CN109557363A - The aided detection method of Correctness checking after the importing of automated power curve - Google Patents

The aided detection method of Correctness checking after the importing of automated power curve Download PDF

Info

Publication number
CN109557363A
CN109557363A CN201811227163.8A CN201811227163A CN109557363A CN 109557363 A CN109557363 A CN 109557363A CN 201811227163 A CN201811227163 A CN 201811227163A CN 109557363 A CN109557363 A CN 109557363A
Authority
CN
China
Prior art keywords
power
curve
automated
adjusting
correctness
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811227163.8A
Other languages
Chinese (zh)
Inventor
周贵勇
黄浩然
申艳红
刘勇
赵丽莹
张自朋
周玉勇
王泽宇
史册
田艳芳
孙英志
赵冠华
贾帅锋
李桂举
马宁
郭建华
李凤龙
甄宏宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Xuji Group Co Ltd
XJ Electric Co Ltd
State Grid Liaoning Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Xuji Group Co Ltd
XJ Electric Co Ltd
State Grid Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Xuji Group Co Ltd, XJ Electric Co Ltd, State Grid Liaoning Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201811227163.8A priority Critical patent/CN109557363A/en
Publication of CN109557363A publication Critical patent/CN109557363A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R21/00Arrangements for measuring electric power or power factor
    • G01R21/01Arrangements for measuring electric power or power factor in circuits having distributed constants

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The aided detection method of Correctness checking after the importing of automated power curve, the same day automated power curve content that this method is completed according to adjusting, electricity was conveyed using the same day that area and mode calculate the curve, average power content is calculated using cumulative rear average mode, daily electricity and average power content convenient for issuing with control centre are checked.Specific beneficial effect of the invention is: on the basis of conventional automatic power function, by the day conveying electricity of automated power curve after calculating adjusting, checking the correctness of automated power curve after adjusting;By calculating current plan transmission power, actual power, the correctness that monitoring automated power plan executes are compared.In the above manner, can effectively mitigate the working strength of operations staff, the extensive work time is saved, and improves working efficiency and reduces operating pressure.

Description

The aided detection method of Correctness checking after the importing of automated power curve
Technical field
The invention belongs to electric system high-voltage dc transmission electrical domains, and in particular to a kind of automatic function of direct current transportation monitoring system The checking method and implementation procedure of rate curve monitor.
Background technique
Direct current transportation power control (powercontrolofDCtransmissonsystem) DC power transmission control system One link.The power of direct current system transmission is maintained at given value by it.It is a kind of control function for belonging to pole control hierarchy. In general, to the control of direct current transportation transmission power being realized by changing the current setting of DC current regulator.
According to the adjustment of grid operation mode and the variation of daily load, actual running DC transmission engineering is every It is required under the arrangement of control centre, carries out the adjustment of transmission power, and the parameter of adjustment mainly needs at the specified time point The performance number to be conveyed.
Power control usually has there are two types of operation control method: (1) it manually controls, power definite value and power ramp rate, It is manually entered by operations staff.(2) it automatically controls, power definite value presses preparatory programmed direct current transmission power and changes (one automatically As unit of day).When daily power adjustment point is more, due to being computer according to time point under automatic control mode Power planning value is sent, therefore the workload of operations staff can be reduced.
The cardinal principle of the implementation method of automated power is saved in the server after power curve is adjusted, and is arrived at time point Corresponding power instruction is sent after reaching, referring to " bipolar automatic power control method of high-voltage direct-current transmission " (application number: 201010245127.1), in automated power control in addition to needing power setting valve, it is also necessary to calculate power slope value and shift to an earlier date Amount, referring to " a kind of HVDC transmission system in automatic power control method " (application number: 201110438628.6).
Automated power project documentation, the daily power transmission meter corresponding to a DC transmission engineering of control centre's publication It draws, file format is Excel file, and content is temporally to put the power transmission plan of arrangement, general every 15 minutes power Point, daily 96 power points.
In practical projects, after operations staff receives automated power curve, there are two types of mode is whole in automated power plan Determine to be input in server on work station, the first is manually entered after printing, and second is imported by file, i.e., scheduling The automated power file at center is importing directly into system for executing.After the completion of input, it is also necessary to carry out a series of meter Calculation process, to guarantee to adjust the consistency of data and primitive scheduling centre data, after the completion of adjusting, it is also necessary to each click-through Row verification of data, to guarantee the correctness of data.Since current load scheduling is increasingly accurate, the same day is likely to occur multiple curve tune Whole situation requires to check after adjusting automated power curve again every time, needs to occupy a part of manpower and time, especially If the time of adjustment is tighter, such as power planning issued in 30 minutes in advance is process 15 minutes of removal power lifting, practical The time of reservation is only left 15 minutes, it is therefore desirable to complete the verification and inspection of data, by a kind of mathematical method to reduce The workload of operations staff's verification.
In the operational process of automated power, operations staff is needed attentively to monitor implementation procedure, is examined with what is guaranteed and dispatch Nuclear Data is consistent, needs to occupy a large amount of time and efforts of operations staff, if there is a kind of automatic method of monitoring implementation procedure, Operations staff is reminded when deviation occur in actual power and scheduling examination data, then operations staff can be effectively relieved and supervise disk pressure Power.It yet there are no report!
Summary of the invention
Goal of the invention:
A kind of aided detection method of Correctness checking after being imported the present invention provides automated power curve, the purpose is to It solves the problems of previous.
Technical solution:
A kind of automated power curve import after Correctness checking aided detection method, it is characterised in that: this method root According to the same day automated power curve content that adjusting is completed, electricity was conveyed using the same day that area and mode calculate the curve, is used Average mode calculates average power content after cumulative, and daily electricity and average power content convenient for issuing with control centre are checked.
The same day automated power curve content that this method is completed according to adjusting temporally obtains practical realtime power, passes through Compare the difference between actual power and unscheduled power, judges whether to meet schedule power check requirements.
This method is by the area coverage of curve after calculating adjusting, that is, the day of curve conveys under electricity, with scheduling after adjusting Daily electricity comparison in the curve of hair, checks the correctness of curve;
Its implementation includes the following steps:
1) the day conveying electricity of automated power curve after adjusting is calculated by area accumulation, calculation method is target power * Duration adds up, and check operations staff's work can by the daily electricity in the value and dispatch curve, to check adjusting The correctness of power curve afterwards;
2) by obtaining power points and power ramp rate in the automated power curve of adjusting, meter is calculated in a linear fashion Current time performance number in drawing obtains the actual power currently conveyed, compares power difference.
2) in step a certain moment unscheduled power calculation method are as follows: power points+power ramp rate * time difference;Wherein Power points is the power points at the previous moment at the moment, unit megawatt;Power ramp rate be the previous moment at the moment extremely Power ramp rate between next moment at the moment, unit megawatt/minute;Time difference is the moment and previous power points Between time difference, unit minute.
After power planning executes monitoring module acquisition current power value, with the unscheduled power value for calculating acquisition in the above method Compare, thinks that mistake occurs in implementation procedure when differing greatly, transmission event notifies operations staff to handle.
Advantageous effect:
It also include daily electricity other than time and corresponding unscheduled power value in the power planning that control centre issues Data, daily electricity is the electricity for working as daily planning conveying, in the area for geometrically showing as curve and covering downwards.
This method is by the area coverage of curve after calculating adjusting, that is, the day of curve conveys under electricity, with scheduling after adjusting Daily electricity comparison in the curve of hair, checks the correctness of curve;The present invention provides implementation procedures after a kind of adjusting of curve just The monitoring method of true property, by obtaining current real-time transmission power, with the unscheduled power value pair being calculated in Tuning curve Than reminding operations staff when error is more than a threshold value, its implementation includes the following steps:
3) the day conveying electricity of automated power curve after adjusting is calculated by area accumulation, calculation method is target power * Duration adds up, and check operations staff's work can by the daily electricity in the value and dispatch curve, to check adjusting The correctness of power curve afterwards;
4) by obtaining power points and power ramp rate in the automated power curve of adjusting, meter is calculated in a linear fashion Current time performance number in drawing obtains the actual power currently conveyed, compares power difference.
Specific beneficial effect of the invention is: on the basis of conventional automatic power function, by automatic after calculating adjusting The day of power curve conveys electricity, checks the correctness of automated power curve after adjusting;Function is conveyed by calculating current plan Rate compares actual power, the correctness that monitoring automated power plan executes.In the above manner, can effectively mitigate operation people The working strength of member saves the extensive work time, and improves working efficiency and reduce operating pressure.
Detailed description of the invention
The automated power curve exemplary diagram that the control centre Fig. 1 issues
Pending automated power curve data point after Fig. 2 adjusting
Specific embodiment
With reference to the accompanying drawing, further details of elaboration is made to technical solution of the present invention.
A kind of automated power curve import after Correctness checking aided detection method, this method completes according to adjusting Same day automated power curve content conveyed electricity using the same day that area and mode calculate the curve, using cumulative rear mean square Formula calculates average power content, and daily electricity and average power content convenient for issuing with control centre are checked.
The same day automated power curve content that this method is completed according to adjusting temporally obtains practical realtime power, passes through Compare the difference between actual power and unscheduled power, judges whether to meet schedule power check requirements.
This method is by the area coverage of curve after calculating adjusting, that is, the day of curve conveys under electricity, with scheduling after adjusting Daily electricity comparison in the curve of hair, checks the correctness of curve;
Its implementation includes the following steps:
5) the day conveying electricity of automated power curve after adjusting is calculated by area accumulation, calculation method is target power * Duration adds up, and check operations staff's work can by the daily electricity in the value and dispatch curve, to check adjusting The correctness of power curve afterwards;
6) by obtaining power points and power ramp rate in the automated power curve of adjusting, meter is calculated in a linear fashion Current time performance number in drawing obtains the actual power currently conveyed, compares power difference.
2) in step a certain moment unscheduled power calculation method are as follows: power points+power ramp rate * time difference;Wherein Power points is the power points at the previous moment at the moment, unit megawatt;Power ramp rate be the previous moment at the moment extremely Power ramp rate between next moment at the moment, unit megawatt/minute;Time difference is the moment and previous power points Between time difference, unit minute.
After power planning executes monitoring module acquisition current power value, with the unscheduled power value for calculating acquisition in the above method Compare, thinks that mistake occurs in implementation procedure when differing greatly, transmission event notifies operations staff to handle.
Embodiment:
Day conveying electricity calculates embodiment
Such as automated power curve after the adjusting in Fig. 2, day conveys electricity calculation are as follows:
(4131*1+3912*1+3842*5+4142*12+3842*4+3741*1+4147*1+4554*1+4960*1+ 5305*9+5605*3+5700*27+5605*1+5305*16+5605*5+5248*1+4842*1+4436*1+4041*5)*15/ 60
Wherein the multiplicand (such as 4131) in each cumulative and unit is set value of the power, and unit is megawatt (MW), multiplier (such as 1) is the last unit time of the power, and 15 indicate chronomere's (minute), and 60 be the number of minutes of a hour, should The changed power in power lifting process is had ignored in calculation.The calculated result of above formula is 120357 megawatt hours.
Power planning calculates embodiment
As unscheduled power calculation is carved in 0: 40 timesharing in Fig. 2 are as follows:
3912+17*10=4082, wherein 3912 be 0 point of 40 minutes previous power points, i.e. 0 point of 30 minutes performance number (unit Megawatt), 17 be the power ramp rate (unit megawatt/minute) between 0: 30 to 0: 45, and 10 be 0: 40 and previous power Point 0: 30/ time difference (unit minute).
After power planning executes monitoring module acquisition current power value, with the unscheduled power value for calculating acquisition in the above method Compare, thinks that mistake occurs in implementation procedure when differing greatly, transmission event notifies operations staff to handle.

Claims (5)

1. a kind of automated power curve import after Correctness checking aided detection method, it is characterised in that: this method according to The same day automated power curve content completed is adjusted, electricity was conveyed using the same day that area and mode calculate the curve, using tired Rear average mode is added to calculate average power content, daily electricity and average power content convenient for issuing with control centre are checked.
2. the aided detection method of the Correctness checking after automated power curve importing according to claim 1, feature Be: the same day automated power curve content that this method is completed according to adjusting temporally obtains practical realtime power, by comparing Difference between actual power and unscheduled power judges whether to meet schedule power check requirements.
3. the aided detection method of the Correctness checking after automated power curve importing according to claim 1 or 2, special Sign is: this method is by the area coverage of curve after calculating adjusting, that is, the day of curve conveys electricity after adjusting, with dispatching down distributing Curve in daily electricity comparison, check the correctness of curve;
Its implementation includes the following steps:
1) the day conveying electricity of automated power curve after adjusting is calculated by area accumulation, calculation method continues for target power * Time adds up, and checks operations staff's work by the daily electricity in the value and dispatch curve, bent with power after inspection adjusting The correctness of line;
2) it by obtaining power points and power ramp rate in the automated power curve of adjusting, calculates in a linear fashion in the works Current time performance number, obtain the actual power that currently conveys, compare power difference.
4. the aided detection method of the Correctness checking after automated power curve importing according to claim 3, feature Be: 2) in step a certain moment unscheduled power calculation method are as follows: power points+power ramp rate * time difference;Wherein power Point is the power points at the previous moment at the moment, unit megawatt;Power ramp rate be the previous moment at the moment to this when Carve the power ramp rate between next moment, unit megawatt/minute;Time difference is between the moment and previous power points Time difference, unit minute.
5. the aided detection method of the Correctness checking after automated power curve importing according to claim 4, feature It is: after power planning executes monitoring module acquisition current power value, with the unscheduled power value ratio for calculating acquisition in the above method Compared with thinking that mistake occurs in implementation procedure when differing greatly, transmission event notifies operations staff to handle.
CN201811227163.8A 2018-10-22 2018-10-22 The aided detection method of Correctness checking after the importing of automated power curve Pending CN109557363A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811227163.8A CN109557363A (en) 2018-10-22 2018-10-22 The aided detection method of Correctness checking after the importing of automated power curve

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811227163.8A CN109557363A (en) 2018-10-22 2018-10-22 The aided detection method of Correctness checking after the importing of automated power curve

Publications (1)

Publication Number Publication Date
CN109557363A true CN109557363A (en) 2019-04-02

Family

ID=65865215

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811227163.8A Pending CN109557363A (en) 2018-10-22 2018-10-22 The aided detection method of Correctness checking after the importing of automated power curve

Country Status (1)

Country Link
CN (1) CN109557363A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102214467A (en) * 2010-04-12 2011-10-12 广明光电股份有限公司 Writing method for optical disk machine
CN102916423A (en) * 2011-12-25 2013-02-06 许继集团有限公司 Automatic power control method in high-voltage direct current transmission system
CN104459302A (en) * 2013-09-23 2015-03-25 鸿富锦精密工业(深圳)有限公司 Power deviation detecting device
CN108133319A (en) * 2017-12-21 2018-06-08 北京金风科创风电设备有限公司 Method, device, equipment and storage medium for determining conformity of power curves

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102214467A (en) * 2010-04-12 2011-10-12 广明光电股份有限公司 Writing method for optical disk machine
CN102916423A (en) * 2011-12-25 2013-02-06 许继集团有限公司 Automatic power control method in high-voltage direct current transmission system
CN104459302A (en) * 2013-09-23 2015-03-25 鸿富锦精密工业(深圳)有限公司 Power deviation detecting device
CN108133319A (en) * 2017-12-21 2018-06-08 北京金风科创风电设备有限公司 Method, device, equipment and storage medium for determining conformity of power curves

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李育发 等: "吉林省模拟电力市场电量考核系统", 《吉林电力技术》 *

Similar Documents

Publication Publication Date Title
CN104219315B (en) A kind of operation monitoring system of power information acquisition system and method for supervising thereof
CN108736465B (en) Future-state power grid model construction method and device
CN110490363B (en) Multi-day unit combination optimization method and system
WO2016062179A1 (en) Method for implementing plan security check on the basis of power grid operation service bus
KR101278309B1 (en) Outage schedule management apparatus and method in ems
CN102545213A (en) System and method for managing line loss of power grid in real time
CN112149842A (en) Power grid maintenance management method and device
CN103440531A (en) Wind power plant short-term wind power prediction system in view of operating state of wind power plant draught fan
CN107622342B (en) MVC (model view controller) architecture-based distribution network area data analysis system
CN113381408B (en) Power utilization abnormity distribution transformer positioning method and device based on distribution automation data
CN116526667B (en) Secondary fusion distribution network feeder terminal system based on current Internet of things feedback mechanism
CN106849064B (en) Regional power grid load prediction management system based on meteorological data
CN114186798A (en) Information processing method and system for improving demand response effectiveness of power consumer
CN111598380A (en) Distribution line negative loss reason distinguishing method
CN104809543B (en) Power system operating mode generation method based on monthly power transmission and transforming equipment repair schedule
Al-Khamis et al. Unit maintenance scheduling with fuel constraints
CN113794279A (en) Intelligent power grid system
Nikolaev et al. Application of the cybernetic approach to price-dependent demand response for underground mining enterprise electricity consumption
CN106909615B (en) Method and device for verifying data information consistency between master station and substation
CN109557363A (en) The aided detection method of Correctness checking after the importing of automated power curve
CN112308437A (en) Line loss management method, system, device and storage medium based on big data analysis
Zhang et al. Optimal strategies for scheduling the hourly demand response considering uncertainties of renewable energy in day-ahead market
CN113052417A (en) Resource allocation method and device
CN108898307B (en) Method for generating production plan on large scale based on strategy by power station equipment
CN104281905A (en) Compressive power failure expert system based on condition based maintenance platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190402

RJ01 Rejection of invention patent application after publication