CN109488346A - Splash guard installs trolley - Google Patents

Splash guard installs trolley Download PDF

Info

Publication number
CN109488346A
CN109488346A CN201811588715.8A CN201811588715A CN109488346A CN 109488346 A CN109488346 A CN 109488346A CN 201811588715 A CN201811588715 A CN 201811588715A CN 109488346 A CN109488346 A CN 109488346A
Authority
CN
China
Prior art keywords
trolley
splash guard
platform
portal frame
frame system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811588715.8A
Other languages
Chinese (zh)
Inventor
马利
武彬华
赵松华
张纪峰
刘骥锴
李燕松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Caofeidian Heavy Industry Machinery Co ltd
Original Assignee
China Railway Sixteen Bureau Group Beijing Jian Gong Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixteen Bureau Group Beijing Jian Gong Machinery Co Ltd filed Critical China Railway Sixteen Bureau Group Beijing Jian Gong Machinery Co Ltd
Priority to CN201811588715.8A priority Critical patent/CN109488346A/en
Publication of CN109488346A publication Critical patent/CN109488346A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • E21D11/406Placing endless lining elements, e.g. from reels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/381Setting apparatus or devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Emergency Lowering Means (AREA)

Abstract

The invention discloses splash guards to install trolley, including portal frame system and the running gear being connect with portal frame system bottom, portal frame system includes the trolley track of the arc of two sides installation, the crawl trolley for installing entire volume splash guard is equipped between trolley track, crawl trolley connects bi-motor, crawl trolley is equipped with splash guard strut and the fixed device of waterproof coiled sheet, splash guard strut is equipped with spring supporting wheel, the dedicated strut of overlapping the slot and padding machine, several layers platform is equipped at intervals with along trolley track direction, each platform is fixed in the fixed link in portal frame system, mesa base is connected with ladder, the side of running gear is equipped with transverse-moving mechanism, transverse-moving mechanism connects jacking system.Beneficial effects of the present invention: entire volume splash guard is mounted on the crawl trolley of trolley, 3-4 meters of splash guards volume two can once be hung, the installation to splash guard is completed on workbench in operator station, reduce the process of splash guard leveling and calibration, labor intensity is alleviated, labor efficiency is improved.

Description

Splash guard installs trolley
Technical field
The present invention relates to technical field of tunnel construction, relate in particular to splash guard installation trolley.
Background technique
Currently, installing in constructing tunnel, splash guard device structure is simple, and the laying of splash guard is mainly or using artificial paving If form of construction work.When artificial laying, geotextiles are first laid with, then installation hot melt washer, reuses hoist engine and mention splash guard Rise to rack top, then by tunnel top center, manually pull downward on splash guard and be laid with, splash guard lap-joint by Artificial hand steered positioning, is then welded using padding machine.Construction efficiency is low, and worker cannot keep long-time construction operation.
Summary of the invention
For the problems in the relevant technologies, the present invention proposes that splash guard installs trolley, solves existing splash guard laying construction Low efficiency and the big problem of labor intensity of workers.
In order to achieve the above technical purposes, the technical scheme is that it is such:
Splash guard installs trolley, the running gear including portal frame system and positioned at the portal frame system bottom, the portal frame system The trolley track of arc including two sides installation is equipped between the trolley track small for installing creeping for entire volume splash guard Vehicle, the crawl trolley connect bi-motor, and the crawl trolley is equipped with splash guard strut and the fixed device of waterproof coiled sheet, described Splash guard strut is equipped with spring supporting wheel, the dedicated strut of overlapping the slot and padding machine, is equipped at intervals with along the trolley track direction Several layers platform, each platform are fixed in the fixed link in portal frame system, and the mesa base is connected with ladder, the row The side of walking system is equipped with transverse-moving mechanism, and the transverse-moving mechanism is connected to portal frame system bottom by jacking system.
Further, the difference in height between platform described in adjacent two layers is 1.9m.
Further, the platform uses scalable platform or folding platform.
Further, each layer platform is equipped with protective fence and hook.
Further, the mechanical rocking bar control device for pushing waterproof coiled sheet to rotate is additionally provided on the crawl trolley.
Further, the running gear is steel wheel, rubber wheel or rail wheel.
Further, laser pick-off target, 36V emergency lighting and eye-catching reflection plaster are additionally provided in the portal frame system.
Beneficial effects of the present invention: splash guard installation trolley does not need to cut out splash guard in advance, directly by entire volume waterproof Plate is mounted on the crawl trolley of trolley, can once hang 3-4 meters of splash guards volume two, the splash guard that 3-4 meters of once-paving One, on the basis of guaranteeing that splash guard overlap joint requires and splash guard is laid with coefficient of relaxation, operator, which only needs to stand, to work The installation to splash guard can be completed on platform, reduced the process of splash guard leveling and calibration, alleviated labor intensity, mention High labor efficiency.The optimization design ladder landing platform system of splash guard trolley simultaneously, enhances the job security of construction personnel.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is the front view of the splash guard installation trolley according to embodiments of the present invention;
Fig. 2 is the side view of the splash guard installation trolley according to embodiments of the present invention.
In figure:
1, portal frame system;2, trolley track;3, crawl trolley;31, spring supporting wheel;4, platform;5, ladder;6, tunnel excavation rock Face;7, running gear;8, jacking system;9, transverse-moving mechanism, 10, ventilation duct.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art's every other embodiment obtained belong to what the present invention protected Range.
As shown in Figs. 1-2, splash guard installs trolley, including portal frame system 1 and the row connecting with 1 bottom of portal frame system Walking system 7, the portal frame system 1 include the trolley track 2 of the arc of two sides installation, are equipped with and are used between the trolley track 2 The crawl trolley 3 of entire volume splash guard is installed, the crawl trolley 3 connects bi-motor, and crawl trolley 3 is driven using bi-motor frequency conversion Dynamic, chain dragging is advanced, and power headroom is stopped, and is guaranteed that crawl trolley 3 is safely and effectively run, is further increased the safety of trolley And practical performance;The crawl trolley 3 is equipped with splash guard strut and the fixed device of waterproof coiled sheet, when being laid with splash guard, by preventing Splash guard is fixed on crawl trolley 3 by the fixed device of water coiled sheet carries out the rotation laying of entire volume splash guard, and a section has been laid with Bi Hou directly adjusts the position of fixed device, carries out the laying of next section, without moving to splash guard trolley, just In worker operation, the construction time is saved;The splash guard strut is equipped with spring supporting wheel 31, the dedicated strut of overlapping the slot and padding Machine, the dedicated strut of overlapping the slot and padding machine can be with the layings of splash guard, while work is fixed, compressed and welded to lap-joint Industry reduces the labor intensity of worker, improves working efficiency and construction quality.Guarantee that overlapping the slot welding meets project construction and sets Meter requires;Spring supporting wheel 31 guarantees that splash guard part is docile with tunnel excavation scar 6 as far as possible;Along the trolley track 2 Direction is equipped at intervals with several layers platform 4, and each platform 4 is fixed in the fixed link in portal frame system 1,4 bottom of platform It is connected with ladder 5, the side of the running gear 7 is equipped with transverse-moving mechanism 9, and the transverse-moving mechanism 9 is connected to by jacking system 8 1 bottom of portal frame system.
In the present embodiment, the trolley track 2 is to reduce design according to tunnel excavation scar 6 is whole, can prevent from being laid with When splash guard, leaves and dig scar excessively closely or too far.
In the present embodiment, the difference in height between platform 4 described in adjacent two layers be 1.9m, facilitate splash guard fixation or its It is operated.
In the present embodiment, the platform 4 guarantees to make using the scalable platform 4 or folding platform 4 of hydraulic cylinder control Industry platform can reach any position of tunnel perimeter, prevent worker due to height problem cause be laid with splash guard when operation not Just the case where.
In the present embodiment, each layer platform 4 is equipped with protective fence and hook, ensures construction worker's operation peace Entirely.
In the present embodiment, the mechanical rocking bar control for pushing waterproof coiled sheet to rotate is additionally provided on the crawl trolley 3 Device, splash guard monovolume width is 3-4 meters, when being laid with splash guard, since waterproof coiled sheet has certain weight, it is contemplated that reel turns When dynamic, certain resistance is had, rotating yardage roll manually can be laborious, therefore this trolley is laid on trolley in splash guard and is equipped with folder Tight and mechanical rocking bar control device, can be fixed on conduit after installing waterproof coiled sheet, by motor or manually shake Rocking bar drives entire volume splash guard volume to be rotated, and being laid with the installation of splash guard becomes more time saving and energy saving.
In the present embodiment, the running gear 7 is steel wheel, rubber wheel or rail wheel, and every group of steel wheel and rubber wheel use Independent ambulation, convenient for trolley, voluntarily correction wanders off in the process of walking, and the adjustment of hydraulic-driven transverse-moving mechanism 9 can also be used;If adopting With track travel, then identical walking track is used with tunnel lining trolley, is used convenient for scene.
In the present embodiment, laser pick-off target, 36V emergency lighting and eye-catching reflection plaster are additionally provided in the portal frame system 1.
In the present embodiment, the portal frame system 1 includes the interior ventilation duct 10 set.
Master control cabinet is set in each operating mechanism of the trolley, and configures remote-control handle, is controlled convenient for constructing operation;Trolley peace Multiple cameras are filled, and configure suitable software, mobile phone or computer can be used remotely to monitor trolley for manager, convenient for understanding The construction operation state of trolley promotes the efficiency of management.
The waterproof is installed trolley and is equipped with vehicle vacuum chuck structure, a spacing can will be drawn outside splash guard after automatic absorbing From guarantee elasticity;It can also voluntarily be grasped in splash guard work progress by site operation personnel, guarantee the pine of splash guard Sag, since back scar flatness is inconsistent, (two sides pour from the bottom up) may support bad anti-when later period casting concrete Water plate, therefore splash guard is laid with and needs certain slackness when fixed, according to construction site situation difference, coefficient of relaxation generally exists Between 1.05-1.2.
Splash guard installation trolley does not need to cut out splash guard in advance, and entire volume splash guard is directly mounted on creeping for trolley On trolley, 3-4 meters of splash guards volume two can be once hung, the splash guard one that 3-4 meters of once-paving is opened, and is guaranteeing that splash guard takes It connects requirement and splash guard is laid on the basis of coefficient of relaxation, operator, which only needs to stand, can complete on workbench to waterproof The installation of plate reduces the process of splash guard leveling and calibration, alleviates labor intensity, improve labor efficiency.It is excellent simultaneously Change the ladder landing platform system for devising splash guard trolley, enhances the job security of construction personnel.
The above is merely preferred embodiments of the present invention, be not intended to limit the invention, it is all in spirit of the invention and Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (7)

1. splash guard installs trolley, which is characterized in that connect including portal frame system (1) and with the portal frame system (1) bottom Running gear (7), the portal frame system (1) include two sides installation arc trolley track (2), the trolley track (2) it Between be equipped with crawl trolley (3) for installing entire volume splash guard, the crawl trolley (3) connects bi-motor, the crawl trolley (3) it is equipped with splash guard strut and the fixed device of waterproof coiled sheet, the splash guard strut is equipped with spring supporting wheel (31), overlap joint Dedicated strut and padding machine are stitched, is equipped at intervals with several layers platform (4) along the trolley track (2) direction, each platform (4) is solid It being scheduled in the fixed link in portal frame system (1), platform (4) bottom is connected with ladder (5), and the one of the running gear (7) Side is equipped with transverse-moving mechanism (9), and the transverse-moving mechanism (9) is connected to portal frame system (1) bottom by jacking system (8).
2. splash guard according to claim 1 installs trolley, which is characterized in that between platform described in adjacent two layers (4) Difference in height is 1.9m.
3. splash guard according to claim 3 installs trolley, which is characterized in that the platform (4) uses scalable platform (4) or folding platform (4).
4. splash guard according to claim 4 installs trolley, which is characterized in that each layer platform (4) is equipped with protection Column and hook.
5. splash guard according to claim 1 installs trolley, which is characterized in that be additionally provided with use on the crawl trolley (3) In the mechanical rocking bar control device for pushing the rotation of waterproof coiled sheet.
6. splash guard according to claim 1 installs trolley, which is characterized in that the running gear (7) is steel wheel, rubber Wheel or rail wheel.
7. splash guard according to claim 1 installs trolley, which is characterized in that be additionally provided in the portal frame system (1) sharp Light-receiving target, 36V emergency lighting and eye-catching reflection plaster.
CN201811588715.8A 2018-12-25 2018-12-25 Splash guard installs trolley Pending CN109488346A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811588715.8A CN109488346A (en) 2018-12-25 2018-12-25 Splash guard installs trolley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811588715.8A CN109488346A (en) 2018-12-25 2018-12-25 Splash guard installs trolley

Publications (1)

Publication Number Publication Date
CN109488346A true CN109488346A (en) 2019-03-19

Family

ID=65711648

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811588715.8A Pending CN109488346A (en) 2018-12-25 2018-12-25 Splash guard installs trolley

Country Status (1)

Country Link
CN (1) CN109488346A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847936A (en) * 2019-12-19 2020-02-28 长沙理工大学 Intelligence tunnel section levels device
CN112963180A (en) * 2021-02-26 2021-06-15 成都建工路桥建设有限公司 Semi-automatic waterproof coiled material laying device and method for waterproof board trolley

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE752474A (en) * 1970-01-22 1970-12-01 Commercial Shearing COATING AND SUPPORT STRUCTURE WITH INTERCHANGE, WITHOUT BOLTS, INTENDED FOR UNDERGROUND EXCAVATIONS
CN103089281A (en) * 2013-01-23 2013-05-08 湘潭光威机械科技有限公司 Trolley used for laying tunnel waterproof layer
CN103758541A (en) * 2014-01-26 2014-04-30 中铁工程装备集团有限公司 Trolley and method for laying tunnel waterproof plate
CN209621341U (en) * 2018-12-25 2019-11-12 中铁十六局集团北京建功机械有限公司 Splash guard installs trolley

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE752474A (en) * 1970-01-22 1970-12-01 Commercial Shearing COATING AND SUPPORT STRUCTURE WITH INTERCHANGE, WITHOUT BOLTS, INTENDED FOR UNDERGROUND EXCAVATIONS
CN103089281A (en) * 2013-01-23 2013-05-08 湘潭光威机械科技有限公司 Trolley used for laying tunnel waterproof layer
CN103758541A (en) * 2014-01-26 2014-04-30 中铁工程装备集团有限公司 Trolley and method for laying tunnel waterproof plate
CN209621341U (en) * 2018-12-25 2019-11-12 中铁十六局集团北京建功机械有限公司 Splash guard installs trolley

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847936A (en) * 2019-12-19 2020-02-28 长沙理工大学 Intelligence tunnel section levels device
CN110847936B (en) * 2019-12-19 2020-12-01 长沙理工大学 Intelligence tunnel section levels device
CN112963180A (en) * 2021-02-26 2021-06-15 成都建工路桥建设有限公司 Semi-automatic waterproof coiled material laying device and method for waterproof board trolley

Similar Documents

Publication Publication Date Title
WO2015154698A1 (en) Installation platform and installation method for tunnel waterproof sheet having wide width
US20220032500A1 (en) Construction and/or materials-handling machine and method for guiding and moving a working head
CN202768021U (en) Waterproof board laying trolley
CN112542808B (en) Cable laying device for electric power engineering construction
CN106194220A (en) Tunnel splash guard installs chassis
CN109488346A (en) Splash guard installs trolley
CN208235351U (en) A kind of bridge combination guardrail Fast Installation plate device
CN104179090B (en) A kind of subway is laid a railway track system
CN111022089B (en) Waterproof board trolley
CN109424318A (en) Drill jumbo and its control method with long-range remote control function
GB2518095B (en) Pulling machine for unloading and laying railway track
CN209621341U (en) Splash guard installs trolley
CN203441504U (en) Construction platform used for hanging waterproof board in tunnel
CN107882581B (en) Automatic platform waterproof board laying trolley
CN108397217B (en) The tunnel steel arch frame transport fitting machine and method that achievable monitoring element is laid in advance
CN204436416U (en) Lay chassis
CN206448820U (en) A kind of tunnel construction trolley
CN110820774A (en) Device for rolling steel wire meshes laid on side slopes and using method thereof
CN110814712B (en) Track beam installation drill carriage
JP2908577B2 (en) Tunnel lining plate installation method
CN211219542U (en) Track beam mounting drill carriage
CN109368137A (en) A kind of dumping plough transition dislocation method
CN207761679U (en) A kind of automatic platform formula splash guard laying trolley
CN205838444U (en) A kind of prefabricated component transport vehicle
CN214939299U (en) Movable suspension operation platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20240819

Address after: 063200 Caofeidian Zhongri Ecological Industrial Park, Caofeidian District, Tangshan City, Hebei Province, China. Building 1, located on the east side of Gaoxin West Road, south side of Zhongri Fifth Road, and north side of Zhongri Fourth Road

Applicant after: China Railway 16th Bureau Group Caofeidian Heavy Industry Machinery Co.,Ltd.

Country or region after: China

Address before: West Gate, No. 29 Xinbei Road, Miyun District, Beijing, 101500

Applicant before: CHINA RAILWAY 16TH BUREAU GROUP BEIJING JIANGONG MACHINERY Co.,Ltd.

Country or region before: China