CN109518698B - Water-rich deep foundation pit support structure close to operating high-iron sand pebble layer and construction method thereof - Google Patents

Water-rich deep foundation pit support structure close to operating high-iron sand pebble layer and construction method thereof Download PDF

Info

Publication number
CN109518698B
CN109518698B CN201811566729.XA CN201811566729A CN109518698B CN 109518698 B CN109518698 B CN 109518698B CN 201811566729 A CN201811566729 A CN 201811566729A CN 109518698 B CN109518698 B CN 109518698B
Authority
CN
China
Prior art keywords
water
foundation pit
deep foundation
occlusion
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811566729.XA
Other languages
Chinese (zh)
Other versions
CN109518698A (en
Inventor
吴沛沛
李宁
姚裕春
李安洪
周成
曾永红
李井元
龚建辉
陈伟志
丁兆锋
胡会星
胡杰
林东升
魏炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201811566729.XA priority Critical patent/CN109518698B/en
Publication of CN109518698A publication Critical patent/CN109518698A/en
Application granted granted Critical
Publication of CN109518698B publication Critical patent/CN109518698B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete

Abstract

A support structure of a foundation pit with a rich water depth and a construction method thereof are provided, which are close to an operation high-speed railway and are used for effectively avoiding disturbance and influence of precipitation and excavation of the foundation pit with the rich water depth of the pebble layer on the immediately adjacent operation high-speed railway. And drilling fender piles which are filled with reinforced concrete are arranged at the far side of the sand pebble layer water-rich deep foundation pit at intervals in the longitudinal direction, engagement fender piles which are filled with reinforced concrete and engagement water stop piles which are filled with plain concrete are arranged at intervals in the longitudinal direction at the near side, and crown beams which are longitudinally pulled through along the sand pebble layer water-rich deep foundation pit are arranged at the tops of the drilling fender piles, the engagement fender piles and the engagement water stop piles. The horizontal limiting supports are arranged in a row along the depth direction and the longitudinal interval of the deep foundation pit rich in water of the sand-gravel layer, the shaft regulator and the steel enclosing purlin are arranged at the near end of the horizontal limiting supports which are arranged on the same side and the same row, the steel enclosing purlin is arranged at the far end, the steel enclosing purlins at the near end and the far end of the uppermost layer respectively act on the crown beams at the near side and the far side, the steel enclosing purlins at the near end of the other layers act on the occlusion enclosing pile and the occlusion water stopping pile, and the steel enclosing purlin at the far end acts on the drilling enclosing pile.

Description

Water-rich deep foundation pit support structure close to operating high-iron sand pebble layer and construction method thereof
Technical Field
The invention relates to a water-rich deep foundation pit enclosure structure adjacent to an operating high-speed rail pebble layer and a construction method thereof, which can be used in the fields of railway engineering, highway engineering, municipal engineering and the like, and is particularly suitable for the water-rich deep foundation pit engineering adjacent to the existing high-speed rail.
Background
With the development of urban construction, the deep foundation pit adjacent to the existing high-speed ballastless track is more and more, because the high-speed ballastless track is extremely sensitive to deformation, the ballastless track high-speed rail in operation is almost required to be in zero sedimentation, when the stratum is a sandy pebble layer with stronger water permeability, the groundwater level is often higher, and the excavation and precipitation of the conventional foundation pit can have different degrees of influence on the railway adjacent to the existing high-speed ballastless track, and even the operation safety of the high-speed rail can be endangered.
Aiming at the difficult reinforcement of the deep foundation pit, the invention not only can ensure the safety of the deep foundation pit, but also can ensure the operation safety of high-speed rails with the periphery adjacent to ballastless tracks, and simultaneously has the advantages of low engineering investment, low carbon and environmental protection, and has popularization.
Disclosure of Invention
The technical problem to be solved by the invention is to provide the enclosure structure of the foundation pit with the water-rich deep in the immediately adjacent operation high-speed railway, so that the disturbance and influence of precipitation and excavation of the foundation pit with the water-rich deep in the sand-gravel layer on the immediately adjacent operation high-speed railway are effectively avoided.
The technical scheme adopted by the invention for solving the technical problems is as follows:
the invention relates to a water-rich deep foundation pit support structure of a sand-gravel layer close to an operation high-speed railway embankment, which is characterized in that: the far side of the sand-gravel layer water-rich deep foundation pit is provided with drilling fender piles which are filled with reinforced concrete at intervals along the longitudinal direction, the near side of the sand-gravel layer water-rich deep foundation pit is provided with interlocking fender piles which are filled with reinforced concrete and interlocking water-stop piles which are filled with plain concrete at intervals along the longitudinal direction, the interlocking fender piles and the interlocking water-stop piles are alternately arranged and are in an interlocking shape, and the tops of the drilling fender piles, the interlocking fender piles and the interlocking water-stop piles are provided with crown beams which are longitudinally pulled through along the sand-gravel layer water-rich deep foundation pit; the deep foundation pit depth direction of rich water of sand gravel layer and vertical interval are arranged in a row and are provided with transverse limit struts, the same side and the same row of transverse limit struts are provided with a shaft regulator and a steel enclosing purlin at the near end, the steel enclosing purlin at the near end and the far end of the uppermost layer respectively acts on the crown beams at the near side and the far side, the steel enclosing purlin at the near end of the other layers acts on the occlusion fender pile and the occlusion water stop pile, the steel enclosing purlin at the far end acts on the drilling fender pile, and the shaft force of each transverse limit strut is regulated through the shaft regulator to limit the deformation of the deep foundation pit of rich water of sand gravel layer and the operation high-speed railway embankment.
The outer side of the far side of the sand-gravel layer water-rich deep foundation pit is provided with a filtering type water-lowering well at a longitudinal interval, a water level adjusting well is arranged between the near side and an operating high-speed railway embankment at a longitudinal interval, and a deformation measuring instrument is arranged outside the toe of the operating high-speed railway embankment.
The bottom of the sandy pebble layer water-rich deep foundation pit is sealed by a pit bottom water-resisting layer.
The invention provides a construction method for a water-rich deep foundation pit support structure close to an operating high-iron sand pebble layer, which comprises the following steps:
(1) a deformation measuring instrument is arranged outside the slope toe of the operating high-speed railway embankment to form a deformation observation system;
(2) positioning the occlusion fender pile and the occlusion water stop pile at the near side of the water-rich deep foundation pit of the sanded pebble layer, and pouring a crescent guide groove according to the positioning;
(3) after the crescent guide groove reaches the design strength, the whole sleeve pipe is adopted for pipe twisting and drilling, the occlusion water stop pile is constructed in a mode of punching and grabbing soil holes, a retarder is added during pouring, and smooth drilling can be ensured when the occlusion fender pile of the next working procedure is implemented;
(4) before pile body plain concrete of the occlusion water stop pile is initially set, constructing adjacent occlusion guard piles by adopting a full sleeve pipe rubbing drilling mode and a mode of punching and grabbing soil holes, and arranging a reinforcement cage, and reversely rubbing a lifting sleeve while pouring pile body concrete to ensure occlusion quality;
(5) alternately repeating the step (3) and the step (4) until the construction of the occlusion fender pile and the occlusion water stop pile is completed;
(6) chiseling pile heads of the occlusion guard piles and the occlusion water stop piles to form 0.5m floating paste, binding a reinforcement cage, and pouring proximal crown beam concrete;
(7) constructing a drilling fender pile on the far side at the same time of the construction step;
(8) constructing a filtering type dewatering well and a water level adjusting well, and starting dewatering operation on the far side;
(9) when the drilling fender piles, the occlusion fender piles and the occlusion water stop piles on the two sides all reach the design strength, the sand gravel layer water-rich deep foundation pit is dug in layers, and real-time deformation monitoring is carried out on the operation high-speed railway embankment and the sand gravel layer water-rich deep foundation pit;
when the sand-gravel layer water-rich deep foundation pit is excavated to a depth of 0.5m below the elevation of the first layer of transverse limiting support, the corresponding steel purlin and the corresponding shaft regulator are arranged, and prestress is applied to the transverse limiting support through the shaft regulator, so that the sand-gravel layer water-rich deep foundation pit is prevented from deforming to the inner side;
continuously digging downwards to a depth of 0.5m below the elevation of the second transverse limit support, and repeating the step (d) until the pit is dug to the bottom of the water-rich deep foundation pit of the sandy pebble layer;
and (3) injecting water-stop slurry into the bottom of the foundation pit to form a pit bottom water-resisting layer.
Aiming at the strict requirement of the operation high-speed rail on deformation, the invention combines the water-rich characteristic of the sand pebble layer, adopts a unilateral occlusion fender pile and an occlusion water stop pile to carry out enclosure, and effectively and accurately determines the pile position through a crescent guide groove and the pile position when the occlusion fender pile and the occlusion water stop pile are constructed, ensures the occlusion size, and furthest reduces the influence on the operation high-speed rail when drilling by the modes of full sleeve pipe rubbing, drilling and earth grabbing; the underground water level is controlled at any time by adopting a mode of combining a filtering type dewatering well with a water level regulating well, so that risks of instability, piping and the like in the process of excavating a foundation pit are reduced, and meanwhile, foundation settlement deformation caused by sudden drop of the water level of the high-iron-base bottom can be greatly reduced; the construction process is to observe the water level change condition of the operation high-speed rail side and the high-speed rail deformation condition at any time through the water level regulating well, and if abnormality is found, the deformation of the operation high-speed rail is controlled by recharging groundwater and increasing the transverse limit supporting axial force through the water level regulating well and the axial force regulator respectively, so that an informationized and dynamic construction method is formed.
Drawings
The specification includes four drawings as follows:
FIG. 1 is a cross-sectional view of a water-rich deep foundation pit enclosure of the present invention immediately adjacent to an operational high-iron sand pebble layer;
FIG. 2 is a plan view of the present invention immediately adjacent to a water-rich deep foundation pit enclosure operating a high-iron sand pebble layer;
FIG. 3 is a graph of the relationship between a shaft adjuster and a transverse limit bracing steel purlin of the present invention immediately adjacent to a water-rich deep foundation pit enclosure operating a high-iron sand pebble layer.
FIG. 4 is a construction diagram of a crescent guide slot for constructing a biting fender pile and a biting water stop pile in the construction method of the invention for operating a high-iron sand pebble layer water-rich deep foundation pit support structure.
The figure shows the components, part names and corresponding labels: the method comprises the following steps of operating a high-speed rail A, a sand pebble layer water-rich deep foundation pit B, a bored pile fender pile 1, a biting fender pile 2, a biting water stop pile 3, a crown beam 4, a transverse limiting support 5, a steel enclosing purlin 6, a shaft regulator 7, a filtering type dewatering well 8, a water level regulating well 9, a deformation observation point 10, a pit bottom sealing layer 11 and a crescent guide groove 12.
Description of the embodiments
The invention will be further described with reference to the drawings and examples.
Referring to fig. 1, 2 and 3, the invention is closely adjacent to a water-rich deep foundation pit enclosure structure of an operation high-speed railway embankment A, a sand-gravel layer water-rich deep foundation pit B is closely adjacent to an operation high-speed railway embankment A, drilling fender piles 1 which are filled with reinforced concrete are longitudinally arranged at intervals on the far side of the sand-gravel layer water-rich deep foundation pit B, occluding fender piles 2 which are filled with reinforced concrete and occluding water-stop piles 3 which are filled with plain concrete are longitudinally arranged at intervals on the near side of the sand-gravel layer water-rich deep foundation pit B, the occluding fender piles 2 and the occluding water-stop piles 3 are alternately arranged and are in an occluding shape, and crown beams 4 which are longitudinally pulled through along the sand-gravel layer water-rich deep foundation pit B are arranged at the tops of the drilling fender piles 1, the occluding fender piles 2 and the occluding water-stop piles 3; the deep foundation pit B with the sand and pebble layer is provided with transverse limiting supports 5 in rows along the depth direction and longitudinal intervals, the transverse limiting supports 5 on the same side and in the same row are provided with an axle regulator 6 and a steel enclosing purlin 7 at the near end, the steel enclosing purlins 7 at the near end and the far end of the uppermost layer are respectively acted on the crown beams 4 at the near side and the far side, the steel enclosing purlins 7 at the near end of the rest layers are acted on the occlusion fender pile 2 and the occlusion water stop pile 3, the steel enclosing purlins 7 at the far end are acted on the drilling fender pile 1, and the axle force of each transverse limiting support 5 is regulated through the axle regulator 6 to limit the deformation of the deep foundation pit B with the sand and pebble layer and the operation high-speed railway embankment A.
Referring to fig. 1 and 2, a filtering type dewatering well 8 is longitudinally arranged at intervals on the outer side of the far side of the sand-pebble layer water-rich deep foundation pit B, a water level adjusting well 9 is longitudinally arranged between the near side and the operating high-speed railway embankment A, and a deformation measuring instrument 10 is arranged outside the toe of the operating high-speed railway embankment A to form a deformation measuring system.
Referring to fig. 1 and 2, the bottom of the sandy pebble layer water-rich deep foundation pit B is closed by a pit bottom water-resisting layer 11, and the pit bottom water-resisting layer 11 can be formed by injecting water-stopping slurry into the bottom of the foundation pit. The steel purlin 7 is longitudinally pulled through along the sand-gravel layer water-rich deep foundation pit B, the transverse limiting support 5 can be made of steel pipes, and the shaft regulator 6 is usually a hydraulic jack.
Referring to fig. 1 and 2, the construction method of the water-rich deep foundation pit enclosure structure adjacent to the operation high-iron sand pebble layer of the invention comprises the following steps:
(1) a deformation measuring instrument 10 is arranged outside the slope toe of the operating high-speed railway embankment A to form a deformation observation system;
(2) positioning the occlusion fender pile 2 and the occlusion water stop pile 3 near the sanded pebble layer water-rich deep foundation pit B, and pouring a crescent guide groove 12 according to the positioning;
(3) after the crescent guide groove 12 reaches the design strength, the whole sleeve pipe is adopted for pipe twisting and drilling, the biting water stop pile 3 is constructed in a mode of punching and grabbing soil holes, retarder is added during pouring, and smooth drilling can be ensured when the biting fender pile 2 is implemented in the next working procedure;
(4) before the pile body plain concrete of the occlusion water stop pile 3 is initially set, constructing adjacent occlusion guard piles 2 by adopting a full sleeve pipe rubbing drilling mode and a mode of punching and grabbing soil holes, and arranging a reinforcement cage, and reversely rubbing and lifting sleeves while pouring pile body concrete to ensure occlusion quality;
(5) alternately repeating the step (3) and the step (4) until the construction of the occlusion fender pile 2 and the occlusion water stop pile 3 is completed;
(6) chiseling pile heads of the occlusion fender pile 2 and the occlusion water stop pile 3 to form 0.5m floating paste, binding a reinforcement cage, and pouring proximal crown beam 4 concrete;
(7) simultaneously with the construction step 6, constructing a drilling fender pile 1 on the far side;
(8) constructing a filtering type dewatering well 8 and a water level adjusting well 9, and starting dewatering operation on the far side;
(9) when the drilling fender piles 1, the occlusion fender piles 2 and the occlusion water stop piles 3 on the two sides reach the design strength, the sand and pebble layer water-rich deep foundation pit B is dug in layers, and real-time deformation monitoring is carried out on the operation high-speed railway embankment A and the sand and pebble layer water-rich deep foundation pit B;
when the sand-gravel layer water-rich deep foundation pit B is excavated to a depth of 0.5m below the elevation of the first layer of transverse limiting support 5, arranging the first layer of transverse limiting support 5, the corresponding steel enclosing purlin 7 and the shaft regulator 6) and applying prestress to the transverse limiting support 5 through the shaft regulator 6, so that the sand-gravel layer water-rich deep foundation pit B is prevented from deforming inwards;
continuously digging downwards to a depth of 0.5m below the 5 elevation of the second transverse limit support, and repeating the step (F) until the bottom of the foundation pit B with the sandy pebble layer and rich water is excavated;
is injected with water-stop slurry at the bottom of the foundation pit to form a pit bottom water-resisting layer 11.
Referring to fig. 4, the crescent guide groove 12 is formed by casting concrete, and is cast before the construction of the engagement fender post 2 and the engagement water stop post 3, and the crescent guide groove is strictly positioned before casting, so that the engagement size is ensured.
The foregoing is provided by way of illustration of the principles of the present invention in close proximity to a water-rich deep foundation pit enclosure for operating a high-iron sand pebble layer and method of construction thereof, and is not intended to limit the invention to the particular structure and steps shown and described, so that all such modifications and equivalents may be employed as are deemed to fall within the true scope of the invention.

Claims (6)

1. Adjacent operation high-speed railway embankment (A), characterized by is followed to rich water deep foundation ditch building of gravel layer, rich water deep foundation ditch (B) of gravel layer: the method comprises the steps that drilling fender piles (1) which are filled with reinforced concrete are arranged on the far side of a sand-pebble layer water-rich deep foundation pit (B) at intervals in the longitudinal direction, meshing fender piles (2) which are filled with reinforced concrete and meshing water-stop piles (3) which are filled with plain concrete are arranged on the near side of the sand-pebble layer water-rich deep foundation pit (B) at intervals in the longitudinal direction, the meshing fender piles (2) and the meshing water-stop piles (3) are alternately arranged and are meshed, and crown beams (4) which are longitudinally pulled through along the sand-pebble layer water-rich deep foundation pit (B) are arranged on the tops of the drilling fender piles (1), the meshing fender piles (2) and the meshing water-stop piles (3); the deep foundation pit (B) is provided with transverse limiting supports (5) in rows along the depth direction and longitudinal intervals of the sand-gravel layer, the transverse limiting supports (5) on the same side and in the same row are provided with an axle regulator (6) and steel enclosing purlins (7) at the near end, the steel enclosing purlins (7) at the near end and the far end of the uppermost layer are respectively acted on the crown beams (4) at the near side and the far side, the steel enclosing purlins (7) at the near end of the rest layers are acted on the occlusion fender pile (2) and the occlusion water stop pile (3), the steel enclosing purlins (7) at the far end are acted on the drilling fender pile (1), and the axle force of each transverse limiting support (5) is regulated through the axle regulator (6) to limit the deformation of the sand-gravel layer deep foundation pit (B) and the operation high-speed railway embankment (A).
2. The water-rich deep foundation pit enclosure immediately adjacent to an operational high-iron sand pebble layer of claim 1, wherein: the sand-gravel layer water-rich deep foundation pit (B) is characterized in that a filtering type dewatering well (8) is arranged at a longitudinal interval outside the far side, a water level adjusting well (9) is arranged between the near side and an operating high-speed railway embankment (A) at a longitudinal interval, and a deformation measuring instrument (10) is arranged outside the slope toe of the operating high-speed railway embankment (A).
3. The water-rich deep foundation pit enclosure immediately adjacent to an operational high-iron sand pebble layer of claim 1, wherein: the bottom of the sandy pebble layer water-rich deep foundation pit (B) is sealed by a pit bottom water-resisting layer (11).
4. The water-rich deep foundation pit enclosure immediately adjacent to an operational high-iron sand pebble layer of claim 1, wherein: the steel purlin (7) is longitudinally pulled through along the sand pebble layer water-rich deep foundation pit (B).
5. The water-rich deep foundation pit enclosure immediately adjacent to an operational high-iron sand pebble layer of claim 1, wherein: the transverse limiting support (5) is made of steel pipes, and the shaft regulator (6) is a hydraulic jack.
6. The construction method of the water-rich deep foundation pit enclosure structure adjacent to the operational high-iron sand pebble layer according to any one of claims 1 to 5, comprising the following steps:
(1) a deformation measuring instrument (10) is arranged outside the slope toe of the operating high-speed railway embankment (A) to form a deformation observation system;
(2) positioning the occlusion guard pile (2) and the occlusion water stop pile (3) near the sandy pebble layer water-rich deep foundation pit (B), and pouring a crescent guide groove (12) according to the positioning;
(3) after the crescent guide groove (12) reaches the design strength, constructing the occlusion water stop pile (3) by adopting a full sleeve pipe rubbing drilling mode and a soil grabbing pore-forming mode, adding a retarder during pouring, and ensuring that the occlusion fender pile (2) in the next working procedure can smoothly drill when being implemented;
(4) before pile body plain concrete of the occlusion water stop pile (3) is initially set, constructing adjacent occlusion guard piles (2) by adopting a full sleeve pipe rubbing drilling mode and a mode of punching grabbing soil to form holes, and reversely rubbing and lifting sleeves while pouring pile body concrete to ensure occlusion quality;
(5) alternately repeating the step (3) and the step (4) until the construction of the occlusion fender pile (2) and the occlusion water stop pile (3) is completed;
(6) chiseling pile heads of the occlusion fender pile (2) and the occlusion water stop pile (3) to form 0.5m floating paste, binding a reinforcement cage, and pouring the concrete of the crown beam (4) at the near side;
(7) simultaneously with the construction step (6), constructing a drilling fender pile (1) on the far side;
(8) constructing a filtering type dewatering well (8) and a water level adjusting well (9), and starting dewatering operation on the far side;
(9) when the drilling fender piles (1), the occlusion fender piles (2) and the occlusion water stop piles (3) on two sides all reach the design strength, the sand-gravel layer water-rich deep foundation pit (B) is dug in layers, and real-time deformation monitoring is carried out on the operating high-speed railway embankment (A) and the sand-gravel layer water-rich deep foundation pit (B);
when the sand-gravel layer water-rich deep foundation pit (B) is excavated to a depth of 0.5m below the elevation of the first layer of transverse limiting support (5), arranging the first layer of transverse limiting support (5) and corresponding steel enclosing purlin (7) and a shaft regulator (6), and applying prestress to the transverse limiting support (5) through the shaft regulator (6) to ensure that the sand-gravel layer water-rich deep foundation pit (B) is not deformed inwards;
continuously digging downwards to a depth of 0.5m below the elevation of the second transverse limit support (5), and repeating the step (I) until the bottom of the sandy pebble layer water-rich deep foundation pit (B) is excavated;
is injected with water-stop slurry at the bottom of the foundation pit to form a pit bottom water-resisting layer (11).
CN201811566729.XA 2018-12-20 2018-12-20 Water-rich deep foundation pit support structure close to operating high-iron sand pebble layer and construction method thereof Active CN109518698B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811566729.XA CN109518698B (en) 2018-12-20 2018-12-20 Water-rich deep foundation pit support structure close to operating high-iron sand pebble layer and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811566729.XA CN109518698B (en) 2018-12-20 2018-12-20 Water-rich deep foundation pit support structure close to operating high-iron sand pebble layer and construction method thereof

Publications (2)

Publication Number Publication Date
CN109518698A CN109518698A (en) 2019-03-26
CN109518698B true CN109518698B (en) 2023-11-17

Family

ID=65796521

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811566729.XA Active CN109518698B (en) 2018-12-20 2018-12-20 Water-rich deep foundation pit support structure close to operating high-iron sand pebble layer and construction method thereof

Country Status (1)

Country Link
CN (1) CN109518698B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110397092B (en) * 2019-05-14 2021-09-17 洛阳市轨道交通有限责任公司 Sand and pebble foundation pit displacement prediction method
CN110761301A (en) * 2019-11-08 2020-02-07 向怀轶 Protection structure close to existing high-speed rail pebble layer water-rich deep foundation pit
CN111005388A (en) * 2019-12-12 2020-04-14 中冶天工集团有限公司 Deep foundation pit integral supporting device and supporting method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09209371A (en) * 1996-02-02 1997-08-12 Mitani Sekisan Co Ltd Method for constructing foundation
CN104060613A (en) * 2013-03-22 2014-09-24 上海市城市建设设计研究总院 Directional secant pile grouting structure and directional secant pile grouting soil reinforcement method
CN104612162A (en) * 2014-12-15 2015-05-13 中铁二十局集团第三工程有限公司 Subway station deep foundation pit excavation construction method
KR101662072B1 (en) * 2015-12-01 2016-10-06 (주)서현컨스텍 Temporary retaining wall using underground wall and connector and the construction method therefor
CN107119691A (en) * 2017-06-22 2017-09-01 中交二航局第四工程有限公司 One kind is applied to the square deep basal pit of the high pressure-bearing of rich water sand gravel layer and its excavation method
CN208105281U (en) * 2018-04-08 2018-11-16 中建五局土木工程有限公司 A kind of the Metro station excavation sealing and precipitation system of the sand-pebble layer containing rich water
CN108842789A (en) * 2018-08-31 2018-11-20 中建四局第四建筑工程有限公司 A kind of support pile and the two-in-one constructing structure of water-stop curtain
CN209891207U (en) * 2018-12-20 2020-01-03 中铁二院工程集团有限责任公司 Retaining structure of water-rich deep foundation pit next to operating high-iron sand pebble bed

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09209371A (en) * 1996-02-02 1997-08-12 Mitani Sekisan Co Ltd Method for constructing foundation
CN104060613A (en) * 2013-03-22 2014-09-24 上海市城市建设设计研究总院 Directional secant pile grouting structure and directional secant pile grouting soil reinforcement method
CN104612162A (en) * 2014-12-15 2015-05-13 中铁二十局集团第三工程有限公司 Subway station deep foundation pit excavation construction method
KR101662072B1 (en) * 2015-12-01 2016-10-06 (주)서현컨스텍 Temporary retaining wall using underground wall and connector and the construction method therefor
CN107119691A (en) * 2017-06-22 2017-09-01 中交二航局第四工程有限公司 One kind is applied to the square deep basal pit of the high pressure-bearing of rich water sand gravel layer and its excavation method
CN208105281U (en) * 2018-04-08 2018-11-16 中建五局土木工程有限公司 A kind of the Metro station excavation sealing and precipitation system of the sand-pebble layer containing rich water
CN108842789A (en) * 2018-08-31 2018-11-20 中建四局第四建筑工程有限公司 A kind of support pile and the two-in-one constructing structure of water-stop curtain
CN209891207U (en) * 2018-12-20 2020-01-03 中铁二院工程集团有限责任公司 Retaining structure of water-rich deep foundation pit next to operating high-iron sand pebble bed

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
富水半成岩砂岩地层地铁车站深基坑变形监测与数值模拟分析;向亮;;铁道标准设计(11);全文 *
砂卵地层城市下穿隧道施工咬合桩新技术;徐少平;;四川建筑(02);全文 *

Also Published As

Publication number Publication date
CN109518698A (en) 2019-03-26

Similar Documents

Publication Publication Date Title
CN106369223B (en) A kind of silt stratum pipe jacking construction method
CN106402490B (en) Silt stratum push pipe jacking construction method based on steel bushing head tool pipe
CN109518698B (en) Water-rich deep foundation pit support structure close to operating high-iron sand pebble layer and construction method thereof
CN102733413A (en) Method for controlling subsidence of operating subway tunnel
CN110306593A (en) A kind of station construction method
CN104120731A (en) Tunnel settlement protecting device and construction method thereof
CN109578014B (en) Anti-surging bottom sealing structure and construction method
CN111101540B (en) Construction method for passing existing electric power tunnel on open cut tunnel
CN109339079B (en) Foundation pit water stopping system adjacent to river permeable stratum and construction process thereof
CN113638445A (en) Semi-inverse construction method for ultra-deep circular foundation pit
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN111365005A (en) Reinforcing structure and method for shield tunnel lower-penetrating elevated bridge foundation
CN113669073B (en) Construction method for controlling adjacent building deformation of water-rich sandy stratum by tunneling before station
CN209891207U (en) Retaining structure of water-rich deep foundation pit next to operating high-iron sand pebble bed
CN104894926A (en) Retaining structure on existing railway high embankment and construction method thereof
CN204753262U (en) A fender structure on high embankment of existing railway
CN116398165A (en) New tunnel penetrating through existing station at zero distance and construction method thereof
CN216664152U (en) Water sealing structure for anchorage support
CN215252918U (en) Deep foundation pit supporting structure of soft soil foundation high-pressure-bearing water environment adjacent to high-speed rail
CN85202494U (en) Interlocked reinforced concrete sheet pile
CN210141142U (en) Underground structure is built in same direction as digging in hole stake secret
CN210857242U (en) Side slope anti-skidding supporting construction
CN218969976U (en) Pushing structure suitable for pushing method construction continuous wall
CN216304659U (en) Foundation pit supporting structure
CN212154779U (en) Plugging structure suitable for construction of railway tunnel, bridge and tunnel connected portal

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant