Summary of the invention
In view of the above problems, the present invention is intended to provide car trim totally enclosed type lacquer spraying technique, the present invention from
The technique and the structure in technical process of spray painting improve simultaneously, and it is poor to solve painting environment of the existing technology, ring
Guaranteed cost is low, spray painting low efficiency, painting quality be low and coating cloud cannot thorough efficient absorption the problem of.
To achieve the goals above, the technical solution adopted in the present invention is as follows:
Car trim totally enclosed type lacquer spraying technique, comprising the following steps:
1) commissioning device: debugging primer painting room, UV hothouse one, inspection chamber, coating chamber, an electrostatic precipitation room,
Secondary basecoat spray booth, UV hothouse two, secondary electrostatic precipitation room, finishing coat spray booth, UV hothouse three;
2) be surface-treated: by product with air gun purge surface, then use carbon dioxide wipe product surface, into priming paint before outside
Portion first carries out electrostatic precipitation to product surface;
3) a primer painting: by adjusting robot program, primer painting is carried out, priming paint is painted on enclosed primary bottom
Paint booth is painted to complete;
4) primary drying: it is dry that UV is preheated after the completion of a primer painting, it is ensured that energy and time;
5) check: the stage checks in inspection chamber carries out appearance, rejects substandard products;
6) plated film: completing in coating chamber, and product, which is hung on, carries out plated film in the coating machine of coating chamber;
7) the PVD coated component after plated film an electrostatic precipitation: is installed on fixture simultaneously electrostatic precipitation;
8) secondary primer painting: robot sets painting, and a product surface after electrostatic precipitation carries out two
Secondary operation of priming;
9) redrying: carrying out redrying in UV hothouse two, and dry object remains as the product after priming;
10) secondary electrostatic precipitation equally secondary electrostatic precipitation: is carried out to the product of redrying;
11) spraying of product finishing coat coating finish: is carried out in finishing coat spray booth;
12) it dries three times: carrying out the final drying after finishing coat coating in UV hothouse three;
13) it examines and packs.
Preferably, a primer painting room, UV hothouse one, inspection chamber, coating chamber, an electrostatic precipitation room,
Secondary basecoat spray booth, UV hothouse two, secondary electrostatic precipitation room, finishing coat spray booth, UV hothouse three set gradually a row,
It is corresponding in each sealing chamber that respective production equipment, a primer painting are installed using the sealing chamber of transparence
Room, UV hothouse one, inspection chamber, coating chamber, an electrostatic precipitation room, secondary basecoat spray booth, UV hothouse two, secondary electrostatic
Dirt pocket, finishing coat spray booth, UV hothouse form the production line of a whole sealing chamber, together with setting between sealing chamber, and the
One sealing chamber between a last sealing chamber be arranged an automatic transportation line.
Preferably, the structure phase of a primer painting room, secondary primer painting room and finishing coat paint booth three
Together, include transparent sealing chamber, robotic spray gun, inhale mist device and catch basin, the robotic spray gun, automatic transportation
Line is located above catch basin, and induction type rotator is arranged in catch basin.
Preferably, the suction mist device is arranged at robot spray head upper end 20-30cm.
Preferably, the suction mist device includes settling drum, umbrella shape mist arrester, water-feed and lifter, the arrangement
Cylinder top is fixed on the ceiling of the sealing chamber, and the umbrella shape mist arrester is located at the robot by the lifter
At spray head, the fuselage of the water-feed and the robot is each provided in the settling drum, and the water-feed is to the umbrella shape
Mist arrester water spray.
Preferably, the umbrella shape mist arrester includes if that dry plate sector inhales mist piece and round cage plate, the circle cage plate
It is fixedly attached to the bottom end of the settling drum, partial intersection setting between every two adjacent fan-shaped suction mist piece, and every institute
Fan-shaped mist piece top of inhaling is stated to connect with the round cage plate rotation.
Preferably, the every fan-shaped mist piece of inhaling is aluminum plate, and thickness 2-5mm, and sector suction mist piece is squeezed into
Section is wavy shaped configuration.
Preferably, vertical suction mist piece is also hung in the every fan-shaped bottom for inhaling mist piece.
