CN109610447A - Connecting beam structure of pile top of double-row type steel cement soil mixing pile - Google Patents

Connecting beam structure of pile top of double-row type steel cement soil mixing pile Download PDF

Info

Publication number
CN109610447A
CN109610447A CN201811578737.6A CN201811578737A CN109610447A CN 109610447 A CN109610447 A CN 109610447A CN 201811578737 A CN201811578737 A CN 201811578737A CN 109610447 A CN109610447 A CN 109610447A
Authority
CN
China
Prior art keywords
concrete slab
type steel
pile
row type
beam structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811578737.6A
Other languages
Chinese (zh)
Inventor
宋志强
马凯青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201811578737.6A priority Critical patent/CN109610447A/en
Publication of CN109610447A publication Critical patent/CN109610447A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A connecting beam structure of a pile top of a double-row type steel cement soil mixing pile is composed of an upper reinforced concrete plate and a lower reinforced concrete plate, wherein an isolation layer is arranged between the lower reinforced concrete plate and the internal section steel of the mixing pile; the lower reinforced concrete plate is wrapped in the upper reinforced concrete plate. The invention can form a consolidation node on the pile top of the mixing pile, fully exert the mechanical properties of large rigidity and small deformation of the double-row pile, reduce the displacement deformation of the supporting structure and avoid influencing the extraction of the section steel after the supporting is finished.

