CN109610350A - A kind of ruggedized construction of prestressed concrete box girder - Google Patents

A kind of ruggedized construction of prestressed concrete box girder Download PDF

Info

Publication number
CN109610350A
CN109610350A CN201811631810.1A CN201811631810A CN109610350A CN 109610350 A CN109610350 A CN 109610350A CN 201811631810 A CN201811631810 A CN 201811631810A CN 109610350 A CN109610350 A CN 109610350A
Authority
CN
China
Prior art keywords
prestressed concrete
concrete box
box girder
steel
channel steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811631810.1A
Other languages
Chinese (zh)
Inventor
周宏宇
刘亚南
麻全周
袁慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing University of Technology
Original Assignee
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Technology filed Critical Beijing University of Technology
Priority to CN201811631810.1A priority Critical patent/CN109610350A/en
Publication of CN109610350A publication Critical patent/CN109610350A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The present invention relates to a kind of ruggedized constructions of prestressed concrete box girder, for reinforcing original prestressed concrete box girder, including channel steel, angle steel, anchor bolt;Channel steel is fixed on the abdomen of original prestressed concrete box girder, top, on bottom plate, by channel steel aperture, channel steel is fixed on prestressed concrete box girder with the anchor bolt being embedded on former prestressed concrete box girder, with the mode of welding that the channel steel welding on abdomen, top, bottom plate is integral, the position of welding forms weld seam, and two angle steel are one group, totally two groups, each group of angle steel is parallel to each other at " V " type, two groups of angle steel, and is fixedly mounted between upper and lower two channel steels.The present invention is by adding steelframe, improve the global sections rigidity of box beam, so that box beam stress is more uniform, effect of the steelframe as rigid support is played, structure holistic resistant behavior improves, and easy construction, solve the problems such as method is complicated, difficulty of construction is big, self weight increase is big present in existing box beam reinforcing.