Preferably, the lifter includes motor, a head pulley, several auxiliary pulley and several halliards, it is a piece of
Sector inhales the corresponding auxiliary pulley of mist piece, and several auxiliary pulley are equally distributed on the periphery of the settling drum, described in every
Sector inhales the mist piece back side and connects a halliard, and the head pulley is fixed in the settling drum, the halliard bottom end
The fan-shaped suction mist piece is connected, top is connected on head pulley by binding yarn cylinder, and then is connected to motor, motor control halliard
Lifting, and then fan-shaped mist piece of inhaling is driven to open or tighten to automatically adjust the space size for inhaling fog-zone domain.
Preferably, the water-feed includes main-supply and several angled water jet pipes, several angled water jet pipes
Radiation is arranged in the round cage plate bottom, a circle angled water jet pipe along the inner wall that sector described in every inhales mist piece, often
A angled water jet tube end is respectively provided with fountain head, fountain head by water spray and along the suction mist piece inner wall of sector described in every to
Lower flowing, the water flowed down enter catch basin and carry out centralized collection.
The beneficial effects of the present invention are:
Improvement of the invention is one totally enclosed production line of design first, is directed to the spray painting setting of car trim, will spray
Each committed step of paint is placed in enclosed operating room and completes, and connection, facilitates operator's debugging and maintenance inside sealing chamber,
When clamping product is placed in tooling after exclusive fixture, tooling is arranged on automatic transportation line, an automation fortune
Always through the entire production line, using above-mentioned production line, environmental-protecting performance improves defeated line, and the painting quality of product improves, spray
The efficiency of paint also improves, and labor intensity greatly reduces, and saves cost of labor;
Secondly, improvement of the invention also resides in, the finishing coat operations improvement is added to be in the priming paint that car trim paints, a priming paint,
Secondary priming paint adds finishing coat, and intermediate every step also adds electrostatic precipitation and drying process, existing unification priming paint is improved to two
Secondary basecoat paint, its advantage is that the coating quality of priming paint is improved, spraying effect of the finishing coat on priming paint is also further mentioned
Height totally improves the painting quality of car trim;
Again, the present invention improves the suction mist structure in painting process, devises umbrella shape mist arrester, umbrella shape mist arrester is not only
It can be realized enclosed and thoroughly inhale mist purpose, and can also carry out inhaling the automation tune of mist area size for products of different specifications
Section, reasonable in design, it is convenient to operate, easy to adjust.
Embodiment
Car trim totally enclosed type lacquer spraying technique, comprising the following steps:
1) commissioning device: debugging primer painting room, UV hothouse one, inspection chamber, coating chamber, an electrostatic precipitation room,
Secondary basecoat spray booth, UV hothouse two, secondary electrostatic precipitation room, finishing coat spray booth, UV hothouse three;
Primer painting room, UV hothouse one, inspection chamber, coating chamber, an electrostatic precipitation room, secondary basecoat paint
Room, UV hothouse two, secondary electrostatic precipitation room, finishing coat spray booth, UV hothouse three set gradually a row, and what is be all made of is transparent
The sealing chamber of change, it is corresponding in each sealing chamber that respective production equipment, a primer painting room, UV hothouse are installed
One, inspection chamber, coating chamber, an electrostatic precipitation room, secondary basecoat spray booth, UV hothouse two, secondary electrostatic precipitation room, finishing coat
Spray booth, UV hothouse form the production line of a whole sealing chamber, and the targeted technique of the production line is PVD production technology,
Together with setting between sealing chamber, and first sealing chamber is to being arranged an automatic transportation line between a last sealing chamber;
Primer painting room, UV hothouse one, inspection chamber, coating chamber, an electrostatic precipitation room, secondary basecoat spray booth, UV
Hothouse two, finishing coat spray booth, in UV hothouse, is respectively provided with channel between every two is closed at secondary electrostatic precipitation room, convenient
Worker's installation and debugging;
2) be surface-treated: by product with air gun purge surface, then use carbon dioxide wipe product surface, into priming paint before outside
Portion first carries out electrostatic precipitation to product surface;Before putting into production line, in a primer painting outdoor setting pretreatment
Room is surface-treated product in pretreatment chamber, and concrete operation step is to immerse white spirit, wipe product table with electrostatic cloth
Face, manual oil removing, dedusting are mounted on the component (fixture installation) on fixture, duration: 5 seconds according to specified quantity and spacing;It connects
With air gun purge product surface, then use CO2Airblast product, duration: 25 seconds, into before priming paint, electrostatic precipitation, it is ensured that
Product surface free from admixture, duration: 20 seconds;
3) a primer painting: by adjusting robot program, primer painting is carried out, priming paint is painted on enclosed primary bottom
It paints paint booth to complete, it is ensured that film thickness reaches standard;Thickness: 8-25um, duration: 150 seconds;
Referring to shown in attached drawing 1-8, a primer painting room includes transparent sealing chamber 1, robotic spray gun 2, inhales mist device
And catch basin 3, the robotic spray gun 2, automatic transportation line 4 are located above catch basin 3, catch basin 3 is circular configuration, from
Dynamicization supply line 4 is located at 3 top of catch basin, and induction type rotator is arranged in catch basin 3, when the fixture equipped with product is transported to sense
When answering formula rotor-position, 10-15cm is increased in the controller of induction type rotator, starts to carry out corresponding operation, the suction
Mist device is set in the robot, and the robot is surrounded, at robot spray head upper end 20-30cm described in setting
Inhale mist device.
