CN109564673A - Seal construction, the system of seal construction management and seal construction training, program and method - Google Patents

Seal construction, the system of seal construction management and seal construction training, program and method Download PDF

Info

Publication number
CN109564673A
CN109564673A CN201780049429.1A CN201780049429A CN109564673A CN 109564673 A CN109564673 A CN 109564673A CN 201780049429 A CN201780049429 A CN 201780049429A CN 109564673 A CN109564673 A CN 109564673A
Authority
CN
China
Prior art keywords
seal construction
construction
training
computer
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201780049429.1A
Other languages
Chinese (zh)
Other versions
CN109564673B (en
Inventor
山边雅之
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co Walka
Original Assignee
Co Walka
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Walka filed Critical Co Walka
Publication of CN109564673A publication Critical patent/CN109564673A/en
Application granted granted Critical
Publication of CN109564673B publication Critical patent/CN109564673B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B19/00Teaching not covered by other main groups of this subclass

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Educational Administration (AREA)
  • Educational Technology (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • General Business, Economics & Management (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Collating Specific Patterns (AREA)

Abstract

Realization seal construction training, sealing element are selected and the unified management of seal construction, improves the precision of seal construction, reliability.Make the client (4) for ordering seal construction, undertake the construction personnel (6) of seal construction and the Support center (8) of seal construction is supported to cooperate, instruction is paid attention to the class from the client to the seal construction training that the construction personnel is emitted in the Support center, opportunity is designated as to pay attention to the class described in the client, make the condition for permitting the construction personnel, the seal construction training that the construction personnel carries out in the Support center is paid attention to the class.