Description

A kind of ruggedized construction of prestressed concrete box girder
Technical field
The invention belongs to bridge strengthening field, specially a kind of prestressed concrete box girder transversely strengthening structure.
Background technique
With the development of Chinese national economy, car ownership is continuously increased, and vehicle develops to heavy-duty, is built in the past Partial Bridges, bearing capacity have been unable to meet the needs of Modern Traffic, multiple diseases occur, influence the safety that bridge uses Property.Bridge must be reinforced.
The crack of concrete structure is the initial imperfection of inside of solid material, is a kind of discontinuous phenomenon.Belong to structure Strength theory scope.There are many factor for causing concrete structure to crack, and emphasis different classifications are also different.To the Bridge Crack origin cause of formation Careful analysis, be the basis for judging Bridge Crack risk and how being prevented it and be reinforced;If not fracture By meticulously dissecting research, is just at will handled for it, do not obtain the good result of anticipation not only, or even also have initiation A possibility that unexpected incidents, has seriously affected the service life of bridge structure.
It is fewer for the diaphragm plate of the prestressed concrete box-beam bridge of large span, especially box beam setting, in load Under effect, the deformation of concrete box girder meets classical theory peripheral rigid it is assumed that can cause to distort.Web will appear vertically certainly Direct stress.The web horizontal fracture as caused by vertical direct stress, it is general concentrate appear in end bay support near zone and in across Region between the 1/4~3/4 of single span length all occurs in web upper limb substantially.Since the practical distortion of box beam does not meet rigidity It is assumed that tank wall is than relatively thin, diaphragm plate is very little on periphery, too small to torsional restraint, can generate distortion deformation.
For the various cracks that bridge generates, existing reinforcement means mainly has following 8 kinds: 1, bridge strengthening course reinforcing side Method;2, prestressing;3, sticking carbon fiber piece method for strengthening;4, affixing steel plate reinforcement method;5, reinforced with external steel encased;6, increase Section and arrangement of reinforcement method for strengthening;7, increase strengthening member method;8, change structure stress system method for strengthening.The specific reinforcement means of bridge Comprehensively careful analysis should be carried out according to Causes of Cracking, each regio defect, economic effect of bridge etc. are many-sided, select above-mentioned one Kind or a variety of reinforcement means.The prior art is primarily present following both sides problem: although the 1, technology that has is to the crack of bridge Prevent the effect that can have been played, but the method reinforced is complicated, difficulty of construction is high, it is also bad in economic effect.2, most to add Gu technology carries out reinforcing prevention both for the diagonal crack of bridge, the horizontal fracture of bridge is not accounted for.
Summary of the invention
It is an object of the invention to aiming at the problems existing in the prior art, propose a kind of cross of prestressed concrete box girder To reinforcement means.The present invention improves the global sections rigidity of box beam by adding steelframe, so that box beam stress is more uniformly, Effect of the steelframe as rigid support is played, and structure holistic resistant behavior improves.And the method reinforced is simple, construction It is convenient, economical height.
The present invention is realized by following technical method:
A kind of ruggedized construction of prestressed concrete box girder, for reinforcing original prestressed concrete box girder 1, feature exists In: including channel steel 2, angle steel 3, anchor bolt 5;Channel steel 2 is fixed on the abdomen of original prestressed concrete box girder 1, top, on bottom plate, it will Channel steel 2 is fixed in prestressed concrete box girder with the anchor bolt 5 being embedded on former prestressed concrete box girder 1 by 2 aperture of channel steel On 1, the channel steel 2 on abdomen, top, bottom plate is welded to integral, the position formation weld seam 4 of welding, two angle steel 3 with the mode of welding It is one group, totally two groups, each group of angle steel is parallel to each other at " V " type, two groups of angle steel 3, and is fixedly mounted on upper and lower two channel steels 2 Between.
Channel steel 2 can also be fixed on former prestressed concrete box girder 1 using bonding method.
Region between the 1/4~3/4 of prestressed concrete box girder single span longitudinal length is used for together every 2 meters of increases Improve the lateral stiffness of prestressed concrete box girder and the prestressed concrete box girder ruggedized construction of torsional restraint.
The aperture on channel steel 2, position is on the middle line of channel steel 2, and at equidistantly distributed.
The pad of the contact area of channel steel 2 and angle steel 3 can also be arranged to add between angle steel 3 and the edge of a wing of channel steel 2 Plate 7 is fixedly connected by bolt 6 between angle steel 3 and channel steel 2, can also be riveted.
The present invention provides a kind of novel prestressed concrete box girder transversely strengthening structure.Closed steelframe can increase bridge The lateral stiffness of beam can effectively improve the holistic resistant behavior of prestressed concrete box girder, improve the stress of web.It will Channel steel is pasted onto the abdomen of prestressed concrete box girder, top with epoxy resin mortar, on bottom plate, and is anchored with anchor bolt.With bolt by angle steel It is fixed on channel steel up and down, increases the overall stiffness of steelframe, improve stress performance.Due to increasing steelframe, the transverse direction of box beam is just Degree and holistic resistant behavior will be greatly improved.Prestressed concrete box girder is reinforced using this method, construction is simple is applied Expenses of labour is also little to the self weight increase of beam with low.
" V " font web member among steelframe is that angle steel is connected with bolt with the edge of a wing of channel steel made of angle steel, is formed Two groups of " V " font web members, two groups of web member parallel arrangements.
The utility model has the advantages that
1, the global sections rigidity of box beam is improved after reinforcing, laterally each beam stress more uniformly, has played steelframe conduct The effect of rigid support, and structure holistic resistant behavior improves.
2, the method reinforced is simple, easy for construction, economical height.
Detailed description of the invention
Fig. 1, steelframe reinforce prestressed concrete box beams structure transverse face figure
Fig. 2, steelframe reinforce prestressed concrete box beams structure skiagraph
Fig. 3, partial schematic diagram
Wherein: 1, concrete box girder, 2, channel steel, 3, angle steel, 4, weld seam, 5, anchor bolt, 6, bolt, 7, backing plate.
Specific embodiment
This programme is described in further details with reference to the accompanying drawing:
Channel steel 2 is pasted onto originally when being reinforced with epoxy resin mortar by prestressed concrete box girder as shown in Figure 1 The abdomen of prestressed concrete box girder 1, top, on bottom plate.By 2 aperture of channel steel, with the anchor being embedded on former prestressed concrete box beams 1 Channel steel 2 is fixed on prestressed concrete box girder 1 by fixing bolt 5, is welded the channel steel 2 on abdomen, top, bottom plate with the mode of welding Integral, the position of welding forms weld seam 4.In channel steel 2 with backing plate 7 is arranged between angle steel 3, the bolt 6 of angle steel 3 is fixed in slot On steel 2.Region between the 1/4~3/4 of prestressed concrete box girder single span longitudinal length increases by one of prestressing force every 2 meters and mixes The ruggedized construction of solidifying soil box beam, can form multiple reinforcement elements.
As described above, being just able to achieve the present invention.