Specifically, the suction mist device includes settling drum 6, umbrella shape mist arrester 7, water-feed 8 and lifter 9, it is described whole
Reason 6 top of cylinder is fixed on the ceiling of the sealing chamber 1, and settling drum 6 can be bending cylinder, vertical cylinder or arc tube, angle
Degree moves towards design according to the structure of paint-spray robot, and robot fuselage is extended downwardly out by bending cylinder, and bending cylinder is wrapped around
On robot fuselage, and the internal diameter of bending cylinder can be such that 2 robot fuselages pass through, and the space having more is for placing other
Equipment, the umbrella shape mist arrester 7 is located at the spray head of the robot by the lifter 9, the water-feed 8 with it is described
The fuselage of robot is each provided in the settling drum 6, and the water-feed 8 is sprayed water to the umbrella shape mist arrester 7, in settling drum 6
Space be enough that robot fuselage, water-feed 8 and lifter 9 are arranged simultaneously, settling drum 6 is divided into three by demarcation plate 10
Point, the fuselage, water-feed 8 and lifter 9 that the paint-spray robot is set are respectively corresponded in three parts.
Specifically, the umbrella shape mist arrester 7 includes if that dry plate sector inhales mist piece 71 and round cage plate 72, the round set
Plate 72 is fixedly attached to the bottom end of the settling drum 6, and partial intersection is arranged between every two adjacent fan-shaped suction mist piece 71, and every two
It is interspersed setting between a, and every fan-shaped 71 top of mist piece of inhaling is connected with the round rotation of cage plate 72, often
Sector described in piece inhales mist piece 71 and is articulated and connected by hinge and the round cage plate 72, and the every fan-shaped mist piece 71 of inhaling is aluminum
It is wavy shaped configuration that plate, thickness 2-5mm, and the sector, which inhale mist piece 71 to be squeezed into section, and the every sector inhales mist piece 71
Also hang vertical suction mist piece 73 in bottom.Shackle is arranged in vertical 73 top of suction mist piece, on fan-shaped suction 71 bottom edge of mist piece
It is machined with annular distance, the vertical suction mist piece 73 is by shackle and annular distance hanging in fan-shaped suction 71 bottom of mist piece;It is vertical to inhale mist
Piece 73 is located at the top of automatic transportation line 4, the structure design of umbrella shape mist arrester 7 can according to the size of practical spray painting product come
Opening size inside adjust automatically umbrella shape, to meet the spray painting requirement of different car trims, such as automobile handle decoration knot
Structure is small and exquisite, is fixed in the tooling of automatic transportation line 4 after being clamped on exclusive fixture 5, required spray gun area with regard to small,
And the structure size of vehicle air conditioning outlet is bigger, clamping rear area occupied on exclusive fixture 5 is larger, the spray painting face needed
With regard to larger, the space of the umbrella shape mist arrester 7 needed at this time will expand, and the fan-shaped of umbrella shape mist arrester 7 of the invention inhales mist piece
71 can open and shrink automatically, be used with adapting to the car trim spray painting of different dimensions, the present invention is by traditional wall
Wall type mist of oil Xi Wu mechanism is improved to umbrella shape enclosed and inhales mist structure, and suction mist is direct, and quickly, the effect for inhaling mist is good, thoroughly, spray painting
Environment-friendly type is strong in the process.
