Prior art keywords
flange
built
foundation pit
plate
oblique
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910014365.2A
Other languages
Chinese (zh)
Other versions
CN109555131B (en
Inventor
朱登元
王玉兰
付厚利
韩吉才
于本福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Linda Hengtong Architectural Technology Co Ltd
Linyi University
Original Assignee
Shandong Linda Hengtong Architectural Technology Co Ltd
Linyi University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Linda Hengtong Architectural Technology Co Ltd, Linyi University filed Critical Shandong Linda Hengtong Architectural Technology Co Ltd
Priority to CN201910014365.2A priority Critical patent/CN109555131B/en
Publication of CN109555131A publication Critical patent/CN109555131A/en
Application granted granted Critical
Publication of CN109555131B publication Critical patent/CN109555131B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a kind of Construction of Civil Engineering foundation pit side-wall covering protection devices, including foundation pit, side wall protective device, outer lateral fixing device and outer oblique fixed device, built-in water pipe is located at branch baffle interior by the present invention, protection effectively can not only be supported to foundation pit side-wall, the ponding problem in foundation pit can also be handled in time, it avoids when handling pit water accumulation, need to be repeated several times the work for being laid with drinking-water pipe, and the ponding extracted from foundation pit, it collects and is recycled again in external hydrotreater, energy conservation and environmental protection, furthermore, when building connecting plate inside foundation pit, sliding connection block need to be only placed in built-in slot and be slided, then according to different connecting plates, select different fixation devices: cross connecting plate selects outer lateral fixing device;Oblique connecting plate selects outer oblique fixed device, and the fixed form of the fixation device is securely and installation is quick, time saving and energy saving, can greatly reduce and build the time, efficiency is built in raising.