Description

A kind of coupling beam structure of double row type steel cement mixing method stake top
Technical field:
The invention belongs to building engineering field, in particular to a kind of coupling beam knot of double row type steel cement mixing method stake top Structure.
Background technique:
Fashioned iron cement mixing method is often used in architectural engineering pit supporting, and it is commonly used be Single row pillars branch Shield form.When using the cement mixing method supporting of double row type steel, the crown beam knot of conventional single fashioned iron Soil-cement stake top Structure will be unable to that crown beam and support pile is made to form consolidated node, (usually adopt this is because crown beam must be effectively isolated between fashioned iron It is isolated with the plank sheathing of foamed plastics or thickness 10mm or so), to extract fashioned iron after supporting terminates, and because isolation produces Raw gap will make to produce relative sliding displacement between fashioned iron and crown beam, therefore be unable to reach the effect of consolidation.When can not be formed When consolidated node, double-row pile will generate biggish displacement deformation as supporting construction.
Fashioned iron will be first with crown beam as the jack base for loosening fashioned iron when extracting, therefore crown beam is that fashioned iron soil cement stirs Mix one of essential component part of stake (crown beam while having both other function).
Currently, there is end item foundation pit using the cement mixing method supporting of double row type steel, coupling beam still uses traditional The crown beam of Single row pillars and the connection type of fashioned iron, do not efficiently solve this problem.
Summary of the invention:
It is an object of the invention to overcome the defect of existing crown beam Yu fashioned iron type of attachment, a kind of double row type molten steel mud is provided The coupling beam structure of soil stirring stake top, the coupling beam structure can both make to stir stake top formation consolidated node, give full play to double-row pile The mechanical property that rigidity is big, deformation is small, reduces the displacement deformation of supporting construction, and does not influence the extraction of fashioned iron after supporting.
As above design, the present invention is achieved by the following technical solutions:
A kind of coupling beam structure of double row type steel cement mixing method stake top, is made of upper and lower two parts armoured concrete slab, Separation layer is housed, upper reinforcement concrete slab is by the two blocks of reinforcing bars in left and right in lower rebar concrete slab and mixing pile between fashioned iron The overall structure that concrete slab is formed by connecting by reinforced concrete coupling beams, upper reinforcement concrete slab and fashioned iron in mixing pile are straight Contact pours into overall structure;Lower rebar concrete slab is wrapped in upper reinforcement concrete slab.
Above-mentioned upper reinforcement concrete slab will turn under two sides and wrap up lower rebar concrete slab.
Flexible material separation layer is housed between above-mentioned upper and lower two parts armoured concrete slab.
Above-mentioned lower rebar concrete slab is the cast-in-situ reinforced concrete slab of a monolith thickness 200mm.
Two pieces of the left and right armoured concrete slab of above-mentioned upper reinforcement concrete slab is with a thickness of 500mm.
The advantages and benefits of the present invention are:
1, the present invention can meet the consolidation requirement of double-row pile coupling beam and stake using upper reinforcement concrete slab, give full play to double The advantage that campshed rigidity is big, deformation is small.
2, it is isolated between lower rebar concrete slab of the present invention and fashioned iron in mixing pile with materials such as foamed plastics, is not influenced Fashioned iron is smoothly extracted, while lower rebar concrete slab can be used as jack base when extracting fashioned iron, therefore remain fashioned iron The advantages of cement mixing method low cost.
3) upper reinforcement concrete slab of the present invention and coupling beam can limit left and right two in two sides package lower rebar concrete slab The horizontal alternate displacement of block armoured concrete slab is allowed to be formed as a stress entirety, is conducive to eliminate the non-consolidation section of lower panel The adverse effect that point generates.
4) can be worked together between upper reinforcement concrete slab and coupling beam and lower rebar concrete slab of the present invention and Separately remove.
5) present invention is easy for construction, quality controllable.
Detailed description of the invention:
Fig. 1 is top view of the invention;
Fig. 2 is the 1-1 sectional view of Fig. 1;
Fig. 3 is the 2-2 sectional view of Fig. 1.
In figure: 1- flexible material separation layer;2- upper reinforcement concrete slab and coupling beam;3- lower rebar concrete slab;4- Separation layer;5- mixing pile;6- fashioned iron.
Specific embodiment:
Below by specific embodiment, the invention will be further described, and it is not limit that following embodiment, which is descriptive, Qualitatively, this does not limit the scope of protection of the present invention.
It is as shown in the figure: a kind of coupling beam structure of double row type steel cement mixing method stake top, by upper and lower two parts reinforced concrete Native plate 2,3 forms, and its underpart armoured concrete slab is the cast-in-situ reinforced concrete slab of a monolith thickness 200mm, the plate and stirring Equipped with the separation layer 4 made of foamed plastics (or plank sheathing, malthoid etc.) between fashioned iron in stake 5.Upper reinforcement concrete slab 2 is The cast-in-situ reinforced concrete slab of two pieces of thickness 500mm, and an overall structure being formed by connecting by reinforced concrete coupling beams 2, Lower rebar concrete slab 3 is wrapped up by being turned under 2 two sides of upper reinforcement concrete slab.Upper reinforcement concrete slab 2 and mixing pile 5 Interior fashioned iron 6 directly contacts, and pours as an entirety.It can be isolated with flexible material layer 1 between upper and lower armoured concrete slab.
Application method of the invention is: after supporting, upper board first abolished, retains lower panel, then pulls out fashioned iron, Finally remove lower panel.It comprises the concrete steps that
1, after in the pile body part of related cement mixing method, construction is finished, pile crown soil is excavated by design altitude, clearly Relevant surfaces dregs are managed, isolated material is wrapped up, then ties up muscle formwork and pour lower part board concrete.
2, the side form for removing lower rebar concrete slab, in upper reinforcement concrete slab and coupling beam and lower rebar concrete The separation layer of one layer of plastic cloth or malthoid etc is spread between plate.
3, upper reinforcement concrete slab and coupling beam tie up muscle formwork casting concrete.
4, after supporting terminates, upper reinforcement concrete slab and coupling beam is first removed, must not pay attention to and damage lower panel.
5, after extracting fashioned iron, lower rebar concrete slab is removed.
The present invention is not limited to embodiments described above.Above the description of specific embodiment is intended to describe and say Bright technical solution of the present invention, above-mentioned specific embodiment are only to illustrate, and are not restrictive.This hair is not being departed from In the case of bright objective and scope of the claimed protection, those skilled in the art can also do under the inspiration of the present invention The specific transformation of many forms out, within these are all belonged to the scope of protection of the present invention.

Claims (5)

1. a kind of coupling beam structure of double row type steel cement mixing method stake top, it is characterised in that: by upper and lower two parts reinforced concrete Native board group is at equipped with separation layer between fashioned iron in lower rebar concrete slab and mixing pile, upper reinforcement concrete slab is by a left side The overall structure that right two pieces of armoured concrete slabs are formed by connecting by reinforced concrete coupling beams, upper reinforcement concrete slab and stirring Fashioned iron, which directly contacts, in stake pours into overall structure;Lower rebar concrete slab is wrapped in upper reinforcement concrete slab.
2. a kind of coupling beam structure of double row type steel cement mixing method stake top according to claim 1, it is characterised in that: on It states upper reinforcement concrete slab and will be turned under two sides and wrap up lower rebar concrete slab.
3. a kind of coupling beam structure of double row type steel cement mixing method stake top according to claim 1, it is characterised in that: on It states between upper and lower two parts armoured concrete slab equipped with flexible material separation layer.
4. a kind of coupling beam structure of double row type steel cement mixing method stake top according to claim 1, it is characterised in that: on State the cast-in-situ reinforced concrete slab that lower rebar concrete slab is a monolith thickness 200mm.
5. a kind of coupling beam structure of double row type steel cement mixing method stake top according to claim 1, it is characterised in that: on Two pieces of the left and right armoured concrete slab of upper reinforcement concrete slab is stated with a thickness of 500mm.
CN201811578737.6A 2018-12-24 2018-12-24 Connecting beam structure of pile top of double-row type steel cement soil mixing pile Pending CN109610447A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811578737.6A CN109610447A (en) 2018-12-24 2018-12-24 Connecting beam structure of pile top of double-row type steel cement soil mixing pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811578737.6A CN109610447A (en) 2018-12-24 2018-12-24 Connecting beam structure of pile top of double-row type steel cement soil mixing pile