Specifically, the lifter 9 includes 91, head pulleys 92 of motor, several auxiliary pulley 93 and several halliards
94, a piece of fan-shaped mist piece 71 of inhaling corresponds to an auxiliary pulley 93, and several auxiliary pulley 93 are equally distributed on the outer of the settling drum 6
Zhou Shang, every fan-shaped 71 back side of mist piece of inhaling connect a halliard 94, and the head pulley 92 is fixed on the arrangement
In cylinder 6,94 bottom end of the halliard connection fan-shaped suction mist piece 71, top is connected on head pulley 92 by binding yarn cylinder 95,
And then connect with motor 91, motor 91 controls the lifting of halliard 94, and then the fan-shaped suction mist piece 71 of drive is opened or tightening comes from
It is dynamic to adjust the space size for inhaling fog-zone domain.Sector inhales 71 back side of mist piece and annulus 711 is arranged, and halliard 94 is cord, halliard 94
Bottom end be connected in annulus 711, a circle pulley groove is set on 6 periphery of settling drum, auxiliary pulley 93 is slidably arranged in pulley groove,
Lower cord hole is also set up on settling drum 6, lower cord hole is located at 93 upper end of auxiliary pulley, and halliard 94 passes through auxiliary pulley 93, using lower rope
Hole enters inside settling drum 6, connects binding yarn cylinder 95 by reinforcing rib inside settling drum 6, a circle is from the multiple of auxiliary pulley 93
Halliard 94 is integral by synthesizing after binding yarn cylinder 95, becomes rope strand, upper cord hole, upper cord hole position are also set up on settling drum 6
In lower cord hole upper end, and it is located in the opposite of lower cord hole, rope strand is connect with motor 91 together, and motor 91 is rotated forward multiple sectors
Suction 71 pull-up of mist piece determines the fan-shaped size of dehiscing for inhaling mist piece 71 according to the size of actual product, arrives properly when dehiscing to adjust
Behind position, button 11 is set on sealing chamber side wall, closing motor 91 by button 11 can be with, button 11 control motor unlatching and
It closes, conversely, motor 91 inverts, sector is inhaled mist piece 71 and shunk, and it is exactly every two panels fan that sector, which inhales the maximum position that mist piece 71 opens,
Shape is inhaled does not intersect between mist piece 71.
Specifically, the water-feed 8 includes main-supply 81 and several angled water jet pipes 82, several angled water jets
The radiation of pipe 82 is inhaled in mist piece 71 in 72 bottom of the round cage plate, a circle angled water jet pipe 82 along sector described in every
Wall setting, each 82 end of angled water jet pipe are respectively provided with fountain head 83, and water is sprayed and along described in every by fountain head 83
Sector inhales 71 inner wall of mist piece and flows downward, and the water flowed down enters catch basin 3 and carries out centralized collection;Tilting sparge pipe is obliquely
Setting, fountain head 83 are arranged obliquely, and intensive hole for water spraying is arranged on fountain head 83, inhale mist piece 71 to sector by hole for water spraying
Inner surface is constantly sprayed water, and water flow can inhale the slowly flowing downwards of mist piece 71 along sector, directly by machine during flowing downward
The extra coating cloud of device people spray gun 2 ejections absorbs, which absorbs in time, quickly and efficiently, and designs in this and supplies water
Device 8, either umbrella shape mist arrester 7, which are adjusted, arrives much sizes, and water flow can be all injected on the fan-shaped inner surface for inhaling mist piece 71, be supplied water
Device 8 is connect with external water tank, is designed the pressure of fountain head 83, is injected in the water flow pressure of fountain head 83 just smoothly
Sector is inhaled on 71 inner surface of mist piece, without sputtering outward;
4) primary drying: it is dry that UV is preheated after the completion of a primer painting, it is ensured that energy and time;Energy: 1000-1300mj/
cm²;Duration: 10 seconds;
5) check: the stage checks in inspection chamber carries out appearance, rejects substandard products;
6) plated film: completing in vacuum film coating chamber, and smelting furnace is filled, and product, which is hung on, carries out plated film in the coating machine of coating chamber;
7) the PVD coated component after plated film an electrostatic precipitation: is installed on fixture simultaneously electrostatic precipitation;Duration: 20 seconds;
8) secondary primer painting: robot sets painting, and a product surface after electrostatic precipitation carries out two
Secondary operation of priming;The structure of primer painting room, secondary primer painting room and finishing coat paint booth three is identical;No