Description

Seal construction, the system of seal construction management and seal construction training, program and Method
Technical field
The present invention relates to the seal construction system for being piped connection etc., seal construction management/seal construction trainings to be System, program and method.
Background technique
In the construction of the equipment such as connection pump, the sealing elements such as gasket are clamped into flange in piping connection or in piping and are connect Head fastens gasket with bolt of the configuration on multiple positions of bamp joint.
About the seal construction, as training, with equipment, it has been known that there is following equipment: being detected using load cell and is pulled by torque The fastening force of the bolt of the fasteners such as hand fastening is simultaneously shown over the display, and the surface pressing (example of flange is confirmed by operator Such as, patent document 1).
Prior art document
Patent document
Patent document 1: Japanese Unexamined Patent Publication 2009-191932 bulletin
Summary of the invention
Subject to be solved by the invention
In addition, comprising the clients such as workshop and its owner, needing to be applied by equipment of seal construction etc. in the seal construction Work object, the construction personnel for being responsible for seal construction and operator, the sealing element for being suitble to construction object, the construction for seal construction Tool, operator multiple elements such as training.In short, the selected of sealing element, purchase and the training of operator are sealed for improving Precision, the reliability of construction are extremely important items.
Suitable sealing element is selected to be not easy to from diversified sealing element, even also, skilled operator, In the construction dependent on experience or intuition, there are also problems for precision and reliability.Even if implementing seal construction training, such as There is mistake in selected sealing element in fruit construction personnel, then can not also obtain the precision and reliability of expectation.
Even if providing the sealing element of high-precision, high quality, if this is selected, there are mistakes, can not also expect high quality Seal construction, also, if the training of seal construction, the purchase of the selected of sealing element, the sealing element are free independent pipe Reason, then be difficult to improve the quality of seal construction, the quality of seal construction can decline.
Therefore, in view of the above subject, it is an object of the invention to realize that seal construction training, sealing element are selected and sealing is applied The unified management of work improves precision, the reliability of seal construction.
Also, it is selected and sealing element purchase, raising seal construction another object of the present invention is to uniformly be sealed part In sealing element q&r.
Means for solving the problems
To achieve the goals above, according to the one aspect of the seal construction system of the disclosure, a kind of seal construction system, It makes the client for ordering seal construction, undertakes the construction personnel of seal construction and supports the Support center phase interworking of seal construction It closes, wherein pay attention to the class finger from what the client was emitted in seal construction training that the Support center carries out to the construction personnel Show, opportunity is designated as with described pay attention to the class, makes the condition for permitting the seal construction of the construction personnel, the construction personnel is in institute State paying attention to the class for the seal construction training of Support center progress.
In above-mentioned seal construction system, it is also possible to also be designated as opportunity to pay attention to the class described in the client, institute is provided Selected or the sealing element the information of sealing element needed for stating seal construction, issues institute from the client to the construction personnel That states sealing element allots instruction.
To achieve the goals above, according to the one aspect of the seal construction system of the disclosure, a kind of seal construction system, It makes the client for ordering seal construction, undertakes the construction personnel of seal construction and supports the Support center phase interworking of seal construction It closes, wherein pay attention to the class finger from what the client was emitted in seal construction training that the Support center carries out to the construction personnel Show, be designated as opportunity to pay attention to the class described in the client, the sealing is carried out to the construction personnel in the Support center and is applied Work training, the information of the selected or sealing element of sealing element needed for the seal construction is provided, from the client to described What construction personnel issued the sealing element allots instruction, makes the condition for permitting seal construction, has carried out the seal construction training Instruction.
To achieve the goals above, according to the one aspect of the seal construction management method of the disclosure, a kind of seal construction Management method executes client computer, construction personnel's computer and Support center computer co-operatively, wherein should Seal construction management method is with the following process: being emitted in support from the client computer to construction personnel's computer The tune for paying attention to the class instruction, sealing element and this both sides of seal construction tool or at least sealing element for the seal construction training that the heart carries out Reversal means is shown;And seal construction training described in the Support center computer management, the instruction of the client computer is received, and Sealing element needed for selected seal construction or the information for obtaining the sealing element.
To achieve the goals above, according to the one aspect of the seal construction management method of the disclosure, a kind of seal construction Management method executes client computer, construction personnel's computer and Support center computer co-operatively, wherein should Seal construction management method is with the following process: being emitted in support from the client computer to construction personnel's computer The tune for paying attention to the class instruction, sealing element and this both sides of seal construction tool or at least sealing element for the seal construction training that the heart carries out Reversal means is shown;Seal construction training described in the Support center computer management, receives the instruction of the client computer, and selectes Sealing element needed for seal construction or the information for obtaining the sealing element;Construction personnel's computer is at least counted to the client What calculation machine notified the seal construction training pays attention to the class report;And the client computer is at least from construction personnel's computer Receive paying attention to the class report and issuing the sealing using the sealing element to construction personnel's computer for the seal construction training The license of construction.
In above-mentioned seal construction management method, be also possible to also comprising following process: the Support center computer with At least one party in the client computer or construction personnel's computer manages the seal construction, described in association Any one in seal construction training or the purchase of the sealing element or two or more.
In above-mentioned seal construction management method, be also possible to also comprising following process: from the client computer to Before construction personnel's computer indicating sealing construction, the Support center computer is issued for the client computer Seal construction pushes.
Also include following process in above-mentioned seal construction management method: the Support center computer obtains described close The record for sealing construction prompts seal construction letter at least one party in the client computer or construction personnel's computer Breath.
In above-mentioned seal construction management method, be also possible to the seal construction tool include flange perimeter component, it is tight Gu tool and the information terminal for being stored with flange fastening information.
To achieve the goals above, according to the one aspect of the seal construction management system of the disclosure, have and cooperate Client computer, construction personnel's computer and Support center computer, counted from the client computer to the construction personnel Calculation machine be emitted in Support center progress seal construction training pay attention to the class instruction, sealing element and this both sides of seal construction tool or At least sealing element allots instruction, and seal construction training described in the Support center computer management receives client's meter The instruction of calculation machine, and sealing element needed for selected seal construction or the information for obtaining the sealing element.
To achieve the goals above, according to the one aspect of the seal construction management system of the disclosure, have and cooperate Client computer, construction personnel's computer and Support center computer, counted from the client computer to the construction personnel Calculation machine be emitted in Support center progress seal construction training pay attention to the class instruction, sealing element and this both sides of seal construction tool or At least sealing element allots instruction, and seal construction training described in the Support center computer management receives client's meter The instruction of calculation machine, and sealing element needed for selected seal construction or the information for obtaining the sealing element, the construction personnel calculate Machine at least notifies the report of paying attention to the class of the seal construction training to the client computer, and the client computer is at least from described Construction personnel's computer receives paying attention to the class report and using institute to construction personnel's computer sending for the seal construction training State the license of the seal construction of sealing element.
To achieve the goals above, according to the one aspect of the seal construction management program of the disclosure, a kind of seal construction Management program is realized, wherein the seal construction pipe by client computer, construction personnel's computer and Support center computer Reason program is for making the computer realize following functions: being emitted in from the client computer to construction personnel's computer Instruction, sealing element and this both sides of seal construction tool or at least sealing are paid attention to the class in the seal construction training that Support center carries out Part allots instruction;And seal construction training described in the Support center computer management, receive the client computer Instruction, and sealing element needed for selected seal construction or the information for obtaining the sealing element.
To achieve the goals above, according to the one aspect of the seal construction management program of the disclosure, a kind of seal construction Management program is realized, wherein the seal construction pipe by client computer, construction personnel's computer and Support center computer Reason program is for making the computer realize following functions: being emitted in from the client computer to construction personnel's computer Instruction, sealing element and this both sides of seal construction tool or at least sealing are paid attention to the class in the seal construction training that Support center carries out Part allots instruction;Seal construction training described in the Support center computer management, receives the instruction of the client computer, And sealing element needed for selected seal construction or the information for obtaining the sealing element, construction personnel's computer is at least to described What client computer notified the seal construction training pays attention to the class report;And the client computer is at least from the construction personnel Computer receives paying attention to the class report and using the sealing element to construction personnel's computer sending for the seal construction training Seal construction license.
To achieve the goals above, according to the one aspect of the seal construction Training Methodology of the disclosure, comprising the following steps: Equipment needed for selection training, the seal construction equipment packet from the seal construction equipment for being set to single or multiple Classrooms It includes, the equipment of simulation piping calibration, the equipment of simulation fastening, the equipment for simulating sealing state, the equipment of simulation flange fastening, mould The equipment of equipment, simulation heat-exchange apparatus that equipment, the analog compression of quasi- creep are destroyed;And obtain the seal construction equipment In the sensor that has of each equipment sensor output, or obtain training information from input unit.
To achieve the goals above, according to the one aspect of the seal construction Training Methodology of the disclosure, comprising the following steps: Equipment needed for selection training, the seal construction equipment packet from the seal construction equipment for being set to single or multiple Classrooms Include the equipment, the equipment of simulation fastening, the equipment for simulating sealing state, the equipment of simulation flange fastening, mould of simulation piping calibration The equipment of equipment, simulation heat-exchange apparatus that equipment, the analog compression of quasi- creep are destroyed;It obtains in the seal construction equipment The sensor for the sensor that each equipment has exports, or obtains training information from input unit;It is defeated to receive the sensor Out or the training information, the analog information with device-dependent included in the seal construction equipment is generated;And benefit The analog information is prompted with either or both of in text information or graphical information.
To achieve the goals above, according to the one aspect of the seal construction training system of the disclosure, comprising: it is single or Multiple Classrooms;Seal construction unit is set to the Classroom, and equipment, simulation comprising simulation piping calibration fasten Equipment, the equipment for simulating sealing state, the equipment of simulation flange fastening, simulate the equipment of creep, the equipment that analog compression is destroyed, Simulate any one in the equipment of heat-exchange apparatus or two or more;Acquisition unit obtains the seal construction unit The sensor that has of each equipment sensor output or the training information with the device-dependent;Processing unit connects The sensor output or the training information are received, the mould with device-dependent included in the seal construction unit is generated Quasi- information;And information alert unit, it is connect in wired or wireless manner with the processing unit, utilizes text information Or either or both of in graphical information come prompt from the processing unit export processing output.
To achieve the goals above, according to the one aspect of the seal construction training program of the disclosure, one kind is by computer The seal construction training program of realization, wherein the seal construction training program makes computer realize following functions: from seal construction In unit selection for training equipment, the seal construction unit include simulation piping calibration equipment, simulation fastening equipment, Simulate equipment, the simulation that the equipment of sealing state, the equipment of simulation flange fastening, equipment, the analog compression for simulating creep are destroyed Any one in the equipment of heat-exchange apparatus or two or more;Each equipment obtained in the seal construction unit is had Sensor sensor output or the training information with the device-dependent;Receive the sensor output or the training Information is instructed, the analog information with device-dependent included in the seal construction unit is generated;And using text information or Any one or both sides in person's graphical information prompt the analog information.
Invention effect
Seal construction system according to the present invention can obtain any one effect below.
