CN109523230A - Completion acceptance method, system, electronic equipment and medium for high-voltage expansion field - Google Patents
Completion acceptance method, system, electronic equipment and medium for high-voltage expansion field Download PDFInfo
- Publication number
- CN109523230A CN109523230A CN201811275806.6A CN201811275806A CN109523230A CN 109523230 A CN109523230 A CN 109523230A CN 201811275806 A CN201811275806 A CN 201811275806A CN 109523230 A CN109523230 A CN 109523230A
- Authority
- CN
- China
- Prior art keywords
- acceptance
- work order
- instruments
- examination
- module
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title abstract description 18
- 238000010276 construction Methods 0.000 claims description 21
- 238000003860 storage Methods 0.000 claims description 13
- 238000012986 modification Methods 0.000 claims 2
- 230000004048 modification Effects 0.000 claims 2
- 230000018199 S phase Effects 0.000 claims 1
- 238000012217 deletion Methods 0.000 claims 1
- 230000037430 deletion Effects 0.000 claims 1
- 238000007689 inspection Methods 0.000 abstract description 6
- 238000009434 installation Methods 0.000 abstract description 3
- 238000004590 computer program Methods 0.000 description 13
- 230000006870 function Effects 0.000 description 9
- 230000008569 process Effects 0.000 description 6
- 238000009826 distribution Methods 0.000 description 3
- 238000012360 testing method Methods 0.000 description 3
- 238000004364 calculation method Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000005611 electricity Effects 0.000 description 2
- 230000003993 interaction Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000002537 cosmetic Substances 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002372 labelling Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005192 partition Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F40/00—Handling natural language data
- G06F40/10—Text processing
- G06F40/166—Editing, e.g. inserting or deleting
- G06F40/174—Form filling; Merging
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F40/00—Handling natural language data
- G06F40/10—Text processing
- G06F40/166—Editing, e.g. inserting or deleting
- G06F40/177—Editing, e.g. inserting or deleting of tables; using ruled lines
- G06F40/18—Editing, e.g. inserting or deleting of tables; using ruled lines of spreadsheets
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Tourism & Hospitality (AREA)
- Health & Medical Sciences (AREA)
- Marketing (AREA)
- Entrepreneurship & Innovation (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Data Mining & Analysis (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention provides a completion acceptance method, a completion acceptance system, an intelligent terminal and a medium for a high-voltage industry expansion site, which comprise the following steps: acquiring relevant information of the acceptance personnel; determining the authority of the acceptance personnel according to the relevant information of the acceptance personnel and generating a corresponding initial acceptance work order; adding one or more instruments to be accepted based on the initial acceptance work order; generating one or more instrument acceptance tables for the one or more instruments, the tables including respective instrument information; acquiring on-site instrument acceptance information and completing filling of one or more instrument acceptance forms according to the on-site instrument acceptance information; and (4) assisting to perform acceptance according to the filled one or more instrument acceptance forms, and performing second acceptance until the acceptance is successful. The invention solves the technical problems that the on-site inspection business standards of the current business expansion and installation are not uniform and the work efficiency of acceptance and approval is low.
Description
Technical field
The present invention relates to technical field of electric power, and in particular to a kind of high pressure industry expands live final acceptance of construction method, system, intelligence
Terminal and medium.
Background technique
The on-site examination business tine of Business Process System is complex and is related to the factor of various aspects, if not seeking unity of standard
And process, the development of inspection business can only just solve some cosmetic issues., there are the various origin causes of formation, risk point in the problem of Business Process System
It is hidden in every aspect, has transformer information as industry expands the various aspects situation that need to check, stoichiometric point information, all kinds of electrically sets
Standby adjusting situation, ambient conditions etc., and there is also the risks of different depth degrees for various aspects situation, it is therefore desirable to comprehensively, have
Level has these risk points of the understanding of depth just can preferably carry out on-site examination work.