Same is the type of priming paint, and the priming paint of coating is passed through priming paint, and the spray gun for passing through robot in mechanical hand according to actual needs
Head is automatic to be sprayed;8 ~ 20um thickness;Duration 10 seconds;
9) redrying: carrying out redrying in UV hothouse two, and dry object remains as the product after priming;700-
900mj/cm2 energy, duration 10 seconds;
10) secondary electrostatic precipitation equally secondary electrostatic precipitation: is carried out to the product of redrying;UV hothouse after drying,
Exclusive fixture 5 flows to secondary electrostatic precipitation room automatically under the drive of automatic transportation line 4 and carries out secondary electrostatic precipitation;Duration 20
Second;
11) spraying of product finishing coat coating finish: is carried out in finishing coat spray booth;Primer painting room, secondary priming paint
The structure of paint booth and finishing coat paint booth three are identical;Unlike finishing coat material and once prime, secondary prime
It is different, target face paint is packed into robot according to the requirement of practical finishing coat coating;Same exclusive 5 automatic flowing of fixture is to face
Paint paint spray booth position, progress topcoating operation, 8 ~ 25um thickness, duration 10 seconds;
12) it dries three times: carrying out the final drying after finishing coat coating in UV hothouse three;Drying condition: 1000-1300mj/
cm2, duration 10 seconds;
13) it examines and packs: fabricated part being moved into final inspection and packaging, while randomly choosing 5 from every batch of internal lab
A part carries out functional test, checks appearance according to test stone, then packs product according to packing specification, and by qualified portion
Part moves into shipment warehouse.
Improvement of the invention is one totally enclosed production line of design first, is directed to the spray painting setting of car trim,
Each committed step of spray painting is placed in enclosed operating room to complete, is connected to inside sealing chamber 1, operator is facilitated to debug
Maintenance, when clamping product is placed in tooling after exclusive fixture 5, tooling is arranged on automatic transportation line 4, and one certainly
Always through the entire production line, using above-mentioned production line, environmental-protecting performance improves dynamicization supply line 4, the painting quality of product
It improves, the efficiency of spray painting also improves, and labor intensity greatly reduces, and saves cost of labor;
Secondly, improvement of the invention also resides in, the finishing coat operations improvement is added to be in the priming paint that car trim paints, a priming paint,
Secondary priming paint adds finishing coat, and intermediate every step also adds electrostatic precipitation and drying process, existing unification priming paint is improved to two
Secondary basecoat paint, its advantage is that the coating quality of priming paint is improved, spraying effect of the finishing coat on priming paint is also further mentioned
Height totally improves the painting quality of car trim;
Again, the present invention improves the suction mist structure in painting process, because inhaling mist structure is in painting process than heavier
The structure wanted will certainly generate the more coating cloud not being utilized in robot painting process, if these coating clouds are too late
When be collected processing if can not only pollute influence to the environment of paint spray booth, but also be unfavorable for coating cloud and collect faster
Processing application, will cause the waste of material, although the existing suction mist having using cascade structure, structure is designed to be tied from spray painting
Farther out, while cascade is single-sided structure to structure, can only absorb the coating cloud close to the cascade side, not thorough enough to the absorption of coating cloud,
Therefore, the present invention devises umbrella shape mist arrester 7, and umbrella shape mist arrester 7 can not only realize that enclosed thoroughly inhales mist purpose, but also
The automation that mist area size can be carried out inhaling for products of different specifications is adjusted, reasonable in design, operates convenient, adjusting side
Just.
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of the industry
Personnel are it should be appreciated that the present invention is not limited to the above embodiments, and the above embodiments and description only describe this
The principle of invention, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these changes
Change and improvement all fall within the protetion scope of the claimed invention.The claimed scope of the invention by appended claims and its
Equivalent thereof.