(1) can with the arrival at moment of constructing, promotion of Support center etc. for opportunity, it is unified participate in sealing element it is selected, The training of seal construction, the alloting of sealing element, seal construction are realized and are trusted and the seal construction of safety.
(2) the selected and information for being capable of providing the required sealing element in scene is able to carry out as follows about seal construction training Meet the training at seal construction scene: carrying out the training such as construct using the sealing element based on the selected or provided information.
(3) it is sealed with selected sealing element due to receiving the operator of the training of seal construction and is applied at the scene Work, so being able to carry out high-precision and the seal construction with reliability.
System, program or the method for seal construction management according to the present invention can obtain any one effect below Fruit.
(1) it can be realized with the cooperation of client computer, construction personnel's computer and Support center computer for construction The seal construction training of personnel, the selected of sealing element and the unified management alloted, can be improved the precision of seal construction and raising Reliability.
(2) it can specify client using client computer, construction personnel's computer and Support center computer as medium, apply Worker person and allocation of duties of the Support center in seal construction can be realized the selected and tune of seal construction training, sealing element The automation dialled.
It (3) can be in construction instruction of the Support center unified management from client, the seal construction of construction personnel, sealing element Select, allot instruction and sale, can Support center grasp seal construction content, and to client, construction personnel provide The record content.
(4) training of seal construction, the selecting of sealing element are able to record, allots history with seal construction, can be prompted It records information, is able to confirm that its content.
In addition, system, program or the method for seal construction training according to the present invention, can obtain below any one A effect.
(1) client can be selected using the cooperation of client computer, construction personnel's computer and Support center computer Seal construction object equipment, construction training is carried out with the equipment, further, it is possible to obtain the mould of the equipment of seal construction object Quasi- information or training information, can aid in precision, the reliability for improving seal construction.
It (2) can be using client computer, construction personnel's computer and Support center computer as medium, with seal construction The automation that training is matchingly realized the selected of sealing element and alloted.
(3) sealing element, applying using the sealing element needed for the construction personnel for implementing the seal construction of client can be selected Work training, the training for the equipment being related to using seal construction, further, it is possible to carry out its management in Support center, can be realized with The construction training of seal construction one.
(4) result of seal construction training can be used for the selecting of sealing element, alloted and seal construction, be able to record training History is instructed, it can be prompted to record information, can be realized the facilitation of its content check.
Detailed description of the invention
Fig. 1 is the figure for showing the seal construction system of the 1st embodiment.
Fig. 2 is the figure for showing the processing sequence of seal construction system.
Fig. 3 is the figure for showing the seal construction management system of the 2nd embodiment.
Fig. 4 is the figure for showing the processing sequence of seal construction management.
Fig. 5 is the figure for showing the processing sequence of seal construction management.
Fig. 6 is the figure for showing the sealing element tables of data of sealing element selecting system.
The A of Fig. 7 is the figure for showing the input picture selected for sealing element, and B is the result for illustrating that sealing element is selected Output picture figure.
Fig. 8 is the flow chart for showing the selected treatment process of sealing element.
Fig. 9 is the figure for saying base system for showing seal construction training system.
Figure 10 is the figure for showing the practice system of seal construction training system.
The A of Figure 11 is the figure for showing the hardware of PC, and B is the figure for showing the hardware of Training Server.
Figure 12 is the figure for showing construction raining information table.
The A of Figure 13 is the figure for showing personal information table, and B is to show sealing element information/construction information table figure.
The A of Figure 14 is the figure for showing raining information table, and B is the figure for showing relevant information table.
Figure 15 is the figure for showing course lessons table.
The A of Figure 16 is the figure for showing gasket lecture table, and B is the figure for showing gasket and practicing table.
The A of Figure 17 is the figure for showing envelope axle pad piece lecture table, and B is the figure for showing envelope axle pad piece and practicing table.
Figure 18 is the figure for showing lecture prompt table.
Figure 19 is to show the figure for practicing prompt table.
The A of Figure 20 is the figure for showing an example of input picture of seal construction, and B is to illustrate that seal construction training is completed Output picture an example figure.
Figure 21 is the flow chart for showing the treatment process of seal construction training program.
Figure 22 is the flow chart for showing the treatment process of technical ability judgement.
Figure 23 is the flow chart for showing the treatment process of course selection.
Figure 24 is the flow chart for showing an example of seal construction Training Methodology.
The A of Figure 25 is to show the flange fastening of embodiment 1 to practice the figure of device, and B is to show the spiral shell with strain transducer The figure of screw bolt and nut.
The A of Figure 26 is to show the creep of embodiment 2 to mitigate and practice the figure of device, and B is to show the spiral shell with strain transducer The figure of screw bolt and nut.
Figure 27 is to show the leakproofness of embodiment 3 to practice the figure of device.
Figure 28 is to show the in-site modeling fastening of embodiment 4 to practice the figure of device.
Figure 29 is the figure for being piped calibration and practicing device for showing embodiment 5.
Figure 30 is the figure for showing the training table of other embodiment.
Figure 31 is the figure for showing the processing sequence of seal construction system of other embodiment.
Figure 32 is the figure for showing the processing sequence of seal construction management of other embodiment.
Figure 33 is the flow chart for showing the treatment process of seal construction training program of other embodiment.
Figure 34 is the figure for showing the input picture of the seal construction of other embodiment.
Specific embodiment
[the 1st embodiment]
<seal construction system>
Fig. 1 shows the seal construction system of the 1st embodiment.The seal construction system 2 includes client 4, construction personnel 6, Support center 8 and make the system of their associated seal constructions.
Client 4 can be the various factories, Utilities Electric Co. such as oil plant, chemical plant for ordering seal construction, ship, half Any one in manufacturing companies and its owner etc. such as conductor manufacture.
Construction personnel 6 is that the personnel for being sealed construction are entrusted by client 4.
Support center 8 assists client 4 and construction personnel 6 to be sealed construction.The auxiliary includes related with seal construction Sale of associated members such as training, the offer of sealing technique, seal construction management, sealing element, seal construction tool etc..
Fig. 2 shows the processing sequences of the seal construction system 2.
It makes sequence in order according to this, promotion (Promotion) related with seal construction is executed to client 4 from Support center 8 (S101).Using the promotion and the arrival at seal construction moment as opportunity, the finger of seal construction is issued from client 4 to construction personnel 6 Show, instruction (S102) is paid attention to the class in the seal construction training of Support center 8.The instruction is also informed to Support center 8.
The notice for agreeing to seal construction and seal construction training is issued from construction personnel 6 to client 4 and Support center 8 (S103)。
Client 4 issues the selected instruction of sealing element to Support center 8 using the notice from construction personnel 6 as opportunity (S104)。
Support center 8 is in the notice for being connected to seal construction and seal construction training from client 4 and construction personnel 6 and from visitor When the sealing element at family 4 issues selected instruction, it is sealed selected (S105) of part.Then, Support center 8 to client 4 and is constructed The selected results (S106) of the notice sealing element of personnel 6.
Client 4 issues alloting instruction (S107) for sealing element to construction personnel 6, while reporting that this is alloted to Support center 8 Instruction.At this point, as long as construction personnel 6 buys the construction tool of sealing element and recommendation from Support center 8.
Support center 8 implements seal construction training (S108) to construction personnel 6 using selected sealing element, by the training Result notice is to client 4 and construction personnel 6 (S109).
The case where client 4 is according to the result alloted with seal construction training of sealing element issues sealing to construction personnel 6 and applies The license (S110) of work.
The construction personnel 6 for receiving the license implements the seal construction (S111) specified by client 4.
<effect of the 1st embodiment>
(1) arrival at seal construction moment can be known according to the promotion etc. of Support center 8.
(2) can be with the arrival at seal construction moment, promotion of Support center 8 etc. for opportunity, unification participates in sealing element The selected, training of seal construction, the alloting of sealing element, seal construction are realized and are trusted and the seal construction of safety.
(3) sealing element required for scene can be selected before seal construction, be sealed construction using the sealing element Training, thus allows for the training for meeting seal construction scene, improves the precision of seal construction.
(4) since construction personnel 6 uses selected sealing element, and the training at least to receive seal construction It is sealed construction for condition, therefore is able to carry out high-precision and the seal construction with reliability.
(5) according to the seal construction system 2, the selected of part, seal construction are sealed by then passing through Support center 8 Training and sealing element sale, therefore can realize and unified carry out sealing element related with seal construction and allot.
(6) according to the seal construction system 2, since Support center 8 participates in the selected and seal construction of sealing element always Training, so being able to maintain that the high precision int and high reliability of seal construction, and realizes the high efficiency of seal construction.
[the 2nd embodiment]
Fig. 3 shows the seal construction management system of the 2nd embodiment.In Fig. 3, part identical with Fig. 1 is marked Identical label.Structure shown in Fig. 3 is an example, and the present invention is not limited to the structures.
Seal construction management system 20 is the personnel's letter carried out in above-mentioned seal construction system 2 by using computer The computer system of the support processing of breath, sealing information, construction information, training information, relevant information etc..The seal construction management Comprising selecting the sealing element selecting system of sealing element and implementing to construction personnel 6 for being sealed construction etc. aftermentioned in system 20 The seal construction training system 34 (Fig. 9) of training.
In the seal construction management system 20, as an example, there is client 4 personal computer (hereinafter referred to as to make " PC ") 24 using as client computer, construction personnel 6 has PC 26 using as construction personnel's computer, in Support center 8 With PC 28 and Training Server computer, (hereinafter referred to as work " Training Server 30 " is using as Support center computer.This Outside, in seal construction training system 34, comprising: the sensor for the sensor that each equipment of acquirement seal construction unit has Output or with the training information of device-dependent, receiving sensor output or training information, generation and seal construction unit in The analog information for the device-dependent for including and with any one or the both sides prompt in text information or graphical information from The information alert etc. of the processing output of processing unit output.
PC 24,26,28 is for example cooperated by internet 32.Training Server 30 passes through wired or wirelessly connects with PC 28 It connects.
Instruction, training in the processing of PC 24 including seal construction indicate, the selected instruction of sealing element, allot instruction, hair The license of seal construction out.
Include the notice for agreeing to seal construction, the notice for agreeing to training in the processing of PC 26, train and pay attention to the class report, sealing Part allots report, end notification, monitoring of seal construction for starting notice, issuing seal construction of seal construction etc..
It include the confirmation got push, indicate, reporting, the selected management of sealing element, training in the processing of PC 28 The monitoring of program, the judgement for whether continuing auxiliary etc..
It include the selection procedure etc. for the training program and sealing element for executing seal construction in the processing of Training Server 30.
<processing sequence of seal construction management>
Fig. 4 and Fig. 5 shows the processing sequence of seal construction management.
Seal construction (S201) is pushed for PC 24 by PC 28.If pushed and the arrival one at the time of seal construction It causes, then can be synchronized with the arrival for pushing and informing the maintenance moment.
The instruction of seal construction is issued from PC 24 to PC 26, and notifies the instruction (S202) to PC 28.The instruction is not It is construction beginning or construction permits, and only shows to indicate with aftermentioned seal construction training etc. for the construction of condition.
Agree to the notice of seal construction from receiving the PC 26 of the instruction and issuing to PC 24, and by this agree to notify it is logical Know and gives PC 28 (S203).From the PC agreed to notify 24 is received to the seal construction training of the sending Support center 8 of PC 26 Instruction, also, the instruction (S204) is notified to PC 28.
The notice for agreeing to seal construction training is issued from PC 26, also, notifies this to agree to notify (S205) to PC 28.This When, the selected instruction (S206) of sealing element is issued from PC 24 to PC 28.
In PC 28, the instruction of monitoring seal construction, the training instruction of seal construction and these reports agreed to notify It receives (S207).If receiving seal construction instruction, the training instruction of seal construction and these reports agreed to notify ("Yes" of S207), then sealing element (S208) needed for starting selected seal construction.And by this at the beginning the case where notify to PC 24,26.Training Server 30 is with the selected selection procedure (S209) for starting to execute sealing element for condition.In PC 28, sentence Whether disconnected the selected of sealing element has terminated (S210), if the selected of sealing element has terminated ("Yes" of S210), receives from training The selected results for instructing the sealing element that server 30 provides report the selected results (S211) of the sealing element to PC 24,26.
It is reported as opportunity with the selected results, sealing element is issued from PC 24 to PC 26 allots instruction, also, to PC 28 report the instruction (S212).
Since the training program that PC 28 notifies seal construction to PC 24,26 (S213).The training program of seal construction (S214) is executed in Training Server 30.Operator's Training and Learning program of responsible seal construction in seal construction personnel 6 ?.
The execution (S215) that the training program of seal construction is monitored in PC 28, if the training program knot of seal construction Beam ("Yes" of S215) then notifies the end (S216) of the training program of seal construction from PC 28 to PC 24,26.Receive the knot Shu Tongzhi issues training from PC 26 to PC 24,28 and pays attention to the class report (S217).At this moment, if construction personnel 6 completes sealing element Allot, then issue sealing element from PC 26 to PC 24,28 and allot report (S218).This allots report can also be close in completion The training program of sealing issues before paying attention to the class.
The license of seal construction is issued from PC 24 to PC 26 at least using the training of seal construction as the instruction of condition, and And the instruction (S219) is notified to PC 28.License at least the paying attention to the class for item with seal construction training program of the seal construction Part.Since receive the PC 26 of the instruction to PC 24,28 and issue seal construction notify (S220).It is monitored in PC 26 Seal construction (S221) issues seal construction from PC 26 to PC 24,28 if seal construction terminates ("Yes" of S221) End notification (S222).
In PC 28, judge whether to continue to support (S223), in the case where continuing to support (S223's "Yes"), the notice (S224) for continuing to support is issued to PC 24,26.In the case where not continuing to support ("No" of S223), from PC 28 issues the end notification (S225) supported to PC 24,26.
<sealing element selecting system>
Sealing element database has been used in sealing element selecting system, is stored with gasket associated with use condition etc. Sealing element data.Sealing element tables of data 35 shown in fig. 6 has for example been used in the sealing element database.
Have the gasket group 36 comprising multiple pads in the sealing element tables of data 35, and including use temperature, use pressure, Using fluid, flange shape, be used to determine the conditional information of gasket using equipment and other information etc., using as with each gasket pair The use condition 38 answered.
If selecting 2 or more the conditions selected from use condition, the gasket of recommendation can be selected, and If selecting gasket, the use condition can be obtained.
The selected input picture 40 of sealing element shown in A during the sealing element is selected for example using Fig. 7.In the input picture In 40, have indicate sealing element selected theme portion 42, for example as the use temperature of 5 kinds of use condition, using pressure, Using fluid, flange shape, use the selector 44,46,48,50,52 and retrieval start button 54 of equipment.If choosing selection The select button 56 in portion 44,46,48,50,52 then successively shows the use temperature that select, using pressure etc..If with institute Value of display etc. selects select button 56, then can input required data.Then, if choosing retrieval start button 54, As shown in the B of Fig. 7, it is transferred to the selected output picture 60 of sealing element.
As shown in the B of Fig. 7, the theme portion 62 for indicating the selected results of sealing element is shown on the output picture 60, and " selected 1 ", " selected 2 " ... are shown as multiple selected results.It shown in each selected results comprising product number, used Multiple pads information 64-1,64-2 ... of condition etc. etc..Have return push-button 66 in the output picture 60, is returned if choosing this Button 66 is returned, then can be transferred to input picture 40 shown in the A of Fig. 7.
Fig. 8 shows the selected treatment process of sealing element.It, can be from seal construction management system in the treatment process Selection executes sealing element selection procedure, and the selected input picture 40 of display sealing element inputs use condition from the input picture 40 (S301).After inputting use condition, indicate to execute the selected processing (S302) of sealing element using retrieval.It is selected in the sealing element In processing, referring to the sealing element tables of data 35 of database (DB) 68.
If use condition match input condition, select gasket as with the matched sealing element of the use condition (S303)。
The gasket selected about this exports the gaskets such as above-mentioned use condition information and is shown on output picture 60 (S304), terminate the selected processing.
<seal construction training system 34>
Saying base system 34-1, having used multiple realities for practicing device comprising teaching form in seal construction training system 34 Trample the practice system 34-2 of form.
As shown in figure 9, saying that base system 34-1 has multiple PC 70 in the 1st Classroom 69-1.Each PC 70 is by network 72 connect with Training Server 30, are able to carry out the transmitting-receiving of information.Network 72 is any one in wired or wireless.
Have display 74 and input unit 76 in each PC 70.Display 74 can be to have on display picture and touch Panel and the structure of tangible input.Input unit 76 has keyboard, mouse, and has bar code reader.
Each trainer 78 is the responsible person of the seal constructions such as the practitioner as construction personnel 6.In such a case it is possible to To any one connection lecturer in each PC 70, to illustrate the content of teaching material.
Base system 34-1 is said according to such, trainer 78 can be made to gather in Classroom 69-1, with being sent to each PC 70 Display 74 on public lecture training teaching material learnt.Network 72 can also be according to circumstances set to open to internet 32 It puts, such as private tutoring etc. can be carried out by electronics training (E-training).
As shown in Figure 10, practice system 34-2 be it is multiple practice device, as an example of seal construction unit, there is flange Fastening practice device 80-1, creep mitigation practice device 80-2, leakproofness practices device 80-3 etc..These flange tightening arrangements 80-1, device 80-2 is practiced in creep mitigation, leakproofness practices device 80-3 and is set to the 2nd Classroom 69-2, is respectively provided with PC 82.Each PC 82 is connect by network 72 with Training Server 30, is able to carry out the transmitting-receiving of information.The embodiment has the 1st He 2nd Classroom 69-1,69-2 is but it is also possible to be single Classroom, further, it is also possible to have 3 or more Classrooms, and disperses Equipment is set.
Have data logger 84 and display 86 in each PC 82.Sensor is exported by the sensor from apparatus main body side It is taken into data logger 84, and is input to corresponding PC 82.Display 86, which can be, has touch panel on display picture And the structure of tangible input.As input unit, there is keyboard, mouse, and there is bar code reader.
According to such practice system 34-2, each trainer 78 can receive the support of the lecturer of seal construction, carry out with Training under the identical implementation condition of seal construction equipment.
<hardware of PC 24,26,28,70,82>
PC 90 shown in A of the PC 24,26,28,70,82 using Figure 11.Include processor 92 in the PC 90, deposit Storage portion 94, input and output portion (I/O) 96, operation inputting part 98 and communication unit 100.Display 102 is connect with I/O 96.
Processor 92 executes the OS (Operating System: operating system) being located in storage unit 94, support program, close The various programs such as envelope operational procedure, seal construction training program, sealing element selection procedure simultaneously carry out calculation process, various functions The information processings such as the control in portion.Storage unit 94 has ROM (Read-Only Memory: read-only memory), RAM (Random- Access Memory: random access memory) etc. recording mediums.The recording medium uses hard disk, semiconductor memory, DVD (Digital Versatile Disc: digital versatile disc) etc..Other than OS, also it is stored in the storage unit 94 The various programs such as seal construction sequence sequence, seal construction training program, sealing element selection procedure.The work of RAM configuration information processing Area.
Operation inputting part 98 is used for information input by the control of processor 92.In the operation inputting part 98 comprising keyboard, The information input equipments such as mouse, touch panel, bar code input unit.
Communication unit 100 is wirelessly connect with network 72 by Wi-Fi (Wireless Fidelity) etc..Display 102 is letter An example for ceasing prompt unit, as above-mentioned display 74,86 etc..
<hardware of Training Server 30>
As shown in the B of Figure 11, Training Server 30 has processor 104, storage unit 106, I/O 108 and communication unit 110.
OS, training program in the execution storage unit 106 of processor 104.I/O 108 is used for information input.Communication unit 110 passes through It is communicated by network 72 with above-mentioned PC 90.
Storage unit 106 has the recording mediums such as ROM, RAM, which uses hard disk, semiconductor memory, DVD etc. ?.Other than OS, the various programs such as seal construction training program are also stored in the storage unit 106.At RAM configuration information The workspace of reason.The database 68 for seal construction training program is stored in the storage unit 106.
<construction raining information table 112>
It as shown in figure 12, include classification 114, large project 116, middle project 118 and small project in raining information table 112 of constructing 120.Personal information 114-1, sealing information 114-2, construction information 114-3, training letter in classification 114 comprising substantially dividing Cease the various information such as 114-4, relevant information 114-5.It include administrator information and constructor's information in personal information 114-1.It is close Sealing includes sealing element information in information 114-2, includes construction equipment information, construction tool, seal construction in construction information 114-3 Require information etc..Include construction training program etc. in training information 114-4.Include strategy, standard letter in relevant information 114-5 Breath, analysis information, survey information, support information, statistical information etc..
It include personal information 114-1 in personal information table 122 as shown in the A of Figure 13.Include in personal information 114-1 It determines the administrator information of the manager of management seal construction and is determined as the constructor of the construction personnel 6 of responsible seal construction Constructor's information.It include department, each position and name in administrator information.If, can be true referring to personal information table 122 Recognize the determination for listening speaker and responsible position etc. of training program.
It include Business Name, department, each position, name and technical ability in constructor's information.It is close comprising constructor in technical ability Seal the skill level of construction.The performance information is determined using technical ability decision procedure.Therefore, if referring to the personal information Table 122 is then able to confirm that the determination of constructor, is responsible for the skill level of the seal constructions such as position, technical ability.
As shown in the B of Figure 13, in sealing element information/construction information table 124 comprising determine sealing element sealing element information, and It include name of product and size.It include the identification informations such as symbol, the specific names of determining producer in name of product.Size In include geomery, thickness of sealing element etc..
Include to be determined as the information of the construction equipment of object of seal construction in construction equipment information, and includes convex Edge, bolt/nut, fluid, pressure and temperature be used as in project 118.Include in flange information for determine the shape of flange, Standard (size) and material are using as small project 120.It include the size for determining bolt/nut in bolt/nut information With material using as small project 120.It include the classification for the fluid of seal construction equipment in fluid information.In pressure information It include the pressure for the fluid of seal construction equipment.It include the temperature for seal construction equipment in temperature information.
In construction tool information, about the construction tool for seal construction, include fastening tool and flanged tool with As middle project 118.It include hand spanner, manual torque spanner, torque amplification wrench, air torque wrench, liquid in fastening tool information Press torque wrench, bolt tensioner, ultrasonic wave axial force meter etc. using as small project 120.In flanged tool information, include Flange expander, flange opener, flange closer are using as small project 120.
Include the information for the material particular for indicating required in seal construction in seal construction require information, includes to protect Pipe, transportation resources, installation method, bolt/nut, fastening force and fastener cycle are using as middle project 118.Include in retention information There is its place as small project 120, include its means in transportation resources information as small project 120, in installation method information It include to use flanged tool, flange surface confirmation as small project 120, to include maintenance, lubrication material in bolt/nut information The type of material, replacement, material, size are using as small project 120.It include torque, axial force in fastening force information using as small Project 120.
It include the training information of construction training in raining information table 126, as shown in the A of Figure 14, as middle project 118 It include fastening method, stress mitigation, leakproofness, compression failure, surface pressure distribution, two kinds of live flange constructions.Fastening side In method information, device is practiced in flange fastening, torque feels that practicing device belongs to small project 120.Stress mitigates in information, and creep is slow Belong to small project 120 with device is practiced.In leakproofness information, leakproofness practices device and belongs to small project 120.Pressure destroys information In, compression failure practices device and belongs to small project 120.In surface pressure distribution information, bolt influence practices device and belongs to event Mesh.In one live flange construction information, in-site modeling fastening practices device and belongs to small project 120, another live flange is applied In work, piping calibration practices device and belongs to small project 120.
It include the related letter that should flexibly apply to seal construction training as shown in the B of Figure 14, in relevant information table 128 Breath.It include to trust and the assembling of safety in policy information, for example comprising qualification in standard information as middle project 118 Approval procedure standard includes cause of accident and analysis in analysis information, includes leakaging cause investigation result, branch in survey information It holds in information comprising Support center information.
<course lessons table 130>
It as shown in figure 15, include course 132, lessons 134, lessons content 136 and time 138 in course lessons table 130. Include core curriculum 130-1, higher level's course 130-2 and customization course 130-3 in course 132.It include lecture journey in lessons 134 Sequence practices program, lecture program or practices in program comprising Basic application, application program.Each lecture program and practice program In include " lecture (basis) ", " lecture (application) ", " practicing (basis) ", " practicing (application) " using as indicating that they are bases The identification information of plinth program or application program.The project for indicating the content to be learnt is stored in lessons content 136.Moreover, The numerical value for indicating learning time, the time of practice is stored in time 138.
<gasket lecture table 140>
It include lessons 142, rank 144 and content 146 in gasket lecture table 140 as shown in the A of Figure 16.In lessons 142 It include the project for indicating multiple lessons.It include to indicate that they are Basic application or application program " base in rank 144 Plinth " or " application ".In content 146, include learning Content according to each rank of lessons 142.
<gasket practices table 148>
As shown in the B of Figure 16, gasket, which is practiced, to be included lessons 150, rank 152, content 154 in table 148 and practices device 156.It include the project for indicating multiple lessons in lessons 150.Include in rank 152 indicate they be Basic application or " basis " or " application " of application program.It include learning Content according to each project of lessons 150 in content 154.And And in practicing device 156, device is practiced as the content study for lessons 150, for example, clear in " fastening method " It shows, uses " device is practiced in flange fastening " and " torque is felt to practice device " etc. are corresponding with lessons 150 to practice device.
<envelope axle pad piece lecture table 158>
As shown in the A of Figure 17, sealing in axle pad piece lecture table 158 includes lessons 160 and content 162.Include in lessons 160 There is the project for indicating multiple lessons.It include learning Content according to each project of lessons 160 in content 162.
<envelope axle pad piece practices table 164>
As shown in the B of Figure 17, envelope axle pad piece, which is practiced, to be included lessons 166, summary 168 in table 164 and practices device 170. It include the project for indicating multiple lessons in lessons 166.It include in study according to each project of lessons 166 in summary 168 Hold.Moreover, in practicing device 170, device is practiced in study as the content for lessons 166, for example, including " real machine Valve practices device with envelope axle pad piece ", " real machine rotary pump with seal axle pad piece practice device " etc..
<lecture prompt table 172>
It as shown in figure 18, include study project 174, the project of learning Content 176 and technical ability 178 in lecture prompt table 172. Prompt has multiple projects of learning Content in study project 174.There is in study project 174 prompt in learning Content 176 includes The purpose and summary of learning Content.In technical ability 178, selection corresponding with corresponding position and new person is indicated with "○" or " ◎ " Different degree."○" indicates " it is necessary to ", or " ◎ " expression " extremely important ".
<practicing prompt table 180>
As shown in figure 19, it practices in prompt table 180 comprising practicing project 182, practice content 184, technical ability 186 and device name Claim 188.Practicing prompt in project 182 has the multiple projects for indicating practice content 184 blanketly.There is prompt in practice content 184 Practice the purpose and summary of the practice content for including in project 182.In technical ability 186, indicated with "○" or " ◎ " and corresponding Position and the corresponding selection of new person different degree."○" indicates " it is necessary to ", alternatively, " ◎ " expression " extremely important ".Device It is clearly denoted in title 188 and practices device accordingly.
<training input picture 190>
Training input picture 190 has been used in training program.As shown in the A of Figure 20, have in training input picture 190 Indicate theme portion 192, the Business Name input unit 194, department name input unit 196, name input of the input of trainer's information Portion 198, technical ability input unit 200 and pay attention to the class place input unit 201.There is select button 202, Neng Goutong in technical ability input unit 200 Cross the technical ability for choosing button 202 to determine selection.The training, which inputs, has confirming button 204 in the lower column of picture 190.If hooked The confirming button 204 is selected, then can determine inputted trainer's information.
<training output picture 206>
When training program is completed, expansion training output picture 206.As shown in the B of Figure 20, which exports picture 206 On show indicate training complete data theme portion 208 and training contents display unit 210.It is shown in training contents display unit 210 It is shown with name 210-1, department name 210-2, completes course name 210-3, evaluation 210-4, other relevant information 210-5.
<treatment process of seal construction training>
Figure 21 shows the treatment process of seal construction training.The treatment process is seal construction training program or sealing An example of construction Training Methodology.
In the treatment process of seal construction training, according to the training screen of PC, determine whether to train as to training The wish of person confirms (S401).When being transferred to training ("Yes" of S401), it is confirmed whether to recognize that sealing element is selected important Property (S402).If not recognizing the selected importance ("No" of S402) of sealing element, implement the selected training of sealing element (S403).About the training that the sealing element is selected, as long as re-starting the study of lecture.Like this, confirmation is to sealing element Selected understanding it is intended that identification be used for actual seal construction sealing element, be sealed and applied premised on the identification The training of work improves result of training.If the selected training (S403) of sealing element terminates, S402 is returned.
If having realized that the selected importance ("Yes" of S402) of sealing element, the technical ability of the person of giveing training determines (S404).The technical ability determines that the treatment process (Figure 22) determined by technical ability carries out.
After technical ability judgement, the course selection (S405) that gives training.The processing that the course selection passes through course selection Process (Figure 23) carries out.
After course selection, the wish (S406) of training is confirmed, ("Yes" of S406) is started by training, is carried out first The training (S407) of lecture program.The lecture program is terminated by saying that base system 34-1 is carried out according to the subject of regulation and time.? In this case, may require that and relearn according to the difference of evaluation.
If the lecture EP (end of program) ("Yes" of S408), is transferred to and practices program (S409).This is practiced program and passes through Practice system 34-2 is carried out, and according to the subject of regulation and selection of time equipment and carries out necessary practice.In this case, it carries out Based on the evaluation of input information, it may require that and relearn according to the difference of the evaluation, which exported based on sensor Or the input information of training.
If this practices EP (end of program) ("Yes" of S410), the training program of seal construction terminates, and is prompted and is shown Show completion (S411).
<treatment process that technical ability determines>
Figure 22 shows the treatment process of technical ability judgement.When be transferred to technical ability judgement treatment process when, to be new person also It is that ordinary people is determined (S501).The processing is carried out according to the input information of trainer." new person " indicates seal construction Related personnel, but should " new person " do not have experience related with seal construction or be equal to babe in the wood completely." one As " it is contemplated that at the desired training for receiving seal construction such as student ordinary people.
It if it is new person or ordinary people's ("Yes" of S501), then selects technical ability 1 (S502), returns to seal construction training journey The S404 of sequence (Figure 21).
If not new person or ordinary people's ("No" of S501), then performance information input (S503) is transferred to.In technical ability In information input, input technical ability determines required information, carries out technical ability judgement (S504) according to the information input.Pass through the technical ability Determine, from multiple technical ability distribute technical ability 2, technical ability 3 ... any one (S505) in technical ability N.In this example embodiment, it trains Person is divided into N number of grade from minimum technical ability 1 to highest technical ability N, returns to the S404 of seal construction training program (Figure 21). The grade of skill can be any one in 2 grades, 3 grades, 4 grades, 5 grades etc..
<treatment process that course determines>
Figure 23 shows the treatment process of course selection.When being transferred to the treatment process of course selection, to be new person also It is that ordinary people is determined (S601).As described above, the processing is carried out according to the input information of trainer.
If it is new person or ordinary people's ("Yes" of S601), then basic course (S602) is selected, returns to seal construction The S405 of training program (Figure 21).
If not new person or ordinary people's ("No" of S601), then customization course (S603) is determined whether.If no It is customization course ("No" of S603), the occupation for then not giveing person training determines (S604).Determined according to occupation, from multiple higher level's classes Higher level's course 1, any one (S605) in higher level's course 2 ... higher level's course N are selected in journey.
If it is customization course ("Yes" of S603), the occupation for then not giveing person training determines (S606).Determined according to occupation, Selection customization course 1, customization course 2 ... customize any one (S607) in course N from multiple customization courses.
<lecture program>
There are basic course, higher level's course and customization course in lecture program, saying for lecture corresponding with each course is carried out Class.
In addition, teaching in envelope axle pad piece lecture for envelope axle pad piece.
<practicing program>
With basic course, higher level's course and customization course, practice corresponding with each course is carried out.In the practice, make With device is practiced in the fastening of aftermentioned flange, leakproofness practices device, device is practiced in creep mitigation, torque is felt to practice device, matches Pipe calibration practice device, in-site modeling fastening practice device, compression failure practices device, heat exchanger is practiced device etc. and simulated The multiple of scene practice device.According to the execution for practicing program, equipment required for being selected from these equipment.
In addition, practicing device with envelope axle pad piece using real machine rotary pump, real machine valve seals axle pad in envelope axle pad piece practice Piece practices device.
<system, the methods and procedures of seal construction training>
In the seal construction training system, as the seal construction Training Methodology for having used computer, for example, such as Figure 24 It is shown, it include equipment selection process (S701), the acquirement process (S702) of sensor output or training information, analog information The treatment process of generation process (S703), the prompt process (S704) of analog information.
In equipment selection process (S701), from the Classroom that an example as single or multiple Classrooms is arranged in Device 80-1 is practiced in flange fastening in 69-2, device 80-2 is practiced in creep mitigation, leakproofness practices the selections such as device 80-3 training Equipment needed for instruction.It, can also the equipment comprising simulation piping calibration, simulation fastening other than above equipment in the equipment Equipment, simulate sealing state equipment, the equipment of simulation flange fastening, simulate the equipment of creep, analog compression is destroyed sets Standby, simulation heat-exchange apparatus equipment.
In the acquirement process (S702) of sensor output or training information, each equipment institute of seal construction equipment is obtained The sensor for the sensor having exports, or obtains training information from input unit.
In the generation process (S703) of analog information, receiving sensor output or training information, generation are applied with sealing The analog information of included device-dependent in construction equipment.
Then, in the prompt process (S704) of analog information, with any one in text information or graphical information Or both sides prompt analog information.The information alerts units such as display 86 are used in the prompt of the information.
In the seal construction training system, the seal construction equipment being arranged in Classroom 69-2 (Figure 10) can be tool There is the equipment of the sensor of detection fastening axial force, is also possible to the equipment without sensor.For not having sensor Equipment, as long as using keyboard, the information processing terminal as the input unit of training information.
Processing unit uses the information processing equipments such as above-mentioned PC 82.In the processing unit, receiving sensor is defeated Out or training information, the analog information with device-dependent included in seal construction is generated.In the processing unit, as Connected information alert unit in wired or wireless manner, such as use display 86.The information alert unit With, as display mode, prompt is exported from processing unit either or both of in text information or graphical information etc. Processing output.
The seal construction training program executed by the processing unit is stored in the storage unit 106 of above-mentioned Training Server 30 In, it is executed in training.The seal construction training program has same as the above-mentioned treatment process of seal construction Training Methodology , for execute training processing program function.The function includes equipment selection function, obtains sensor output or training The function of information, the systematic function of analog information, analog information prompt facility.In equipment selection function for example comprising from The function of equipment needed for selection training in seal construction equipment, the seal construction equipment include: simulation piping calibration Equipment, the equipment of simulation fastening, the equipment for simulating sealing state, the equipment of simulation flange fastening, the equipment for simulating creep, simulation The equipment of compression failure, the equipment for simulating heat-exchange apparatus.Moreover, the systematic function of analog information is exported comprising receiving sensor Or training information and function with the analog information of device-dependent included in seal construction equipment is generated, analog information Prompt facility includes the function that analog information is prompted with any one or the both sides in text information or graphical information.
<effect of the 2nd embodiment>
According to the 2nd embodiment, following effect can get.
(1) it can be designated as opportunity with the promotion of the seal construction issued from PC 28, from the seal construction that PC 24 is issued, Uniformly it is sealed part selected, sealing element is alloted with seal construction training, it can be achieved that the high precision int and height of seal construction Effectization.
(2) opportunity is designated as with the seal construction from PC 24, construction personnel 6 receives seal construction training in Support center 8 Instruction, the sealing element of the urgent need when Support center 8 is sealed construction are alloted, and the practice of the sealing element is carried out.
(3) client 4 indicates that the sealing element of going out is selected in the purchase of construction personnel 6 in Support center 8.Thus full to select The sealing element of sufficient seal construction object.I.e. it is capable to ensure the reliability of chosen sealing element.
(4) it can be selected used in Support center 8 in the construction personnel 6 that Support center 8 has participated in seal construction training close Sealing is sealed construction to seal construction object.As a result, it is possible to improve the high precision int of seal construction and reliability.
Embodiment 1
Device 80-1 is practiced in the flange fastening that the A of Figure 25 shows embodiment 1.Device 80-1 is practiced in flange fastening In, apparatus main body portion 222 has a 1st seal construction portion 224-1, the 2nd seal construction portion 224-2, each seal construction portion 224-1, 224-2 has the different bamp joint of diameter, has sandwiched gasket 228-1,228-2 between flange 226, and have multiple bolts 230 and nut 232.Trainer for example uses torque wrench as construction tool, and successively fastening nut 232, are sealed construction.
As shown in the B of Figure 25, has strain transducer 234 on each bolt 230.Each detection of strain transducer 234 is because of spiral shell The tightening torque τ of mother 232 and the axial force that is generated on bolt 230.
Sensor output is taken into PC 82 by data logger 84 (Figure 10).PC 82 is by the axial direction in fastening Power is displayed in real time on display 86 using polygonal shape, which indicates axial force with the distance to center Size.
In the practice for having used flange fastening to practice device 80-1, make trainer's identification due to caused by construction tool The deviation of fastening, due to fastening force and the axial force of adjacent bolt caused by elastic interaction it is relational, due to inappropriate Fastener cycle and the unilateral fastening etc. that generates, and trainer is made to understand fastening force, fastener cycle for playing gasket function Etc. material particulars.The training result and trainer are saved in association in construction raining information table 112.
Embodiment 2
Device 80-2 is practiced in the creep mitigation that the A of Figure 26 shows embodiment 2.In the A of Figure 26, to identical with Figure 25 Part marks identical label.It is practiced in device 80-2 in creep mitigation, is matching pipe portion 235 across seal construction portion 224-3 On having heaters 236-1,236-2 is respectively set.Heater 236-1,236-2 are heat transfer heaters.
Gasket 228 has been sandwiched between flange 226, and has multiple bolts 230 and nut 232.As shown in the B of Figure 26, Has strain transducer 234 on each bolt 230.
In the practice that creep mitigates, for the different gasket of material, the drive manners such as high temperature operation, cycle operation are simulated As operating condition, by the variation of the axial force after the detection fastening of each strain transducer 234.It runs at high speed, cycle operation utilizes It is simulated based on the temperature controlled temperature change of heater 236-1,236-2.
It is practiced in device 80-2 in creep mitigation, the surface after detecting the fastening that can not be observed in real machine in real time Pressure declines to change as axial force, and shows that the axial force changes.Thereby, it is possible to identify trainer under surface pressing Drop, the effective opportunity grasping initial fastening force and tightening.
Embodiment 3
The leakproofness that Figure 27 shows embodiment 3 practices device 80-3.In Figure 27, part identical with Figure 25 is marked Identical label.It is practiced in device 80-3 in the leakproofness, apparatus main body portion 222 has the 1st seal construction portion 224-1, the 2nd sealing Construction portion 224-2 sandwiches gasket 228 between each flange 226, and has multiple bolts 230 and nut 232.
Have on being located at the top side in apparatus main body portion 222, closed side flange 226 in apparatus main body portion 222 The pressure sensor 239 of the pressurizing device 238 and the pressure in detection device main part 222 that pressurize.Pressure sensor Pressure change caused by 239 detections are deteriorated due to the sealing of seal construction portion 224-1,224-2.
The leakproofness of seal construction portion 224-1,224-2 due to flange 226, gasket 228, bolt 230 and be affected.It is convex Damage, surface roughness, the corrosion on the surface of edge 226 will affect the leakproofness of gasket 228, the damage on the surface of gasket 228, dirt The attachment of angstrom equal foreign matters will affect the leakproofness of gasket 228, and in bolt state aspect, iron rust, lubriation material will affect gasket 228 Leakproofness.
It is practiced in device 80-3 in the leakproofness, each shape due to flange 226, gasket 228 or bolt 230 can be reproduced Failure caused by state, the method for making trainer grasp leak test.
Embodiment 4
Device 80-4 is practiced in the in-site modeling fastening that Figure 28 shows embodiment 4.In Figure 28, to portion identical with Figure 25 Minute mark infuses identical label.It practices in device 80-4 in in-site modeling fastening, is simulated under mal-condition in seal construction operation Seal construction scene, make trainer grasp seal construction.
At seal construction scene, can be forced to carry out the seal construction under the mal-conditions such as eminence, narrow place, barrier.In addition to Other than eminence, for example, piping, shelf, works, equipment etc. are intricate, there are small spaces etc..As shown in the A of Figure 28, deposit In adjacent and bamp joint 242-1,242-2,242-3 phase as seal construction portion of multiple piping 240-1,240-2,240-3 Adjacent situation.As shown in the B of Figure 28, it is adjacent there are multiple piping 240-4,240-5 and intersect and as the convex of seal construction portion Adjacent situation in edge connector 242-4,242-5 cross section.In addition, there is piping 240-6 and knot as shown in the C of Figure 28 Structure object 244 is adjacent to arranging and the bamp joint 242-6 situation adjacent with works 244.Imagine showing for such seal construction Field situation, at the scene simulation fastening are practiced in device 80-4, and the sealing for reproducing the imaginations such as eminence, narrow place, barrier freely is applied Work scene makes trainer grasp the seal construction under the mal-condition for interfering workability.
Embodiment 5
Device 80-5 is practiced in the piping calibration that Figure 29 shows embodiment 5.In Figure 29, part identical with Figure 25 is marked Infuse identical label.At the scene of seal construction, following situation etc. can be met with: as shown in the A of Figure 29, it should the piping 240- of connection 11, the interval of each flange 226 of 240-12 is larger;As shown in the B of Figure 29, it is piped between each flange 226 of 240-11,240-12 Every relatively narrow;As shown in the C of Figure 29, due to there is inclination between each flange 226 of piping 240-11,240-12, so can not put down Row;And as shown in the D of Figure 29, it is piped between each flange 226 of 240-11,240-12 and there is bias.In this case, even if With the fastening of uniform fastening force, fastening force appropriate also is transmitted without normal direction gasket 228.Device 80-5 is practiced in piping calibration In, setting gap, slope, bias etc. and actual not calibrated situation is reproduced freely, trainer is made to practice not calibrated situation The seal construction not being resolved.For these situations, fastening (surface pressing) situation of trainer is evaluated.
Embodiment 6
The structure of heat exchanger is more complicated than the flange of general pipe connection, and seal construction requires to understand the heat exchanger Structure.In fixed tube sheet, due to sandwiching 2 gaskets between the flanges and fastening, so being easy to produce unilateral fastening.Big In the flange of diameter, bolt radical is more, adjacent in fastening caused by can not ignoring because of the elastic interaction between flange Fastening force decline between bolt.In addition, about demarcation plate, when Pipe Flange/shell flange generates it is eccentric when, can generate demarcation plate without Method enter in slot and a problem that on slot.Such special tectonic requires most suitable fastening force, appropriate construction The selected and fastener cycle of tool.
It is practiced in device in the heat exchanger, heat exchanger is made to become decomposing state, while real machine training, make to train Person practices the bolt fastening of fixed tube sheet required when seal construction, Pipe Flange/shell flange core alignment etc..
Embodiment 7
It is practiced in device in compression failure, trainer is made to grasp the compression failure etc. because of gasket caused by fastening excessive wait. About compression failure, the shape for being easy to produce compression failure has been reproduced for the type of gasket, thickener coating, minor diameter flange etc. Condition makes trainer grasp the main reason for leaking and its prevent.For example, can be enumerated situations such as following: expanded graphite sheet gasket Compression failure in, surface pressing be lower than other gaskets;In thickener coating, leakproofness is improved, but it is broken to be easy to produce compression It is bad;And in minor diameter flange, due to the radical relative to bolt, gasket area is smaller, and surface pressing is easy to increase, so It is easy to produce compression failure.
Therefore, it is practiced in device in the compression failure, for as compression failure the main reason for leakage, can make to train Instruction person grasps the type of gasket, whether there is or not thickener and as compression failure the main reason for crack deformation or crackle etc. between pass System.
Embodiment 8
In other embodiments, torque has been used to feel that practicing device, real machine rotary pump practices device, reality with envelope axle pad piece Machine valve practices device with envelope axle pad piece.Feel to practice in device in torque, trainer can be made to experience relative to fastening condition not Same multiple screw bolt and nut, the variation of tightening torque and axial force.
[other embodiments]
(1) movable-type practices equipment: seal construction system, the seal construction management system of above embodiment do not limit Equipment is practiced in setting type.Equipment can also be practiced using following movable-type, it can be in the meeting room of client, training Heart etc. is learnt, and can be realized the seal construction for improving the convenience of client.It is practiced in equipment in the movable-type, example Such as, there is the movable-type pedestal etc. for realizing space saving for the area needed for learning, above-mentioned flange is fastened into practice Equipment, torque feel that practicing multiple equipment of practicing such as equipment is arranged on movable-type pedestal.Each equipment is set as can Pass through trolley mobile weight and size.
Equipment is practiced for such movable-type, for example, as shown in figure 30, being aggregated into training table 246, if made Device name 248, basis/application selection 250 can be selected, title 252, practice content 254 are practiced and could implement 256 Deng seal construction corresponding with needs such as budgets then may be implemented.
(2) acquirement of sealing element information: in the 1st embodiment and the 2nd embodiment, by the selected as close of sealing element The permissive condition of construction is sealed, but can also be by the permissive condition of sealing element information obtained as seal construction.Implement about the 1st Mode can receive the sending (S104) of the selected instruction of sealing element from client 4, obtain in Support center 8 as shown in figure 31 Sealing element information (S112) notifies it to obtain result (S113) to client 4 and construction personnel 6.About the 2nd embodiment, such as scheme Shown in 32, the sending (S206) for being also possible to receive the selected instruction of sealing element from PC 24 with PC 28 is sealed for opportunity The acquirement (S226) of part information notifies it to obtain result (S227) to PC 24 and PC 26.In such a process, exist as follows Convenience, can without sealing element it is selected in the case where obtain sealing element information, client 4 or construction personnel 6 obtain institute The sealing element needed, is sealed construction.
(3) sealing element of training program is selected: in the processing shown in Figure 21, using following treatment process: confirmation is The selected training (S403) of the no importance (S402) for recognizing that sealing element is selected, sealing element, but not limited to this.For example, as schemed Shown in 33, following treatment process can also be used: with training start determine whether to have selected sealing element (S412) for opportunity, If unselected sealing element ("No" of S412), it is sealed selected (S413) of part, sealing element is selected as condition turn It moves on to technical ability and determines (S404).
(4) information input: in the training input picture 190 for information input, as shown in the A of Figure 20, training is had input Instruction person's information, but not limited thereto.For example, as shown in figure 34, it can be using such as flowering structure: in addition to affiliated, responsible as input Other than the input unit 191 of people's information, it can also be directed in advance and pay attention to the class the preparation of content 193 number of days, number, pay attention to the class place, course etc. Detailed content is carried out to the choosing of check box, information selection.As other information input, also can be set into can input it is standby Infuse item 195.
(5) practice device and obtain the processing of information: what is used in the above-described embodiment practices in device comprising having Detect practicing device and practicing this both sides of device without sensor for the sensor of axial force etc. of bolt.It is passed not having Sensor is practiced in device, is inputted relevant information to as with the PC for practicing related information input unit, is believed according to the correlation Breath generates analog information.
(6) sealing element and its seal construction: in the above-described embodiment, instantiating gasket as sealing element, but can also be with It is other sealing elements.In addition, above-mentioned seal construction not only considers the use aspect of sealing element, it is also contemplated that design, manufacture view.
As described above, most preferred embodiment of the invention, embodiment are illustrated.The present invention is unlimited Due to above-mentioned record.Those skilled in the art can of course be according to the record of claims or for carrying out an invention or in fact It applies inventive concept disclosed in the mode of example and carries out various modifications and changes.The deformation, change are also contained in model of the invention certainly In enclosing.
Industrial availability
In accordance with the invention it is possible to make client PC, construction personnel PC and Support center PC cooperation, realize for construction personnel's Seal construction training, selected and purchase the unified management of sealing element, improve the precision of seal construction, improve reliability.
Label declaration
2: seal construction system;4: client;6: construction personnel;8: Support center;20: seal construction management system;24, 26,28:PC;30: Training Server;32: internet;34: seal construction training system;34-1: base system is said;34-2: practice System;35: sealing element tables of data;36: gasket group;38: use condition;40: input picture;42: theme portion;44,46,48,50, 52: selector;54: retrieval start button;56: select button;60: output picture;62: theme portion;64-1,64-2 ...: pad Piece information;66: return push-button;68: database;69-1,69-2: Classroom;70:PC;72: network;74: display;76: input Device;78 trainers;80-1: device is practiced in flange fastening;80-2: device is practiced in creep mitigation;80-3: leakproofness practice dress It sets;80-4: device is practiced in in-site modeling fastening;80-5: device is practiced in piping calibration;82:PC;84: data logger;86: aobvious Show device;90:PC;92: processor;94: storage unit;96: input and output portion (I/O);98: operation inputting part;100: communication unit; 102: display;104: processor;106: storage unit;108:I/O;110: communication unit;112: construction raining information table;114: class Not;116: large project;118: middle project;120: small project;114-1: personal information;114-2: sealing information;114-3: construction Information;114-4: training information;114-5: relevant information;122: personal information table;124: sealing element information/construction information table; 126: raining information table;128: relevant information table;130: course lessons table;130-1: core curriculum;130-2: higher level's course; 130-3: customization course;132: course;134: lessons;136: lessons content;138: the time;140: gasket lecture table;142: class Industry;144: rank;146: content;148: gasket practices table;150: lessons;152: rank;154: content;156: practicing device; 158: envelope axle pad piece lecture table;160: lessons;162: content;164: envelope axle pad piece practices table;166: lessons;168: summary; 170: practicing device;172: lecture prompt table;174: study project;176: learning Content;178: technical ability;180: practice prompt Table;182: practicing project;184: practice content;186: technical ability;188: device name;190: training input picture;192: theme Portion;194: department name input unit;196: each position input unit;198: name input unit;200: technical ability input unit;202: selection Button;204: confirming button;206: training output picture;208: theme portion;210: training contents display unit;210-1: name; 210-2: department name;210-3: course name is completed;210-4: evaluation;210-5: relevant information;222: apparatus main body portion; 224-1: the 1 seal construction portion;224-2: the 2 seal construction portion;224-3: seal construction portion;226: flange;228: gasket; 228-1,228-2: gasket;230: bolt;232: nut;234: strain transducer;235: matching pipe portion;236-1,236-2: heating Device;238: pressurizing device;239: pressure sensor;240-1,240-2,240-3: piping;240-4,240-5,240-6: piping; 240-11,240-12: piping;242-1,242-2,242-3: bamp joint;242-4,242-5,242-6: bamp joint;244: Works;246: training table;248: device name;250: basis/application selection;252: practicing title;254: practice content; 256: could implement.