Publications (1)

Publication Number Publication Date
CN109610447A true CN109610447A (en) 2019-04-12

Family

ID=66011258

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811578737.6A Pending CN109610447A (en) 2018-12-24 2018-12-24 Connecting beam structure of pile top of double-row type steel cement soil mixing pile

Country Status (1)

Country Link
CN (1) CN109610447A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112323788A (en) * 2020-12-18 2021-02-05 中交三公局第三工程有限公司 Anti-seismic cement mixing pile and construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030010407A (en) * 2001-07-27 2003-02-05 정란 A fiber reinforced earth retaining wall, a constructing method thereof, and a composite underground wall structure using thereof
CN205776241U (en) * 2016-05-10 2016-12-07 中国建筑股份有限公司 A kind of truss-like Double-row Piles Support system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030010407A (en) * 2001-07-27 2003-02-05 정란 A fiber reinforced earth retaining wall, a constructing method thereof, and a composite underground wall structure using thereof
CN205776241U (en) * 2016-05-10 2016-12-07 中国建筑股份有限公司 A kind of truss-like Double-row Piles Support system

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
徐立斌等: "双排桩式围护结构在深基坑开挖中的应用", 《建筑施工》 *
谭广兵: "型钢水泥搅拌墙在工程中的应用", 《建材与装饰(下旬刊)》 *
高英林: "杨高路超大型地下商场结构设计", 《地下工程与隧道》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112323788A (en) * 2020-12-18 2021-02-05 中交三公局第三工程有限公司 Anti-seismic cement mixing pile and construction method
CN112323788B (en) * 2020-12-18 2022-04-19 中交三公局第三工程有限公司 Anti-seismic cement mixing pile and construction method

Similar Documents

Publication Publication Date Title
CN103615053B (en) Monolithic reinforced concrete structure post empiricism engineering method
CN108360712A (en) A kind of assembled steel reinforced concrete shear force wall and its construction method
CN207616844U (en) Foundation platform precast concrete side form and molding machine
WO2021023245A1 (en) Pile slab-type soil retaining wall integral casting formwork structure and construction method therefor
CN105926804A (en) Reinforcement method of 3D printed reinforced masonry shear wall
CN101736832B (en) Confined masonry structure and making method thereof
CN105275097A (en) A post-cast strip water-stop steel plate and demolition-free template net installing method
CN104295003A (en) Structural column construction method
CN109267585A (en) Assembled prismoid shaped basis and rod structure and assembly method
CN108547337A (en) Tear down and build the foundation construction technology of house foundation
CN106149877B (en) Concrete frame structure prefabricated post and the docking structure and method at beam slab node
CN107227845A (en) One kind filling wall construction post mold method
CN109610447A (en) Connecting beam structure of pile top of double-row type steel cement soil mixing pile
CN202247938U (en) Wedge-shaped foundation bolt preformed hole core formwork device
CN106968366A (en) A kind of construction method for pouring constructional column free removal template
CN104878756B (en) Sand-filling hollow structure based cast-in-place special-shaped pile construction method
CN106759266B (en) Combine reinforcement diaphragm wall and its construction method
CN214993788U (en) Assembled cement soil composite pile
CN107366427A (en) A kind of city cast-in-situ hollow Sandwich Plates concrete construction method
CN107558606A (en) A kind of prefabricated construction construction method
CN207846656U (en) A kind of strong ties construction of assembled vertical member and basis
CN201991015U (en) Foundation underpinning structure
CN207032227U (en) A kind of Rapid Combination stake of civil engineering
CN107165280B (en) A kind of large span open-spandrel sandwich board stay in place form support system and construction method
CN212612431U (en) Reinforced high-pressure jet grouting pile reinforcement structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190412