Claims (5)

1. a kind of ruggedized construction of prestressed concrete box girder, for reinforcing original prestressed concrete box girder 1, feature exists In: including channel steel 2, angle steel 3, anchor bolt 5;Channel steel 2 is fixed on the abdomen of original prestressed concrete box girder 1, top, on bottom plate, it will Channel steel 2 is fixed in prestressed concrete box girder with the anchor bolt 5 being embedded on former prestressed concrete box girder 1 by 2 aperture of channel steel On 1, the channel steel 2 on abdomen, top, bottom plate is welded to integral, the position formation weld seam 4 of welding, two angle steel 3 with the mode of welding It is one group, totally two groups, each group of angle steel is parallel to each other at " V " type, two groups of angle steel 3, and is fixedly mounted on upper and lower two channel steels 2 Between.
2. requiring a kind of ruggedized construction of prestressed concrete box girder according to right 1, it is characterised in that: can also use Channel steel 2 is fixed on former prestressed concrete box girder 1 by bonding method.
3. requiring a kind of ruggedized construction of prestressed concrete box girder according to right 1, it is characterised in that: mixed in prestressing force Region between the 1/4~3/4 of solidifying soil box beam single span longitudinal length, increases together every 2 meters for improving prestressed concrete box The lateral stiffness of beam and the prestressed concrete box girder ruggedized construction of torsional restraint.
4. requiring a kind of ruggedized construction of prestressed concrete box girder according to right 1, it is characterised in that: described in slot Aperture on steel 2, position is on the middle line of channel steel 2, and at equidistantly distributed.
5. requiring a kind of ruggedized construction of prestressed concrete box girder according to right 1, it is characterised in that: can also be at angle Be arranged to add to the backing plate 7 of the contact area of channel steel 2 and angle steel 3 between steel 3 and the edge of a wing of channel steel 2, angle steel 3 and channel steel 2 it Between be fixedly connected by bolt 6.
CN201811631810.1A 2018-12-29 2018-12-29 A kind of ruggedized construction of prestressed concrete box girder Pending CN109610350A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811631810.1A CN109610350A (en) 2018-12-29 2018-12-29 A kind of ruggedized construction of prestressed concrete box girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811631810.1A CN109610350A (en) 2018-12-29 2018-12-29 A kind of ruggedized construction of prestressed concrete box girder

Publications (1)

Publication Number Publication Date
CN109610350A true CN109610350A (en) 2019-04-12

Family

ID=66011007

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811631810.1A Pending CN109610350A (en) 2018-12-29 2018-12-29 A kind of ruggedized construction of prestressed concrete box girder

Country Status (1)

Country Link
CN (1) CN109610350A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110735387A (en) * 2019-11-04 2020-01-31 河南省交通规划设计研究院股份有限公司 Transverse connection device for small box girders of bridge and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0425364A1 (en) * 1989-10-24 1991-05-02 Jean Muller International Station on a railway or other line, situated on a viaduct
JP2007092392A (en) * 2005-09-29 2007-04-12 Sho Bond Constr Co Ltd Hinge portion repairing structure of concrete construction
CN202227254U (en) * 2011-06-30 2012-05-23 广东工业大学 Structure for reinforcing prestressed concrete box beam by horizontal reinforced steel frame
CN104233963A (en) * 2014-09-10 2014-12-24 北京工业大学 Prestress-adjustable steel truss for reinforcing PSC (prestressed concrete) continuous box girder bridge and construction method
CN107938525A (en) * 2017-12-20 2018-04-20 山西省交通规划勘察设计院 A kind of ruggedized construction and its method of assembled continuous box girder
CN208266707U (en) * 2018-05-15 2018-12-21 李旺兴 A kind of prefabricated box -beam segment chamber bracing means

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0425364A1 (en) * 1989-10-24 1991-05-02 Jean Muller International Station on a railway or other line, situated on a viaduct
JP2007092392A (en) * 2005-09-29 2007-04-12 Sho Bond Constr Co Ltd Hinge portion repairing structure of concrete construction
CN202227254U (en) * 2011-06-30 2012-05-23 广东工业大学 Structure for reinforcing prestressed concrete box beam by horizontal reinforced steel frame
CN104233963A (en) * 2014-09-10 2014-12-24 北京工业大学 Prestress-adjustable steel truss for reinforcing PSC (prestressed concrete) continuous box girder bridge and construction method
CN107938525A (en) * 2017-12-20 2018-04-20 山西省交通规划勘察设计院 A kind of ruggedized construction and its method of assembled continuous box girder
CN208266707U (en) * 2018-05-15 2018-12-21 李旺兴 A kind of prefabricated box -beam segment chamber bracing means

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110735387A (en) * 2019-11-04 2020-01-31 河南省交通规划设计研究院股份有限公司 Transverse connection device for small box girders of bridge and construction method thereof

Similar Documents

Publication Publication Date Title
CN104831627A (en) Bridge deck slab longitudinal unequal strength steel-concrete composite structure bridge and construction method thereof
CN106567320B (en) The local gravity rigidity and auxiliary suspension cable structure system of large span stayed-cable bridge
CN103388303A (en) Horizontal splicing corrugated steel web plate combined box girder and construction method
CN106758743A (en) It is a kind of to improve the method that steel reinforced concrete combines many case continuous bridge hogging moment area stress performances
CN110904864B (en) Steel-concrete combined system for improving bearing capacity of concrete box girder bridge
CN108517793A (en) A kind of combination T beam bridges assembled lateral connection ruggedized construction and its reinforcement means
CN104532760B (en) The reinforcement means of a kind of simply supported slab or simply supported beam bridge
CN105297641A (en) Highway T beam diaphragm plate prestress reinforcing structure and working method for reinforcement using reinforcing structure
CN109137760A (en) The active reinforcement means of multispan normal reinforced concrete beam bridge
CN108457182A (en) A kind of cross bridge floor board and its construction technology
CN203559329U (en) Steel-RPC (reactive powder concrete) combined bridge
CN109610350A (en) A kind of ruggedized construction of prestressed concrete box girder
CN110644361A (en) Steel-concrete composite beam bridge deck
CN207862764U (en) A kind of steel anticollision barrier connecting structure being easy to construction suitable for STC bridge decks
CN208309407U (en) A kind of combination T beam bridge assembled lateral connection ruggedized construction
Stroetmann et al. Development of an orthotropic composite slab system for road bridges
CN210827072U (en) Middle seamless telescopic structure of middle and small-span simply-supported highway bridge
CN109235235B (en) Longitudinal connection method for main beams at continuous part of steel-concrete composite bridge deck
CN204715222U (en) A kind of external prestressing strengthening structure of pier cap beam
CN214737322U (en) Assembled mound roof beam concreties structure
CN109356034A (en) A kind of mixed composite continuous bridge superstructure system of vertically and horizontally Prestressed CFRP concrete steel
CN210104592U (en) Prestressed composite reinforcing structure of pier bent cap
CN212223609U (en) FRP section bar reinforcing steel bridge deck structure
CN211368335U (en) Bridge small box girder transverse connection device
CN208415099U (en) Rib steel reinforced floorings

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190412