CN109538254A - 隧道的仰拱结构验证方法、装置、存储器及处理器 - Google Patents
隧道的仰拱结构验证方法、装置、存储器及处理器 Download PDFInfo
- Publication number
- CN109538254A CN109538254A CN201811644910.8A CN201811644910A CN109538254A CN 109538254 A CN109538254 A CN 109538254A CN 201811644910 A CN201811644910 A CN 201811644910A CN 109538254 A CN109538254 A CN 109538254A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- parameter
- inverted arch
- arch structure
- built
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 49
- 238000012795 verification Methods 0.000 title claims abstract description 25
- 239000011435 rock Substances 0.000 claims abstract description 92
- 238000002474 experimental method Methods 0.000 claims abstract description 17
- 230000008093 supporting effect Effects 0.000 claims description 80
- 238000010276 construction Methods 0.000 claims description 54
- 239000000463 material Substances 0.000 claims description 6
- 230000006641 stabilisation Effects 0.000 claims description 3
- 238000011105 stabilization Methods 0.000 claims description 3
- 241000208340 Araliaceae Species 0.000 claims description 2
- 235000005035 Panax pseudoginseng ssp. pseudoginseng Nutrition 0.000 claims description 2
- 235000003140 Panax quinquefolius Nutrition 0.000 claims description 2
- 235000008434 ginseng Nutrition 0.000 claims description 2
- 238000013461 design Methods 0.000 abstract description 12
- 238000005516 engineering process Methods 0.000 abstract description 7
- 230000008569 process Effects 0.000 description 10
- 238000004590 computer program Methods 0.000 description 9
- 238000010586 diagram Methods 0.000 description 6
- 238000012545 processing Methods 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 3
- 230000006870 function Effects 0.000 description 3
- 230000003287 optical effect Effects 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 238000010146 3D printing Methods 0.000 description 2
- 238000004458 analytical method Methods 0.000 description 2
- 201000010099 disease Diseases 0.000 description 2
- 208000037265 diseases, disorders, signs and symptoms Diseases 0.000 description 2
- 238000004088 simulation Methods 0.000 description 2
- 238000012549 training Methods 0.000 description 2
- 238000013473 artificial intelligence Methods 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000005094 computer simulation Methods 0.000 description 1
- 239000004567 concrete Substances 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000007639 printing Methods 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 238000010187 selection method Methods 0.000 description 1
- 239000011378 shotcrete Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/18—Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/18—Special adaptations of signalling or alarm devices
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/02—Agriculture; Fishing; Forestry; Mining
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Geochemistry & Mineralogy (AREA)
- Business, Economics & Management (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- Agronomy & Crop Science (AREA)
- Animal Husbandry (AREA)
- Marine Sciences & Fisheries (AREA)
- Architecture (AREA)
- Health & Medical Sciences (AREA)
- Structural Engineering (AREA)
- General Health & Medical Sciences (AREA)
- Civil Engineering (AREA)
- Economics (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Human Resources & Organizations (AREA)
- Lining And Supports For Tunnels (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
Description
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811644910.8A CN109538254B (zh) | 2018-12-30 | 2018-12-30 | 隧道的仰拱结构验证方法、装置、存储器及处理器 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811644910.8A CN109538254B (zh) | 2018-12-30 | 2018-12-30 | 隧道的仰拱结构验证方法、装置、存储器及处理器 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109538254A true CN109538254A (zh) | 2019-03-29 |
CN109538254B CN109538254B (zh) | 2020-10-30 |
Family
ID=65831577
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811644910.8A Active CN109538254B (zh) | 2018-12-30 | 2018-12-30 | 隧道的仰拱结构验证方法、装置、存储器及处理器 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109538254B (zh) |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102900441A (zh) * | 2012-09-18 | 2013-01-30 | 铁道部经济规划研究院 | 基于围岩完全变形控制的中国隧道修建方法 |
CN103205957A (zh) * | 2013-03-19 | 2013-07-17 | 天津市市政工程设计研究院 | 基坑开挖下卧隧道及基底回弹估算法 |
CN104021254A (zh) * | 2014-06-20 | 2014-09-03 | 暨南大学 | 盾构隧道开挖后应力分布获取方法 |
CN104727828A (zh) * | 2015-01-30 | 2015-06-24 | 北京交通大学 | 基于变形控制的隧道超前支护管理方法 |
CN105787206A (zh) * | 2016-03-23 | 2016-07-20 | 同济大学 | 一种公路隧道锚杆支护设计方法 |
KR20170110790A (ko) * | 2016-03-24 | 2017-10-12 | 김정현 | 비정형부에 시공되는 구조물의 재료량 최적화 방법 |
CN107526873A (zh) * | 2017-07-27 | 2017-12-29 | 西安理工大学 | 一种浅埋隧道围岩坍塌模式识别及支护结构计算方法 |
CN107621231A (zh) * | 2017-06-20 | 2018-01-23 | 北京工业大学 | 一种隧道二次衬砌厚度检测方法 |
CN108108566A (zh) * | 2018-01-02 | 2018-06-01 | 河南省交通规划设计研究院股份有限公司 | 基于bim的公路隧道设计方法 |
CN108614307A (zh) * | 2018-05-14 | 2018-10-02 | 招商局重庆交通科研设计院有限公司 | 一种利用综合物探技术的仰拱质量检测方法及系统 |
CN109057839A (zh) * | 2018-09-06 | 2018-12-21 | 北京交通大学 | 一种基于围岩结构性的隧道锚固体系设计方法及系统 |
-
2018
- 2018-12-30 CN CN201811644910.8A patent/CN109538254B/zh active Active
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102900441A (zh) * | 2012-09-18 | 2013-01-30 | 铁道部经济规划研究院 | 基于围岩完全变形控制的中国隧道修建方法 |
CN103205957A (zh) * | 2013-03-19 | 2013-07-17 | 天津市市政工程设计研究院 | 基坑开挖下卧隧道及基底回弹估算法 |
CN104021254A (zh) * | 2014-06-20 | 2014-09-03 | 暨南大学 | 盾构隧道开挖后应力分布获取方法 |
CN104727828A (zh) * | 2015-01-30 | 2015-06-24 | 北京交通大学 | 基于变形控制的隧道超前支护管理方法 |
CN105787206A (zh) * | 2016-03-23 | 2016-07-20 | 同济大学 | 一种公路隧道锚杆支护设计方法 |
KR20170110790A (ko) * | 2016-03-24 | 2017-10-12 | 김정현 | 비정형부에 시공되는 구조물의 재료량 최적화 방법 |
CN107621231A (zh) * | 2017-06-20 | 2018-01-23 | 北京工业大学 | 一种隧道二次衬砌厚度检测方法 |
CN107526873A (zh) * | 2017-07-27 | 2017-12-29 | 西安理工大学 | 一种浅埋隧道围岩坍塌模式识别及支护结构计算方法 |
CN108108566A (zh) * | 2018-01-02 | 2018-06-01 | 河南省交通规划设计研究院股份有限公司 | 基于bim的公路隧道设计方法 |
CN108614307A (zh) * | 2018-05-14 | 2018-10-02 | 招商局重庆交通科研设计院有限公司 | 一种利用综合物探技术的仰拱质量检测方法及系统 |
CN109057839A (zh) * | 2018-09-06 | 2018-12-21 | 北京交通大学 | 一种基于围岩结构性的隧道锚固体系设计方法及系统 |
Also Published As
Publication number | Publication date |
---|---|
CN109538254B (zh) | 2020-10-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103279415B (zh) | 基于组合测试的嵌入式软件测试方法 | |
Aerts et al. | Using linear integer programming for multi‐site land‐use allocation | |
Chassiakos et al. | Time-cost optimization of construction projects with generalized activity constraints | |
Lesgidis et al. | A time‐domain seismic SSI analysis method for inelastic bridge structures through the use of a frequency‐dependent lumped parameter model | |
Stückelberger et al. | Modeling spatial variability in the life-cycle costs of low-volume forest roads | |
Ha et al. | Reliability approach in economic assessment of adapting infrastructure to climate change | |
Bogenberger et al. | Two-phase earthwork optimization model for highway construction | |
Lawe et al. | TRANSIMS implementation in Chittenden County, Vermont: Development, calibration, and preliminary sensitivity analysis | |
Sumalee | Multi-concentric optimal charging cordon design | |
Park et al. | Life-cycle assessment-based environmental impact estimation model for earthwork-type road projects in the design phase | |
CN109538254A (zh) | 隧道的仰拱结构验证方法、装置、存储器及处理器 | |
Zankoul et al. | Modeling, animating, and optimizing on-shore wind farm construction operations | |
Morley et al. | Identification of invariant average weighted haul distance to simplify earthmoving simulation modeling in planning site grading operations | |
CN109783913A (zh) | 隧道的支护结构选择方法及装置 | |
Gomez Cabrera et al. | Improving construction material and equipment logistics via simulation | |
Shrestha | Rural road network decision model for hilly regions of Nepal | |
CN111667749B (zh) | 一种工程场站建设电子沙盘的制作方法 | |
Mansour et al. | Construction facilities location selection for urban linear infrastructure maintenance projects using uniform cost search method | |
Shen et al. | Object-based 3D intelligent model for construction planning/simulation in a highway construction | |
Stückelberger | A weighted-graph optimization approach for automatic location of forest road networks | |
CN112257916A (zh) | 基于搜索生成场地土方调度路径的方法、装置和电子设备 | |
Jayawardane et al. | A new approach for optimizing earth moving operations. Part II | |
Syed et al. | ‘End to end’linkage structure for integrated impact assessment of infrastructure networks under natural hazards | |
Inzerillo et al. | Isim-Infrastructures & Structures Information Modeling: a New Concept of Bim for Infrastructures | |
Schwartzentruber et al. | Management and use of materials excavated during underground works |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20191008 Address after: Lixia District, Shandong city of Ji'nan province 250000 Olympic road No. 2666, building A, railway construction Applicant after: CHINA RAILWAY SHISIJU Group Corp. Applicant after: CHINA RAILWAY 14TH BUREAU GROUP SHIELD ENGINEERING Co.,Ltd. Address before: Lixia District, Shandong city of Ji'nan province 250000 Olympic road No. 2666, building A, railway construction Applicant before: CHINA RAILWAY SHISIJU Group Corp. |
|
TA01 | Transfer of patent application right | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20221221 Address after: Block a, Tiejian building, 2666 Aoti West Road, Lixia District, Jinan City, Shandong Province Patentee after: CHINA RAILWAY SHISIJU Group Corp. Patentee after: CHINA RAILWAY 14TH BUREAU GROUP SHIELD ENGINEERING Co.,Ltd. Patentee after: TIEZHENG TESTING TECHNOLOGY Co.,Ltd. Address before: Block a, Tiejian building, 2666 Aoti West Road, Lixia District, Jinan City, Shandong Province Patentee before: CHINA RAILWAY SHISIJU Group Corp. Patentee before: CHINA RAILWAY 14TH BUREAU GROUP SHIELD ENGINEERING Co.,Ltd. |
|
TR01 | Transfer of patent right |