CN109534638A - Septic tank integral formation method - Google Patents

Septic tank integral formation method Download PDF

Info

Publication number
CN109534638A
CN109534638A CN201811617290.9A CN201811617290A CN109534638A CN 109534638 A CN109534638 A CN 109534638A CN 201811617290 A CN201811617290 A CN 201811617290A CN 109534638 A CN109534638 A CN 109534638A
Authority
CN
China
Prior art keywords
septic tank
external mold
end external
internal model
septic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811617290.9A
Other languages
Chinese (zh)
Inventor
梅俊祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luohe Junzhan Machinery Equipment Co Ltd
Original Assignee
Luohe Junzhan Machinery Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luohe Junzhan Machinery Equipment Co Ltd filed Critical Luohe Junzhan Machinery Equipment Co Ltd
Priority to CN201811617290.9A priority Critical patent/CN109534638A/en
Publication of CN109534638A publication Critical patent/CN109534638A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F11/00Treatment of sludge; Devices therefor
    • C02F11/02Biological treatment
    • C02F11/04Anaerobic treatment; Production of methane by such processes

Abstract

The invention proposes a kind of septic tank integral formation methods, including septic tank lower end external mold, septic tank upper end external mold, septic tank internal model and septic tank bar construction, specifically forming step includes, fixed septic tank lower end external mold, septic tank bar construction is placed on inside the external mold of septic tank lower end, assemble septic tank internal model, and assembled septic tank internal model is placed in inside septic tank bar construction, septic tank upper end external mold is molded and is fixedly connected with septic tank lower end external mold, obtain external mold cavity, casting concrete in outside die cavity body, reserved septic tank opening, after concrete hardening, enter septic tank internal model from septic tank opening, dismantle septic tank internal model, and it is open by septic tank and takes out septic tank internal model, septic tank upper end external mold and lower end external mold are removed again, obtain septic tank;Forming method of the invention is simple, and the case where gap and leak occurs in the septic tank that can be avoided reinforced concrete structure, improves septic tank overall mechanical strength and using effect.

Description

Septic tank integral formation method
Technical field
The present invention relates to septic tank technical field more particularly to a kind of septic tank integral formation methods.
Background technique
Current coagulation great soil group septic tank product is all seperated production, and finally docking forms an entirety, although producing For in mode, split type production difficulty is low, high-efficient, process is easy to control, however needs in last formative stage to each Seperated interface is sealed processing.
And coagulation soil characteristics makes the encapsulation process effect of its interface and bad, this results in the change of seperated technique production Manure pit is easy to appear sealing problem, serious to result even in septic tank overall mechanical properties problem.
Summary of the invention
In view of this, the invention proposes a kind of septic tank integral formation methods that can be applied to concrete manufacture.
The technical scheme of the present invention is realized as follows: the present invention provides a kind of septic tank integral formation methods, including Septic tank lower end external mold, septic tank upper end external mold, septic tank internal model and septic tank bar construction, septic tank lower end external mold and change excrement Pond upper end external mold, which mutually covers to close, forms the external mold cavity of inner hollow, external mold cavity and septic tank internal model be equipped with it is in the same size, The corresponding septic tank opening in position, further includes following forming step:
Step 1: fixed septic tank lower end external mold;
Step 2: septic tank bar construction is placed on inside the external mold of septic tank lower end;
Step 3: assembling septic tank internal model, assembled septic tank internal model is placed in inside septic tank bar construction;
Step 4: septic tank upper end external mold and septic tank lower end external mold are molded, returns and connect outside septic tank upper end surely Mould and septic tank lower end external mold, obtain external mold cavity, and casting concrete in outside die cavity body reserves septic tank opening;
Step 5: septic tank internal model is entered by septic tank opening, dismantles septic tank internal model after concrete hardening, and It is open by septic tank and takes out septic tank internal model, removed septic tank upper end external mold and septic tank lower end external mold, obtain septic tank.
On the basis of above technical scheme, it is preferred that further include reinforcing bar feet, the step 2 further includes changing excrement Reinforcing bar feet is fixedly mounted in the lower end of pond bar construction.
On the basis of above technical scheme, it is preferred that further include cushion block, the step 3 further includes, in septic tank Cushion block is placed at mould and septic tank bar construction contact position.
On the basis of above technical scheme, it is preferred that further include seal pipe, septic tank opening is reserved in the step 4 Method include, septic tank internal model be equipped with opening place be fixedly mounted seal pipe, the opening of seal pipe and septic tank internal model It is bonded to each other.
It still more preferably, further include checking whether leak Step 6: carry out pressurization of pouring water to septic tank.
Septic tank integrated molding method of the invention has the advantages that compared with the existing technology
(1) septic tank integrated molding method of the invention overcomes sealing caused by concrete septic tank multistep molding Property difference problem, and forming method provided by the invention keeps the internal structure serialization degree of septic tank high, to greatly improve The mechanical strength of septic tank;
(2) entire integrally formed method is simple, and used number of molds is few, occupied space, reduction pours difficulty With the number poured, production efficiency is improved.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with It obtains other drawings based on these drawings.
Fig. 1 is the process flow chart of septic tank integral formation method of the present invention;
Fig. 2 is used die structure dwg by septic tank integral formation method of the present invention;
Fig. 3 for the used mold lower end external mold of septic tank integral formation method of the present invention sectional view;
Fig. 4 for the used mold upper end external mold of septic tank integral formation method of the present invention sectional view;
Fig. 5 for the used mold seal pipe of septic tank integral formation method of the present invention structural schematic diagram.
In figure: 1- septic tank lower end external mold, 2- septic tank upper end external mold, 3- septic tank internal model, 4- septic tank bar construction, 5- reinforcing bar feet, 6- cushion block, 7- seal pipe.
Specific embodiment
Below in conjunction with embodiment of the present invention, the technical solution in embodiment of the present invention is carried out clearly and completely Description, it is clear that described embodiment is only some embodiments of the invention, rather than whole embodiments.Base Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts all Other embodiments shall fall within the protection scope of the present invention.
As shown in Figure 1, in conjunction with Fig. 2-Fig. 4, septic tank integral formation method of the invention comprising septic tank lower end external mold 1, septic tank upper end external mold 2, septic tank internal model 3 and septic tank bar construction 4, outside septic tank lower end external mold 1 and septic tank upper end The mutually lid of mould 2 closes the external mold cavity for forming inner hollow, and external mold cavity and septic tank internal model 3 are equipped in the same size, position pair The septic tank opening answered, specific forming step are as follows:
Step 1: septic tank lower end external mold 1 is fixed, septic tank lower end external mold 1 it is opening up;
Step 2: the septic tank bar construction 4 prepared in advance being welded is placed on inside septic tank lower end external mold 1;
Step 3: detachable septic tank internal model 3 is pre-assembled, 3 being put into of septic tank internal model that assembly is finished Inside manure pit bar construction 4;
Step 4: the lid of septic tank upper end external mold 2 is closed being bolted to connection on septic tank lower end external mold 1 again Manure pit upper end external mold 2 and septic tank lower end external mold 1, obtain external mold cavity, form cavity between external mold cavity and septic tank internal model 3 Interlayer, the reserved inside casting concrete of opening of external mold cavity, while externally die cavity body is shaken, external die cavity body and change excrement Hole is reserved between pond internal model 3 to be open as septic tank;
Step 5: being entered in septic tank by septic tank opening after concrete hardening, dismantling septic tank internal model 3, pass through Septic tank opening removes the septic tank internal model 3 of disassembly, then removes septic tank upper end external mold 2 and septic tank lower end external mold 1, obtains Septic tank.
It in a specific embodiment, further include reinforcing bar feet 5, the step 2 further includes, in septic tank bar construction 4 Reinforcing bar feet 5 is fixedly mounted in lower end, so that reinforcing bar be made to have a distance apart from the inner wall of septic tank lower end external mold 1.
It in a specific embodiment, further include cushion block 6, the step 3 further includes, in septic tank internal model 3 and septic tank steel 4 contact position of muscle structure is placed cushion block 6 and is avoided so that septic tank internal model 3 be made to have a distance apart from septic tank bar construction 4 Bar construction is exposed.
Further include seal pipe 7 as shown in figure 5, in a specific embodiment, in the step 4, reserves septic tank opening Method include that seal pipe 7 is fixedly mounted in the place that septic tank internal model 3 is equipped with opening, seal pipe 7 and septic tank internal model 3 Opening is bonded to each other, and is not connected between seal pipe 7 and septic tank upper end external mold 2 or is not exclusively connected, septic tank upper end external mold 2 with Entrance of the gap as casting concrete between seal pipe 7.
It in a specific embodiment, further include checking whether leak Step 6: carry out pressurization of pouring water to septic tank.
In a specific embodiment, step 5 further includes, and is put into steam pipe into septic tank opening, by steam pipe to change It is passed through heating steam in manure pit internal model, accelerates the hardening of concrete.
The foregoing is merely better embodiments of the invention, are not intended to limit the invention, all of the invention Within spirit and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (5)

1. a kind of septic tank integral formation method, which is characterized in that including septic tank lower end external mold (1), septic tank upper end external mold (2), septic tank internal model (3) and septic tank bar construction (4), septic tank lower end external mold (1) and septic tank upper end external mold (2) are mutual Lid closes the external mold cavity for forming inner hollow, and external mold cavity and septic tank internal model (3) are equipped in the same size, position correspondingization Manure pit opening, further comprising the steps of:
Step 1: fixed septic tank lower end external mold (1);
Step 2: it is internal that septic tank bar construction (4) is placed on septic tank lower end external mold (1);
Step 3: assembling septic tank internal model (3), and assembled septic tank internal model (3) is placed in septic tank bar construction (4) Portion;
Step 4: septic tank upper end external mold (2) and septic tank lower end external mold (1) are molded, it is fixedly connected with septic tank upper end External mold (2) and septic tank lower end external mold (1), obtain external mold cavity, casting concrete in outside die cavity body, and reserved septic tank is opened Mouthful;
Step 5: septic tank internal model (3) are entered by septic tank opening, are dismantled septic tank internal model (3) after concrete hardening, And be open by septic tank and take out septic tank internal model (3), septic tank upper end external mold (2) and septic tank lower end external mold (1) are removed, is obtained To septic tank.
2. septic tank integral formation method as described in claim 1, which is characterized in that further include reinforcing bar feet (5), the step Rapid two further include, and reinforcing bar feet (5) are fixedly mounted in the lower end of septic tank bar construction (4).
3. septic tank integral formation method as described in claim 1, which is characterized in that further include cushion block (6), the step 3 It further include placing cushion block (6) at septic tank internal model (3) and septic tank bar construction (4) contact position.
4. septic tank integral formation method as described in claim 1, which is characterized in that further include seal pipe (7), the step The method that septic tank opening is reserved in four includes that seal pipe (7) are fixedly mounted in the place that septic tank internal model (3) are equipped with opening, The seal pipe (7) and the opening of septic tank internal model (3) are bonded to each other.
5. septic tank integral formation method as described in claim 1, which is characterized in that further include Step 6: to septic tank into Capable pressurization of pouring water, checks whether leak.
CN201811617290.9A 2018-12-27 2018-12-27 Septic tank integral formation method Pending CN109534638A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811617290.9A CN109534638A (en) 2018-12-27 2018-12-27 Septic tank integral formation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811617290.9A CN109534638A (en) 2018-12-27 2018-12-27 Septic tank integral formation method

Publications (1)

Publication Number Publication Date
CN109534638A true CN109534638A (en) 2019-03-29

Family

ID=65857461

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811617290.9A Pending CN109534638A (en) 2018-12-27 2018-12-27 Septic tank integral formation method

Country Status (1)

Country Link
CN (1) CN109534638A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110000906A (en) * 2019-05-05 2019-07-12 漳州庆铭工艺品有限公司 A kind of preparation method of Mould for flower pot and flowerpot
CN110355871A (en) * 2019-08-07 2019-10-22 祁锦明 The concrete frame of core mold support circumferential direction muscle with two-way positioning
CN111531685A (en) * 2020-04-28 2020-08-14 漯河俊展机械设备有限公司 Integral molding method of septic tank
CN112726808A (en) * 2020-12-22 2021-04-30 淮北海聚环保设备有限公司 Commercial concrete integral septic tank and forming method thereof
CN112794597A (en) * 2021-01-21 2021-05-14 淮北海聚环保设备有限公司 Commercial concrete integral septic tank device and using method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060065994A1 (en) * 2004-08-20 2006-03-30 Del Zotto William M Septic tank form
CN202625924U (en) * 2012-05-23 2012-12-26 湖北鼎誉环保科技有限公司 High-compression-resistance intensive integral septic tank mold with wave crest structural wall
CN207841671U (en) * 2018-02-09 2018-09-11 徐州文丞预制构件有限公司 A kind of septic tank mould
CN208034957U (en) * 2018-02-09 2018-11-02 徐州文丞预制构件有限公司 A kind of septic tank mould

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060065994A1 (en) * 2004-08-20 2006-03-30 Del Zotto William M Septic tank form
CN202625924U (en) * 2012-05-23 2012-12-26 湖北鼎誉环保科技有限公司 High-compression-resistance intensive integral septic tank mold with wave crest structural wall
CN207841671U (en) * 2018-02-09 2018-09-11 徐州文丞预制构件有限公司 A kind of septic tank mould
CN208034957U (en) * 2018-02-09 2018-11-02 徐州文丞预制构件有限公司 A kind of septic tank mould

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110000906A (en) * 2019-05-05 2019-07-12 漳州庆铭工艺品有限公司 A kind of preparation method of Mould for flower pot and flowerpot
CN110355871A (en) * 2019-08-07 2019-10-22 祁锦明 The concrete frame of core mold support circumferential direction muscle with two-way positioning
CN111531685A (en) * 2020-04-28 2020-08-14 漯河俊展机械设备有限公司 Integral molding method of septic tank
CN112726808A (en) * 2020-12-22 2021-04-30 淮北海聚环保设备有限公司 Commercial concrete integral septic tank and forming method thereof
CN112794597A (en) * 2021-01-21 2021-05-14 淮北海聚环保设备有限公司 Commercial concrete integral septic tank device and using method thereof
CN112794597B (en) * 2021-01-21 2023-01-17 淮北海聚环保设备有限公司 Commercial concrete integral septic tank device and using method thereof

Similar Documents

Publication Publication Date Title
CN109534638A (en) Septic tank integral formation method
CN106121094B (en) The precast concrete shell structure of concrete shear force wall based on 3D printing
CN101486071B (en) Technique and equipment for pouring flanged fitting combination
CN110847427A (en) Prefabricated wall body, prefabricated wall body mould and connection structure
CN103276850A (en) Prefabricated housing for making reinforced concrete beams and mould thereof.
CN109746395A (en) A kind of sand core structure being easy to depoling
CN103770214A (en) Production method for telegraph pole based on self-compacting concrete
CN203546752U (en) Spherical concrete inspection well and casting molding mold of spherical concrete inspection well
CN207630235U (en) Mold for building sandwich structure prefabricated panel
CN107672120A (en) A kind of mould
CN208245746U (en) A kind of case lid casting die
CN206144008U (en) Reinforced concrete precast component
CN215618854U (en) Prefabricated box culvert mould
CN106426524A (en) Mould special for pouring base of integrally-poured inspection well and pouring method
CN108556271A (en) A kind of lower pool body molding die of leak-proof digestion tank
CN210880152U (en) Pouring structure of concrete prefabricated hollow component
CN208214233U (en) A kind of outer housing casting die
CN207372236U (en) Radiator casting sand type with positioning core print
CN209755547U (en) Fully-enclosed toilet bowl mold structure
CN215549560U (en) Integral prefabricated template in vertical crack formula escape canal in super high-section road surface
CN208324044U (en) A kind of lower pool body molding die of leak-proof digestion tank
CN206106056U (en) Integral cast formula inspection well base pouring special mould
CN109594711A (en) A kind of integrated precast component, sandwich hollow slab and preparation method
CN215202552U (en) Variable cross-section prefabricated part forming die and die set
CN217858663U (en) Piston type flow regulating valve sand mold system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190329