Summary of the invention
For the problems in the relevant technologies, the present invention proposes that splash guard installs trolley, solves existing splash guard laying construction
Low efficiency and the big problem of labor intensity of workers.
In order to achieve the above technical purposes, the technical scheme is that it is such:
Splash guard installs trolley, the running gear including portal frame system and positioned at the portal frame system bottom, the portal frame system
The trolley track of arc including two sides installation is equipped between the trolley track small for installing creeping for entire volume splash guard
Vehicle, the crawl trolley connect bi-motor, and the crawl trolley is equipped with splash guard strut and the fixed device of waterproof coiled sheet, described
Splash guard strut is equipped with spring supporting wheel, the dedicated strut of overlapping the slot and padding machine, is equipped at intervals with along the trolley track direction
Several layers platform, each platform are fixed in the fixed link in portal frame system, and the mesa base is connected with ladder, the row
The side of walking system is equipped with transverse-moving mechanism, and the transverse-moving mechanism is connected to portal frame system bottom by jacking system.
Further, the difference in height between platform described in adjacent two layers is 1.9m.
Further, the platform uses scalable platform or folding platform.
Further, each layer platform is equipped with protective fence and hook.
Further, the mechanical rocking bar control device for pushing waterproof coiled sheet to rotate is additionally provided on the crawl trolley.
Further, the running gear is steel wheel, rubber wheel or rail wheel.
Further, laser pick-off target, 36V emergency lighting and eye-catching reflection plaster are additionally provided in the portal frame system.
Beneficial effects of the present invention: splash guard installation trolley does not need to cut out splash guard in advance, directly by entire volume waterproof
Plate is mounted on the crawl trolley of trolley, can once hang 3-4 meters of splash guards volume two, the splash guard that 3-4 meters of once-paving
One, on the basis of guaranteeing that splash guard overlap joint requires and splash guard is laid with coefficient of relaxation, operator, which only needs to stand, to work
The installation to splash guard can be completed on platform, reduced the process of splash guard leveling and calibration, alleviated labor intensity, mention
High labor efficiency.The optimization design ladder landing platform system of splash guard trolley simultaneously, enhances the job security of construction personnel.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment
Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention
Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings
Obtain other attached drawings.
Fig. 1 is the front view of the splash guard installation trolley according to embodiments of the present invention;
Fig. 2 is the side view of the splash guard installation trolley according to embodiments of the present invention.
In figure:
1, portal frame system;2, trolley track;3, crawl trolley;31, spring supporting wheel;4, platform;5, ladder;6, tunnel excavation rock
Face;7, running gear;8, jacking system;9, transverse-moving mechanism, 10, ventilation duct.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art's every other embodiment obtained belong to what the present invention protected
Range.
As shown in Figs. 1-2, splash guard installs trolley, including portal frame system 1 and the row connecting with 1 bottom of portal frame system
Walking system 7, the portal frame system 1 include the trolley track 2 of the arc of two sides installation, are equipped with and are used between the trolley track 2
The crawl trolley 3 of entire volume splash guard is installed, the crawl trolley 3 connects bi-motor, and crawl trolley 3 is driven using bi-motor frequency conversion
Dynamic, chain dragging is advanced, and power headroom is stopped, and is guaranteed that crawl trolley 3 is safely and effectively run, is further increased the safety of trolley
And practical performance;The crawl trolley 3 is equipped with splash guard strut and the fixed device of waterproof coiled sheet, when being laid with splash guard, by preventing
Splash guard is fixed on crawl trolley 3 by the fixed device of water coiled sheet carries out the rotation laying of entire volume splash guard, and a section has been laid with
Bi Hou directly adjusts the position of fixed device, carries out the laying of next section, without moving to splash guard trolley, just
In worker operation, the construction time is saved;The splash guard strut is equipped with spring supporting wheel 31, the dedicated strut of overlapping the slot and padding
Machine, the dedicated strut of overlapping the slot and padding machine can be with the layings of splash guard, while work is fixed, compressed and welded to lap-joint
Industry reduces the labor intensity of worker, improves working efficiency and construction quality.Guarantee that overlapping the slot welding meets project construction and sets
Meter requires;Spring supporting wheel 31 guarantees that splash guard part is docile with tunnel excavation scar 6 as far as possible;Along the trolley track 2
Direction is equipped at intervals with several layers platform 4, and each platform 4 is fixed in the fixed link in portal frame system 1,4 bottom of platform
It is connected with ladder 5, the side of the running gear 7 is equipped with transverse-moving mechanism 9, and the transverse-moving mechanism 9 is connected to by jacking system 8
1 bottom of portal frame system.
In the present embodiment, the trolley track 2 is to reduce design according to tunnel excavation scar 6 is whole, can prevent from being laid with
When splash guard, leaves and dig scar excessively closely or too far.
In the present embodiment, the difference in height between platform 4 described in adjacent two layers be 1.9m, facilitate splash guard fixation or its
It is operated.
In the present embodiment, the platform 4 guarantees to make using the scalable platform 4 or folding platform 4 of hydraulic cylinder control
Industry platform can reach any position of tunnel perimeter, prevent worker due to height problem cause be laid with splash guard when operation not
Just the case where.
In the present embodiment, each layer platform 4 is equipped with protective fence and hook, ensures construction worker's operation peace
Entirely.
In the present embodiment, the mechanical rocking bar control for pushing waterproof coiled sheet to rotate is additionally provided on the crawl trolley 3
Device, splash guard monovolume width is 3-4 meters, when being laid with splash guard, since waterproof coiled sheet has certain weight, it is contemplated that reel turns
When dynamic, certain resistance is had, rotating yardage roll manually can be laborious, therefore this trolley is laid on trolley in splash guard and is equipped with folder
Tight and mechanical rocking bar control device, can be fixed on conduit after installing waterproof coiled sheet, by motor or manually shake
Rocking bar drives entire volume splash guard volume to be rotated, and being laid with the installation of splash guard becomes more time saving and energy saving.
In the present embodiment, the running gear 7 is steel wheel, rubber wheel or rail wheel, and every group of steel wheel and rubber wheel use
Independent ambulation, convenient for trolley, voluntarily correction wanders off in the process of walking, and the adjustment of hydraulic-driven transverse-moving mechanism 9 can also be used;If adopting
With track travel, then identical walking track is used with tunnel lining trolley, is used convenient for scene.
In the present embodiment, laser pick-off target, 36V emergency lighting and eye-catching reflection plaster are additionally provided in the portal frame system 1.
In the present embodiment, the portal frame system 1 includes the interior ventilation duct 10 set.
Master control cabinet is set in each operating mechanism of the trolley, and configures remote-control handle, is controlled convenient for constructing operation;Trolley peace
Multiple cameras are filled, and configure suitable software, mobile phone or computer can be used remotely to monitor trolley for manager, convenient for understanding
The construction operation state of trolley promotes the efficiency of management.
The waterproof is installed trolley and is equipped with vehicle vacuum chuck structure, a spacing can will be drawn outside splash guard after automatic absorbing
From guarantee elasticity;It can also voluntarily be grasped in splash guard work progress by site operation personnel, guarantee the pine of splash guard
Sag, since back scar flatness is inconsistent, (two sides pour from the bottom up) may support bad anti-when later period casting concrete
Water plate, therefore splash guard is laid with and needs certain slackness when fixed, according to construction site situation difference, coefficient of relaxation generally exists
Between 1.05-1.2.
Splash guard installation trolley does not need to cut out splash guard in advance, and entire volume splash guard is directly mounted on creeping for trolley
On trolley, 3-4 meters of splash guards volume two can be once hung, the splash guard one that 3-4 meters of once-paving is opened, and is guaranteeing that splash guard takes
It connects requirement and splash guard is laid on the basis of coefficient of relaxation, operator, which only needs to stand, can complete on workbench to waterproof
The installation of plate reduces the process of splash guard leveling and calibration, alleviates labor intensity, improve labor efficiency.It is excellent simultaneously
Change the ladder landing platform system for devising splash guard trolley, enhances the job security of construction personnel.
The above is merely preferred embodiments of the present invention, be not intended to limit the invention, it is all in spirit of the invention and
Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.