Claims (17)

1. a kind of seal construction system makes the client for ordering seal construction, undertakes the construction personnel of seal construction and support close The Support center of envelope construction cooperates, wherein
Instruction is paid attention to the class from what the client was emitted in seal construction training that the Support center carries out to the construction personnel,
It is designated as opportunity with described pay attention to the class, listening for the seal construction training is carried out in the Support center with the construction personnel It says as condition, permits the seal construction of the construction personnel.
2. seal construction system according to claim 1, wherein
Also be designated as opportunity to pay attention to the class described in the client, provide the selected of sealing element required for the seal construction or The information of the sealing element allots instruction from what the client issued the sealing element to the construction personnel.
3. a kind of seal construction system makes the client for ordering seal construction, undertakes the construction personnel of seal construction and support close The Support center of envelope construction cooperates, wherein
Instruction is paid attention to the class from what the client was emitted in seal construction training that the Support center carries out to the construction personnel,
It is designated as opportunity to pay attention to the class described in the client, the sealing is carried out to the construction personnel in the Support center and is applied Work training, selected or the sealing element the information of sealing element needed for the seal construction is provided,
Instruction is alloted from what the client issued the sealing element to the construction personnel, to have carried out the seal construction training For condition, permit seal construction.
4. a kind of seal construction management method keeps client computer, construction personnel's computer and Support center computer mutual It ordinatedly executes, wherein the seal construction management method is with the following process:
The seal construction training that Support center carries out is emitted in construction personnel's computer from the client computer to listen Say that instruction and sealing element and this both sides of seal construction tool or at least sealing element allot instruction;
Seal construction training described in the Support center computer management, receives the instruction of the client computer, and selectes close Sealing element needed for envelope construction or the information for obtaining the sealing element.
5. a kind of seal construction management method keeps client computer, construction personnel's computer and Support center computer mutual It ordinatedly executes, wherein the seal construction management method is with the following process:
The seal construction training that Support center carries out is emitted in construction personnel's computer from the client computer to listen Say that instruction and sealing element and this both sides of seal construction tool or at least sealing element allot instruction;
Seal construction training described in the Support center computer management, receives the instruction of the client computer, and selectes close Sealing element needed for envelope construction or the information for obtaining the sealing element;
What construction personnel's computer at least notified the seal construction training to the client computer pays attention to the class report;And
What the client computer at least received the seal construction training from construction personnel's computer pays attention to the class report, and right Construction personnel's computer issues the license of the seal construction using the sealing element.
6. seal construction management method according to claim 4 or 5, wherein the seal construction management method also include with Lower process: the Support center computer and at least one party's phase in the client computer or construction personnel's computer Associatedly manage any one in the seal construction, the seal construction training and the purchase of the sealing element or two More than.
7. according to seal construction management method described in any one in claim 4~6, wherein
The seal construction management method also includes the following process: referring to from the client computer to construction personnel's computer Before showing seal construction, the Support center computer issues the seal construction promotion for the client computer.
8. according to seal construction management method described in any one in claim 4~7, wherein
The seal construction management method also includes following process: the Support center computer obtains the note of the seal construction Record prompts seal construction information at least one party in the client computer and construction personnel's computer.
9. according to seal construction management method described in any one in claim 4~8, wherein
The seal construction tool includes flange perimeter component, fastening tool and the information terminal for being stored with flange fastening information.
10. a kind of seal construction management system, wherein
There is the seal construction management system mutually matched client computer, construction personnel's computer and Support center to calculate Machine,
The seal construction training that Support center carries out is emitted in construction personnel's computer from the client computer to listen Say that instruction, sealing element and this both sides of seal construction tool or at least sealing element allot instruction,
Seal construction training described in the Support center computer management, receives the instruction of the client computer, and selectes close Sealing element needed for envelope construction or the information for obtaining the sealing element.
11. a kind of seal construction management system, wherein
There is the seal construction management system mutually matched client computer, construction personnel's computer and Support center to calculate Machine,
The seal construction training that Support center carries out is emitted in construction personnel's computer from the client computer to listen Say that instruction, sealing element and this both sides of seal construction tool or at least sealing element allot instruction,
Seal construction training described in the Support center computer management, receives the instruction of the client computer, and selectes close Sealing element needed for envelope construction or the information for obtaining the sealing element,
What construction personnel's computer at least notified the seal construction training to the client computer pays attention to the class report,
The client computer at least receives the report of paying attention to the class of the seal construction training from construction personnel's computer, and to Construction personnel's computer issues the license of the seal construction using the sealing element.
12. a kind of seal construction management program, real by client computer, construction personnel's computer and Support center computer It is existing, wherein the seal construction management program is for making the computer realize following functions:
The seal construction training that Support center carries out is emitted in construction personnel's computer from the client computer to listen Say that instruction and sealing element and this both sides of seal construction tool or at least sealing element allot instruction;And
Seal construction training described in the Support center computer management, receives the instruction of the client computer, and selectes close Sealing element needed for envelope construction or the information for obtaining the sealing element.
13. a kind of seal construction management program, real by client computer, construction personnel's computer and Support center computer It is existing, wherein the seal construction management program is for making the computer realize following functions:
The seal construction training that Support center carries out is emitted in construction personnel's computer from the client computer to listen Say that instruction and sealing element and this both sides of seal construction tool or at least sealing element allot instruction;
Seal construction training described in the Support center computer management, receives the instruction of the client computer, and selectes close Sealing element needed for envelope construction or the information for obtaining the sealing element, construction personnel's computer are at least calculated to the client What machine notified the seal construction training pays attention to the class report;And
The client computer at least receives the report of paying attention to the class of the seal construction training from construction personnel's computer, and to Construction personnel's computer issues the license of the seal construction using the sealing element.
14. a kind of seal construction Training Methodology, it includes following processes:
Equipment needed for selection training, the seal construction are set from the seal construction equipment for being set to single or multiple Classrooms Standby includes: that simulation is piped the equipment of calibration, the equipment of simulation fastening, the equipment for simulating sealing state, simulates setting for flange fastening Standby, simulation creep equipment, the equipment that analog compression is destroyed, the equipment for simulating heat exchanger;And
The sensor output for the sensor that each equipment in the seal construction equipment has is obtained, or is taken from input unit Obtain training information.
15. a kind of seal construction Training Methodology, it includes following processes:
Equipment needed for selection training, the seal construction are set from the seal construction equipment for being set to single or multiple Classrooms Standby includes that simulation is piped the equipment of calibration, the equipment of simulation fastening, the equipment for simulating sealing state, simulates setting for flange fastening Standby, simulation creep equipment, the equipment that analog compression is destroyed, the equipment for simulating heat exchanger;
The sensor output for the sensor that each equipment in the seal construction equipment has is obtained, or is taken from input unit Obtain training information;
The sensor output or the training information are received, generating has with equipment included in the seal construction equipment The analog information of pass;And
The analog information is prompted using either or both of in text information and graphical information.
16. a kind of seal construction training system, includes
Single or multiple Classrooms;
Seal construction unit is set to the Classroom, equipment, the equipment of simulation fastening, mould including simulation piping calibration Equipment, the simulation heat that the equipment of quasi- sealing state, the equipment of simulation flange fastening, equipment, the analog compression for simulating creep are destroyed Any one in the equipment of exchanger or two or more;
Acquisition unit, obtain the sensor that each equipment in the seal construction unit has sensor output or with The training information of the device-dependent;
Processing unit receives the sensor output or the training information, generates and institute in the seal construction unit Including device-dependent analog information;And
Information alert unit connect with the processing unit in wired or wireless manner, utilizes text information and figure The processing output exported from the processing unit is prompted either or both of in information.
17. one kind is by computer implemented seal construction training program, which is realized by computer Following functions:
Equipment of the selection for training from seal construction unit, equipment of the seal construction unit comprising simulation piping calibration, The equipment for simulating fastening, the equipment for simulating sealing state, the equipment of simulation flange fastening, equipment, the analog compression for simulating creep Any one in the equipment of destruction, the equipment of simulation heat exchanger or two or more;
It obtains the sensor output for the sensor that each equipment in the seal construction unit has or has with the equipment The training information of pass;
The sensor output or the training information are received, generating has with equipment included in the seal construction unit The analog information of pass;And
The analog information is prompted using either or both of in text information and graphical information.
CN201780049429.1A 2016-07-29 2017-07-20 Sealing construction system, sealing construction management method, and recording medium Active CN109564673B (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2016-149493 2016-07-29
JP2016149493 2016-07-29
PCT/JP2017/026232 WO2018021135A1 (en) 2016-07-29 2017-07-20 Sealing work, sealing work management and sealing work training system, program and method

