CN109625196A - 一种海上风电潮间带风电安装施工方法 - Google Patents
一种海上风电潮间带风电安装施工方法 Download PDFInfo
- Publication number
- CN109625196A CN109625196A CN201811272944.9A CN201811272944A CN109625196A CN 109625196 A CN109625196 A CN 109625196A CN 201811272944 A CN201811272944 A CN 201811272944A CN 109625196 A CN109625196 A CN 109625196A
- Authority
- CN
- China
- Prior art keywords
- wind
- barge
- flat top
- deck
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/28—Barges or lighters
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B27/00—Arrangement of ship-based loading or unloading equipment for cargo or passengers
- B63B27/10—Arrangement of ship-based loading or unloading equipment for cargo or passengers of cranes
Abstract
本发明公开了一种海上风电潮间带风电安装施工方法,包括风电安装设备,所述风电安装设备包括吊机、平板驳船、辅助驳船,包括步骤:平板驳船在高潮位时牵引至风力发电施工位置附近;调节延伸甲板的位置,调节配重块,使平板驳船整体重新平衡;打开水阀,启动水泵主动进水,使水仓充水,直至平板驳船坐滩;将辅助驳船运来的风电组件,安放在船体架;安装吊机的吊臂及其配件;浅水状态下,平板驳船水仓启动水泵主动放水,吊装施工。本发明的方法操作方便,具有允许载重大,载重允许范围大,机动性强,抗风潮作用显著,安装流畅的特点,适用于各种潮间带风电施工,简便高效。
Description
技术领域
本发明属于风电施工设备领域,尤其是一种海上风电潮间带风电安装施工方法。
背景技术
随着世界能源格局的变化,不可再生能源价格持续走高,能源和环境问题促使各国不得不加大对可再生能源开发的力度,风电就是可再生能源之一,并且属于清洁能源。
目前正值中国海上风力发电行业大变革、大发展的时代,我国的电力装机结构正逐渐发生变化。但风力发电设备的施工技术和专用设备的研发还处于起步阶段,原有的技术和设备难以满足风力发电行业爆炸性发展的技术需要。
我国潮间带海域广阔,适合建设海上风电场的资源比近海深水段区域更为丰富,但由于潮水涨落起伏的影响,潮间带涨潮时平均水深只有1.5米,建设海上潮间带风电场在世界上没有成功经验可以借鉴。虽然在我国的风力发电设备中,国产化比例已经超过70%,但复杂多变的环境因素,决定了施工船舶的功能及结构的特殊性。
针对潮间带海上施工船舶的安全形势和施工环境的特殊性,本发明开发一种海上风电潮间带风电安装施工方法,为潮间带风电施工提供技术支持。
发明内容
发明目的:本发明提供一种海上风电潮间带风电安装施工方法,以解决现有技术中存在的问题。
发明内容:一种海上风电潮间带风电安装施工方法,包括风电安装设备,所述风电安装设备包括吊机、平板驳船、辅助驳船,所述平板驳船包括主船体和主船体上部连接的上甲板,所述主船体下部为下船体,下船体内开有水仓、侧面开有水阀,水仓内设置有水泵并与水阀连接;所述主船体两侧设置有重量相等的配重块,上甲板上方一侧设置有船体架,所述船体架至少具有两层,所述上甲板中部设置有牵引架,牵引架上开有储缆盘,上甲板在船体架对向一侧嵌合地安装有延伸甲板;延伸甲板上放置吊机,所述吊机一侧具有的辅助支架以牵引绳缠绕连接储缆盘;
所述施工方法包括以下步骤:
(1)、将吊机的吊臂及其配件卸除,平板驳船在高潮位时牵引至风力发电施工位置附近;
(2)、调节延伸甲板的位置,并选择牵引绳固定在储缆盘的位置,调节配重块,使平板驳船整体重新平衡;
(3)、打开水阀,启动水泵主动进水,使水仓充水,直至平板驳船坐滩;
(4)、将辅助驳船运来的风电组件,安放在船体架;安装吊机的吊臂及其配件;
(5)、浅水状态下,平板驳船水仓启动水泵主动放水,吊机对风电组件进行吊装施工。
作为优选,所述延伸甲板下底面与上甲板上底面通过滑动摩擦接触连接。滑动摩擦接触连接可以直接滑动,结构简单,损耗少。
作为优选,所述延伸甲板与上甲板的侧面以“T”型槽、弧形槽或滑轨形式相互配合。以上槽形式的配合使延伸甲板和上甲板的侧面契合度高,配合下部的摩擦接触,传动比较稳定。
作为优选,所述主船体两侧设置有滑动轨,滑动轨配合以滑块,滑块连接配重块,所述配重块两侧向上还设置有锁止销。锁止销使配重块位置固定,完成平衡动作后稳定。
作为优选,步骤(1)中,平板驳船在高潮位时牵引至距离风力发电施工位置中心2~10m处。牵引的位置方便施工操作,同时与延伸甲板伸出上甲板的距离对应。
作为优选,所述平板驳船的规格,长度不小于60m,宽度不小于25m。平板驳船的规格布局使其具有较好的施工操作性和机动性。
进一步,所述延伸甲板伸出上甲板的距离为0-8m。该距离方便施工操作时的进动调节,使与平板驳船在高潮位时牵引至距离风力发电施工位置中心距离对应。
和现有技术相比,本发明的有益效果在于:本发明的一种海上风电潮间带风电安装施工方法,结构准确,步骤条理清楚,安装层次性鲜明。水阀和水泵的设置位置合理,方便引水和排水操作;船体架的设置具有方便放置和安装固定的效果;配重块的设置便于调节整体的平衡;延伸甲板使操作具有更高的灵活性;牵引架、辅助支架、储缆盘的配合使用方便吊机的上下安装和作业,调节方便。本发明的方法操作方便,具有允许载重大,载重允许范围大,机动性强,抗风潮作用显著,安装流畅的特点,适用于各种潮间带风电施工,简便高效。
附图说明
图1是本发明的平板驳船总体结构示意图,图2是本发明的辅助驳船总体结构示意图。
图中:1-平板驳船,101-滑动轨,102-配重块,103-锁止销,11-主船体,12-上甲板,13-下船体,130-水仓,131-水阀,132-水泵,14-船体架,15-牵引架,151-储缆盘,16-延伸甲板,2-辅助驳船,3-吊机,4-牵引绳。
具体实施方式
为了更清楚地说明本申请实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单的介绍。
如图1,一种海上风电潮间带风电安装施工方法,包括风电安装设备,所述风电安装设备包括吊机3、平板驳船1、辅助驳船2,所述平板驳船1包括主船体11和主船体11上部连接的上甲板12,所述主船体11下部为下船体13,下船体13内开有水仓130、侧面开有水阀131,水仓130内设置有水泵132并与水阀131连接;所述主船体11两侧设置有滑动轨101和重量相等的配重块102,滑动轨101配合以滑块,滑块连接配重块102,所述配重块102两侧向上还设置有锁止销103;
上甲板12上方一侧设置有船体架14,所述船体架14至少具有两层,所述上甲板12中部设置有牵引架15,牵引架15上开有储缆盘151,上甲板12在船体架14对向一侧嵌合地安装有延伸甲板16,所述延伸甲板16与上甲板12的侧面以“T”型槽、弧形槽或滑轨形式相互配合,所述延伸甲板16下底面与上甲板12上底面通过滑动摩擦接触连接;延伸甲板16上放置吊机3,所述吊机3一侧具有的辅助支架31以牵引绳4缠绕连接储缆盘151;
其中,所述平板驳船1的规格,长度不小于60m,宽度不小于25m;所述延伸甲板16伸出上甲板12的距离为0-8m;
所述辅助驳船2,三个维度尺寸均小于平板驳船1,基本结构与平板驳船1相似,但没有滑动轨、配重块、锁止销,无延伸甲板、储缆盘、牵引绳等连接吊机的配件;
所述施工方法包括以下步骤:
(1)、将吊机3的吊臂及其配件卸除,平板驳船1在高潮位时牵引至风力发电施工位置附近,具体为距离风力发电施工位置中心2~10m处;
(2)、调节延伸甲板16的位置,并选择牵引绳4固定在储缆盘151的位置,调节配重块102,使平板驳船1整体重新平衡;
(3)、打开水阀131,启动水泵132主动进水,使水仓充水,直至平板驳船1坐滩;
(4)、将辅助驳船2运来的风电组件,安放在船体架14;安装吊机3的吊臂及其配件;
(5)、浅水状态下,平板驳船1的水仓130启动水泵132主动放水,吊机3对风电组件进行吊装施工。
最后,还需要说明,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。
Claims (7)
1.一种海上风电潮间带风电安装施工方法,其特征在于,包括风电安装设备,所述风电安装设备包括吊机、平板驳船、辅助驳船,所述平板驳船包括主船体和主船体上部连接的上甲板,所述主船体下部为下船体,下船体内开有水仓、侧面开有水阀,水仓内设置有水泵并与水阀连接;所述主船体两侧设置有重量相等的配重块,上甲板上方一侧设置有船体架,所述船体架至少具有两层,所述上甲板中部设置有牵引架,牵引架上开有储缆盘,上甲板在船体架对向一侧嵌合地安装有延伸甲板;延伸甲板上放置吊机,所述吊机一侧具有的辅助支架以牵引绳缠绕连接储缆盘;
所述施工方法包括以下步骤:
(1)、将吊机的吊臂及其配件卸除,平板驳船在高潮位时牵引至风力发电施工位置附近;
(2)、调节延伸甲板的位置,并选择牵引绳固定在储缆盘的位置,调节配重块,使平板驳船整体重新平衡;
(3)、打开水阀,启动水泵主动进水,使水仓充水,直至平板驳船坐滩;
(4)、将辅助驳船运来的风电组件,安放在船体架;安装吊机的吊臂及其配件;
(5)、浅水状态下,平板驳船水仓启动水泵主动放水,吊机对风电组件进行吊装施工。
2.根据权利要求1所述的一种海上风电潮间带风电安装施工方法,其特征在于,所述延伸甲板下底面与上甲板上底面通过滑动摩擦接触连接。
3.根据权利要求2所述的一种海上风电潮间带风电安装施工方法,其特征在于,所述延伸甲板与上甲板的侧面以“T”型槽、弧形槽或滑轨形式相互配合。
4.根据权利要求1所述的一种海上风电潮间带风电安装施工方法,其特征在于,所述主船体两侧设置有滑动轨,滑动轨配合以滑块,滑块连接配重块,所述配重块两侧向上还设置有锁止销。
5.根据权利要求1所述的一种海上风电潮间带风电安装施工方法,其特征在于,步骤(1)中,平板驳船在高潮位时牵引至距离风力发电施工位置中心2~10m处。
6.根据权利要求1所述的一种海上风电潮间带风电安装施工方法,其特征在于,所述平板驳船的规格,长度不小于60m,宽度不小于25m。
7.根据权利要求5所述的一种海上风电潮间带风电安装施工方法,其特征在于,所述延伸甲板伸出上甲板的距离为0-8m。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811272944.9A CN109625196A (zh) | 2018-10-30 | 2018-10-30 | 一种海上风电潮间带风电安装施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811272944.9A CN109625196A (zh) | 2018-10-30 | 2018-10-30 | 一种海上风电潮间带风电安装施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109625196A true CN109625196A (zh) | 2019-04-16 |
Family
ID=66066780
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811272944.9A Pending CN109625196A (zh) | 2018-10-30 | 2018-10-30 | 一种海上风电潮间带风电安装施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109625196A (zh) |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101318542A (zh) * | 2008-05-16 | 2008-12-10 | 中国海洋石油总公司 | 一种风电机组海上整体安全运输的方法 |
CN101513923A (zh) * | 2009-04-03 | 2009-08-26 | 上海电力设计院有限公司 | 潮间带风力发电设备施工吊装方法及潮间带专用工程驳船 |
CN102101521A (zh) * | 2009-12-17 | 2011-06-22 | 江苏龙源风力发电有限公司 | 海上潮间带风电施工设备 |
CN102530194A (zh) * | 2010-12-25 | 2012-07-04 | 叶伦志 | 吊运船 |
KR20120113013A (ko) * | 2011-04-04 | 2012-10-12 | 삼성중공업 주식회사 | 해상풍력발전기 설치선박 및 이를 이용한 해상풍력발전기 설치방법 |
CN202559412U (zh) * | 2012-04-25 | 2012-11-28 | 浙江海洋学院 | 新型海洋挖泥船 |
CN202754109U (zh) * | 2012-07-03 | 2013-02-27 | 珠海天岳科技有限公司 | 一种带伸缩装置的船舶 |
JP2017166169A (ja) * | 2016-03-15 | 2017-09-21 | 鹿島建設株式会社 | 構造物の施工方法および作業台船 |
CN107237722A (zh) * | 2017-05-26 | 2017-10-10 | 江苏华西村海洋工程服务有限公司 | 一种海上风电施工工艺 |
CN107512366A (zh) * | 2017-07-28 | 2017-12-26 | 安徽信息工程学院 | 用于船舶的传输机 |
-
2018
- 2018-10-30 CN CN201811272944.9A patent/CN109625196A/zh active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101318542A (zh) * | 2008-05-16 | 2008-12-10 | 中国海洋石油总公司 | 一种风电机组海上整体安全运输的方法 |
CN101513923A (zh) * | 2009-04-03 | 2009-08-26 | 上海电力设计院有限公司 | 潮间带风力发电设备施工吊装方法及潮间带专用工程驳船 |
CN102101521A (zh) * | 2009-12-17 | 2011-06-22 | 江苏龙源风力发电有限公司 | 海上潮间带风电施工设备 |
CN102530194A (zh) * | 2010-12-25 | 2012-07-04 | 叶伦志 | 吊运船 |
KR20120113013A (ko) * | 2011-04-04 | 2012-10-12 | 삼성중공업 주식회사 | 해상풍력발전기 설치선박 및 이를 이용한 해상풍력발전기 설치방법 |
CN202559412U (zh) * | 2012-04-25 | 2012-11-28 | 浙江海洋学院 | 新型海洋挖泥船 |
CN202754109U (zh) * | 2012-07-03 | 2013-02-27 | 珠海天岳科技有限公司 | 一种带伸缩装置的船舶 |
JP2017166169A (ja) * | 2016-03-15 | 2017-09-21 | 鹿島建設株式会社 | 構造物の施工方法および作業台船 |
CN107237722A (zh) * | 2017-05-26 | 2017-10-10 | 江苏华西村海洋工程服务有限公司 | 一种海上风电施工工艺 |
CN107512366A (zh) * | 2017-07-28 | 2017-12-26 | 安徽信息工程学院 | 用于船舶的传输机 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103967713B (zh) | 基于浮式张力腿平台的风能-波浪能集成发电结构 | |
Edwards et al. | Evolution of floating offshore wind platforms: A review of at-sea devices | |
US20200128798A1 (en) | Floating integrated system of breakwater and wind energy for deep-sea aquaculture | |
CN205822138U (zh) | 一种海上风电浮式防撞护舷结构 | |
CN102155352B (zh) | 漂浮式水上风力发电设备 | |
Bachynski et al. | Point absorber design for a combined wind and wave energy converter on a tension-leg support structure | |
CN203161445U (zh) | 海洋能综合发电及氢能生产的装置 | |
CN111469992A (zh) | 一种具有阻尼效应的漂浮式海上风电结构基础及控制稳定性方法 | |
US20020067043A1 (en) | System for conversion of wave energy | |
CN103133249B (zh) | 漂浮支撑装置和风力发电机组 | |
CN212243735U (zh) | 一种具有阻尼效应的漂浮式海上风电结构基础 | |
CN207089600U (zh) | 可自浮安装的张力腿式海上浮动风机基础 | |
CN102146873A (zh) | 具有周向稳定柱的单柱式海上风力发电装置 | |
CN203039614U (zh) | 海上漂浮型太阳能光伏发电装置 | |
CN104627331A (zh) | 一种风力发电浮式基础 | |
CN109488518A (zh) | 一种基于海上风机单桩平台的风能波浪能综合发电装置及发电方法 | |
KR101262089B1 (ko) | 기상타워 및 풍력 발전기의 해상 설치방법 | |
CN109625196A (zh) | 一种海上风电潮间带风电安装施工方法 | |
Lian et al. | Integrated transportation of offshore wind turbine and bucket foundation based on a U and K shaped assembled platform | |
CN202807056U (zh) | 风能浮动提取平台 | |
CN102146682B (zh) | 一种螃蟹式的海洋潮流能发电海底固定装置及方法 | |
CN207998856U (zh) | 一种海上风机浮式基础 | |
CN105221346B (zh) | 海上移动式风力发电系统 | |
CN208364303U (zh) | 一种光伏与风机联合发电的海上半潜式平台发电系统 | |
CN209274844U (zh) | 一种用于潮间带风电施工的平板驳船 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190416 |