Description

A kind of Construction of Civil Engineering foundation pit side-wall covering protection device
Technical field
The present invention relates to technical field of building construction, specially a kind of Construction of Civil Engineering is filled with foundation pit side-wall covering protection It sets.
Background technique
Foundation pit is the heatable adobe sleeping platform excavated in basic engineering position by substrate absolute altitude and basic plane size, and foundation pit belongs to temporarily Property engineering, effect is to provide a space, the operation that builds on basis enable to carry out according to the specified position of design, therefore Often before construction, side wall support protection first is carried out to foundation pit.
And currently used foundation pit side-wall supporting protection device is to be supported using external retaining-plate, then assist outer The drinking-water pipe set eliminates the ponding in foundation pit, and this apparatus structure is complicated, and troublesome in poeration, will in ponding per treatment Each laying drinking-water pipe work is carried out, the workload of construction personnel is increased, in addition, existing supporting protection device is not also square Just building for built-in connecting plate is carried out, certain difficulty is caused to subsequent construction working.
Summary of the invention
It is above-mentioned to solve the purpose of the present invention is to provide a kind of Construction of Civil Engineering foundation pit side-wall covering protection device The problem of being proposed in background technique.
To achieve the above object, the invention provides the following technical scheme:
A kind of Construction of Civil Engineering foundation pit side-wall covering protection device, including foundation pit, side wall protective device, outer laterally fixed dress It sets and is respectively arranged with side wall protective device with outer oblique fixed device, the foundation pit side-wall outside, the side wall protective device Side is " L " type, and side wall protective device is fixedly connected with foundation pit side-wall, side wall protective device upper end by fastening long steel nail It is fixed by outer fixing seat, and foundation pit upper surface is fixedly connected with by outer fastening stay bolt below outer fixing seat;
The side wall protective device includes branch baffle, built-in water pipe and built-in slot, and branch baffle outer surface offers several steel Mounting hole is followed closely, and is welded and connected with lug tooth slot structure below branch baffle, is provided with built-in water on the inside of branch baffle outer surface Pipe, and filter structure is connected below built-in water pipe, the filter structure side is fixedly connected with branch baffle, and the other side is arranged in supporting and retaining system On the outside of plate, the branch baffle outer surface is provided with built-in slot, and built-in slot is located at built-in water pipe two sides, the side of the built-in slot Twice lateral sliding slot is had on wall, and built-in slot bottom side is provided with first positioning hole, sliding in the lateral sliding slot Lateral sliding shoe is connected, the lateral sliding block is located on two sides of sliding connection block, setting on the inside of the sliding connection block There are two second location hole, threaded hole, the threaded hole internal screw thread are offered on the sliding connection block between the second location hole Outer lateral fixing device or outer oblique fixed device be installed, among the outer lateral fixing device can bolt be fixedly connected with transverse direction and connect Fishplate bar, among the outer oblique fixed device can bolt be fixedly connected with oblique connecting plate;
The outer lateral fixing device includes connecting flange and installation axle, and the connecting flange is welded to connect installation axle, and connects Several flange connecting holes are provided on flange, the connecting flange is internally provided with installation screw, and connecting flange outer surface It is arranged fluted, the installation axle is internally provided with card hole, and screw thread is provided on the outside of installation axle and on the inside of card hole, and install The control of axis is identical with the installation screw size inside connecting flange, the threaded connection threaded hole outside the installation axle, card hole The threaded connection snap-gauge of inside, the snap-gauge welded connecting plate flange are provided with several flange connecting holes on the plate flange, and Plate flange outer surface is provided with the convex block being cooperatively connected with groove, and the connecting flange and plate flange pass through stay bolt transfixion Blue connecting hole connection, and on the outside by being fixed to tight nut, the plate flange other end is welded to connect steel plate, and the steel plate is another Side is welded to connect another plate flange, and the plate flange other side bolt is fixedly connected with outer oblique fixed device, the length The place of being bolted is equipped with gasket;