Publications (2)

Publication Number Publication Date
CN109564673A true CN109564673A (en) 2019-04-02
CN109564673B CN109564673B (en) 2023-06-16

Family

ID=61016262

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201780049429.1A Active CN109564673B (en) 2016-07-29 2017-07-20 Sealing construction system, sealing construction management method, and recording medium

Country Status (6)

Country Link
JP (2) JP6616513B2 (en)
KR (1) KR102184475B1 (en)
CN (1) CN109564673B (en)
SG (1) SG11201900792RA (en)
TW (1) TWI757310B (en)
WO (1) WO2018021135A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112106128A (en) * 2018-05-11 2020-12-18 株式会社华尔卡 Flange fastening training system, device, program, method, and information terminal
KR20230066771A (en) 2021-11-08 2023-05-16 김지훈 Installation work management system of semiconductor manufacturing equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002041801A (en) * 2000-07-21 2002-02-08 Tatsutoushi Midorikawa Method and system for contract for flaw guarantee responsibility insurance in construction industry
JP2003140540A (en) * 2001-10-30 2003-05-16 Total Staff:Kk Employee training system
US20070048702A1 (en) * 2005-08-25 2007-03-01 Jang Gil S Immersion-type live-line work training system and method
EP1614375B1 (en) * 2000-06-05 2008-12-17 LIBERMAN, Barnet, L Method of delivering items purchased over the Internet
JP2009191932A (en) * 2008-02-14 2009-08-27 Hitachi Plant Technologies Ltd Equipment and material for flange fastening training

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CZ298178B6 (en) * 1998-03-02 2007-07-11 Northeast Equipment, Inc. Doing Business As Deltamechanical Seals Apparatus for precise determination of a seal for a piece of equipment
JP2001338197A (en) * 2000-05-29 2001-12-07 Maruni Toryo Kk Method for reserving prescribed device and device for reserving potter's wheel
JP2006268528A (en) * 2005-03-24 2006-10-05 Chugoku Electric Power Co Inc:The Orderer liability support system
JP5068460B2 (en) * 2006-01-30 2012-11-07 コスモ石油株式会社 Education support device and education support system
JP5050779B2 (en) * 2007-10-29 2012-10-17 トヨタ自動車株式会社 Training work curriculum creation device
TWM441173U (en) * 2012-05-17 2012-11-11 Univ Ching Yun E-management device for construction engineering
JP2015141345A (en) * 2014-01-29 2015-08-03 日本バルカー工業株式会社 Flange fastening training system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1614375B1 (en) * 2000-06-05 2008-12-17 LIBERMAN, Barnet, L Method of delivering items purchased over the Internet
JP2002041801A (en) * 2000-07-21 2002-02-08 Tatsutoushi Midorikawa Method and system for contract for flaw guarantee responsibility insurance in construction industry
JP2003140540A (en) * 2001-10-30 2003-05-16 Total Staff:Kk Employee training system
US20070048702A1 (en) * 2005-08-25 2007-03-01 Jang Gil S Immersion-type live-line work training system and method
JP2009191932A (en) * 2008-02-14 2009-08-27 Hitachi Plant Technologies Ltd Equipment and material for flange fastening training

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
高永军等: "如何做好新时期职业技能培训工作", 《门窗》 *

Also Published As

Publication number Publication date
JP2019204122A (en) 2019-11-28
TWI757310B (en) 2022-03-11
TW201812239A (en) 2018-04-01
CN109564673B (en) 2023-06-16
JP6616513B2 (en) 2019-12-04
SG11201900792RA (en) 2019-02-27
JP7000389B2 (en) 2022-01-19
WO2018021135A1 (en) 2018-02-01
JPWO2018021135A1 (en) 2019-05-09
KR20190022825A (en) 2019-03-06
KR102184475B1 (en) 2020-11-30

Similar Documents

Publication Publication Date Title
Liu et al. Survey: Common knowledge in BIM for facility maintenance
Xu et al. Formulating a learner model for evaluating construction workers’ learning ability during safety training
Michel et al. A dashboard to regulate project-based learning
CN109564673A (en) Seal construction, the system of seal construction management and seal construction training, program and method
Khan et al. Integrating building information modeling with augmented reality: application and empirical assessment in building facility management
May Regulatory implementation: Examining barriers from regulatory processes
Baborska-Narożny et al. Service controls interfaces in housing: usability and engagement tool development
Yin Kwok et al. A quality control and improvement system based on the total control methodology (TCM)
Iswahyudi et al. Impact self-efficacy and supervisor support on transfer of training: two-stage approach analysis
Syafar et al. Mobile collaboration technology in engineering asset maintenance: a Delphi study
Ikuma et al. A human factors-based assessment framework for evaluating performance in control room interface design
Bachtiar et al. The Needs for Developing Clinical Supervision Model for Headmaster of Primary School in Gowa, Indonesia
WO2019216328A1 (en) Flange fastening training system, device, program, method, and information terminal
Fernandes et al. Towards a readiness model derived from critical success factors, for the general data protection regulation implementation in higher education institutions
Feinstein et al. Assessing the effectiveness of ServSafe® online
Gazil et al. Simulating dynamically: A longitudinal and practical simulation approach for students
CN111612586B (en) Live-action shopping method based on visual model
Wilderom et al. BALANCED LEADERSHIP, PROFESSIONALISM, AND TEAM TRUST PREDICT POSITIVE ATTITUDES TOWARD PERFORMANCE MEASUREMENT.
Li et al. Integrating Manufacturing-related Materials and Quality Control Standards into Master-level Engineering Education
Pramono et al. The effect of 5s culture and workshop alignment on the application of industrial work culture in vocational education
Yang A formal approach to provide information support for troubleshooting of HVAC related problems
Wahyudin Management of Teaching Factory Program Implementation to Increase Absorption Rate Labor in the Business World and the Industrial World
Osuya et al. Assessment of Maintenance Management Practice in Government-owned Tertiary Institution
Roslan et al. A study on student satisfaction in relation to building maintenance practice at a residential college
Nik Mutasim et al. A Method for Evaluating Maintenance Capabilities in a Developing Community Using a Multiple DSM Framework

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant