right angle steel angles 4 are arranged on the same plane and are all arranged along the length direction of the prefabricated drainage ditch; one side of the right angle steel 4 is a horizontal side fixed on the upper part of the groove body side plate, and the other side of the right angle steel is a vertical side positioned above the outer side of the horizontal side, the inner side wall of the horizontal side is flush with the inner side wall of the groove body side plate, and the outer side wall of the vertical side is flush with the outer side wall of the groove body side plate in the groove body basic section 1 or positioned inside the outer side wall of the groove body side plate in the groove body basic section 1;
The joints between two adjacent drainage ditch segments 3 in the front and the back are all the positions where one groove body thickened section 2 is located, and the groove body thickened sections 2 positioned at the joints between the two adjacent drainage ditch segments 3 in the front and the back in the plurality of groove body thickened sections 2 are all groove body connecting sections; each groove body connecting section is formed by splicing a socket connecting section with the socket and a socket connecting section with the socket which can be inserted into the socket;
in the third step, the upper surface of the backfill layer is not higher than the top surface of the ditch body side plate;
When any drainage ditch in the constructed underground chamber is constructed, the process is as follows:
Step 401, excavating a foundation trench: according to the pre-designed layout position of the drainage ditch currently constructed, a base groove for installing the drainage ditch currently constructed is dug on the backfill layer in the third step, wherein the base groove is a groove arranged along the length direction of the drainage ditch currently constructed;
step 402, drain assembly: splicing a plurality of drainage ditch segments 3 of the drainage ditch which is processed and formed in advance into a whole from front to back along the length direction of the drainage ditch which is constructed currently, and finishing the assembly process of the drainage ditch which is constructed currently;
Step five, concrete surface layer construction: after all drainage ditches in the constructed underground chamber are constructed, a concrete surface layer 6 is poured on the backfill layer;
in the fourth step, the top surface of the vertical edge is flush with the upper surface of the concrete surface layer 6, the concrete surface layer 6 is poured on the outer side of the right-angle steel 4, and the vertical edge is a side template for pouring the concrete surface layer 6;
After the construction of the bearing structure in the basement constructed in the second step is completed, constructing a top plate of the basement constructed; the top plate is horizontally arranged and supported on the bearing structure; the top plate is a cast-in-place reinforced concrete plate.
in this embodiment, the prefabricated escape canal is arranged on the same horizontal plane.
for prefabrication and splicing convenience, in this embodiment, each drainage ditch segment 3 includes N ditch body basic sections 1. Wherein N is a positive integer and N is 1-5. In actual construction, the number of the gutter segments 1 included in each of the drain segments 3 may be adjusted accordingly according to specific needs.
As shown in fig. 2 and 3, a plurality of bottom connecting steel bars 15 are welded to the bottom of the horizontal side of the right angle steel 4 from front to back, and the bottom connecting steel bars 15 are poured into the drainage ditch segments 3. Therefore, the right angle 4 is fixed simply and firmly. And a plurality of the bottom connecting steel bars 15 are arranged from front to back along the length direction of the right angle steel 4, and each bottom connecting steel bar 15 is vertically arranged and is vertically arranged with the groove body side plate. In this embodiment, the bottom connecting steel bar 15 is a V-shaped steel bar. In practical use, the bottom connecting reinforcement 15 may also be a reinforcement of another shape such as a U-shaped reinforcement.
As can be seen from the above, the two adjacent drainage ditch segments 3 are connected in a socket manner, so that the integrity of the prefabricated drainage ditch can be effectively ensured. Simultaneously, can effectively ensure a plurality ofly escape canal section 3's installation elevation is accurate, unanimous, and assembly forming prefabricated escape canal is unobstructed in the same direction as straight, adjacent two around the interface between the escape canal section 3 is tight.
the left and right sides lateral wall of prefabricated escape canal is the rectangular waveform lateral wall, therefore the left and right sides lateral wall of prefabricated escape canal is rectangular waveform, therefore can effectively strengthen prefabricated escape canal and both sides backfill the quality of connection and the joint strength between the layer, ensure the wholeness and the steadiness of prefabricated escape canal can effectively increase the self intensity of prefabricated escape canal. Simultaneously, prefabricated escape canal and the interlock each other of backfill layer can ensure prefabricated escape canal can not remove.
in this embodiment, the right angle steel 4 is equal-edge steel, the width of both sides of the equal-edge steel is 30mm, and the thickness of the right angle steel 4 is 3 mm. During actual construction, the size of the right angle steel 4 can be adjusted correspondingly according to specific requirements.
for further increase the wholeness and the steadiness of prefabricated escape canal are right simultaneously the front and back end of prefabricated escape canal is effectively consolidated, and step four the front end and the rear end of prefabricated escape canal are ditch body thickened section 2, can effectively ensure the integrality of prefabricated escape canal front and back end structure improves escape canal life and result of use.
every prefabricated escape canal all is located two between the vertical bearing structure, every the front and back end in escape canal all with one vertical bearing structure's inside wall is hugged closely.
in this embodiment, the basement under construction is a frame structure or a frame shear wall structure.
The frame structure or frame shear wall structure is a building structure well known to those skilled in the art. The frame structure is formed by connecting beams and columns by reinforcing steel bars to form a structure of a bearing system, namely, a frame formed by the beams and the columns jointly resists horizontal load and vertical load in the using process, and the bearing structure in the frame structure is a bearing frame formed by frame columns and frame beams.
the frame shear wall structure is also called a frame shear structure, a certain number of shear walls are arranged in the frame structure to form a flexible and free use space, the requirements of different building functions are met, meanwhile, enough shear walls are provided, and the shear walls have quite large lateral rigidity (the large lateral rigidity of the shear walls means strong deformation resistance under the action of horizontal load (wind load and horizontal earthquake force)). The frame shear wall structure the bearing structure is the bearing frame and the shear wall.
The vertical bearing structure is the bearing frame or the bearing frame and the shear wall.
In the fourth embodiment, outer connecting steel bars 7 are welded and fixed on the outer side walls of the vertical edges of the right angle steel 4 in the fourth step, and the outer connecting steel bars 7 are horizontally arranged; the outer connecting steel bars 7 positioned above the left side of the prefabricated drainage ditch are left steel bars, the outer connecting steel bars 7 positioned above the right side of the prefabricated drainage ditch are right steel bars, and the left steel bars and the right steel bars are symmetrically distributed;
the left side reinforcing bar with the quantity of right side reinforcing bar is a plurality of and its equipartition locates on the same horizontal plane, the left side reinforcing bar with the right side reinforcing bar all is fixed in the concrete surface course 6. Like this, through outside tie bar 7, can effectively strengthen prefabricated escape canal and week side concrete surface course 6's joint strength and connection quality further ensure the wholeness and the steadiness of prefabricated escape canal.
In this embodiment, the outer connecting steel bars 7 are V-shaped steel bars.
in practical use, the outer connecting reinforcement 7 may be a reinforcement of other shape such as an outer connecting reinforcement.
In this embodiment, it is a plurality of the left side reinforcing bar is evenly laid, and is a plurality of the right side reinforcing bar is evenly laid.
in this embodiment, the distance between two adjacent front and back left side reinforcing bars and the distance between two adjacent front and back right side reinforcing bars are 150 mm-200 mm. During actual construction, the distance between the front and back adjacent two left side reinforcing steel bars and the distance between the front and back adjacent two right side reinforcing steel bars can be correspondingly adjusted according to specific requirements.
In this embodiment, after the excavation of the foundation trench is completed in step 401, a layer of lime soil cushion layer 17 is tiled at the bottom of the inner side of the excavated foundation trench, and the assembled resin concrete drainage ditch is supported on the lime soil cushion layer 17.
In this embodiment, with reference to fig. 8 and 9, in step 401, the cross section of the base groove is an isosceles trapezoid, the width of the base groove is gradually reduced from top to bottom, and the width of the bottom of the base groove is greater than the width of the thickened groove section 2;
after the drainage ditch is assembled in step 402 and before the concrete surface layer is constructed in step five, backfilling construction needs to be performed on a gap between the currently constructed drainage ditch and the foundation trench in which the drainage ditch is located.
in this embodiment, as shown in fig. 4, 5, 6, and 7, in step four, a socket 8 with a concave cross section is formed on the socket, and a plug 9 with a concave cross section is inserted into the socket 8; the slot 8 and the plug 9 are both horizontally arranged.
a slot 8 with a concave cross section is formed on the socket, and a plug 9 which is inserted into the slot 8 and has a concave cross section is arranged on the socket; the slot 8 and the plug 9 are both horizontally arranged.
The front width of the slot 8 is consistent with the front width of the plug 9, the rear width of the slot is consistent with the rear width of the plug 9, and the depth of the slot 8 is consistent with the length of the plug 9.
The plug 9 is a horizontal plug inserted into the slot 8 from front to back, the width of the plug 9 is gradually reduced from front to back, the inner side wall of the plug 9 is the inner side wall of the side plate of the trench body, the bottom surface of the inner side of the plug is the upper surface of the bottom plate of the trench body, the outer side walls of the left side and the right side of the plug 9 are inclined surfaces which are gradually inclined inwards from front to back, and the bottom surface of the outer side of the plug 9 is an inclined surface which is gradually inclined downwards from front to back; the width of the front end of the plug 9 is larger than that of the inner wall groove, and the width of the rear end of the plug 9 is smaller than that of the groove body thickened section 2; the length of the plug 9 is 35 mm-45 mm;
the width of the slot 8 is gradually reduced from front to back, the outer side wall of the slot 8 is the outer side wall of the side plate of the ditch body, the outer bottom surface of the slot 8 is the bottom surface of the bottom plate of the ditch body, the inner side walls of the left side and the right side of the slot 8 are inclined planes which are gradually inclined inwards from front to back, and the inner bottom surface of the slot 8 is an inclined plane which is gradually inclined upwards from front to back.
in this embodiment, the length of plug 9 is 40mm, the length of slot 8 is the same with the length of plug 9, can effectively guarantee two adjacent front and back the joint strength between the escape canal festival section 3 to the length of plug 9 is not long, and processing is simple and convenient, and transport and removal are convenient, two adjacent front and back when escape canal festival section 3 carries out socket joint and connects, connect the counterpoint simple and convenient, and counterpoint effectually. During actual construction, the length of the plug 9 can be adjusted correspondingly according to specific requirements.
In this embodiment, each plug 9 is located in front of the slot 8 into which it is inserted for ease of assembly. When the prefabricated drainage ditch is assembled, the plurality of drainage ditch segments 3 are spliced one by one from back to front according to the layout positions of the plurality of drainage ditch segments 3 in the prefabricated drainage ditch under construction.
in this embodiment, adjacent two around the junction between the escape canal segment 3 all is provided with water inflation sealing rod 10 and the junction of the two carries out sealing connection through sealed glue 12, water inflation sealing rod 10 is character cut in bas-relief shape sealing rod.
In this embodiment, the back end of the socket segment is a socket and the front end thereof is a socket, the back end of the front end segment is a socket, and the front end of the back end segment is a socket
In order to increase the sealing effect, the front end surface and the rear end surface of the plug 9 are both vertical surfaces, and the front end surface and the rear end surface of the slot 8 are both vertical surfaces;
And the rear end surface of the plug 9 and the rear end surface of the slot 8 are both provided with a water stop strip placing groove 11 for placing a water-swelling water stop strip 10, and the water stop strip placing groove 11 is a concave groove.
The rear end face of the plug 9 and the rear end face of the slot 8 are both provided with a sealing groove 13 for filling the sealant, and the sealing groove 13 is a concave groove and is positioned above the water stop strip placing groove 11; the plug 9, the sealing groove 13 on the slot 8 and the water stop strip placing groove 11 are separated by a concave-shaped baffle strip;
seal groove 13 on the plug 9 is laid along the inside contour line of plug 9 rear end and its with inside slot intercommunication, seal groove 13 on the slot 8 is laid along the inside contour line of slot 8 rear end and its with inside slot intercommunication.
in this embodiment, the cross section of the water stop strip placement groove 11 is rectangular, the width of the water stop strip placement groove is 10mm, and the depth of the water stop strip placement groove is 5 mm. The cross section of the sealing groove 13 is square, and the width and the depth of the sealing groove are both 5 mm.
During the actual use, can be according to concrete needs, carry out corresponding adjustment to the cross section structure and the size of sealing strip standing groove 11 and seal groove 13.
In this embodiment, when the drainage ditch is assembled in step 402, according to the layout position of a plurality of drainage ditch segments 3 in the drainage ditch under construction at present, the drainage ditch segments 3 are spliced one by one from back to front, and the process is as follows:
Step 4021, rear end section installation: horizontally placing the rear end section of the currently constructed drainage ditch on the inner side of the rear end of the base groove, and tightly attaching the rear end of the currently constructed drainage ditch to the vertical bearing structure positioned on the rear side of the currently constructed drainage ditch;
step 4022, splicing the next drainage ditch segment: fixing a water swelling water stop strip 10 in a water stop strip placement groove 11 at the rear end of the next spliced drainage ditch segment 3 in the currently constructed drainage ditch, horizontally placing the currently spliced drainage ditch segment 3 in the base groove, horizontally pushing the currently spliced drainage ditch segment 3 from front to back, inserting the socket at the rear end of the currently spliced drainage ditch segment 3 into the socket at the front end of the drainage ditch segment 3 at the rear side of the currently spliced drainage ditch segment, and simultaneously fastening and clamping the water swelling water stop strip 10 between the currently spliced drainage ditch segment 3 and the drainage ditch segment 3 at the rear side of the currently spliced drainage ditch segment;
And 4023, repeating the step 4022 one or more times until the splicing process of all drainage ditch segments 3 in the currently constructed drainage ditch is completed, and obtaining the assembled resin concrete drainage ditch.
in this embodiment, when fixing the water-swelling water stop strip 10 in the water stop strip placement groove 11 at the rear end of the next spliced drainage ditch segment 3 in the currently constructed drainage ditch in step 4022, the water-swelling water stop strip 10 is fixed in the water stop strip placement groove 11 and is fixed and stable by pasting the glue, and it is ensured that the water-swelling water stop strip 10 is fixed and does not shift after the butt joint of the drainage ditch segments 3 and the water stop strip placement groove 11 on one side of the socket is right opposite to and forms a certain degree of extrusion and water stop for the water-swelling water stop strip 10.
In the step 4022, in the process of splicing the next drainage ditch segment, tight splicing of the connector is ensured, and the drainage ditch is smooth and straight.
In this embodiment, the rear end surfaces of the plug 9 and the slot 8 are both provided with a sealing groove 13 for filling the sealant, and the sealing groove 13 is a concave groove and is located above the water stop strip placing groove 11; the plug 9, the sealing groove 13 on the slot 8 and the water stop strip placing groove 11 are separated by a concave-shaped baffle strip;
The sealing groove 13 on the plug 9 is arranged along the inner contour line of the rear end of the plug 9 and is communicated with the inner groove, and the sealing groove 13 on the slot 8 is arranged along the inner contour line of the rear end of the slot 8 and is communicated with the inner groove;
Two sealing grooves 13 at the joint between two adjacent drainage ditch segments 3 in the front and the back are spliced to form a sealant filling seam.
in the embodiment, the joint between two adjacent drainage ditch segments 3 is a splicing seam, a joint sealing structure is arranged on the inner side of the splicing seam, the joint sealing structure is positioned on the inner side of the sealant filling seam, and the joint sealing structure is in a concave shape and is arranged along the length direction of the splicing seam; the seam sealing structure comprises glass fiber gridding cloth paved on the inner wall of the prefabricated drainage ditch and a polyurethane coating formed by polyurethane paint coated on the glass fiber gridding cloth uniformly. As shown in fig. 10, the seam seal is a seam inboard seal 18.
According to the above, the joint between the two adjacent drainage ditch segments 3 in the front and the back is double-layer waterproof by adopting the water swelling water stop strip 10 and the sealant 12, the polyurethane coating is coated on the inner side of the joint, and the glass fiber mesh cloth is arranged to enhance the ductility of the joint between the two adjacent drainage ditch segments 3 in the front and the back.
As shown in fig. 6, two of the water stop placement grooves 11 at the joint between two adjacent drainage ditch segments 3 in the front and back are buckled to form a mounting groove for placing the water-swellable water stop 10. In this embodiment, the cross section of water swelling sealing rod 10 is square and its cross section length of side is 10mm, adjacent two around like this the assembly of escape canal segment 3 is accomplished the back, can extrude in order to further ensure stagnant water effect and sealed effect meeting water swelling sealing rod 10.
Correspondingly, two sealing grooves 13 at the joint between two adjacent drainage ditch segments 3 in the front and back are buckled to form a sealant injection groove for injecting sealant 12 (namely, the sealant filling seam).
Therefore, the structure, the size and the arrangement position of the water stop placement grooves 11 formed in the plugs 9 and the slots 8 are the same, and the structure, the size and the arrangement position of the sealing grooves 13 formed in the plugs 9 and the slots 8 are the same.
Meanwhile, angle irons (namely right angle irons 4) are installed at the upper openings of the drainage ditch segments 3, so that the edges and corners are protected, and the edges and corners are used as side molds for pouring concrete ground (namely a concrete surface layer 6); outside connecting reinforcement is welded respectively in angle bar dorsal part two sides, strengthen the angle bar with be connected between prefabricated escape canal and the concrete ground.
After the concrete surface layer construction is finished in the step five, sealant caulking construction needs to be carried out on the sealant filling seam between the front adjacent drainage ditch section 3 and the rear adjacent drainage ditch section 3 in the fabricated resin concrete drainage ditch; when sealant caulking construction is carried out on the sealant filling joints between the front and rear adjacent drainage ditch segments 3, the sealant filling joints are uniformly filled with sealant and the sealant is tightly filled;
Adjacent two in front and back between the drainage ditch section 3 the sealed glue is filled the seam and is carried out sealed gluey caulking construction back, still need adjacent two in front and back the seam inboard between the drainage ditch section 3 is provided with seam seal structure.
in the embodiment, when the sealant caulking construction is performed on the sealant filling joints between the front and rear adjacent drainage ditch segments 3, sealant is poured into the sealant filling joints, the sealant is silicone adhesive, the coating is rapid and uniform, and the coating thickness is preferably full of the grooves.
the sealant is a silicone sealant with seam displacement capacity of 7.5 grade and N-type fluidity, and the caulking seam of the sealant is full and dense.
During actual construction, the groove body side plate positioned above the left side of the groove body bottom plate is a left side plate, and the groove body side plate positioned above the right side of the groove body bottom plate is a right side plate; the outer side wall of the left side plate is flush with the left side wall of the groove body bottom plate positioned below the left side plate, and the outer side wall of the right side plate is flush with the right side wall of the groove body bottom plate positioned below the right side plate; the width of the groove body basic section 1 is the horizontal distance between the outer side walls of the two groove body side plates in the groove body basic section 1, and the width of the groove body thickened section 2 is the horizontal distance between the outer side walls of the two groove body side plates in the groove body thickened section 2; the width of the groove body bottom plate in the groove body basic section 1 is smaller than that of the groove body bottom plate in the groove body thickened section 2.
the length of the groove body basic section 1 is 250 mm-350 mm;
the height of the groove body side plate is 210 mm-230 mm, the plate thickness of the groove body bottom plate and the groove body side plate in the groove body basic section 1 is 25 mm-35 mm, and the plate thickness of the groove body bottom plate and the groove body side plate in the groove body thickening section 2 is 75 mm-85 mm;
the width of the inner groove is 280 mm-320 mm.
In order to further ensure the construction quality of the prefabricated drainage ditch and the service life and the use effect of the prefabricated drainage ditch, the length of the socket connecting section is 65-75 mm, and the length of the socket connecting section is 75-85 mm; the length of the groove body thickening section 2 is 100 mm-120 mm.
in the present embodiment, the length of the groove body basic section 1 is 280mm, the height of the groove body side plate is 220mm, the plate thicknesses of the groove body bottom plate and the groove body side plate in the groove body basic section 1 are both 30mm, and the plate thicknesses of the groove body bottom plate and the groove body side plate in the groove body thickening section 2 are both 80 mm. The width of the inner groove is 300 mm. The length of the socket connecting section is 70mm, and the length of the socket connecting section is 80 mm; the length of the groove body thickened section 2 is 110 mm. The length of the bell mouth connecting section is smaller than that of the spigot connecting section, so that socket and spigot are simple and convenient, alignment is simple and convenient during socket and spigot, and in the process of inserting the spigot connecting section, the guiding and positioning process can be automatically completed through the spigot connecting section.
in actual construction, the length of the groove body basic section 1, the height of the groove body side plate, the plate thicknesses of the groove body bottom plate and the groove body side plate in the groove body basic section 1, the plate thicknesses of the groove body bottom plate and the groove body side plate in the groove body thickening section 2, the width of the internal groove, and the lengths of the socket connecting section and the socket connecting section can be adjusted according to specific needs.
In this embodiment, the groove body side plate and the groove body bottom plate are both cubic flat plates, and a reinforcing layer with a right-angled triangle-shaped cross section is arranged at the joint between the groove body side plate and the groove body bottom plate. Thus, the strength of the prefabricated drain can be further ensured.
The polyurethane coating is a common coating at present and can be divided into a two-component polyurethane coating and a one-component polyurethane coating. During actual construction, the corresponding type of polyurethane coating can be selected according to actual needs. The selected polyurethane coating is a double-component polyurethane coating or a single-component waterborne polyurethane coating.
In the embodiment, the single-component polyurethane coating is selected, and the tensile strength is greater than 2 MPa.
after the sealant is filled into the seams and the joints of the front and the rear adjacent drainage ditch sections 3 are caulked, polyurethane paint with the thickness of 1.5mm and the width of 100mm is coated at the joints, and glass fiber mesh cloth is arranged in the polyurethane paint to enhance the ductility of the polyurethane paint. After the polyurethane coating is dried, an anti-crack mortar protective layer with the thickness of 6mm is coated.
The adopted glass fiber mesh cloth is alkali-resistant glass fiber mesh cloth, and the center distance of meshes of the alkali-resistant glass fiber mesh cloth is 4mm multiplied by 4mm or 5mm multiplied by 5 mm; the mass per unit area is more than or equal to 160g/m2。
in this embodiment, after the assembly of the drainage ditch in step 402 is completed, the assembly is completed and slope is found by using waterproof mortar according to the design gradient of a drawing along the drainage direction at the bottom of the inner side of the prefabricated drainage ditch, so that drainage is smooth.
the prefabricated drainage ditch is a drainage ditch positioned in the basement.
in this embodiment, the base groove is an excavation groove 16 with an isosceles trapezoid cross section, the width of the excavation groove 16 is gradually reduced from top to bottom, and the width of the bottom of the excavation groove is greater than the width of the groove body thickened section 2.
as shown in fig. 8, the walls of the digging grooves 16 are sidewalls gradually inclined downward from top to bottom, and the included angle between the sidewalls and the horizontal plane is 45 °. During actual construction, the included angle between the wall of the excavation groove 16 and the horizontal plane can be adjusted within the range of 40-50 degrees according to specific requirements.
after the foundation trench is excavated, a lime soil cushion layer 17 which is 3-8 cm thick and is formed after being tamped is laid at the bottom of the excavated trench 16, and the lime soil cushion layer 17 is formed by flattening and tamping the pseudo-ginseng lime soil. The volume ratio of ash to soil in the pseudo-ginseng grey soil is 3: 7. The assembled prefabricated drain is located on the lime soil mat layer 17 and is located in the middle of the interior of the cut groove 16.
during actual construction, the thickness of the lime soil cushion layer 17 can be adjusted according to specific requirements.
In this embodiment, the top plate is a basement top plate;
a plurality of concealed pipes and a plurality of junction boxes 25 are arranged in the top plate of the basement, the concealed pipes are threading pipes pre-embedded in the top plate of the basement, each threading pipe is connected with one junction box 25 through one wire pipe connecting section 26, the threading pipes are electric wire pipes, the threading pipes are connected with the wire pipe connecting sections 26 connected with the threading pipes through connecting joints 30, and each threading pipe is coaxially arranged with the wire pipe connecting sections 26 connected with the threading pipes and the connecting joints 30; spool linkage segment 26 for the inner insert the pipeline on terminal box 25 downthehole and the outer end with the electric wire tube section of threading union coupling, every spool linkage segment 26 all is rather than the terminal box 25 welded fastening who cartridges as an organic whole, every spool linkage segment 26 constitutes the area joint spool linkage segment with the attach fitting 30 that its outer end is connected, every terminal box 25 all assembles an assembled spool terminal box with all area joint spool linkage segments that the inner inserted it.
According to the common knowledge in the art, piping, i.e., conduit laying, is used for auxiliary circuit laying and protection of electric wires in building construction or home appliance decoration. The piping is divided into a clear piping and a dark piping according to the way of laying. The exposed pipe is laid on the surface of the wall and the ceiling, the truss, the bracket and the like; the concealed piping is laid inside a wall, a ceiling, a floor, or the like. In the present embodiment, the junction box 25 is a junction box.
before the basement top plate is constructed, determining the number of assembled type conduit junction boxes to be laid in the basement top plate, the number of sections of conduit with joints connected on each assembled type conduit junction box and the laying position of each conduit with joints according to the number of pre-designed junction boxes 25 to be buried in the basement top plate, the number of conduits to be connected on each junction box 25 and the laying position of each conduit, wherein the number of the assembled type conduit junction boxes is the same as that of the junction boxes 25; and then, according to the determined number of the assembled wire tube junction boxes, the number of the wire tube connecting sections with joints connected on each assembled wire tube junction box and the arrangement positions of the wire tube connecting sections with joints, respectively assembling all the assembled wire tube junction boxes to be arranged in the top plate of the basement in a processing field to obtain all the assembled wire tube junction boxes which are assembled and formed, and the detailed description is shown in figure 15.
in this embodiment, as shown in fig. 15, four conduit connection sections 26 are inserted into the assembled conduit junction box.
During actual construction, the number of the inserted conduit connection sections 26 in each assembled conduit terminal box and the arrangement positions of the conduit connection sections 26 can be arranged according to specific requirements.
in this embodiment, when constructing the basement roof, the method includes the following steps:
step A1, formwork support: erecting a forming template for constructing the basement top plate;
The forming template comprises a bottom template and a side template, wherein the bottom template is horizontally arranged, and the side template is arranged above the bottom template;
step A2, binding a reinforcement cage: binding a reinforcement cage arranged in the top plate of the basement to obtain the reinforcement cage formed by binding;
step A3, arranging the assembled wire tube junction box and the threading tube: uniformly distributing all assembled wire tube junction boxes and all wire tubes to be distributed in the top plate of the basement in the forming template in the step A1 according to the number of the pre-designed junction boxes 25 to be embedded in the top plate of the basement and the distribution positions of the junction boxes 25, the number of the pre-designed wire tubes to be embedded in the top plate of the basement and the distribution positions of the wire tubes and the distribution positions of the junction boxes 25 connected with the wire tubes, and connecting each wire tube with the wire tube connecting section 26 connected with the wire tube connecting section through a connecting joint 30;
step A4, pouring concrete: and carrying out concrete pouring on the basement top plate to obtain the constructed and molded basement top plate.
wherein, the processing field is a temporary shed set up near a processing factory or a construction field.
in this embodiment, when all the assembled line tube junction boxes to be laid in the top plate of the basement are assembled in a processing field, the assembling methods of all the assembled line tube junction boxes are the same;
When any assembled wire tube junction box is assembled, a wire tube is fed into a junction box adjusting mold for assembly;
as shown in fig. 12, 13 and 14, the threading pipe feeding junction box adjusting mold comprises a base plate 21, a vertical sleeve 22, a vertical limiting rod 23, an insertion length limiting member and a wire pipe support rod 29, wherein the base plate 21 is horizontally arranged, the vertical sleeve 22 is fixed on the base plate 21 and is positioned in the vertical sleeve 22, the insertion length limiting member limits the insertion length of a wire pipe connecting section 26 horizontally inserted into a junction box 25, the wire pipe support rod 29 horizontally supports the wire pipe connecting section 26 and limits the placement position of the wire pipe connecting section 26, and the vertical limiting rod 23 is arranged on a central axis of the vertical sleeve 22; each spool connecting section 26 is uniformly distributed on one spool support 29, and each spool connecting section 26 is distributed along the central axis of the distributed spool support 29; the number of the conduit supporting rods 29 is multiple and is the same as that of the conduit connecting sections 26 which are horizontally inserted into the junction box 25, the conduit supporting rods 29 are horizontally arranged, the inner ends of the conduit supporting rods 29 are fixed at the upper part of the vertical sleeve 22, and the plurality of the conduit supporting rods 29 are the same in structure and size and are positioned on the same horizontal plane; a wire releasing groove for horizontally placing one wire pipe connecting section 26 is formed in the wire pipe supporting rod 29, and the wire releasing groove is opposite to a pipeline hole formed in the junction box 25 and used for inserting the wire pipe connecting section 26 placed in the wire releasing groove;
The insertion length limiting member is located in the vertical sleeve 22; the insertion length limiting part comprises a limiting sleeve 24 coaxially sleeved on the vertical limiting rod 23 from top to bottom, a horizontal limiting plate 27 fixed on the limiting sleeve 24 and a line pipe limiting plate 28 arranged on the horizontal limiting plate 27, wherein the limiting sleeve 24 is arranged vertically; the horizontal limiting plate 27 is positioned right above the limiting sleeve 24 and is vertically arranged with the limiting sleeve 24, and the horizontal limiting plate 27 is positioned below the wire laying groove; spool limiting plate 28 is the vertical limiting plate that lays perpendicularly with horizontal limiting plate 27, the quantity of spool limiting plate 28 is the same with the quantity of spool branch 29, every the inboard equipartition of spool branch 29 is equipped with one and carries out spacing spool limiting plate 28 to the inner of the spool linkage segment 26 of placing on this spool branch 29.
The junction box 25 is an electrical junction box used in construction work. In the present embodiment, the junction box 25 is a junction box.
In this embodiment, the box body of the junction box 25 is a cube. The middle parts of the four side walls of the junction box 25 are all provided with one pipeline hole.
In this embodiment, the vertical sleeve 22 is a cubic sleeve.
The cross section of the vertical sleeve 22 is square, and the cross section area of the junction box 25 is smaller than that of the inner cavity of the vertical sleeve 22.
In this embodiment, the number of conduit support rods 29 is four, four the inner ends of the conduit support rods 29 are fixed on the upper portions of the four side walls of the vertical sleeve 22, and each of the conduit support rods 29 is located right above one side wall of the vertical sleeve 22.
And the inner end of each conduit strut 29 is flush with the inner surface of the side wall of the vertical sleeve 22 to which it is fixed.
The horizontal limiting plates 27 and the line pipe limiting plates 28 are both square flat plates, the number of the line pipe limiting plates 28 is four, and each line pipe limiting plate 28 is uniformly distributed above one side wall of each horizontal limiting plate 27.
for convenient processing and reliable performance to can used repeatedly many times, in this embodiment, every spool branch 29 all is the perpendicular laying with its inboard spool limiting plate 28 of laying, every spool limiting plate 28 equipartition is located on the central axis of the spool branch 29 that is located its outside. Thus, each of the conduit-limiting plates 28 is disposed immediately in front of the conduit support rod 29 located outside thereof. In this embodiment, the length of the conduit support rod 29 is 50mm to 80 mm.
In this embodiment, the junction box 25 is located right above the vertical limiting rod 23.
In actual processing, the diameter of the vertical limiting rod 23 is round steel with the diameter of 10 mm-15 mm. In this embodiment, the diameter of the vertical limiting rod 23 is phi 12mm, so that the supporting strength can meet the actual requirement, the dead weight is light, and the overall weight of the die is not affected.
The cross-sectional area of the vertical sleeve 22 is determined according to the cross-sectional area of the junction box 25, the inner cavity of the vertical sleeve 22 is a cubic cavity, the cross-section of the cubic cavity is square, and the cross-sectional area of the cubic cavity is larger than that of the junction box 25. In this embodiment, the length of the cross section and the length of the cross section of the cubic cavity are both 100 mm. During actual processing, the cross-sectional area of the vertical sleeve 22 can be adjusted accordingly according to specific needs.
In this embodiment, the base plate 21 is a horizontal steel plate. The vertical limiting rod 23 is a cylindrical metal rod with the bottom welded and fixed on the base plate 21. Therefore, the practical processing is simple and convenient, and the fixation is reliable.
The limiting sleeve 24 is a round steel pipe. In order to ensure the connection reliability, the horizontal limiting plate 27 and the spool limiting plate 28 are flat steel plates, and the limiting sleeve 24 and the horizontal limiting plate 27 and the spool limiting plate 28 are fixedly connected into a whole in a welding manner.
In this embodiment, the horizontal limiting plate 27 and the line pipe limiting plate 28 are both square steel plates.
in order to smoothly insert the insertion length limiting member into the vertical sleeve 22, the width of the spool limiting plate 28 is smaller than the cross-sectional length of the cubic cavity, and the cross-sectional area of the horizontal limiting plate 27 is smaller than the cross-sectional area of the cubic cavity.
The outer side wall of each line pipe limiting plate 28 is a limiting plate for limiting the inner end of the line pipe connecting section 26, and the position of the outer side wall of each line pipe limiting plate 28 is the same as the position of the inner end of the pre-designed limiting line pipe connecting section 26, which is inserted into the junction box 25. In this embodiment, four the spool limiting plate 28 includes two first limiting plates that are the symmetry and lay and two second limiting plates that are the parallel layout, two first limiting plate is the symmetry and lays, two the second limiting plate is the symmetry and lays, two horizontal interval between the lateral wall of first limiting plate is the same with two horizontal interval between the lateral wall of second limiting plate. The horizontal spacing between the central axes of the four spool limiting plates 28 and the limiting sleeve 24 is the same. The horizontal distance between the outer side walls of the two first limiting plates is smaller than the length of the junction box 25.
in order to ensure that the insertion length limiting members can be smoothly inserted, the horizontal distance between the outer side walls of the two first limiting plates is not less than the length of the horizontal limiting plate 27, and the length of the horizontal limiting plate 27 is the same as the width of the horizontal limiting plate 27. In this embodiment, the outer sidewall of each horizontal limiting plate 27 is flush with the outer surface of the sidewall of the horizontal limiting plate 27 fixed thereto.
In this embodiment, four the structure and the size of spool limiting plate 28 are all the same, four spool limiting plate 28 constitutes the box body bearing structure that supports terminal box 25, terminal box 25 can from top to bottom the suit in the box body bearing structure outside. The inner cavity of the junction box 25 is a cube, the horizontal distance between the outer side walls of the two first limiting plates is smaller than the cross section length of the inner cavity of the junction box 25, and the cross section length of the inner cavity of the junction box 25 is the same as the width of the inner cavity of the junction box.
the bottom of the box body of the junction box 25 is provided with an opening, and the junction box 25 can be sleeved on the box body supporting structure from top to bottom. In order to ensure that the junction box 25 is positioned right above the vertical limiting rod 23, the horizontal distance between the outer side walls of the two first limiting plates is 2-6 mm smaller than the cross section length of the inner cavity of the junction box 25.
the height of the vertical limiting rod 23 is determined according to the height of the vertical sleeve 22, the placement height of the junction box 25 and the arrangement position of the pipeline holes formed in the junction box 25, and the height of the vertical sleeve 22 is larger than that of the vertical limiting rod 23. When the heights of the vertical limiting rod 23 and the vertical sleeve 22 are determined, the wiring groove on the wiring pipe supporting rod 29 and the pipeline hole on the wiring box 25 are positioned on the same horizontal plane only after the wiring box 25 is horizontally supported on the box body supporting structure, so that the wiring groove on the wiring pipe supporting rod 29 and the pipeline hole of the wiring box 25 horizontally supported on the box body supporting structure are positioned on the same horizontal plane. In order to not increase the self weight of the die, the height of the vertical sleeve 22 is 200 mm-500 mm. During actual processing, the height of the vertical sleeve 22 and the height of the vertical limiting rod 23 can be adjusted correspondingly according to specific requirements.
The inner diameter of the limiting sleeve 24 is larger than the diameter of the vertical limiting rod 23 and is coaxially arranged with the vertical limiting rod 23. In order to ensure that the limiting sleeve 24 and the vertical limiting rod 23 are coaxially arranged, the inner diameter of the limiting sleeve 24 is 2-6 mm larger than the diameter of the vertical limiting rod 23. In this embodiment, the inner diameter of the position-limiting sleeve 24 is phi 16 mm.
In this embodiment, the vertical sleeve 22 is a cubic steel sleeve with the bottom welded to the base plate 21.
the base plate 21 is a horizontal steel plate. The base plate 21 is a rectangular steel plate. The bottom of the vertical sleeve 22 is fixed in the middle of the base plate 21.
For fixing simply, conveniently and firmly, a plurality of fastening bolts are arranged on the base plate 21, and the base plate 21 is stably and firmly fixed on the operation platform through the plurality of fastening bolts.
in this embodiment, the base plate 21 has a length of 400mm, a width of 250mm, and a plate thickness of 10 mm. During practical processing, the size of the base plate 21 can be correspondingly adjusted according to specific requirements, and the fixing requirement of the vertical sleeve 22 can be met.
The spool supporting rod 29 is an angle steel which is horizontally arranged, the spool supporting rod 29 is welded and fixed on the vertical sleeve 22, and a triangular mounting hole for mounting the spool supporting rod 29 is formed in the upper portion of the vertical sleeve 22; the angle steel is characterized in that two sides of the angle steel are symmetrically arranged, the included angle between the two sides is gradually increased from bottom to top, and the wire laying grooves are triangular grooves in the angle steel.
In this embodiment, the conduit support rod 29 is a right angle steel and is welded and fixed with the vertical sleeve 22 into a whole.
The conduit supporting rod 29, the vertical sleeve 22, the vertical limiting rod 23 and the base plate 21 are fastened and connected to form a template main body. In addition, the limiting sleeve 24, the horizontal limiting plate 27 and the line pipe limiting plate 28 are connected into a whole, so that the practical processing is simple and convenient, the operation is convenient, and the carrying and moving are simple and convenient. Before actual processing, according to the length of the inner end of the wire pipe connecting section 26 inserted into the terminal box 25 and the length of the terminal box 25 which are designed in advance, the horizontal distance between the outer side walls of the two first limiting plates and the horizontal distance between the outer side walls of the two second limiting plates are determined, the horizontal distance between the outer side walls of the two first limiting plates is marked as D, wherein D is L-2D, L is the length of the terminal box 25 (also called as the length of the terminal box 25 and the width of the terminal box), and D is the length of the inner end of the wire pipe connecting section 26 inserted into the terminal box 25 which is designed in advance.
in this embodiment, the four spool limiting plates 28 have the same structure and size. The four line pipe limiting plates 28 form a box body supporting structure for supporting the junction box 25, and the junction box 25 can be sleeved outside the box body supporting structure from top to bottom.
In this embodiment, when any one of the assembled wire tube junction boxes is assembled by using the wire tube junction box adjusting mold, the template main body is stably supported on the horizontal operating platform, and then the insertion length limiting pieces are inserted into the vertical sleeves 22 from top to bottom, so that the limiting sleeves 24 are coaxially sleeved on the vertical limiting rods 23, and each wire tube limiting plate 28 is arranged in parallel with one side wall of the vertical sleeve 22; then, the junction box 25 of the currently assembled wire tube junction box is sleeved on a box body supporting structure consisting of four wire tube limiting plates 28 from top to bottom, and the wire discharge grooves on each wire tube supporting rod 29 and the pipeline holes of the junction box 25 horizontally supported on the box body supporting structure are positioned on the same horizontal plane; finally, according to the number of the conduit connecting sections 26 inserted in the currently assembled assembly type conduit junction box and the arrangement position of each conduit connecting section 26, horizontally placing one or more conduit connecting sections 26 on one or more conduit supporting rods 29 respectively, and moving each conduit connecting section 26 inwards along the central axis of the placed conduit supporting rod 29 respectively until the inner end of the conduit connecting section 26 abuts against the outer side wall of a conduit limiting plate 28 for limiting the inner end of the conduit connecting section 26, so that the inlet wire adjusting process of the conduit connecting section 26 is completed; after all the wire pipe connecting sections 26 are adjusted in place, all the wire pipe connecting sections 26 which are adjusted in place are welded and fixed with the junction box 25 by adopting a welding tool, the wire inlet adjusting and fixing process that the wire pipe connecting sections 26 enter the junction box 25 is completed, and the assembled wire pipe junction box is obtained.
When the formwork main body is stably supported on the horizontal operation platform, specifically, the base plate 21 is horizontally supported on the horizontal operation platform, and in order to ensure that the fixing is firm, the base plate 21 is fixed on the horizontal operation platform through a plurality of fastening bolts.
In this embodiment, as shown in fig. 14, after the four conduit connection sections 26 are locally adjusted in place, each conduit connection section 26 adjusted in place is welded and fixed with the junction box 25 by using a welding tool, so as to complete the wire feeding adjustment process of the conduit connection section 26 entering the junction box 25.
To ensure that the base plate 21 is firmly supported on the horizontal operation platform, a plurality of fastening bolts 31 are installed on the base plate 21, and the base plate 21 is fixed on the horizontal operation platform through the plurality of fastening bolts 31. In this embodiment, the horizontal operation platform is a ground, and the ground is a concrete ground. The base plate 21 is provided with a plurality of bolt mounting holes for mounting the fastening bolts 31.
in this embodiment, the number of the fastening bolts 31 is two, and the two fastening bolts are symmetrically arranged, so that the base plate 21 can be effectively prevented from shifting by the two fastening bolts 31.
Meanwhile, the threading pipe inlet junction box adjusting die further comprises a reinforcing plate 33 arranged on the base plate 21, wherein the reinforcing plate 33 is a rectangular flat plate and is arranged along the length direction of the base plate 21. The reinforcing plate 33 is located on the side of the vertical sleeve 22. During the in-service use, can steadily reinforce the base plate 21 through gusset plate 33, ensure the stationarity and the firm nature of base plate 21, prevent that base plate 21 from taking place distortion.
in order to further ensure the fixing effect of the base plate 21, in this embodiment, one end of the reinforcing plate 33 is provided with a vertical limiting sleeve 32 coaxially sleeved on the vertical limiting member from top to bottom, the vertical limiting member is fastened and fixed on the horizontal operating platform, and the reinforcing plate 33 and the base plate 21 are both provided with insertion holes for inserting the vertical limiting member.
the two fastening bolts 31 are respectively arranged on two top corners of the base plate 21. The other end of the reinforcing plate 33 is provided with one of the fastening bolts 31, the other one of the fastening bolts 31 is arranged at a vertex angle of the base plate 21, the two fastening bolts 31 and the vertical sleeve 22 are arranged on the same vertical surface, and the two fastening bolts 31 are positioned on a diagonal line of the base plate 21.
In this embodiment, the length of the vertical limiting sleeve 32 is 10mm to 30 mm.
When any spool connection section 26 is adjusted, the adjusted spool connection section 26 is horizontally moved inwards along the central axis of the supported spool support rod 29 until the inner end of the spool connection section 26 abuts against the outer side wall of the spool limiting plate 28 for limiting the spool connection section. When the adjusted conduit connecting section 26 is horizontally moved inwards along the central axis of the supporting conduit support rod 29, the conduit connecting section 26 is pushed to translate inwards on the supporting conduit support rod 29, the actual operation is very simple and convenient, and the insertion length can be effectively controlled. Therefore, the threading pipe inlet junction box adjusting die limits the insertion length of the threading pipe connecting section 26 entering the junction box 25 through the insertion length limiting part, and simultaneously horizontally supports and guides the threading pipe connecting section 26 through the threading pipe supporting rod 29, so that the position accuracy of the threading pipe connecting section 26 entering the junction box 25 can be effectively ensured, the length of the threading pipe connecting section 26 entering the junction box 25 can be ensured, the welding connection quality of the threading pipe and the junction box can be ensured, the labor and the time are saved, and the adjusting process of the threading pipe connecting section 26 entering the junction box 25 can be simply, conveniently and quickly completed.
according to the common knowledge in the field, the junction box is a necessary electrician auxiliary tool in building engineering or various decoration construction. In order to keep the building surface clean and beautiful, the wiring cassette generally needs to be installed in an embedded manner. Therefore, the installation quality of the connection cassette is very high, and the connection quality between the connection cassette and the conduit connection section 26 must be effectively ensured, otherwise the post repair is very difficult.
in the building construction process, the junction box 15 is one of the electrical accessories, because the electric wires used in the building are inserted into the threading pipe (also called as electric wire pipe, usually steel pipe, etc.), and the junction of the electric wires (for example, the part where the wire is longer or the electric wire pipe needs to be turned) is used as a transition part, the threading pipe needs to be connected with the junction box, and the electric wires in the threading pipe are connected in the junction box 15, so that the junction box 15 plays a role in protecting and connecting the electric wires. At present, when the threading pipe is connected with the junction box 15, the threading pipe is generally manually operated, and the threading pipe is threaded into the junction box 15 (namely, the threading pipe is threaded into the junction box 15) and then welded, so that the threading pipe is connected with the junction box 15. However, during actual construction, the difficulty of field operation is very large, and because the intensity of the threading pipe is large and the plasticity is poor, the randomness when the constructor threads the threading pipe into the junction box 15 during construction is large, the length of the threading pipe entering the junction box 15 is not easy to control, so that the contact area of the junction box 15 and the threading pipe is small, welding is not easy to perform, the welding quality is difficult to guarantee, and the connection quality of the threading pipe and the junction box 15 cannot be guaranteed. And, also can't guarantee terminal box 15's position accuracy to can't guarantee that the threading pipe lays violently flat vertical, therefore there is the great, the threading pipe slope of terminal box 15 positional deviation or distortion scheduling problem, later stage needs to spend a large amount of manpower and materials to maintain, and whole reworking even influences the threading pipe and is connected the efficiency of construction with the terminal box to a great extent, and the threading pipe is relatively poor with the quality of being connected of terminal box 15.
particularly, when the top plate of the basement (the top plate of the basement for short) such as an underground garage, an underground warehouse and the like is constructed, a large number of wiring hidden boxes are usually pre-buried in the top plate of the basement, the engineering quantity is large, the requirement on the connection quality between each wiring hidden box and the wiring pipe connecting section 26 penetrating through the wiring hidden box is very high, the wire inlet adjusting quality when the wiring pipe connecting section 26 enters the wiring box 25 is ensured in order to ensure the position accuracy of the wiring hidden boxes and the horizontal and vertical laying of the wiring pipe connecting section 26 penetrating through the wiring hidden boxes, reduce or even avoid the problems of larger position deviation of the wiring box 25, inclination or distortion of the wiring pipe connecting section 26 and the like, the wire inlet adjusting quality when the wiring pipe connecting section 26 enters the wiring box 25 can be effectively solved by adopting the wire inlet wiring box adjusting mould, the wire inlet adjusting quality when the wiring pipe connecting section 26 enters the wiring box 25, the construction qualification rate of the electrical concealed piping (namely the wiring pipe connecting section 26) of the top plate of the basement can be effectively improved, and various problems existing when the existing penetrating pipe is connected with the junction box 15 can be effectively solved. The inner end of the conduit connecting section 26 is inserted into the junction box 25, the outer end of the conduit connecting section is connected with the connecting joint 30, the conduit connecting section 26 is connected with the connecting joint 30 in a threaded connection mode, and the connecting joint 30 is a threaded joint.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the present invention, and all simple modifications, changes and equivalent structural changes made to the above embodiment according to the technical spirit of the present invention still fall within the protection scope of the technical solution of the present invention.
Claims (10)
1. a basement construction method based on an assembly type resin concrete drainage ditch is characterized by comprising the following steps:
Step one, excavation of a foundation pit: excavating a foundation pit of the constructed basement from top to bottom;
The constructed basement is supported on a raft foundation and comprises a top plate and a bearing structure supported between the raft foundation and the top plate, wherein the top plate, the bearing structure and the raft foundation are all of cast-in-place reinforced concrete structures, the raft foundation and the top plate are horizontally arranged, and the top plate is positioned right above the raft foundation; the bearing structures comprise a plurality of vertical bearing structures distributed along the contour line of the raft foundation;
Step two, raft foundation and bearing structure construction: constructing a raft foundation and the bearing structure of the constructed basement respectively;
Step three, basic layer treatment: performing backfill construction on the raft foundation in the step two to obtain a constructed backfill layer;
step four, drainage ditch construction: constructing the drainage ditches in the constructed underground chamber on the backfill layer in the step three according to the number of the drainage ditches arranged in the constructed underground chamber and the arrangement positions of the drainage ditches which are designed in advance; all drainage ditches in the constructed underground chamber have the same structure and the same construction method, and each drainage ditch is an assembled resin concrete drainage ditch;
The prefabricated drainage ditch comprises a prefabricated drainage ditch formed by connecting a plurality of ditch body basic sections (1) arranged from front to back and a plurality of ditch body thickened sections (2) arranged from front to back, wherein the bottom surface inside the prefabricated drainage ditch and the inner walls on the left side and the right side of the prefabricated drainage ditch are both planes; the groove body basic sections (1) and the groove body thickened sections (2) are arranged in a staggered mode, and every two adjacent groove body thickened sections (2) are connected through one groove body basic section (1); the cross sections of the groove body basic section (1) and the groove body thickened section (2) are both in a concave shape, and the cross section structures and the sizes of the inner grooves of the groove body basic section and the groove body thickened section are the same; the groove body basic section (1) and the groove body thickened section (2) are respectively formed by connecting a groove body bottom plate and a left groove body side plate and a right groove body side plate which are symmetrically arranged above two sides of the groove body bottom plate, the two groove body side plates are arranged in parallel and are both vertically arranged with the groove body bottom plate; the groove body bottom plate is horizontally arranged, and the inner side wall and the outer side wall of the groove body side plate are vertical surfaces; the height of the groove body side plate in the groove body basic section (1) and the groove body thickened section (2) is the same, the plate thickness of the groove body side plate in the groove body basic section (1) is smaller than that of the groove body side plate in the groove body thickened section (2), and the plate thickness of the groove body bottom plate in the groove body basic section (1) is smaller than that of the groove body bottom plate in the groove body thickened section (2); the outer side walls of the left side and the right side of the prefabricated drainage ditch are rectangular waveform side walls;
the prefabricated drainage ditch is formed by splicing a plurality of drainage ditch segments (3) arranged from front to back, the drainage ditch segments (3) are resin concrete drainage ditch segments formed by pouring resin concrete in advance, and the drainage ditch segments (3) are arranged on the same straight line; the front and the rear adjacent drainage ditch segments (3) are in socket connection; -one drain segment (3) of the plurality of drain segments (3) located at the foremost side is a front end segment, one drain segment (3) of the plurality of drain segments (3) located at the rearmost side is a rear end segment, the front end surface of the front end segment and the rear end surface of the rear end segment are both vertical surfaces, and the drain segments (3) of the prefabricated drain located between the front end segment and the rear end segment are both socket segments; one end of the socket segment is a bell mouth, the other end of the socket segment is a spigot which can be inserted into the bell mouth, the rear end of the front end segment is the bell mouth or the spigot, and the front end of the rear end segment is the spigot or the bell mouth; each drainage ditch segment (3) is provided with two right angle steel angles (4), the two right angle steel angles (4) are symmetrically distributed at the upper parts of the left side and the right side of the drainage ditch segment (3), and the two right angle steel angles (4) are distributed on the same plane and are distributed along the length direction of the prefabricated drainage ditch; one side of the right angle steel (4) is a horizontal side fixed at the upper part of the groove body side plate, and the other side of the right angle steel is a vertical side positioned above the outer side of the horizontal side, the inner side wall of the horizontal side is flush with the inner side wall of the groove body side plate, and the outer side wall of the vertical side is flush with the outer side wall of the groove body side plate in the groove body basic section (1) or positioned inside the outer side wall of the groove body side plate in the groove body basic section (1);
The joints between two adjacent drainage ditch segments (3) in the front and the back are the positions where the groove body thickened sections (2) are located, and the groove body thickened sections (2) located at the joints between the two adjacent drainage ditch segments (3) in the front and the back in the plurality of groove body thickened sections (2) are groove body connecting sections; each groove body connecting section is formed by splicing a socket connecting section with the socket and a socket connecting section with the socket which can be inserted into the socket;
in the third step, the upper surface of the backfill layer is not higher than the top surface of the ditch body side plate;
When any drainage ditch in the constructed underground chamber is constructed, the process is as follows:
Step 401, excavating a foundation trench: according to the pre-designed layout position of the drainage ditch currently constructed, a base groove for installing the drainage ditch currently constructed is dug on the backfill layer in the third step, wherein the base groove is a groove arranged along the length direction of the drainage ditch currently constructed;
Step 402, drain assembly: splicing a plurality of drainage ditch segments (3) of the drainage ditch which is processed and formed in advance into a whole from front to back along the length direction of the drainage ditch which is constructed currently, and finishing the assembly process of the drainage ditch which is constructed currently;
step five, concrete surface layer construction: after all drainage ditches in the underground chamber are constructed, a concrete surface layer (6) is poured on the backfill layer;
in the fourth step, the top surfaces of the vertical edges are flush with the upper surface of the concrete surface layer (6), the concrete surface layer (6) is poured on the outer side of the right-angle steel (4), and the vertical edges are side templates for pouring the concrete surface layer (6);
After the construction of the bearing structure in the basement constructed in the second step is completed, constructing a top plate of the basement constructed; the top plate is horizontally arranged and supported on the bearing structure; the top plate is a cast-in-place reinforced concrete plate.
2. The basement construction method based on the fabricated resin concrete drainage ditch according to claim 1, wherein: after the excavation of the foundation trench is finished in the step 401, a layer of lime soil cushion layer (17) is paved at the bottom of the inner side of the excavated foundation trench, and the assembled resin concrete drainage ditch is supported on the lime soil cushion layer (17).
3. the basement construction method based on the fabricated resin concrete drainage ditch according to claim 1 or 2, wherein: in the step 401, the cross section of the base groove is in an isosceles trapezoid shape, the width of the base groove is gradually reduced from top to bottom, and the width of the bottom of the base groove is larger than that of the groove body thickening section (2);
After the drainage ditch is assembled in step 402 and before the concrete surface layer is constructed in step five, backfilling construction needs to be performed on a gap between the currently constructed drainage ditch and the foundation trench in which the drainage ditch is located.
4. the basement construction method based on the fabricated resin concrete drainage ditch according to claim 1 or 2, wherein: in the fourth step, the front end and the rear end of the prefabricated drainage ditch are both ditch body thickened sections (2);
Every the escape canal all is located two between the vertical bearing structure, every the front and back end in escape canal all with one vertical bearing structure's inside wall is hugged closely.
5. The basement construction method based on the fabricated resin concrete drainage ditch according to claim 1 or 2, wherein: in the fourth step, outer side connecting steel bars (7) are welded and fixed on the outer side walls of the vertical edges in the right angle steel (4), and the outer side connecting steel bars (7) are horizontally arranged; the outer connecting steel bars (7) positioned above the left side of the prefabricated drainage ditch are left steel bars, the outer connecting steel bars (7) positioned above the right side of the prefabricated drainage ditch are right steel bars, and the left steel bars and the right steel bars are symmetrically distributed;
the left side reinforcing bar with the quantity of right side reinforcing bar is a plurality of and its equipartition locates on the same horizontal plane, the left side reinforcing bar with the right side reinforcing bar all is fixed in concrete surface course (6).
6. the basement construction method based on the fabricated resin concrete drainage ditch according to claim 1 or 2, wherein: in the fourth step, a socket (8) with a concave cross section is arranged on the socket, and a plug (9) which is inserted into the socket (8) and has a concave cross section is arranged on the socket; the slot (8) and the plug (9) are horizontally arranged;
the plug (9) is a horizontal plug inserted into the slot (8) from front to back, the width of the plug (9) is gradually reduced from front to back, the inner side wall of the plug (9) is the inner side wall of the groove body side plate, the bottom surface of the inner side of the plug is the upper surface of the groove body bottom plate, the outer side walls of the left side and the right side of the plug (9) are inclined surfaces which are gradually inclined inwards from front to back, and the bottom surface of the outer side of the plug (9) is an inclined surface which is gradually inclined downwards from front to back; the width of the front end of the plug (9) is larger than that of the inner wall groove, and the width of the rear end of the plug (9) is smaller than that of the groove body thickened section (2); the length of the plug (9) is 35 mm-45 mm;
The width of slot (8) is dwindled by preceding backward gradually, the lateral wall of slot (8) is the lateral wall of ditch body curb plate, the outside bottom surface of slot (8) is the bottom surface of ditch body bottom plate, the left and right sides inside wall of slot (8) is the inclined plane of leanin gradually by preceding to back, the inboard bottom surface of slot (8) is by preceding inclined plane of leanin gradually to the back.
7. The basement construction method based on the fabricated resin concrete drainage ditch according to claim 1 or 2, wherein: in the fourth step, a socket (8) with a concave cross section is arranged on the socket, and a plug (9) which is inserted into the socket (8) and has a concave cross section is arranged on the socket; the slot (8) and the plug (9) are horizontally arranged;
The joint between two adjacent drainage ditch segments (3) in the front and the back is provided with a water swelling water stop strip (10), the joint of the two is hermetically connected through a sealant (12), and the water swelling water stop strip (10) is a concave water stop strip;
Each plug (9) is positioned at the front side of the slot (8) inserted by the plug;
the front end face and the rear end face of the plug (9) are vertical faces, and the front end face and the rear end face of the slot (8) are vertical faces;
the rear end surface of the plug (9) and the rear end surface of the slot (8) are both provided with a water stop strip placing groove (11) for placing a water stop strip (10) capable of expanding when encountering water, and the water stop strip placing groove (11) is a concave groove;
The rear end of the socket section is a spigot, the front end of the socket section is a socket, the rear end of the front end section is a spigot, and the front end of the rear end section is a socket;
When the drainage ditch is assembled in the step 402, according to the layout positions of a plurality of drainage ditch segments (3) in the drainage ditch under construction, the drainage ditch segments (3) are spliced one by one from back to front, and the process is as follows:
Step 4021, rear end section installation: horizontally placing the rear end section of the currently constructed drainage ditch on the inner side of the rear end of the base groove, and tightly attaching the rear end of the currently constructed drainage ditch to the vertical bearing structure positioned on the rear side of the currently constructed drainage ditch;
Step 4022, splicing the next drainage ditch segment: fixing a water swelling water stop strip (10) in a water stop strip placement groove (11) at the rear end of the next spliced drainage ditch segment (3) in the currently constructed drainage ditch, horizontally placing the currently spliced drainage ditch segment (3) in the base groove, and horizontally pushing the currently spliced drainage ditch segment (3) from front to back, so that the socket at the rear end of the currently spliced drainage ditch segment (3) is inserted in the socket at the front end of the drainage ditch segment (3) at the rear side of the currently spliced drainage ditch segment, and simultaneously, the water swelling water stop strip (10) is tightly clamped between the currently spliced drainage ditch segment (3) and the drainage ditch segment (3) at the rear side of the currently spliced drainage ditch segment;
And 4023, repeating the step 4022 one or more times until the splicing process of all drainage ditch segments (3) in the currently constructed drainage ditch is completed, and obtaining the assembled resin concrete drainage ditch.
8. the basement construction method based on the fabricated resin concrete drainage ditch according to claim 7, wherein: the rear end face of the plug (9) and the rear end face of the slot (8) are both provided with a sealing groove (13) for filling the sealant, and the sealing groove (13) is a concave groove and is positioned above the water stop strip placing groove (11); the plug (9) and the sealing groove (13) on the slot (8) are separated from the water stop strip placing groove (11) through concave-shaped baffle strips;
The sealing groove (13) on the plug (9) is arranged along the inner contour line at the rear end of the plug (9) and is communicated with the inner groove, and the sealing groove (13) on the slot (8) is arranged along the inner contour line at the rear end of the slot (8) and is communicated with the inner groove;
Two sealing grooves (13) at the connecting part between two adjacent drainage ditch segments (3) in the front and the back are spliced to form a sealing glue filling seam;
the joint between two adjacent drainage ditch segments (3) at the front and the back is a splicing seam, a joint sealing structure is arranged on the inner side of the splicing seam, the joint sealing structure is positioned on the inner side of the sealant filling seam, and the joint sealing structure is in a concave shape and is arranged along the length direction of the splicing seam; the joint sealing structure comprises glass fiber gridding cloth paved on the inner wall of the prefabricated drainage ditch and a polyurethane coating formed by a layer of polyurethane coating uniformly coated on the glass fiber gridding cloth;
After the concrete surface layer construction is finished in the step five, sealant caulking construction needs to be carried out on the sealant filling seam between two adjacent drainage ditch sections (3) in the assembly type resin concrete drainage ditch; when sealant caulking construction is carried out on the sealant filling joints between the front and rear adjacent drainage ditch segments (3), the sealant filling joints are uniformly filled with sealant and the sealant is tightly filled;
adjacent two in front and back between the escape canal section (3) the sealed glue is filled the seam and is carried out sealed gluey caulking construction back, still need adjacent two in front and back the seam inboard between escape canal section (3) is provided with seam seal structure.
9. The basement construction method based on the fabricated resin concrete drainage ditch according to claim 1 or 2, wherein: the top plate is a basement top plate;
the underground room roof is internally provided with a plurality of concealed pipes and a plurality of junction boxes (25), the concealed pipes are threading pipes pre-buried in the underground room roof, each threading pipe is connected with one junction box (25) through one wire pipe connecting section (26), the threading pipes are electric wire pipes, the threading pipes are connected with the wire pipe connecting sections (26) connected with the threading pipes through connecting joints (30), and each threading pipe is coaxially arranged with the wire pipe connecting sections (26) and the connecting joints (30) connected with the threading pipes; the wire pipe connecting sections (26) are wire pipe sections, the inner ends of the wire pipe connecting sections are inserted into the pipeline holes in the junction boxes (25), the outer ends of the wire pipe connecting sections are connected with the threading pipes, each wire pipe connecting section (26) is welded and fixed with the junction box (25) inserted into the wire pipe connecting section into a whole, each wire pipe connecting section (26) and a connecting joint (30) connected with the outer end of the wire pipe connecting section form a joint-equipped wire pipe connecting section, and each junction box (25) and all joint-equipped wire pipe connecting sections, the inner ends of which are inserted into the junction box, are assembled into an assembled wire pipe;
before the basement top plate is constructed, determining the number of assembled type conduit junction boxes to be arranged in the basement top plate, the number of sections of conduit with joints connected to each assembled type conduit junction box and the arrangement positions of the sections of the conduit with the joints according to the number of pre-designed junction boxes (25) to be buried in the basement top plate, the number of the conduits to be connected to each junction box (25) and the arrangement positions of the conduits, wherein the number of the assembled type conduit junction boxes is the same as the number of the junction boxes (25); then, according to the determined number of the assembled wire tube junction boxes, the number of the wire tube connecting sections with joints connected on each assembled wire tube junction box and the arrangement positions of the wire tube connecting sections with joints, respectively assembling all the assembled wire tube junction boxes to be arranged in the top plate of the basement in a processing field to obtain all the assembled wire tube junction boxes which are assembled and formed;
When the basement roof is constructed, the method comprises the following steps:
Step A1, formwork support: erecting a forming template for constructing the basement top plate;
the forming template comprises a bottom template and a side template, wherein the bottom template is horizontally arranged, and the side template is arranged above the bottom template;
Step A2, binding a reinforcement cage: binding a reinforcement cage arranged in the top plate of the basement to obtain the reinforcement cage formed by binding;
Step A3, arranging the assembled wire tube junction box and the threading tube: uniformly distributing all assembled wire tube junction boxes which are assembled in advance and all wire tubes which are required to be distributed in the basement top plate in the forming template in the step A1 according to the number of the pre-designed junction boxes (25) which need to be embedded in the basement top plate, the distribution positions of all the junction boxes (25), the number of the wire tubes which need to be embedded in the basement top plate, the distribution positions of all the wire tubes and the distribution positions of the junction boxes (25) which are connected with all the wire tubes, and enabling each wire tube to be connected with the wire tube connecting section (26) which is connected with the wire tube connecting section through a connecting joint (30);
Step A4, pouring concrete: and carrying out concrete pouring on the basement top plate to obtain the constructed and molded basement top plate.
10. the basement construction method based on the fabricated resin concrete drainage ditch according to claim 9, wherein: when all the assembled wire tube junction boxes needing to be distributed in the top plate of the basement are assembled in a processing field respectively, the assembling methods of all the assembled wire tube junction boxes are the same;
When any assembled wire tube junction box is assembled, a wire tube is fed into a junction box adjusting mold for assembly;
the threading pipe inlet junction box adjusting mold comprises a base plate (21) which is horizontally arranged, a vertical sleeve (22) which is fixed on the base plate (21), a vertical limiting rod (23) which is fixed on the base plate (21) and is positioned in the vertical sleeve (22), an insertion length limiting part which limits the insertion length of a wire pipe connecting section (26) which is horizontally inserted into the junction box (25), and a wire pipe supporting rod (29) which horizontally supports the wire pipe connecting section (26) and limits the placement position of the wire pipe connecting section (26), wherein the vertical limiting rod (23) is arranged on a central axis of the vertical sleeve (22); each line pipe connecting section (26) is uniformly distributed on one line pipe supporting rod (29), and each line pipe connecting section (26) is distributed along the central axis of the distributed line pipe supporting rod (29); the number of the conduit supporting rods (29) is multiple and is the same as that of the conduit connecting sections (26) which are horizontally inserted into the junction box (25), the conduit supporting rods (29) are horizontally arranged, the inner ends of the conduit supporting rods are fixed at the upper part of the vertical sleeve (22), and the plurality of the conduit supporting rods (29) are the same in structure and size and are all located on the same horizontal plane; a wire releasing groove for horizontally placing one wire pipe connecting section (26) is formed in the wire pipe supporting rod (29), and the wire releasing groove is opposite to a pipeline hole formed in the junction box (25) and used for inserting the wire pipe connecting section (26) placed in the wire releasing groove;
the insertion length limiting part is positioned in the vertical sleeve (22); the insertion length limiting part comprises a limiting sleeve (24) coaxially sleeved on the vertical limiting rod (23) from top to bottom, a horizontal limiting plate (27) fixed on the limiting sleeve (24) and a line pipe limiting plate (28) arranged on the horizontal limiting plate (27), and the limiting sleeve (24) is arranged vertically; the horizontal limiting plate (27) is positioned right above the limiting sleeve (24) and is vertically arranged with the limiting sleeve (24), and the horizontal limiting plate (27) is positioned below the wire laying groove; spool limiting plate (28) are the vertical limiting plate of laying perpendicularly for being with horizontal limiting plate (27), the quantity of spool limiting plate (28) is the same with the quantity of spool branch (29), every the inboard equipartition of spool branch (29) is equipped with one and carries out spacing spool limiting plate (28) to the inner of placing spool linkage segment (26) on this spool branch (29).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811651316.1A CN109629664B (en) | 2018-12-31 | 2018-12-31 | basement construction method based on assembled resin concrete drainage ditch |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811651316.1A CN109629664B (en) | 2018-12-31 | 2018-12-31 | basement construction method based on assembled resin concrete drainage ditch |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109629664A CN109629664A (en) | 2019-04-16 |
CN109629664B true CN109629664B (en) | 2019-12-13 |
Family
ID=66056304
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811651316.1A Active CN109629664B (en) | 2018-12-31 | 2018-12-31 | basement construction method based on assembled resin concrete drainage ditch |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109629664B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110792148A (en) * | 2019-11-06 | 2020-02-14 | 上海建工七建集团有限公司 | Prefabricated reinforced concrete drainage ditch and construction method |
CN113565114A (en) * | 2020-04-29 | 2021-10-29 | 淮安鑫塬铭新材料有限公司 | Resin concrete escape canal |
CN113882863B (en) * | 2021-09-29 | 2024-07-05 | 重庆建工第七建筑工程有限责任公司 | Construction method of underground complex frame shear structure based on BIM technology |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8109046B2 (en) * | 2009-02-19 | 2012-02-07 | Scott Nordhoff | Water drainage device |
US9422708B2 (en) * | 2012-01-23 | 2016-08-23 | Oatey Co. | Floor drain assembly and method |
CN204001146U (en) * | 2014-07-24 | 2014-12-10 | 中国建筑一局(集团)有限公司 | Prefabricated reinforced concrete temporary drainage ditch |
CN206902890U (en) * | 2017-05-25 | 2018-01-19 | 华恒建设集团有限公司 | A kind of basement drainage ditch |
CN207405730U (en) * | 2017-10-20 | 2018-05-25 | 深圳城市建筑装饰工程有限公司 | A kind of discharge structure of basement |
-
2018
- 2018-12-31 CN CN201811651316.1A patent/CN109629664B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN109629664A (en) | 2019-04-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109629664B (en) | basement construction method based on assembled resin concrete drainage ditch | |
KR101331261B1 (en) | Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same | |
CN106759420B (en) | A kind of prefabricated assembled transformer substation foundation structure | |
CN106555408A (en) | The structure and construction method of underground pipe gallery | |
CN111395391B (en) | Construction method for multi-hole rectangular jacking pipe and light and dark excavation joint pipe gallery joint | |
CN114482135B (en) | Advanced water stop structure of basement outer wall post-pouring belt and construction method | |
CN109853625B (en) | Integrated concrete comprehensive pipe gallery connected and assembled in mixed mode | |
KR100808676B1 (en) | Method of constructing for hume pipe underground | |
KR20150141264A (en) | Retaining nature-rock wall and building method thereof | |
CN109695347B (en) | Building construction method based on round steel holding bender | |
US20210017755A1 (en) | Composite wall and methods of constructing a composite wall | |
CN110685234B (en) | Construction method of corrugated steel pipe culvert | |
CN112482436A (en) | A exempt from to tear open water proof formwork system for underground structure side wall | |
CN110821256A (en) | Prefabricated assembled biochemical pool of sewage plant and installation method thereof | |
CN206635786U (en) | Prefabricated assembled transformer substation foundation structure | |
CN110629792A (en) | Splicing construction method for corrugated steel pipe gallery | |
CN105951885B (en) | A kind of assembled work well standard knot and its installation method in new construction | |
KR100462236B1 (en) | panel for external underground wall of building, structure and construction method using the same | |
CN213926387U (en) | Simple plugging structure for reserved sleeve of underground structure outer wall | |
CN113802670A (en) | Assembly type temporary pipeline comprehensive arrangement structure | |
CN208782449U (en) | A kind of cable duct bank | |
CN107100198B (en) | Prefabricated underground pipe gallery of piecing together of type of permeating water | |
KR200275363Y1 (en) | The mold establishment necessit do not exist assembly road water pipe | |
CN212784703U (en) | Modular self-drainage cable trench | |
CN218758236U (en) | Filling wall building block |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |