CN109514114A - One kind is for storing concrete test block fabrication of reinforcing cage method - Google Patents
One kind is for storing concrete test block fabrication of reinforcing cage method Download PDFInfo
- Publication number
- CN109514114A CN109514114A CN201811358983.0A CN201811358983A CN109514114A CN 109514114 A CN109514114 A CN 109514114A CN 201811358983 A CN201811358983 A CN 201811358983A CN 109514114 A CN109514114 A CN 109514114A
- Authority
- CN
- China
- Prior art keywords
- reinforcement cage
- steel
- test block
- welded
- reinforcing bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K31/00—Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
- B23K31/02—Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
Abstract
One kind is for storing concrete test block fabrication of reinforcing cage method, it is characterised in that the following steps are included: a, reinforcement cage skeleton weld, b, hinge is welded on steel reinforcement cage, c, the production of steel reinforcement cage cover board.Of the invention is simple with test block reinforcement cage structure for storing concrete test block fabrication of reinforcing cage method, it is easy to make, the storage of concrete test block, finished product protection, cured under same condition mark etc., the concrete test block steel reinforcement cage of unified standard can not only reach the finished product protection of concrete test block, function is stored in test block, and it is able to reflect good management of the enterprise to engineering specification part, concrete test block steel reinforcement cage is to prevent test block from losing, damage, it is also a kind of embodiment of the enterprise to project demand fine-grained management, and it provides quality goods or brilliant to project, the advantages of bright spot of innovation also plays supporting role.
Description
Technical field
The present invention relates to a kind of steel reinforcement cages set up with reinforcing bar, specifically, being a kind of for storing concrete test block
Fabrication of reinforcing cage method.
Background technique
According to the regulation of " concrete structure engineering construction quality accident specification ", concrete structure engineering construction should be by regulation
Indwelling standard curing concrete strength test block.In engineering structure work progress, the quality of concrete certainly will become entire engineering
Core, the maintenance of test block must control in place when engineering entity concrete construction, and integrality and curing condition have to comply with
The finished product protection of quality requirement, i.e., live test block must be in place, it is ensured that concrete test block is not damaged, do not lost.This project is 201
The commercial residential building building of the high frame+core wall structure mode of rice, engineering is multi-party up to 30,000 using amount of concrete, and concrete is most high-strength
Degree reaches 60MPa.The necessary management regulation of the concrete test block at scene saves completely, timely, effective to react coagulation in work progress
The actual strength of soil, it is ensured that the safety of total construction.
Therefore to ensure that concrete test block is not damaged, do not lost, a kind of highly desirable device for holding guarantor's concrete test block.
Summary of the invention
The purpose of the present invention is to propose that a kind of guarantee concrete test block is completely used to store concrete test block steel reinforcement cage
Production method.
To achieve the above object, the technical solution of the invention is as follows:
One kind is for storing concrete test block fabrication of reinforcing cage method, it is characterised in that the following steps are included:
A, reinforcement cage skeleton welds
The both ends of reinforcement cage skeleton are two square steel bar frameworks being welded to each other by eight first reinforcing bars, in two pros
It connects to form the cuboid steel bar framework for lacking a rib with three second reinforcing bars between shape steel bar framework;
B, hinge is welded on steel reinforcement cage, comprising the following steps:
1) hinge radially is overlapped to be welded and fixed and is made down by two sections of long 50mm, diameter 20mm steel pipe, and prefabricated one is two secondary
Hinge;
2) the 4th second reinforcing bar is taken to pass through a steel pipe below two hinges, two hinges are fixedly welded on respectively from the 4th
At the end reinforced 50mm of root second, and keep a steel pipe above two hinges vacant spare, then by the 4th second reinforcing bar
Welding, the rib lacked with cuboid steel bar framework described in polishing;
3) welded reinforcement cage protects muscle: by the first reinforcing bar of two end faces of steel reinforcement cage cuboid steel bar framework according to the three of side length
Equal part divides, i.e., each equal part spacing is 80mm, and the second reinforcing bar and the first reinforcement welding, jail are carried out at the first reinforcing bar Along ent
Admittedly being welded on reinforcement cage skeleton;
C, steel reinforcement cage cover board makes, comprising the following steps:
1) both ends of second reinforcing bar are first respectively welded to the one end for being fixed on two first concrete-steels, make its orthogonal shape
At door shape frame;
2) the every side of the first reinforcing bar is subjected to 3 equal points of divisions again, i.e. equal part spacing is 80mm, uses second in door shape lower portion
Reinforcing bar is welded, and is welded two second reinforcing bars, is formed preliminary cover board;
3) steel pipe that 1 second reinforcing bar is passed through to the top of two steel pipe hinges on steel reinforcement cage, makes second reinforcing bar
It is welded with the both ends of two first reinforcing bars on preliminary cover board, forms complete rectangle steel reinforcement cage cover board;
4) the welded limiting muscle on steel reinforcement cage cover board activity opening end two sides, limit rib specification be long 20mm, diameter 10mm round steel,
At the end 60mm of the first reinforcing bar, limit rib is welded in the inside of the first reinforcing bar of steel reinforcement cage cover board, when steel reinforcement cage cover plate lid
When upper steel reinforcement cage, the limit rib at both ends enters in steel reinforcement cage just, plays the role of limiting steel reinforcement cage cap locations.
It is of the invention for store concrete test block fabrication of reinforcing cage method can also using technical measures below come into
One step is realized.
Method above-mentioned, wherein first reinforcing bar is length >=240mm, diameter 10mm round steel.
Method above-mentioned, wherein second reinforcing bar is length >=6500mm, diameter 10mm round steel.
Method above-mentioned, wherein the limit rib vertical welding is on the inside of the first reinforcing bar of steel reinforcement cage cover board.
After adopting the above technical scheme, of the invention is used to store concrete test block fabrication of reinforcing cage method with following excellent
Point:
1, test block reinforcement cage structure is simple, easy to make;
2, the storage of concrete test block, finished product protection, cured under same condition mark etc., the concrete test block steel reinforcement cage of unified standard is not
It is only capable of reaching finished product protection, the test block storage function of concrete test block, and is able to reflect enterprise to the good of engineering specification part
Management;
3, concrete test block steel reinforcement cage is to prevent test block loss, damage and enterprise to one kind of project demand fine-grained management
Embody, and provide quality goods or brilliant to project, the bright spot innovated also plays supporting role.
Detailed description of the invention
Fig. 1 is the reinforcement cage skeleton reinforcement welding structural schematic diagram of the embodiment of the present invention, wherein indicating the length of a scarce rib
Cube steel reinforcement cage frame;
Fig. 2 is that the steel pipe hinge of the embodiment of the present invention and reinforcement cage skeleton carry out welding structure schematic diagram;
Fig. 3 is the steel reinforcement cage covering plate structure schematic diagram of the embodiment of the present invention;
Fig. 4 is the concrete test block reinforcement cage structure schematic diagram of the embodiment of the present invention.
In figure: 1 first reinforcing bar, 2 second reinforcing bars, 3 steel reinforcement cage cover boards, 4 hinges, 5 limit ribs.
Specific embodiment
With reference to embodiments and its attached drawing further explains the present invention.
Embodiment 1
It is of the invention for storing concrete test block fabrication of reinforcing cage construction process: determine concrete test block size → to round steel into
Row Length-fixing cutting → cut to steel pipe → welded still pipe is fixed on a root long round steel as hinge → by steel pipe hinge →
4 root long round steel (containing the round steel for having steel pipe hinge) and 8 short round steel are welded to each other to form a cuboid → welding each
The protection muscle in face → in the other hole of steel pipe hinge wears long round steel → welded reinforcement cage mesh sheet cover board → welded reinforcement mesh sheet cover board
Limit rib → antirust treatment.
Of the invention is used to store concrete test block fabrication of reinforcing cage method, comprising the following steps:
A, reinforcement cage skeleton welds.Referring now to Fig. 1, Fig. 1 is that the reinforcement cage skeleton reinforcement welding structure of the embodiment of the present invention is shown
It is intended to, wherein indicating the cuboid steel reinforcement cage frame of a scarce rib.As shown, the both ends of the reinforcement cage skeleton are by eight
Two square steel bar frameworks that first reinforcing bar is welded to each other, with three second reinforcing bars between two square steel bar frameworks
Connection forms the cuboid steel bar framework for lacking a rib.First reinforcing bar is long 240mm, diameter 10mm round steel.It is described
Second reinforcing bar is long 650mm, diameter 10mm round steel.
B, hinge is welded on steel reinforcement cage, comprising the following steps:
1) hinge radially is overlapped to be welded and fixed and is made down by two sections of long 50mm, diameter 20mm steel pipe, and prefabricated one is two secondary
Hinge;Fig. 2 is that the steel pipe hinge of the embodiment of the present invention and reinforcement cage skeleton carry out welding structure schematic diagram.
2) the 4th second reinforcing bar is taken to pass through a steel pipe below two hinges, two hinges be fixedly welded on respectively from
At 4th second end reinforced 50mm, and keep a steel pipe above two hinges vacant spare, then by the 4th second
Reinforcement welding, the rib lacked with cuboid steel bar framework described in polishing.
3) welded reinforcement cage protects muscle: by the first reinforcing bar of two end faces of steel reinforcement cage cuboid steel bar framework according to side length
Trisection divide, i.e., each equal part spacing is 80mm, and the second reinforcing bar and the first steel bar welding are carried out at the first reinforcing bar Along ent
It connects, is securely welded on reinforcement cage skeleton.
C, steel reinforcement cage cover board makes, comprising the following steps:
1) both ends of second reinforcing bar are first respectively welded to the one end for being fixed on two first concrete-steels, make its orthogonal shape
At door shape frame;Fig. 3 is the steel reinforcement cage covering plate structure schematic diagram of the embodiment of the present invention.
2) the every side of the first reinforcing bar is subjected to 3 equal points of divisions again, i.e. equal part spacing is 80mm, is used in door shape lower portion
Second reinforcing bar is welded, and is welded two second reinforcing bars, is formed preliminary cover board.
3) steel pipe that 1 second reinforcing bar is passed through to the top of two steel pipe hinges on steel reinforcement cage, makes described second
The both ends of reinforcing bar and two first reinforcing bars on preliminary cover board are welded, and complete rectangle steel reinforcement cage cover board is formed.
4) the welded limiting muscle on steel reinforcement cage cover board activity opening end two sides, limit rib specification are long 20mm, diameter 10mm
Round steel, at the end 60mm of the first reinforcing bar, limit rib is welded in the inside of the first reinforcing bar of steel reinforcement cage cover board, when steel reinforcement cage lid
When plate covers steel reinforcement cage, the limit rib at both ends enters in steel reinforcement cage just, plays the role of limiting steel reinforcement cage cap locations.It is described
Limit rib vertical welding is on the inside of the first reinforcing bar of steel reinforcement cage cover board.
Fig. 4 is the concrete test block reinforcement cage structure schematic diagram of the embodiment of the present invention.Of the invention is used to store concrete
To welding requirements between round steel in test block fabrication of reinforcing cage method: welding uses butt welding between steel reinforcement cage and cover board round steel,
It is small to weld space, but must assure that firm welding;The welding of equal part spacing, which must assure that, to be parallel to each other, and answers at antirust after the completion of welding
Reason.
Production requirement for storing in concrete test block fabrication of reinforcing cage method to steel pipe hinge of the invention: steel pipe closes
Page is mutually close to, is welded using two section short steel pipes, and welding abutting face answers that joint filling is full, firm welding, it is necessary to ensure that after
Phase concrete test block steel reinforcement cage is not broken compared with the opening and closing of multi-frequency.
Of the invention is used to store in concrete test block fabrication of reinforcing cage method to the company of steel pipe hinge and steel reinforcement cage, cover board
Connect requirement: using welding form between steel pipe hinge and steel reinforcement cage, steel pipe hinge internal diameter is greater than steel reinforcement cage round steel outer diameter, therefore steel
Muscle cage round steel should be close by the gap filling between steel pipe hinge and steel reinforcement cage round steel using filling welding after penetrating in steel pipe hinge
It is real, it is ensured that welding position is not destroyed when later period cover board multi-frequency opens and closes.The connection of steel pipe hinge and cover board is to move freely shape
Formula, directly perforation are freely rotated in steel pipe hinge without secondary fixation convenient for cover board round steel.
Production requirement for storing in concrete test block fabrication of reinforcing cage method to limit rib of the invention: steel reinforcement cage lid
Plate belongs to the form of moveing freely in steel pipe hinge, and limit rib mainly limits the good capping of cover board on steel reinforcement cage, avoids
It horizontally slips, it is ensured that closed reinforced mesh form is integrally formed in steel reinforcement cage.
The present invention has substantive distinguishing features and significant technological progress, and of the invention is used to store concrete test block steel reinforcement cage
Production method has test block reinforcement cage structure simple, easy to make, can place the concrete test block conserved wherein,
It can not only preferably guarantee the complete of concrete test block, play the role of finished product protection, and show the good of company standard part
Management.
Of the invention is used to store concrete test block fabrication of reinforcing cage method in Bengbu foreign exchange commercial square the second stage of the project
Middle utilization.This project concrete test block is made rational planning for condition preservation, has manufactured and designed a kind of concrete test block reinforcing bar
Cage not only ensures the requirement that concrete is not damaged, is not lost for the preservation of on-site concrete test block, and meets
Bright spot required for the requirement that enterprise effectively applies live standard component, more later period wound are encouraged plays support.Of the invention
For storing concrete test block steel reinforcement cage, not only solved the problems, such as not being damaged, avoiding loss for concrete test block, but also can be flexible
It is mobile, reduce the increase of engineering cost;Meanwhile effective application has been carried out to the live standard component of enterprise requirements, in successive projects
In can directly use, reduce engineering cost.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field
Member, without departing from the spirit and scope of the present invention, can also make various transformation or variation.Therefore, all equivalent
Technical solution also should belong to scope of the invention, should be limited by each claim.
Claims (4)
1. one kind is for storing concrete test block fabrication of reinforcing cage method, it is characterised in that the following steps are included:
A, reinforcement cage skeleton welds
The both ends of reinforcement cage skeleton are two square steel bar frameworks being welded to each other by eight first reinforcing bars, in two pros
It connects to form the cuboid steel bar framework for lacking a rib with three second reinforcing bars between shape steel bar framework;
B, hinge is welded on steel reinforcement cage, comprising the following steps:
1) hinge radially is overlapped to be welded and fixed and is made down by two sections of long 50mm, diameter 20mm steel pipe, and prefabricated one is two secondary
Hinge;
2) the 4th second reinforcing bar is taken to pass through a steel pipe below two hinges, two hinges are fixedly welded on respectively from the 4th
At the end reinforced 50mm of root second, and keep a steel pipe above two hinges vacant spare, then by the 4th second reinforcing bar
Welding, the rib lacked with cuboid steel bar framework described in polishing;
3) welded reinforcement cage protects muscle: by the first reinforcing bar of two end faces of steel reinforcement cage cuboid steel bar framework according to the three of side length
Equal part divides, i.e., each equal part spacing is 80mm, and the second reinforcing bar and the first reinforcement welding, jail are carried out at the first reinforcing bar Along ent
Admittedly being welded on reinforcement cage skeleton;
C, steel reinforcement cage cover board makes, comprising the following steps:
1) both ends of second reinforcing bar are first respectively welded to the one end for being fixed on two first concrete-steels, make its orthogonal shape
At door shape frame;
2) the every side of the first reinforcing bar is subjected to 3 equal points of divisions again, i.e. equal part spacing is 80mm, uses second in door shape lower portion
Reinforcing bar is welded, and is welded two second reinforcing bars, is formed preliminary cover board;
3) steel pipe that 1 second reinforcing bar is passed through to the top of two steel pipe hinges on steel reinforcement cage, makes second reinforcing bar
It is welded with the both ends of two first reinforcing bars on preliminary cover board, forms complete rectangle steel reinforcement cage cover board;
4) the welded limiting muscle on steel reinforcement cage cover board activity opening end two sides, limit rib specification be long 20mm, diameter 10mm round steel,
At the end 60mm of the first reinforcing bar, limit rib is welded in the inside of the first reinforcing bar of steel reinforcement cage cover board, when steel reinforcement cage cover plate lid
When upper steel reinforcement cage, the limit rib at both ends enters in steel reinforcement cage just, plays the role of limiting steel reinforcement cage cap locations.
2. as described in claim 1 for storing concrete test block fabrication of reinforcing cage method, which is characterized in that first steel
Muscle is length >=240mm, diameter 10mm round steel.
3. as described in claim 1 for storing concrete test block fabrication of reinforcing cage method, which is characterized in that second steel
Muscle is length >=6500mm, diameter 10mm round steel.
4. as described in claim 1 for storing concrete test block fabrication of reinforcing cage method, which is characterized in that the limit rib
Vertical welding is on the inside of the first reinforcing bar of steel reinforcement cage cover board.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811358983.0A CN109514114A (en) | 2018-11-15 | 2018-11-15 | One kind is for storing concrete test block fabrication of reinforcing cage method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811358983.0A CN109514114A (en) | 2018-11-15 | 2018-11-15 | One kind is for storing concrete test block fabrication of reinforcing cage method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109514114A true CN109514114A (en) | 2019-03-26 |
Family
ID=65777772
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811358983.0A Pending CN109514114A (en) | 2018-11-15 | 2018-11-15 | One kind is for storing concrete test block fabrication of reinforcing cage method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109514114A (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62253816A (en) * | 1986-04-24 | 1987-11-05 | Ohbayashigumi Ltd | Welder for reinforcing bar cage in continuous underground wall construction |
US6244014B1 (en) * | 1999-07-22 | 2001-06-12 | Andrew Barmakian | Steel rod-reinforced plastic piling |
CN201620613U (en) * | 2010-02-09 | 2010-11-03 | 中天建设集团有限公司天津分公司 | Test block cage for protecting test block with identical condition on construction site |
CN101967825A (en) * | 2010-09-15 | 2011-02-09 | 中铁四局集团第五工程有限公司 | Reinforcement cage and manufacturing method thereof |
CN205367411U (en) * | 2015-12-28 | 2016-07-06 | 大连三川建筑科技有限公司 | A safety protection apron for construction elevator gate department |
CN105945479A (en) * | 2016-05-24 | 2016-09-21 | 中交航局第四工程有限公司 | Arch type tyre film frame and method for manufacturing shield segment reinforcement cage by utilizing arch type tyre film frame |
-
2018
- 2018-11-15 CN CN201811358983.0A patent/CN109514114A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62253816A (en) * | 1986-04-24 | 1987-11-05 | Ohbayashigumi Ltd | Welder for reinforcing bar cage in continuous underground wall construction |
US6244014B1 (en) * | 1999-07-22 | 2001-06-12 | Andrew Barmakian | Steel rod-reinforced plastic piling |
CN201620613U (en) * | 2010-02-09 | 2010-11-03 | 中天建设集团有限公司天津分公司 | Test block cage for protecting test block with identical condition on construction site |
CN101967825A (en) * | 2010-09-15 | 2011-02-09 | 中铁四局集团第五工程有限公司 | Reinforcement cage and manufacturing method thereof |
CN205367411U (en) * | 2015-12-28 | 2016-07-06 | 大连三川建筑科技有限公司 | A safety protection apron for construction elevator gate department |
CN105945479A (en) * | 2016-05-24 | 2016-09-21 | 中交航局第四工程有限公司 | Arch type tyre film frame and method for manufacturing shield segment reinforcement cage by utilizing arch type tyre film frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE112016002341B4 (en) | Arrangement of several tubular piles arranged next to one another with a heat transfer pipe arrangement embedded in at least one prefabricated tubular pile and a pump unit | |
CN108755950A (en) | Prefabricated concrete structure column and column rigid connection node and construction method | |
CN205000553U (en) | Fire prevention steel column and building body | |
CN206360086U (en) | Clod wash multi-cavity steel tube concrete Special-Shaped Column and the rigid connection node of U-shaped combination beam | |
CN104863384A (en) | Historic building column root pier connection structure | |
CN106760940A (en) | A kind of hollow enclosure member of prefabricated complex fiber cement and construction method | |
CN208472734U (en) | A kind of bracing members for base pit engineering stay support joint structure | |
CN109514114A (en) | One kind is for storing concrete test block fabrication of reinforcing cage method | |
KR101184511B1 (en) | Site Reinforcing Method of Thick Wall with Using Plant Welded Steel Bar Frames | |
CN214497891U (en) | Circular concrete column and masonry infilled wall constructional column linking section | |
CN103711200B (en) | A kind of assembling stiffness combo box support structure | |
CN106969252B (en) | Single-section rubber film sealed gas holder reconstructed from regular polygon thin oil sealed gas holder | |
CN202401667U (en) | Prefabricated column with reserved embedded column porous channel and embedded column type full-assembly anti-seismic building | |
CN209397707U (en) | A kind of connecting node of column and steel lid beam | |
CN107471428A (en) | Manufacture method in a kind of non-standard box beam field | |
CN104790405B (en) | A kind of method that steel reinforcement cage manually transfers that caisson is overweight | |
CN212715667U (en) | Protective layer thickness positioner | |
CN107013049B (en) | A kind of method that faying face reinforces beam column component | |
CN105735505B (en) | The prefabricated filled type buckling restrained brace structure of twin-core plate | |
CN204850192U (en) | Prefabricated assembled steel bar truss combination floor | |
CN205153244U (en) | Metal roof waterproof people pore structure | |
CN208105873U (en) | The collar tie beam of building indoor partition | |
CN207714618U (en) | A kind of pre-cast building wall body structure | |
CN204112211U (en) | Pier structure in the bridge water of the anti-freeze thawing plate of a kind of coated RPC | |
CN209179177U (en) | A kind of prefabricated column component, assembled combine prefabricated post |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190326 |
|