However, inspector specializes in different business direction, inevitably hurry under the conditions of standard disunity, linking up insufficient in go out
Mistake, causing high pressure industry to expand on-site examination professional skill occasionally has height, and inspection result tends not to comprehensively reflect Marketing
With risk, normality inspecting efficiency still has the space that can be improved, and needs guidance tool that working efficiency and decision can be improved
Accuracy rate can also facilitate the collection of live evidence and material.Meanwhile checking and accepting is also that often problem is found in inspection
Important link had both influenced industry and has expanded flow path efficiency, and also increased the workload of inspection, it is also desirable to instruct work if checking and accepting is not in place
Tool can provide convenience for checking and accepting, check and accept all kinds of electricity consumption electrical equipments and require carefully, provide to execute according to standard.Check and accept knot
The examination & approval of fruit and summarizes and need inspector is hand-written to fill in paper list, then submit gaffer's examination & approval and summarize, whole process ratio
It is cumbersome, heavy workload, low efficiency, and paper list is easily damaged and loses.
Summary of the invention
It is an object of that present invention to provide a kind of high pressure industry to expand live final acceptance of construction method, system, electronic equipment and medium, with
It solves the on-site examination traffic criteria disunity of current Business Process System, check and accept the technical issues of examination and approval work low efficiency.
In order to achieve the object of the present invention, first aspect present invention provides a kind of live final acceptance of construction method of high pressure industry expansion, packet
Include following steps:
Obtain inspector's relevant information;
Inspector's permission is determined according to inspector's relevant information and generates corresponding initial examination work order;
The one or more instruments that need to be checked and accepted are added based on the initial work order of checking and accepting;
Corresponding one or more of instruments generate one or more instruments and check and accept table, and the table includes corresponding instrument letter
Breath;
It obtains field instrumentation acceptance information and one or more of instruments is completed according to the field instrumentation acceptance information and check and accept
Table is filled in;
Table, which is checked and accepted, according to the one or more instruments for completing to fill in generates list to be tested of knocking off;
Pass through if single assistance to be tested of knocking off is checked and accepted, terminates to check and accept work order;If the Dan Wei to be tested that knocks off passes through, return
Step obtains field instrumentation acceptance information and completes one or more of instruments according to the field instrumentation acceptance information and checks and accepts
Table is filled in.
Wherein, inspector's relevant information includes user name, the listed name of transformer, Customs Assigned Number and power supply unit letter
Breath.
Wherein, described that filling in for one or more of instruments examination tables is completed according to the field instrumentation acceptance information
Include:
It fills in the instrument and checks and accepts whether actual phenomenon is consistent with device information;
Wherein, if not being consistent, the pictorial information of pertinent instruments when needing to add practical examination.
Wherein, determine that inspector's permission includes employee's permission or gaffer's permission according to inspector's relevant information,
Employee's permission includes establishing initially check and accept work order, fill in instrument examination table, assist to check and accept work order and modify not pass through
Examination work order;Gaffer's permission includes establishing initial examination work order, filling in instrument examination table, assist to check and accept work order, delete
Remove and modify unsanctioned examination work order and creation user.
Second aspect of the present invention, which provides, a kind of expands live final acceptance of construction method for realizing high pressure industry described in first aspect
System, comprising:
Newly-built work order module is configured as obtaining inspector's relevant information;
User management module is configured as determining inspector's permission according to inspector's relevant information;
First work order generation module is configured as generating corresponding initial examination work order according to inspector's relevant information;
Instrument adding module is configured as adding the one or more instruments that need to be checked and accepted based on the initial work order of checking and accepting;
Table generation module is configured as corresponding to the one or more instruments examination tables of one or more of instruments generations;
Input module is configured as obtaining field instrumentation acceptance information and completes described one according to the field instrumentation acceptance information
A or multiple instruments check and accept filling in for table;
Second work order generation module is configured as generating copending test according to the one or more instruments examination table for completing to fill in
Knock off list;
Module to be checked and accepted is configured as saving the work order checked and accepted;
First checks and accepts module, is configured as examining the work order to be checked and accepted.
It wherein, further include picture adding module, correlator when the picture adding module is configured as adding practical examination
The pictorial information of device.
Wherein, further include the second examination module, be configured as saving approved work order.
Wherein, further include summarizing module, be configured as summarizing and show all examination work orders, including it is to be tested knock off it is single and
Check and accept work order.
Third aspect present invention provides a kind of electronic equipment, and the electronic equipment includes:
Memory stores at least one instruction;And
Processor executes the instruction stored in the memory to realize that high pressure industry expansion scene completion as described in relation to the first aspect is tested
Receiving method.
Fourth aspect present invention provides a kind of computer readable storage medium, stores in the computer readable storage medium
There is at least one instruction, at least one described instruction is executed by the processor in electronic equipment to realize as described in relation to the first aspect
High pressure industry expands live final acceptance of construction method.
Above technical scheme at least has the advantages that
It provides a kind of high pressure industry and expands live final acceptance of construction method, system, electronic equipment and medium, tested by establishing an assistance
Receipts system, examination & approval of check and acceptance result and summarizing do not need the hand-written paper list of filling in of inspector and then submit gaffer's examination & approval and converge
Always, checking and accepting is realized by the system as auxiliary tool, checks and accepts spreadsheeting, it is not easy to damage and loss, Neng Goubang
It helps the power utility check personnel for carrying out live final acceptance of construction work, industry to expand crewmember and carries out the marketing inspection people of on-site examination
The problems such as personnel such as the member scene of rapidly and accurately checking whether there is violation business norms, there are security risks, quick and precisely sends out
Existing problem, specification proposes improving suggestions in time, substantially increases checking and accepting efficiency, power-assisted checking and accepting lean management level
It is promoted.
In addition, other beneficial effects will be explained further below.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with
It obtains other drawings based on these drawings.
Fig. 1 is the flow chart that high pressure industry described in the embodiment of the present invention one expands live final acceptance of construction method.
Fig. 2 is system construction drawing described in the embodiment of the present invention two.
Component labelling in figure:
Newly-built work order module -1, user management module -2, the first work order generation module -3, instrument adding module -4, table generate
Module -5, input module -6, the second work order generation module -7, module -8, the first to be checked and accepted check and accept module -9, and picture adds mould
Block -10, the second checks and accepts module -11, summarizing module -12.
Specific embodiment
Various exemplary embodiments, feature and the aspect of the disclosure are described in detail below with reference to attached drawing.It is identical in attached drawing
Appended drawing reference indicate element functionally identical or similar.Although the various aspects of embodiment are shown in the attached drawings, remove
It non-specifically points out, it is not necessary to attached drawing drawn to scale.
In addition, in order to better illustrate the present invention, numerous details is given in specific embodiment below.This
Field is it will be appreciated by the skilled person that without certain details, the present invention equally be can be implemented.In some instances, for this
Means known to the technical staff of field, element and circuit are not described in detail, in order to highlight purport of the invention.
As shown in Figure 1, the embodiment of the present invention one provides a kind of live final acceptance of construction method of high pressure industry expansion, including walk as follows
It is rapid:
S10 obtains inspector's relevant information;
S20 determines inspector's permission according to inspector's relevant information and generates corresponding initial examination work order;
S30 adds the one or more instruments that need to be checked and accepted based on the initial work order of checking and accepting;
S40 corresponds to one or more of instruments and generates one or more instruments examination tables, and the table includes corresponding instrument
Information;
S50 obtains field instrumentation acceptance information and completes one or more of instruments according to the field instrumentation acceptance information and tests
Receive filling in for table;
S60 checks and accepts table according to the one or more instruments for completing to fill in and generates list to be tested of knocking off;It should be noted that only when testing
It receives the content for needing to fill in table to be filled out completely, list to be tested of knocking off just can be generated;
If S70 it is described it is to be tested knock off it is single automatically by terminating to check and accept work order;If single check and accept to be tested of knocking off does not pass through,
Return step obtains field instrumentation acceptance information and completes one or more of instruments according to the field instrumentation acceptance information
Check and accept filling in for table.
Wherein, the instrument that addition may be selected has: overhead transmission line, cable, oil-immersed type transformer, dry-type transformer, box type transformation
It stands, rack, high-tension switch cabinet, outdoor cable distribution box, low-voltage distribution cabinet, bus, disk cabinet and secondary circuit tie lines, single-phase electric energy
Table, three-phase electric energy meter, metering secondary wiring and metering device connecting pin, mutual inductor, secondary circuit, DC power system, direct current
Shield main components, construction temporary electricity, the earth leakage protective of architecture indoor, metering device, public project, public looped network cashier's office,
Dedicated looped network cashier's office and low-voltage power distribution room etc..
Wherein, inspector's relevant information includes user name, the listed name of transformer, Customs Assigned Number and power supply unit letter
Breath.
Wherein, described that filling in for one or more of instruments examination tables is completed according to the field instrumentation acceptance information
Include:
It fills in the instrument and checks and accepts whether actual phenomenon is consistent with device information;
Wherein, if not being consistent, the pictorial information of pertinent instruments when needing to add practical examination.
Specifically, corresponding instrument is selected to carry out information solicitation, select ' being ', then shows that the instrument checks and accepts actual phenomenon
Meet with description.'No' is selected, then shows that the instrument is checked and accepted actual phenomenon and do not met with description, selects 'No', at least need to add
Add the picture for not meeting description in relation to the instrument, in a preferred embodiment, at least adds three.
Wherein, determine that inspector's permission includes employee's permission or gaffer's permission according to inspector's relevant information,
Employee's permission includes establishing initially check and accept work order, fill in instrument examination table, assist to check and accept work order and modify not pass through
Examination work order;Gaffer's permission includes establishing initial examination work order, filling in instrument examination table, assist to check and accept work order, delete
Remove and modify unsanctioned examination work order, creation user etc..
Specifically, user is divided into two class roles: gaffer and employee by the present embodiment.For Fig. 1, this be gaffer and
The page that employee shares.Wherein employee enjoys the permission of newly-built work order, clicks newly-built work order, pointing device enters equipment and fills out later
Page is write, relevant content is carried out and fills in, takes pictures, chooses.That completes all devices fills in the examination that just can be carried out work order afterwards, i.e.,
Generate list to be tested of knocking off.
Gaffer enjoys newly-built work order, deletes work order and the permission of newly-built user, after having filled in work order, if work order is not tested
It receives, then needs to rectify and improve, i.e. return step S50.All instruments just represent work order examination after having checked and accepted is completed to assist to check and accept
Function.
Expand live final acceptance of construction method second embodiment of the present invention provides a kind of for realizing high pressure industry described in embodiment one
System, the system can be the form of APP to realize, comprising:
Newly-built work order module 1 is configured as obtaining inspector's relevant information of inspector's input;
User management module 2 is configured as determining inspector's permission according to inspector's relevant information;
First work order generation module 3 is configured as generating corresponding initial examination work order according to inspector's relevant information;
Instrument adding module 4 is configured as adding the one or more instruments that need to be checked and accepted based on the initial work order of checking and accepting;
Table generation module 5 is configured as corresponding to the one or more instruments examination tables of one or more of instruments generations;
Input module 6 is configured as obtaining field instrumentation acceptance information and according to field instrumentation acceptance information completion
One or more instruments check and accept filling in for table;
Second work order generation module 7 is configured as being generated according to the one or more instruments examination table for completing to fill in wait check and accept
Check and accept work order;
Module 8 to be checked and accepted is configured as saving work order to be checked and accepted;
First checks and accepts module 9, is configured as carrying out assistance examination to the work order to be checked and accepted.
It wherein, further include picture adding module 10, the picture adding module is configured as adding related when practical examination
The pictorial information of instrument.
Wherein, further include the second examination module 11, be configured as saving approved work order.
Wherein, further include summarizing module 12, be configured as summarizing and show all examination work orders, including it is to be tested knock off it is single and
Work order is checked and accepted.
For the system disclosed in the embodiment two, since it is corresponding with method disclosed in embodiment one, so description
It is fairly simple, reference may be made to the description of the method.
The embodiment of the present invention three provides a kind of electronic equipment, and the electronic equipment includes:
Memory stores at least one instruction;And
Processor executes the instruction stored in the memory and is tested with realizing that the high pressure industry as described in embodiment one expands scene completion
Receiving method.
The electronic equipment can be any electronic product that human-computer interaction can be carried out with user, for example, personal meter
Calculation machine, tablet computer, smart phone, personal digital assistant (PersonalDigitalAssistant, PDA), game machine, interaction
Formula Web TV (InternetProtocolTelevision, IPTV), intellectual wearable device etc..
The electronic equipment can also include the network equipment and/or user equipment.Wherein, the network equipment includes, but
It is not limited to single network server, the server group of multiple network servers composition or based on cloud computing (CloudComputing)
The cloud being made of a large amount of hosts or network server.
Network locating for the electronic equipment include but is not limited to internet, wide area network, Metropolitan Area Network (MAN), local area network, it is virtual specially
With network (VirtualPrivateNetwork, VPN) etc..
In one embodiment, the electronic equipment includes, but are not limited to memory, processor, and is stored in described
In memory and the computer program that can run on the processor, such as automobile parts polling routine.
It will be understood by those skilled in the art that the schematic diagram is only the example of electronic equipment, not structure paired electrons
The restriction of equipment may include perhaps combining certain components or different components, example than illustrating more or fewer components
Such as described electronic equipment can also include input-output equipment, network access equipment, bus.
Alleged processor can be central processing unit (Central Processing Unit, CPU), can also be it
His general processor, digital signal processor (Digital Signal Processor, DSP), specific integrated circuit
(Application Specific Integrated Circuit, ASIC), ready-made programmable gate array (Field-
Programmable Gate Array, FPGA) either other programmable logic device, discrete gate or transistor logic,
Discrete hardware components etc..General processor can be microprocessor or the processor is also possible to any conventional processor
Deng the processor is arithmetic core and the control centre of the electronic equipment, entirely electric using various interfaces and connection
The various pieces of sub- equipment, and execute the operating system and the types of applications program of installation, program code of the electronic equipment
Deng.
The processor executes the operating system of the electronic equipment and the types of applications program of installation.The processor
The application program is executed to realize the step in above-mentioned each automobile parts querying method embodiment, such as step shown in FIG. 1
Rapid S10-S70.
Illustratively, the computer program can be divided into one or more module/units, one or more
A module/unit is stored in the memory, and is executed by the processor, to complete the present invention.It is one or more
A module/unit can be the series of computation machine program instruction section that can complete specific function, and the instruction segment is for describing institute
State implementation procedure of the computer program in the electronic equipment.For example, the computer program can be divided into newly-built work
Single module, user management module, the first work order generation module, instrument adding module, table generation module, input module, second
Work order generation module, copending module, the first approval module, picture adding module, the second approval module and summarizing module etc..
The memory can be used for storing the computer program and/or module, and the processor is by operation or executes
Computer program in the memory and/or module are stored, and calls the data being stored in memory, described in realization
The various functions of electronic equipment.The memory can mainly include storing program area and storage data area, wherein storing program area
It can application program (such as sound-playing function, image player function etc.) needed for storage program area, at least one function etc.;
Storage data area, which can be stored, uses created data (such as audio data, phone directory etc.) etc. according to mobile phone.In addition, storage
Device may include high-speed random access memory, can also be hard including nonvolatile memory, such as hard disk, memory, plug-in type
Disk, intelligent memory card (SmartMediaCard, SMC), secure digital (SecureDigital, SD) card, flash card
(FlashCard), at least one disk memory, flush memory device or other volatile solid-state parts.
The memory can be the external memory and/or internal storage of electronic equipment.Further, the storage
Device can be the circuit with store function for not having physical form in integrated circuit, as RAM (Random-AccessMemory,
Random access memory), FIFO (FirstInFirstOut) etc..Alternatively, the memory is also possible to physical form
Memory, such as memory bar, TF card (Trans-flashCard).
If the integrated module/unit of the electronic equipment is realized in the form of SFU software functional unit and as independent production
Product when selling or using, can store in a computer readable storage medium.Based on this understanding, the present invention realizes
All or part of the process in above-described embodiment method can also instruct relevant hardware to complete by computer program,
The computer program can be stored in a computer readable storage medium, the computer program when being executed by processor,
The step of above-mentioned each embodiment of the method can be achieved.
Wherein, the computer program includes computer program code, and the computer program code can be source code
Form, object identification code form, executable file or certain intermediate forms etc..The computer-readable medium may include: can
Carry any entity or device, recording medium, USB flash disk, mobile hard disk, magnetic disk, CD, computer of the computer program code
Memory, read-only memory (ROM, Read-OnlyMemory), random access memory (RAM,
RandomAccessMemory), electric carrier signal, telecommunication signal and software distribution medium etc..It should be noted that the meter
The content that calculation machine readable medium includes can carry out increase and decrease appropriate according to the requirement made laws in jurisdiction with patent practice,
It such as does not include electric carrier signal and telecommunications according to legislation and patent practice, computer-readable medium in certain jurisdictions
Signal.
The embodiment of the present invention four provides a kind of computer readable storage medium, stores in the computer readable storage medium
There is at least one instruction, at least one described instruction is executed by the processor in electronic equipment to realize as described in embodiment one
High pressure industry expands live final acceptance of construction method.
In several embodiments provided by the present invention, it should be understood that disclosed system, device and method can be with
It realizes by another way.For example, the apparatus embodiments described above are merely exemplary, for example, the module
It divides, only a kind of logical function partition, there may be another division manner in actual implementation.
The module as illustrated by the separation member may or may not be physically separated, aobvious as module
The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple
In network unit.Some or all of the modules therein can be selected to realize the mesh of this embodiment scheme according to the actual needs
's.
It, can also be in addition, each functional module in each embodiment of the present invention can integrate in one processing unit
It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list
Member both can take the form of hardware realization, can also realize in the form of hardware adds software function module.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie
In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.
Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this
The range of invention is indicated by the appended claims rather than the foregoing description, it is intended that the equivalent requirements of the claims will be fallen in
All changes in meaning and scope are included in the present invention.Any attached associated diagram label in claim should not be considered as limit
Claim involved in making.
Furthermore, it is to be understood that one word of " comprising " does not exclude other units or steps, odd number is not excluded for plural number.In system claims
The multiple units or device of statement can also be implemented through software or hardware by a unit or device.Second equal words are used
It indicates title, and does not indicate any particular order.
Finally it should be noted that the above examples are only used to illustrate the technical scheme of the present invention and are not limiting, although reference
Preferred embodiment describes the invention in detail, those skilled in the art should understand that, it can be to of the invention
Technical solution is modified or equivalent replacement, without departing from the spirit and scope of the technical solution of the present invention.
Claims (10)
1. a kind of high pressure industry expands live final acceptance of construction method, which comprises the steps of:
Obtain inspector's relevant information;
Inspector's permission is determined according to inspector's relevant information and generates corresponding initial examination work order;
The one or more instruments that need to be checked and accepted are added based on the initial work order of checking and accepting;
Corresponding one or more of instruments generate one or more instruments and check and accept table, and the table includes corresponding instrument letter
Breath;
It obtains field instrumentation acceptance information and one or more of instruments is completed according to the field instrumentation acceptance information and check and accept
Table is filled in;
Table, which is checked and accepted, according to the one or more instruments for completing to fill in generates list to be tested of knocking off;
Pass through if single assistance to be tested of knocking off is checked and accepted, terminates to check and accept work order;If single assistance to be tested of knocking off is checked and accepted obstructed
It crosses, then return step obtains field instrumentation acceptance information and completed according to the field instrumentation acceptance information one or more of
Instrument is checked and accepted filling in for table and is passed through until checking and accepting.
2. high pressure industry as described in claim 1 expands live final acceptance of construction method, which is characterized in that inspector's correlation letter
Breath includes user name, the listed name of transformer, Customs Assigned Number and power supply unit information.
3. high pressure industry as described in claim 1 expands live final acceptance of construction method, which is characterized in that described according to the live instrument
Device acceptance information completes one or more of filling in for table of instruments examination
It fills in the instrument and checks and accepts whether actual phenomenon is consistent with device information;
Wherein, if not being consistent, the pictorial information of pertinent instruments when needing to add practical examination.
4. high pressure industry as described in claim 1 expands live final acceptance of construction method, which is characterized in that according to inspector's phase
It closes information and determines that inspector's permission includes employee's permission or gaffer's permission, employee's permission includes establishing initial examination work
List fills in instrument examination table and the unsanctioned examination work order of modification;Gaffer's permission include establish it is initial check and accept work order,
It fills in instrument and checks and accepts table, deletion and the unsanctioned examination work order of modification and creation user.
5. a kind of system for expanding live final acceptance of construction method for realizing the high pressure industry characterized by comprising
Newly-built work order module is configured as obtaining inspector's relevant information;
User management module is configured as determining inspector's permission according to inspector's relevant information;
First work order generation module is configured as generating corresponding initial examination work order according to inspector's relevant information;
Instrument adding module is configured as adding the one or more instruments that need to be checked and accepted based on the initial work order of checking and accepting;
Table generation module is configured as corresponding to the one or more instruments examination tables of one or more of instruments generations;
Input module is configured as obtaining field instrumentation acceptance information and completes described one according to the field instrumentation acceptance information
A or multiple instruments check and accept filling in for table;
Second work order generation module is configured as not checking and accepting work according to the one or more instruments examination table generation for completing to fill in
It is single;
Module to be checked and accepted is configured as saving work order to be checked and accepted;
First checks and accepts module, is configured as singly carrying out assistance examination to be tested knock off.
6. system as claimed in claim 5, which is characterized in that it further include picture adding module, the picture adding module quilt
The pictorial information of pertinent instruments when being configured to add practical examination.
7. system as claimed in claim 5, which is characterized in that further include the second examination module, be configured as saving and check and accept
Successful work order.
8. system as claimed in claim 5, which is characterized in that further include summarizing module, it is all to be configured as summarizing display
Work order is checked and accepted, including to be tested knock off single and has checked and accepted work order.
9. a kind of electronic equipment, which is characterized in that the electronic equipment includes:
Memory stores at least one instruction;And
Processor executes the instruction stored in the memory to realize the high pressure as described in any one of Claims 1-4
Industry expands live final acceptance of construction method.
10. a kind of computer readable storage medium, it is characterised in that: be stored at least one in the computer readable storage medium
A instruction, at least one described instruction are executed by the processor in electronic equipment to realize such as any one of Claims 1-4
The high pressure industry expands live final acceptance of construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811275806.6A CN109523230A (en) | 2018-10-30 | 2018-10-30 | Completion acceptance method, system, electronic equipment and medium for high-voltage expansion field |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811275806.6A CN109523230A (en) | 2018-10-30 | 2018-10-30 | Completion acceptance method, system, electronic equipment and medium for high-voltage expansion field |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109523230A true CN109523230A (en) | 2019-03-26 |
Family
ID=65774349
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811275806.6A Pending CN109523230A (en) | 2018-10-30 | 2018-10-30 | Completion acceptance method, system, electronic equipment and medium for high-voltage expansion field |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109523230A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113762925A (en) * | 2021-09-07 | 2021-12-07 | 广东电网有限责任公司 | Auxiliary ticket filling method and device, electronic equipment and storage medium |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2013026097A1 (en) * | 2011-08-23 | 2013-02-28 | Cirianni Giuseppe | Recording, tracking and evaluating system |
CN104182839A (en) * | 2014-08-26 | 2014-12-03 | 国家电网公司 | Electric marketing service expansion mobile application system and work method thereof |
CN105701619A (en) * | 2016-01-15 | 2016-06-22 | 上海建科工程咨询有限公司 | Method for acquiring constructional engineering quality safety information |
CN106897642A (en) * | 2017-01-25 | 2017-06-27 | 上海建工五建集团有限公司 | Prefabricated components are received acceptance method and system |
CN207115482U (en) * | 2017-08-01 | 2018-03-16 | 广东电网有限责任公司佛山供电局 | Power engineering project quality in site receipt control system |
-
2018
- 2018-10-30 CN CN201811275806.6A patent/CN109523230A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2013026097A1 (en) * | 2011-08-23 | 2013-02-28 | Cirianni Giuseppe | Recording, tracking and evaluating system |
CN104182839A (en) * | 2014-08-26 | 2014-12-03 | 国家电网公司 | Electric marketing service expansion mobile application system and work method thereof |
CN105701619A (en) * | 2016-01-15 | 2016-06-22 | 上海建科工程咨询有限公司 | Method for acquiring constructional engineering quality safety information |
CN106897642A (en) * | 2017-01-25 | 2017-06-27 | 上海建工五建集团有限公司 | Prefabricated components are received acceptance method and system |
CN207115482U (en) * | 2017-08-01 | 2018-03-16 | 广东电网有限责任公司佛山供电局 | Power engineering project quality in site receipt control system |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113762925A (en) * | 2021-09-07 | 2021-12-07 | 广东电网有限责任公司 | Auxiliary ticket filling method and device, electronic equipment and storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102622463B (en) | Drawing-model uniformity based method for automatic check of design drawings | |
CN105955878A (en) | Server-side test method and system | |
CN108197036A (en) | For determining the method and apparatus of the coverage rate information of incremental code | |
CN110852023B (en) | Automatic generation method and device for primary main wiring diagram of intelligent substation | |
CN103677815B (en) | A kind of spacecraft low-frequency cable electrical property autotest program generates method | |
CN105760603B (en) | A kind of grid model data conversion method and device | |
CN109460595A (en) | A kind of power cable laying design method | |
CN116561941B (en) | SCD virtual loop template model and modeling and application method thereof | |
CN109408502A (en) | A kind of data standard processing method, device and its storage medium | |
CN106095948A (en) | The querying method of form, device and equipment | |
CN109523230A (en) | Completion acceptance method, system, electronic equipment and medium for high-voltage expansion field | |
CN106301976A (en) | A kind of intelligent substation schedule information automated testing method | |
CN112634436A (en) | Equipment lightweight display system of power system BIM model | |
CN107169175A (en) | One kind verification rational method and system of overhead transmission line topology design | |
CN115794245B (en) | Data loading method and device, electronic equipment and storage medium | |
CN106940827A (en) | Modularization power supply plan automatic generation method based on AR technologies and VR technologies | |
CN115420993B (en) | Method, device and terminal equipment for locating single-phase disconnection fault of power distribution network | |
CN106301833A (en) | A kind of transformer station schedule information method of testing | |
US8886507B2 (en) | Methods and systems for simulating circuit operation | |
CN107451188A (en) | A kind of dissemination method and system of power grid regulation model data multistage combination of nodes | |
CN108629131B (en) | Intelligent generation method and device of cross-connection structure diagram | |
CN109066973B (en) | Visualization method and system for intelligent substation and terminal equipment | |
CN104574200B (en) | Power network nucleus correcting system and method | |
CN112861368A (en) | Power distribution network information model construction method and device and terminal equipment | |
CN109088950A (en) | Data transmission method, device, system and computer readable storage medium |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190326 |
|