The outer oblique fixed device includes installation axle, inclined plate and oblique flange, screw thread is provided with outside the installation axle, and pacify Dress axle thread is mounted in the threaded hole of sliding connection block, and the installation axle other end is welded to connect inclined plate, the inclined plate inside It is provided with threaded hole, and the inclined plate other end is welded to connect oblique flange, is provided with several flange connecting holes on the oblique flange, It being provided with threaded hole on the inside of oblique flange, and the threaded hole is identical as inclined plate screw thread pore size, the snap-gauge runs through oblique flange, It is threadably mounted in inclined plate, the oblique flange is connect by stay bolt through flange connecting hole with plate flange, and is led on the outside It crosses and tight nut is fixed, the plate flange other end is welded to connect steel plate, and the steel plate other side is welded to connect another plate Flange, and the plate flange other side bolt is fixedly connected with outer oblique fixed device, the stay bolt junction is equipped with gasket.
Preferably, the outer connecting pipe hole of built-in water pipe is provided in the outer fixing seat, which is set as Threaded hole, outer connecting pipe hole is threadedly coupled outer water pipe, and threaded connection place is provided with band, the water outlet of the outer water pipe other side It is fixedly connected with suction pump, and suction pump passes through piping connection water treatment facilities.
Preferably, the branch baffle, built-in water pipe and built-in slot are structure as a whole, and built-in water pipe is that branch baffle is processed Preset pore in journey.
Preferably, the outer fastening stay bolt upper surface is welded to connect end flanges, and the outer fixing seat lower surface welding connects Bottom flange is connect, several flange connecting holes are equipped in end flanges and bottom flange, and end flanges and bottom flange pass through bolt-through method Blue connecting hole is fixedly connected with outer fixing seat.
Preferably, the filter structure includes strainer and sand control water permeable membrane, and strainer outermost layer is fixedly connected with sand control water permeable membrane, Can prevent when drawing water to foundation pit, silt blocking filter structure the case where occur.
Compared with prior art, the beneficial effects of the present invention are: the foundation pit side-wall covering protection device sets built-in water pipe In branch baffle interior, protection effectively can not only be supported to foundation pit side-wall, additionally it is possible to the ponding in processing foundation pit in time Problem avoids the work for needing to be repeated several times when handling pit water accumulation and being laid with drinking-water pipe, and the product extracted from foundation pit Water is collected and is recycled again in external hydrotreater, energy conservation and environmental protection, in addition, when building connecting plate inside foundation pit, only Sliding connection block need to be placed in built-in slot and be slided, then according to different connecting plates, select different fixation devices: Cross connecting plate selects outer lateral fixing device;Oblique connecting plate selects outer oblique fixed device, the fixation side of the fixation device Formula is securely and installation is quick, time saving and energy saving, can greatly reduce and build the time, efficiency is built in raising.
Detailed description of the invention
Fig. 1 is foundation pit side-wall covering protection apparatus structure schematic diagram of the present invention.
Fig. 2 is the schematic diagram of the section structure of side wall protective device of the present invention.
Fig. 3 is the structural schematic diagram of built-in slot of the present invention.
Fig. 4 is the structural schematic diagram of sliding connection block of the present invention.
Fig. 5 is cross connecting plate attachment structure schematic diagram of the present invention.
Fig. 6 is the structural schematic diagram of the outer lateral fixing device of the present invention.
Fig. 7 is the structural schematic diagram of the outer oblique fixed device of the present invention.
In figure: 1, foundation pit;2, side wall protective device;3, branch baffle;4, built-in water pipe;5, long steel nail is fastened;6, outer fastening Stay bolt;7, outer fixing seat;8, water outlet;9, steel nail mounting hole;10, built-in slot;11, sliding connection block;12, filter structure; 13, lug tooth slot structure;14, first positioning hole;15, lateral sliding slot;16, second location hole;17, lateral sliding block;18, outer Lateral fixing device;19, connecting flange;20, threaded hole;21, installation axle;22, card hole;23, flange connecting hole;24, gasket; 25, stay bolt;26, to tight nut;27, convex block;28, snap-gauge;29, plate flange;30, steel plate;31, groove;32, lateral connection Plate;33, oblique connecting plate;34, outer oblique fixed device;35, inclined plate;36, oblique flange.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to Convenient for description the present invention and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation, It is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.In addition, term " first ", " second ", " third " is used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
Referring to Fig. 1, a kind of Construction of Civil Engineering foundation pit side-wall covering protection device, including foundation pit 1, side wall protection dress 2, outer lateral fixing device 18 and outer oblique fixed device 34 are set, 1 side-wall outer side of foundation pit is respectively arranged with side wall protection dress 2 are set, the side of the side wall protective device 2 is " L " type, and side wall protective device 2 is fixedly connected with foundation pit by fastening long steel nail 5 1 side wall, 2 upper end of side wall protective device is fixed by outer fixing seat 7, and passes through outer fastening stay bolt 6 below outer fixing seat 7 It is fixedly connected with 1 upper surface of foundation pit, outer 6 upper surface of fastening stay bolt is welded to connect end flanges, outer 7 lower surface of fixing seat It is welded to connect bottom flange, is equipped with several flange connecting holes 23 in end flanges and bottom flange, and end flanges and bottom flange pass through spiral shell Bolt is fixedly connected with outer fixing seat 7 through flange connecting hole 23, and the outer connecting pipe of built-in water pipe 4 is provided in the outer fixing seat 7 Hole, the outer connecting pipe hole inner wall are set as threaded hole, and outer connecting pipe hole is threadedly coupled outer water pipe, and threaded connection place is provided with sealing Band, the water outlet 8 of the outer water pipe other side is fixedly connected with suction pump, and suction pump passes through piping connection water treatment facilities;
Please refer to 1-5, the side wall protective device 2 includes branch baffle 3, built-in water pipe 4 and built-in slot 10, the branch baffle 3, interior It sets water pipe 4 and built-in slot 10 is structure as a whole, and built-in water pipe 4 is the preset pore in 3 process of branch baffle, the supporting and retaining system 3 outer surface of plate offers several steel nail mounting holes 9, and lug tooth slot structure 13 is welded and connected with below branch baffle 3, the supporting and retaining system It is provided with built-in water pipe 4 on the inside of 3 outer surface of plate, and connects filter structure 12 below built-in water pipe 4, the filter structure 12 includes Strainer and sand control water permeable membrane, strainer outermost layer are fixedly connected with sand control water permeable membrane, can prevent when drawing water to foundation pit 1, silt The case where blocking filter structure 12 occurs, and 12 side of filter structure is fixedly connected with branch baffle 3, and the other side is arranged in branch baffle 3 outsides, 3 outer surface of branch baffle is provided with built-in slot 10, and built-in slot 10 is located at built-in 4 two sides of water pipe, described built-in Twice lateral sliding slot 15 is had on the side wall of slot 10, and 10 bottom side of built-in slot is provided with first positioning hole 14, the side Be slidably connected lateral sliding block 17 into sliding groove 15, and the lateral sliding block 17 is located on 11 two sides of sliding connection block, Setting is there are two second location hole 16 on the inside of the sliding connection block 11, on the sliding connection block 11 between the second location hole 16 Threaded hole 20 is offered, 20 internal screw thread of threaded hole installs outer lateral fixing device 18 or outer oblique fixed device 34, described Among outer lateral fixing device 18 can bolt be fixedly connected with cross connecting plate 32, can bolt among the outer oblique fixed device 34 It is fixedly connected with oblique connecting plate 33;
Fig. 5-6 is please referred to, the outer lateral fixing device 18 includes connecting flange 19 and installation axle 21, and the connecting flange 19 welds Installation axle 21 is connect in succession, and is provided with several flange connecting holes 23 on connecting flange 19, and the connecting flange 19 is internally provided with Installation screw, and 19 outer surface of connecting flange setting fluted 31, the installation axle 21 is internally provided with card hole 22, and installs Be provided with screw thread on the inside of the outside of axis 21 and card hole 22, and installation axle 21 control 22 and the installation screw inside connecting flange 19 Size is identical, the threaded connection threaded hole 20 outside the installation axle 21, the threaded connection snap-gauge 28 of 22 inside of card hole, the card 28 welded connecting plate flange 29 of plate is provided with several flange connecting holes 23, and 29 outer surface of plate flange on the plate flange 29 It is provided with the convex block 27 being cooperatively connected with groove 31, the connecting flange 19 is connected by stay bolt 25 through flange with plate flange 29 The connection of hole 23 is connect, and on the outside by fixed to tight nut 26,29 other end of plate flange is welded to connect steel plate 30, the steel 30 other side of plate is welded to connect another plate flange 29, and 29 other side bolt of plate flange is fixedly connected with outer oblique fixed dress 34 are set, 25 junction of stay bolt is equipped with gasket 24;
Fig. 5-7 is please referred to, the outer oblique fixed device 34 includes installation axle 21, inclined plate 35 and oblique flange 36, the installation Screw thread is provided with outside axis 21, and installation axle 21 is threadably mounted in the threaded hole 20 of sliding connection block 11, the installation axle 21 The other end is welded to connect inclined plate 35, threaded hole is provided on the inside of the inclined plate 35, and 35 other end of inclined plate is welded to connect oblique method Orchid 36 is provided with several flange connecting holes 23 on the oblique flange 36, threaded hole, and the spiral shell is provided on the inside of oblique flange 36 Pit is identical as 35 screw thread pore size of inclined plate, and the snap-gauge 28 runs through oblique flange 36, is threadably mounted in inclined plate 35, described oblique It is connect by stay bolt 25 through flange connecting hole 23 to flange 36 with plate flange 29, and on the outside by solid to tight nut 26 Fixed, 29 other end of plate flange is welded to connect steel plate 30, and 30 other side of steel plate is welded to connect another plate flange 29, And 29 other side bolt of plate flange is fixedly connected with outer oblique fixed device 34,25 junction of stay bolt is equipped with gasket 24。
Side wall protective device 2: when carrying out 1 side wall covering protection of foundation pit, being first placed in foundation pit 1 by working principle, leads to It crosses and fastens long steel nail 5 side wall protective device 2 is fixedly connected with 1 side wall of foundation pit at steel nail mounting hole 9, side wall is protected fill later The built-in water pipe 4 for setting 2 tops is directed at outer connecting pipe hole and the fixation of outer fixing seat 7, passes through the outer long spiral shell of fastening below outer fixing seat 7 Bolt 6 is fixedly connected with 1 upper surface of foundation pit, and when needing to be fixedly connected plate inside foundation pit, sliding connection block 11 is placed built-in slot In 10, the lateral sliding block 17 on sliding connection block 11 is embedded in lateral sliding slot 15, is then slowly slided, is slided into least significant end When, it is required according to connecting plate, lateral sliding block 17 is moved to suitable position, and by the second location hole of lateral sliding block 17 16 It is directed at the first positioning hole 14 of built-in slot 10, and is fixed using long spiro nail, then according to the difference of connecting plate, selects different consolidate Determine device:
When fixed lateral connecting plate 32, outer lateral fixing device 18, the spiral shell in the threaded hole 20 in lateral sliding block 17 are selected Line connects installation axle 21, and 21 other side of installation axle is welded to connect flange 19,28 spiral shell of snap-gauge for then welding 29 side of plate flange Line is mounted on inside installation axle 21, while connecting flange 19 and plate flange 29 are connected by stay bolt 25 through flange connecting hole 23 It connects, and on the outside by fixed to tight nut 26,29 other end of plate flange is welded to connect steel plate 30,30 other side of the steel plate weldering Another plate flange 29 is connect in succession, and 29 other side bolt of plate flange is fixedly connected with outer lateral fixing device 18;
When the oblique connecting plate 33 of fixation, outer oblique fixed device 34, the spiral shell in the threaded hole 20 in lateral sliding block 17 are selected Line connects installation axle 21, and 21 other side of installation axle is welded to connect inclined plate 35, and 35 other end of inclined plate is welded to connect oblique flange 36, so The snap-gauge 28 by the welding of 29 side of plate flange runs through oblique flange 36 afterwards, is threadably mounted in inclined plate 35, while oblique flange 36 It is connect by stay bolt 25 through flange connecting hole 23 with plate flange 29, and passes through fixed, the plate flange to tight nut 26 on the outside 29 other ends are welded to connect steel plate 30, and 30 other side of steel plate is welded to connect another plate flange 29, and the plate flange 29 Other side bolt is fixedly connected with outer oblique fixed device 34;
When there is seeping phenomenon in foundation pit 1, external suction pump extracts base by outer water pipe, built-in water pipe 4 and filter structure 12 Water in hole 1, and be collected into external water treatment facilities by pipeline, 12 Inner filter net outermost layer of filter structure is fixedly connected anti- The case where sand water permeable membrane can be prevented when drawing water to foundation pit 1, silt blocking filter structure 12 occurs, and guarantees 1 inner product of foundation pit Water is quickly extracted, and is at all damaged inside foundation pit 1.
Built-in water pipe is located at branch baffle interior by the present invention, effectively can not only be supported protection to foundation pit side-wall, The ponding problem in foundation pit can also be handled in time, avoided when handling pit water accumulation, needed to be repeated several times laying drinking-water pipe Work, and the ponding extracted from foundation pit collects and recycles again in external hydrotreater, energy conservation and environmental protection, this Outside, when building connecting plate inside foundation pit, sliding connection block need to be only placed in built-in slot and is slided, then according to difference Connecting plate, select different fixation devices: cross connecting plate selects outer lateral fixing device;Oblique connecting plate is selected outer oblique Fixed device, fixed form is securely quick, time saving and energy saving, greatly reduces and builds the time, and efficiency is built in raising, to accelerate to build Build construction efficiency.
Although the present invention is described in detail referring to the foregoing embodiments, for those skilled in the art, It is still possible to modify the technical solutions described in the foregoing embodiments, or part of technical characteristic is carried out etc. With replacement, all within the spirits and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in this Within the protection scope of invention.

Claims (5)

1. a kind of Construction of Civil Engineering foundation pit side-wall covering protection device, including foundation pit (1), side wall protective device (2), outer cross To fixed device (18) and outer oblique fixed device (34), it is characterised in that: foundation pit (1) side-wall outer side is respectively arranged with side Wall protective device (2), the side of the side wall protective device (2) is " L " type, and side wall protective device (2) is by fastening long steel Nail (5) is fixedly connected with foundation pit (1) side wall, and side wall protective device (2) upper end is fixed by outer fixing seat (7), and outer fixed Foundation pit (1) upper surface is fixedly connected with by outer fastening stay bolt (6) below seat (7);
The side wall protective device (2) includes branch baffle (3), built-in water pipe (4) and built-in slot (10), and the branch baffle (3) is outside Surface offers several steel nail mounting holes (9), and is welded and connected with lug tooth slot structure (13), the branch below branch baffle (3) It is provided with built-in water pipe (4) on the inside of baffle (3) outer surface, and connects filter structure (12) below built-in water pipe (4), the strainer Structure (12) side is fixedly connected branch baffle (3), and other side setting is on the outside of branch baffle (3), branch baffle (3) outer surface It is provided with built-in slot (10), and built-in slot (10) is located at built-in water pipe (4) two sides, opens respectively on the side wall of the built-in slot (10) There is twice lateral sliding slot (15), and built-in slot (10) bottom side is provided with first positioning hole (14), the lateral sliding slot (15) Inside be slidably connected lateral sliding block (17), and the lateral sliding block (17) is located on (11) two sides of sliding connection block, described Sliding connection block on the inside of sliding connection block (11) there are two settings second location hole (16), between the second location hole (16) (11) it is offered on threaded hole (20), threaded hole (20) internal screw thread installs outer lateral fixing device (18) or outer oblique fixation Device (34), the outer lateral fixing device (18) it is intermediate can bolt be fixedly connected cross connecting plate (32), it is described outer oblique solid Determine device (34) it is intermediate can bolt be fixedly connected with oblique connecting plate (33);
The outer lateral fixing device (18) includes connecting flange (19) and installation axle (21), and connecting flange (19) welding connects It connects installation axle (21), and is provided with several flange connecting holes (23) on connecting flange (19), set inside the connecting flange (19) It is equipped with installation screw, and fluted (31) are arranged in connecting flange (19) outer surface, the installation axle (21) is internally provided with card Hole (22), and screw thread is provided on the outside of installation axle (21) and on the inside of card hole (22), and control (22) and the company of installation axle (21) The internal installation screw size of acting flange (19) is identical, the external threaded connection threaded hole (20) of the installation axle (21), card hole (22) the threaded connection snap-gauge (28) on the inside of, snap-gauge (28) the welded connecting plate flange (29) set on the plate flange (29) It is equipped with several flange connecting holes (23), and plate flange (29) outer surface is provided with the convex block being cooperatively connected with groove (31) (27), the connecting flange (19) is connect by stay bolt (25) through flange connecting hole (23) with plate flange (29), and outside By fixed to tight nut (26), plate flange (29) other end is welded to connect steel plate (30) for side, and the steel plate (30) is another Side is welded to connect another plate flange (29), and plate flange (29) other side bolt is fixedly connected with outer oblique fixed device (34), stay bolt (25) junction is equipped with gasket (24);
The outer oblique fixed device (34) includes installation axle (21), inclined plate (35) and oblique flange (36), the installation axle (21) external to be provided with screw thread, and installation axle (21) is threadably mounted in the threaded hole (20) of sliding connection block (11), the peace It fills axis (21) other end and is welded to connect inclined plate (35), be provided with threaded hole, and inclined plate (35) other end on the inside of the inclined plate (35) It is welded to connect oblique flange (36), is provided with several flange connecting holes (23) on the oblique flange (36), oblique flange (36) Inside is provided with threaded hole, and the threaded hole is identical as inclined plate (35) screw thread pore size, and the snap-gauge (28) runs through oblique flange (36), it is threadably mounted in inclined plate (35), the oblique flange (36) and plate flange (29) pass through stay bolt (25) and run through flange Connecting hole (23) connection, and on the outside by fixed to tight nut (26), plate flange (29) other end is welded to connect steel plate (30), steel plate (30) other side is welded to connect another plate flange (29), and plate flange (29) other side bolt is solid Fixed to connect outer oblique fixed device (34), stay bolt (25) junction is equipped with gasket (24).
2. a kind of Construction of Civil Engineering according to claim 1 foundation pit side-wall covering protection device, it is characterised in that: institute The outer connecting pipe hole that built-in water pipe (4) is provided in outer fixing seat (7) is stated, which is set as threaded hole, outer company It takes over hole and is threadedly coupled outer water pipe, and threaded connection place is provided with band, the water outlet (8) of the outer water pipe other side is fixedly connected Suction pump, and suction pump passes through piping connection water treatment facilities.
3. a kind of Construction of Civil Engineering according to claim 1 foundation pit side-wall covering protection device, it is characterised in that: institute It states branch baffle (3), built-in water pipe (4) and built-in slot (10) to be structure as a whole, and built-in water pipe (4) is that branch baffle (3) is processed Preset pore in journey.
4. a kind of Construction of Civil Engineering according to claim 1 foundation pit side-wall covering protection device, it is characterised in that: institute It states outer fastening stay bolt (6) upper surface and is welded to connect end flanges, outer fixing seat (7) lower surface is welded to connect bottom flange, end It is equipped on flange and bottom flange several flange connecting holes (23), and end flanges and bottom flange pass through bolt-through flange connecting hole (23) outer fixing seat (7) are fixedly connected with.
5. a kind of Construction of Civil Engineering according to claim 1 foundation pit side-wall covering protection device, it is characterised in that: institute Stating filter structure (12) includes strainer and sand control water permeable membrane, and strainer outermost layer is fixedly connected with sand control water permeable membrane.
CN201910014365.2A 2019-01-08 2019-01-08 Civil engineering construction is with foundation ditch lateral wall cover protection device Active CN109555131B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910014365.2A CN109555131B (en) 2019-01-08 2019-01-08 Civil engineering construction is with foundation ditch lateral wall cover protection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910014365.2A CN109555131B (en) 2019-01-08 2019-01-08 Civil engineering construction is with foundation ditch lateral wall cover protection device

Publications (2)

Publication Number Publication Date
CN109555131A true CN109555131A (en) 2019-04-02
CN109555131B CN109555131B (en) 2020-07-07

Family

ID=65872426

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910014365.2A Active CN109555131B (en) 2019-01-08 2019-01-08 Civil engineering construction is with foundation ditch lateral wall cover protection device

Country Status (1)

Country Link
CN (1) CN109555131B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113562631A (en) * 2021-07-24 2021-10-29 江苏天力建设集团有限公司 Protective structure for building deep foundation pit construction

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205276336U (en) * 2016-01-04 2016-06-01 杭州科技职业技术学院 A protection device that is used for deep basal pit underground continuous wall construction midboard body examination pipe chute
CN106638641A (en) * 2016-12-16 2017-05-10 中建四局第建筑工程有限公司 Water well structure for foundation pit dewatering and construction method thereof
CN107119693A (en) * 2017-05-11 2017-09-01 中国建筑第八工程局有限公司 Foundation pit supporting construction and its construction method with precipitation function
CN108330983A (en) * 2018-01-09 2018-07-27 闵喜梅 A kind of deep basal pit safety guard of construction

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205276336U (en) * 2016-01-04 2016-06-01 杭州科技职业技术学院 A protection device that is used for deep basal pit underground continuous wall construction midboard body examination pipe chute
CN106638641A (en) * 2016-12-16 2017-05-10 中建四局第建筑工程有限公司 Water well structure for foundation pit dewatering and construction method thereof
CN107119693A (en) * 2017-05-11 2017-09-01 中国建筑第八工程局有限公司 Foundation pit supporting construction and its construction method with precipitation function
CN108330983A (en) * 2018-01-09 2018-07-27 闵喜梅 A kind of deep basal pit safety guard of construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113562631A (en) * 2021-07-24 2021-10-29 江苏天力建设集团有限公司 Protective structure for building deep foundation pit construction
CN113562631B (en) * 2021-07-24 2024-03-08 江苏天力建设集团有限公司 Protective structure for construction of deep foundation pit of house building

Also Published As

Publication number Publication date
CN109555131B (en) 2020-07-07

Similar Documents

Publication Publication Date Title
CN101126279B (en) Silo slipform construction technique
CN101832049B (en) Concrete-structured conjoined cylindrical shell construction device and method therefor
US10995999B2 (en) Cooling unit, installation and process
CN106013233B (en) Sliding system and its construction method for underground pipe gallery cast-in-place construction
CN107060075A (en) A kind of supporting construction connected for fabricated construction beam slab and installation method
CN103882813B (en) For calf support platform and the building method thereof of bridge pier and straining beam synchronous construction
CN105544604A (en) Slipform device and construction method using same
CN106836836B (en) A kind of secondary hydraulic lifting installation method of Flue Gas Desulphurization for Coal-burning Power Plant tower transformation
CN204876547U (en) Big template system of APC shell structure
CN109555131A (en) A kind of Construction of Civil Engineering foundation pit side-wall covering protection device
CN212799790U (en) Biological filter body water distribution system
CN210173861U (en) Steam health preserving system is controlled to precast beam intelligence
CN108951699B (en) Festival segmentation removal centre form and support of utility tunnel
CN209537075U (en) A kind of decanter type aerating system
CN108867683A (en) Rail-type movable foundation and construction method thereof
CN210597020U (en) Construction support device and system
CN103835501B (en) The large-scale concentration basin construction method of assembling combination construction
CN206667465U (en) A kind of supporting construction for the connection of fabricated construction beam slab
RU2682414C1 (en) Method of synchronous lifting and lowering of a part of a building design
CN106149854A (en) Prefabricated pumping plant
CN110656658A (en) Pipe gallery formwork installation and construction process
CN110952765A (en) Formwork supporting platform for shear wall high-altitude concrete cantilever structure and assembling method of formwork supporting platform
CN109179633A (en) Underwater propeller installation method
CN204874435U (en) Sled dress formula sweetener and desulfurization system
CN109537599A (en) The construction method of deep foundation pit support system support changing structure for use

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant