CN109488103B - Hydraulic lifting construction method for large all-steel structure intercooling tower - Google Patents

Hydraulic lifting construction method for large all-steel structure intercooling tower Download PDF

Info

Publication number
CN109488103B
CN109488103B CN201811323038.7A CN201811323038A CN109488103B CN 109488103 B CN109488103 B CN 109488103B CN 201811323038 A CN201811323038 A CN 201811323038A CN 109488103 B CN109488103 B CN 109488103B
Authority
CN
China
Prior art keywords
hydraulic
lifting
steel structure
layer
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811323038.7A
Other languages
Chinese (zh)
Other versions
CN109488103A (en
Inventor
王德
罗会田
程志
伏迎喜
马彪
罗胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Chemical Engineering Third Construction Co Ltd
Original Assignee
China National Chemical Engineering Third Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Chemical Engineering Third Construction Co Ltd filed Critical China National Chemical Engineering Third Construction Co Ltd
Priority to CN201811323038.7A priority Critical patent/CN109488103B/en
Publication of CN109488103A publication Critical patent/CN109488103A/en
Application granted granted Critical
Publication of CN109488103B publication Critical patent/CN109488103B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/163Jacks specially adapted for working-up building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Jib Cranes (AREA)

Abstract

The invention relates to a hydraulic lifting construction method of a large-scale all-steel structure intercooling tower, which comprises the steps of steel structure cone section lifting construction, steel structure cylinder section lifting construction and reinforcing ring lifting construction, wherein a cone section tripod is installed on the ground, a plurality of layers of reinforcing rings are assembled and welded to complete the multi-layer lifting construction, then a hydraulic lifting mechanism is fixed, the multi-layer reinforcing rings are integrally lifted to the top of a cone section to be in place by the hydraulic lifting mechanism, a first layer of tripod of a straight cylinder section is installed with the cone section tripod and a first layer of reinforcing ring by a movable tower crane, then the rest reinforcing rings are integrally lifted to the top of the first layer of the straight cylinder section to be in place, and a second layer of the straight cylinder section is connected with the first layer of the straight cylinder section and the second layer of the reinforcing ring by the movable tower crane, the method is always installed on the top layer. And the improved process method is advanced, feasible, safe and reliable.

Description

Hydraulic lifting construction method for large all-steel structure intercooling tower
Technical Field
The invention relates to a construction technology of a large all-steel structure intercooling tower, in particular to a hydraulic lifting construction method of the large all-steel structure intercooling tower.
Background
In a certain project, two intercooling towers in a steel structure form need to be built, and each intercooling tower consists of a lower cone section, an upper cylinder section and a reinforcing ring. Lower cone section, upper portion cylinder section and strengthening ring all adopt the tripod structure, and wherein, lower cone section and upper portion cylinder section still include metal backplate. The height of the indirect cooling tower is 175m, the diameter of the bottom of the indirect cooling tower is 150m, the diameter of the upper part of the indirect cooling tower is 102m, and the total weight of the indirect cooling tower in the form of a single steel structure is 8500 tons.
For the indirect cooling tower with the diameter less than 80m, the existing construction method, such as the Chinese invention patent with the application number of 201711082436.X, utilizes a tower crane for construction, and the construction of a temporary platform during construction is all aerial installation, so that the danger is high, the existing construction method utilizing the tower crane cannot be applied to the construction of the indirect cooling tower with the diameter more than 80m, and the indirect cooling tower with the steel structure with the diameter larger than 80m does not have a construction precedent in China, so that the construction method with high reliability and good safety performance is urgently needed.
Disclosure of Invention
The technical problem to be solved by the invention is to provide a hydraulic lifting construction method for a large all-steel structure intercooling tower, which is suitable for an ultrahigh building with an oversized diameter, and has high reliability and good safety performance.
The invention discloses a hydraulic lifting construction method of a large-scale all-steel structure intercooling tower, which comprises intercooling tower steel structure cone section construction, intercooling tower steel structure multilayer reinforcing ring construction and intercooling tower steel structure cylinder section construction, wherein the intercooling tower steel structure cone section construction is carried out on the ground through a hoisting machine, the intercooling tower steel structure reinforcing ring construction is carried out through lifting of a hydraulic lifting mechanism, the intercooling tower steel structure cylinder section construction is carried out through hoisting of a movable tower crane, the intercooling tower steel structure cylinder section comprises a multilayer steel structure straight cylinder section, and the hydraulic lifting construction method comprises the following specific steps:
1) installing the conical section of the indirect cooling tower steel structure on the ground through a hoisting machine, and carrying out ground assembly and welding work on the straight cylinder section of the multilayer steel structure and the multilayer reinforcing ring;
2) arrange a plurality of hydraulic jack, hydraulic power unit, switch board in top layer beaded finish bottom according to the needs that promote weight to arrange corresponding hydraulic pressure oil pipe, arrange the master control cabinet on ground, debug equipment:
a. firstly, placing a hydraulic jack, a hydraulic pump station and a control cabinet, and connecting a hydraulic oil pipe, a control cable and a sensor;
b. the debugging equipment is used for observing whether the hydraulic jack acts as required or not by operating the touch screen of the main control cabinet;
c. taking down the hydraulic oil pipe, the control cable and the sensor;
d. installing a hydraulic jack: the hydraulic jack penetrates through the lower part of the lifting jack and is integrally fixed on the lifting member, wherein the lifting jack is a power mechanism fixed below the lifting member;
e. placing the main control cabinet at a proper position on the ground;
f. reconnecting the hydraulic oil pipe, the control cable and the sensor;
g. setting parameters to enable all hydraulic jacks to synchronously jack, and observing the change of displacement and pressure on a touch screen of the main control cabinet in real time;
3) a plurality of standard hydraulic lifting rods are arranged on the ground through a hoisting machine, and are matched with a hydraulic jack;
4) installing hydraulic lifting supports and hydraulic lifting heads corresponding to a plurality of hydraulic jacks through a crawler crane;
5) the continuous connection lifting rods are installed through a hoisting machine, two adjacent continuous connection lifting rods are connected through a pin shaft to form a continuous connection lifting rod group, and the upper end and the lower end of the continuous connection lifting rod group are respectively connected with a standard hydraulic lifting rod and a hydraulic lifting head through wedge plates;
6) hydraulic lifting operation, namely lifting the multilayer reinforcing rings to the top of the steel structure conical section integrally by a plurality of hydraulic jacks;
7) installing two movable tower cranes through a crawler crane, and installing a first layer of a steel structure straight cylinder section by using the two movable tower cranes;
8) hydraulic lifting operation, namely lifting the reinforcing ring to the top of the first layer of steel structure straight cylinder section integrally under the action of a plurality of hydraulic jacks;
9) installing a second layer of the steel structure straight cylinder section through a movable tower crane;
10) installing a lifting support, a plurality of lifting heads and a standard lifting rod through a movable tower crane;
11) hydraulic lifting operation, namely lifting the steel structure reinforcing ring to a first layer of in-place position, and mounting the first layer of reinforcing ring;
12) and (5) continuing hydraulic lifting operation, and installing the steel structure straight cylinder section to the top layer according to the method.
The invention relates to a hydraulic lifting construction method of a large all-steel structure intercooling tower, wherein a plurality of layers of reinforcing rings are used as a hydraulic lifting support platform and also used as an annular operating platform, the reinforcing rings are integrally combined and formed on the ground and integrally move along with a hydraulic lifting mechanism, two annular rails are arranged on the upper plane of the top reinforcing ring, and a movable tower crane is arranged on the annular rails.
The invention discloses a hydraulic lifting construction method of a large all-steel structure intercooling tower, wherein a plurality of hydraulic jacks are uniformly arranged on a reinforcing ring, each hydraulic jack is controlled by one hydraulic pump station, a sensor comprises a displacement sensor and a pressure sensor which are both arranged on the hydraulic jacks, the displacement sensor and the pressure sensor are used for feeding back signals to a PLC control system, and the PLC control system sends out instructions to the hydraulic pump stations according to the fed-back signals.
The invention relates to a hydraulic lifting construction method of a large all-steel structure intercooling tower, wherein a network type framework is adopted for a hydraulic lifting mechanism, each control cabinet controls a plurality of hydraulic jacks to lift, a main control console and each control station are in data connection through an industrial control network, a control system has remote and local two working modes, an automatic operating mode and a manual operating mode are provided in the remote mode, the automatic mode has a synchronization function, the local mode only has the manual operating mode, the system has overpressure monitoring and alarming functions, displacement difference monitoring and alarming functions, and the system automatically stops running while sending an alarm prompt.
The invention relates to a hydraulic lifting construction method of a large all-steel structure indirect cooling tower, which is characterized in that during synchronous hydraulic lifting, the displacement and the pressure are monitored simultaneously, a hydraulic pump station supplies oil to hydraulic jacks of all hydraulic lifting mechanisms, the pistons of the hydraulic jacks stretch out, a displacement sensor monitors the stretching amount of the piston of each hydraulic jack, when the height difference of a certain piston exceeds a required error value, a control system controls the action of an electromagnetic reversing valve of the hydraulic pump station, the action of the piston is stopped temporarily, and after the pistons of the jacks of other hydraulic lifters stretch out and follow up, the electromagnetic reversing valve is controlled to be opened, so that the piston which stops the action moves upwards again.
The hydraulic lifting construction method of the large-scale all-steel structure intercooling tower is different from the prior art in that the hydraulic lifting construction method of the large-scale all-steel structure intercooling tower takes the hydraulic jack as power, the hydraulic jack can be selected according to the weight of a lifting member and the lifting height, the type selection of the hydraulic jack can be 10-200 tons, the lifting height can be 10-500 m, and the lifting diameter can meet 10-300m, so that the hydraulic lifting construction method is suitable for the hydraulic lifting of the large-scale all-steel structure intercooling tower at with ultrahigh and ultra-long distance; the construction method comprises the steps of installing a cone section tripod on the ground, assembling and welding to complete a plurality of layers of reinforcing rings, arranging a fixed hydraulic lifting mechanism, integrally lifting the plurality of layers of reinforcing rings to the top of the cone section in place by using the hydraulic lifting mechanism, installing a straight cylinder section first layer tripod, the cone section tripod and the first layer of reinforcing rings by using a movable tower crane, then lifting the rest reinforcing rings to the top of the straight cylinder section first layer in place, and connecting a straight cylinder section second layer, the straight cylinder section first layer and the reinforcing ring second layer by using the movable tower crane.
The hydraulic lifting construction method of the large all-steel structure indirect cooling tower of the invention is further explained with reference to the attached drawings.
Drawings
FIG. 1 is a hydraulic lifting overall schematic diagram of a hydraulic lifting construction method of a large all-steel structure intercooling tower of the invention;
FIG. 2 is a schematic diagram of a hydraulic lifting mechanism adopted in the hydraulic lifting construction method of the large all-steel structure intercooling tower of the invention.
Detailed Description
Referring to fig. 1 and fig. 2, the construction method of the present invention is illustrated by taking an indirect cooling tower in a steel structure form with a height of 175m, a bottom diameter of 150m and an upper diameter of 102m as an example, wherein a conical section 101 of the indirect cooling tower steel structure is 55 m high, a straight cylinder section 102 of the indirect cooling tower steel structure is 55 m to 175m, reinforcing rings 103 of the indirect cooling tower steel structure are 5 layers, the 5 layers of reinforcing rings are distributed in the straight cylinder section at intervals of 30m, 5 layers of reinforcing ring steel structures, reinforcing ring connectors thereof and ring beam rails are arranged in the lifting section of the steel structure with a height of 0m to 55 m to be lifted, the weight of the auxiliary platform and 2 mobile tower cranes 104 is not included, the total weight of the lifting section with a height of 0m to 55 m is 1683.33 t, 25 lifting points are uniformly distributed at a position of 55 m, each lifting point is not less than 80 ton of lifting force, a rated total lifting amount of 2000 t, the lifting amount of 55 m to, the lifting weight is gradually decreased layer by layer after each layer of the reinforcing ring is installed in place, and the reinforcing ring is installed and fixed to the installation position. As the all-steel structural tower is ultrahigh in height, the hydraulic lifting construction of 0-175 m is a step-by-step multi-process construction.
The invention discloses a hydraulic lifting construction method of a large all-steel structure intercooling tower, which comprises the following specific steps of:
1) installing the conical section of the indirect cooling tower steel structure on the ground through a hoisting machine, and carrying out ground assembly and welding work on the straight cylinder section of the multilayer steel structure and the multilayer reinforcing ring;
2) arrange a plurality of hydraulic jack 2, hydraulic power unit, switch board according to the needs that promote weight in top layer beaded finish bottom to arrange corresponding hydraulic pressure oil pipe, arrange the master control cabinet on ground, debug equipment:
a. firstly, placing a hydraulic jack 2, a hydraulic pump station and a control cabinet, and connecting a hydraulic oil pipe, a control cable and a sensor;
b. the debugging equipment is used for observing whether the hydraulic jack 2 acts as required or not by operating the touch screen of the main control cabinet;
c. taking down the hydraulic oil pipe, the control cable and the sensor;
d. installing a hydraulic jack: the hydraulic jack 2 penetrates through the lower part of the lifting jack and then is integrally fixed on the lifting member 1, wherein the lifting jack is a power mechanism fixed below the lifting member 1;
e. placing the main control cabinet at a proper position on the ground;
f. reconnecting the hydraulic oil pipe, the control cable and the sensor;
g. setting parameters to enable all the hydraulic jacks 2 to synchronously jack, and observing the change of displacement and pressure on a touch screen of the main control cabinet in real time;
3) a plurality of standard hydraulic lifting rods 3 are installed on the ground through a hoisting machine, and the plurality of standard hydraulic lifting rods 3 are matched with the hydraulic jack 2;
4) installing hydraulic lifting supports 8 and hydraulic lifting heads 7 corresponding to a plurality of hydraulic jacks through a crawler crane;
5) the continuous connection lifting rods 5 are installed through a hoisting machine, the adjacent two continuous connection lifting rods 5 are connected through a pin shaft 6 to form a continuous connection lifting rod group, and the upper end and the lower end of the continuous connection lifting rod group are respectively connected with a standard hydraulic lifting rod 3 and a hydraulic lifting head 7 through a wedge plate 4 and a wedge plate 9;
6) hydraulic lifting operation, wherein a plurality of hydraulic jacks 2 integrally lift the multilayer reinforcing rings to the top of the steel structure conical section; at the moment, the multilayer reinforcing rings are sequentially distributed into a first layer reinforcing ring, a second layer reinforcing ring, a third layer reinforcing ring, a fourth layer reinforcing ring and a fifth layer reinforcing ring (top layer reinforcing ring) from bottom to top;
7) installing two movable tower cranes through a crawler crane, and installing a first layer of a steel structure straight cylinder section by using the two movable tower cranes;
8) hydraulic lifting operation, namely lifting the whole reinforcing ring to the top of the first layer of steel structure straight cylinder section under the action of a plurality of hydraulic jacks 2;
9) installing a second layer of the steel structure straight cylinder section through a movable tower crane 104;
10) installing a lifting support, a plurality of lifting heads and a standard lifting rod through a movable tower crane;
11) hydraulic lifting operation, namely lifting the steel structure reinforcing ring to a first layer of in-place position, and mounting the first layer of reinforcing ring; after the first layer of reinforcing rings are in place, the continuously lifted weight comprises a second layer, a third layer, a fourth layer and a fifth layer of reinforcing rings, and the lifted weight is reduced;
12) and (5) continuing hydraulic lifting operation, and installing the steel structure straight cylinder section to the top layer according to the method.
The installation of this embodiment is according to the order of steel construction cone section, first layer steel construction straight section, the straight section of second floor steel construction, first layer beaded finish, the straight section of third layer steel construction, the straight section of second floor beaded finish, the straight section of fourth layer steel construction, third layer beaded finish. The hydraulic lifting mechanism in the embodiment comprises a lifting component, a hydraulic jack, a standard hydraulic lifting rod, a wedge plate, a continuous lifting rod, a pin shaft, a hydraulic lifting head, a hydraulic lifting support and a fixing rod.
Wherein, multilayer strengthening ring is as hydraulic lifting supporting platform, also as annular operation platform, is provided with formal railing walkways, at the whole integrated combined moulding in ground, along with hydraulic lifting mechanism bulk movement, the upper plane of top layer strengthening ring (the fifth layer strengthening ring in this embodiment) is provided with twice circular orbit, and portable tower machine 104 sets up on circular orbit. In the invention, one to two movable tower cranes can be arranged, and the rated hoisting weight of the movable tower crane is 10 tons. The annular rail can not be dismantled after the indirect cooling tower is built, and is used for maintenance.
A plurality of hydraulic jack evenly arrange on the beaded finish, every hydraulic jack is controlled by a hydraulic power unit, and the sensor includes displacement sensor and pressure sensor, all installs on hydraulic jack, and displacement sensor and pressure sensor are used for feedback signal to give PLC control system, and PLC control system gives hydraulic power unit according to the signal send instruction of feedback.
Hydraulic lifting mechanism adopts network formula framework, a plurality of hydraulic jack of every switch board control promote, main control cabinet and each control station carry out data connection through the industrial control net, control system possesses long-range and two kinds of mode on the spot, there are automatic and two kinds of mode of operation manual under long-range mode, automatic mode possesses the synchronization function, only manual mode is under the mode on the spot, the system possesses superpressure monitoring and warning, the poor monitoring of displacement and alarming function, automatic shutdown when the system sends the warning suggestion moves.
When synchronous hydraulic lifting is carried out, displacement and pressure are monitored simultaneously, a hydraulic pump station supplies oil to all hydraulic jacks of a hydraulic lifting mechanism, pistons of the hydraulic jacks stretch out, a displacement sensor monitors the stretching amount of each piston of the hydraulic jacks, when the height difference of a certain piston exceeds a required error value, a control system controls the action of an electromagnetic reversing valve of the hydraulic pump station, the action of the piston is stopped temporarily, and after the pistons of the jacks of other hydraulic lifters stretch out and follow up, the electromagnetic reversing valve is controlled to be opened, so that the piston which stops the action moves upwards again.
The invention has the advantages that: the hydraulic jack is used as power, the hydraulic jack can be selected according to the requirements of the weight and the lifting height of a lifting component, the type selection of the hydraulic jack can be 10-200 tons, the lifting height can be 10-500 m, the lifting diameter can meet 10-300m, the standard lifting rod and the continuous lifting rod are used as a climbing channel, the standard lifting rod and the continuous lifting rod are replaced by utilizing spare cables in the lifting process, and finally the ultrahigh and ultra-long distance hydraulic lifting of the cooling tower between large-scale all-steel structures is completed.
The above-mentioned embodiments are merely illustrative of the preferred embodiments of the present invention, and do not limit the scope of the present invention, and various modifications and improvements of the technical solution of the present invention by those skilled in the art should fall within the protection scope defined by the claims of the present invention without departing from the spirit of the present invention.

Claims (4)

1. A hydraulic lifting construction method for a large all-steel structure intercooling tower is characterized by comprising the following steps: including intercooling tower steel construction cone section construction, intercooling tower steel construction multilayer strengthening ring construction and intercooling tower steel construction cylinder section construction, wherein, intercooling tower steel construction cone section construction is gone on ground through hoisting machinery, and intercooling tower steel construction strengthening ring construction promotes through hydraulic lifting mechanism and goes on, and intercooling tower steel construction cylinder section construction is gone on through portable tower machine hoist and mount, and intercooling tower steel construction cylinder section includes the straight section of multilayer steel construction, and concrete step is as follows:
1) installing the conical section of the indirect cooling tower steel structure on the ground through a hoisting machine, and carrying out ground assembly and welding work on the straight cylinder section of the multilayer steel structure and the multilayer reinforcing ring;
2) arrange a plurality of hydraulic jack (2), hydraulic power unit, switch board in top layer beaded finish bottom according to the needs that promote weight to arrange corresponding hydraulic pressure oil pipe, arrange the master control cabinet on ground, debug equipment:
a. firstly, placing a hydraulic jack (2), a hydraulic pump station and a control cabinet, and connecting a hydraulic oil pipe, a control cable and a sensor;
b. the debugging equipment is used for observing whether the hydraulic jack (2) acts as required or not by operating the touch screen of the main control cabinet;
c. taking down the hydraulic oil pipe, the control cable and the sensor;
d. installing a hydraulic jack: the hydraulic jack (2) penetrates through the lower part of the lifting jack and then is integrally fixed on the lifting member (1), wherein the lifting jack is a power mechanism fixed below the lifting member (1);
e. placing the main control cabinet at a proper position on the ground;
f. reconnecting the hydraulic oil pipe, the control cable and the sensor;
g. setting parameters to enable all the hydraulic jacks (2) to synchronously jack, and observing the change of displacement and pressure on a touch screen of the main control cabinet in real time;
3) a plurality of standard hydraulic lifting rods (3) are installed on the ground through a hoisting machine, and the standard hydraulic lifting rods (3) are matched with the hydraulic jack (2);
4) installing hydraulic lifting supports (8) and hydraulic lifting heads (7) corresponding to the hydraulic jacks through a crawler crane;
5) continuous connection lifting rods (5) are installed through a hoisting machine, adjacent two continuous connection lifting rods (5) are connected through a pin shaft (6) to form a continuous connection lifting rod group, and the upper end and the lower end of the continuous connection lifting rod group are respectively connected with a standard hydraulic lifting rod (3) and a hydraulic lifting head (7) through a wedge plate;
6) hydraulic lifting operation, namely lifting the multilayer reinforcing ring to the top of the steel structure conical section integrally by a plurality of hydraulic jacks (2);
7) installing two movable tower cranes through a crawler crane, and installing a first layer of a steel structure straight cylinder section by using the two movable tower cranes;
8) hydraulic lifting operation, namely lifting the reinforcing ring to the top of the first layer of steel structure straight cylinder section integrally under the action of a plurality of hydraulic jacks;
9) installing a second layer of the steel structure straight cylinder section through a movable tower crane;
10) installing a lifting support, a plurality of lifting heads and a standard lifting rod through a movable tower crane;
11) hydraulic lifting operation, namely lifting the steel structure reinforcing ring to a first layer of in-place position, and mounting the first layer of reinforcing ring;
12) continuing hydraulic lifting operation, and installing the steel structure straight cylinder section to the top layer according to the method;
the multi-layer reinforcing ring is integrally combined and formed on the ground as a hydraulic lifting supporting platform and an operating platform, and integrally moves along with a hydraulic lifting mechanism, the upper plane of the top layer reinforcing ring is provided with two annular rails, and the movable tower crane is arranged on the annular rails.
2. The hydraulic lifting construction method of the large all-steel structure intercooling tower according to claim 1, characterized in that: a plurality of hydraulic jack evenly arranges on the beaded finish, and every hydraulic jack is controlled by a hydraulic power unit, the sensor includes displacement sensor and pressure sensor, all installs on hydraulic jack, displacement sensor and pressure sensor are used for feedback signal to give PLC control system, and PLC control system gives hydraulic power unit according to the signal send instruction of feedback.
3. The hydraulic lifting construction method of the large all-steel structure intercooling tower according to claim 1, characterized in that: hydraulic lifting mechanism adopts network formula framework, a plurality of hydraulic jack of every switch board control promote, main control cabinet and each control station carry out data connection through the industrial control net, control system possesses long-range and two kinds of mode on the spot, there are automatic and two kinds of mode of operation manual under long-range mode, automatic mode possesses the synchronization function, only manual mode is under the mode on the spot, the system possesses superpressure monitoring and warning, the poor monitoring of displacement and alarming function, automatic shutdown when the system sends the warning suggestion moves.
4. The hydraulic lifting construction method of the large all-steel structure intercooling tower according to claim 1, characterized in that: when synchronous hydraulic lifting is carried out, displacement and pressure are monitored simultaneously, a hydraulic pump station supplies oil to all hydraulic jacks of a hydraulic lifting mechanism, pistons of the hydraulic jacks stretch out, a displacement sensor monitors the stretching amount of each piston of the hydraulic jacks, when the height difference of a certain piston exceeds a required error value, a control system controls the action of an electromagnetic reversing valve of the hydraulic pump station, the action of the piston is stopped temporarily, and after the pistons of the jacks of other hydraulic lifters stretch out and follow up, the electromagnetic reversing valve is controlled to be opened, so that the piston which stops the action moves upwards again.
CN201811323038.7A 2018-11-08 2018-11-08 Hydraulic lifting construction method for large all-steel structure intercooling tower Active CN109488103B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811323038.7A CN109488103B (en) 2018-11-08 2018-11-08 Hydraulic lifting construction method for large all-steel structure intercooling tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811323038.7A CN109488103B (en) 2018-11-08 2018-11-08 Hydraulic lifting construction method for large all-steel structure intercooling tower

Publications (2)

Publication Number Publication Date
CN109488103A CN109488103A (en) 2019-03-19
CN109488103B true CN109488103B (en) 2021-06-01

Family

ID=65695271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811323038.7A Active CN109488103B (en) 2018-11-08 2018-11-08 Hydraulic lifting construction method for large all-steel structure intercooling tower

Country Status (1)

Country Link
CN (1) CN109488103B (en)

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102235107B (en) * 2010-04-27 2013-02-06 中国华冶科工集团有限公司 Hydraulic lifting construction method for chimney steel inner cylinder
WO2012162800A1 (en) * 2011-06-02 2012-12-06 National Oilwell Varco, L.P. Drilling rig system with self-elevating drill floor
US8584429B2 (en) * 2011-09-30 2013-11-19 Tindall Corporation Tower erection system and method
US9140029B2 (en) * 2012-01-20 2015-09-22 Illinois Tool Works Inc. Tower erecting system
ES2554828T3 (en) * 2012-09-19 2015-12-23 Alstom Technology Ltd. Set and method of concentrated solar tower
CN106759883B (en) * 2016-11-30 2019-05-24 上海市机械施工集团有限公司 The tower crane construction method of large-scale steel structure air cooling tower
CN106759924A (en) * 2017-01-20 2017-05-31 华电重工股份有限公司 A kind of lifting installation method of steel structure cooling tower
CN107882339B (en) * 2017-11-07 2019-12-31 中国化学工程第三建设有限公司 Construction method of large all-steel structure type indirect cooling tower
CN108049694A (en) * 2017-12-22 2018-05-18 陕西能源麟北发电有限公司 Steel construction indirect cool tower with smoke discharging function
CN108086784A (en) * 2017-12-25 2018-05-29 中国化学工程第三建设有限公司 The construction method of steel construction indirect cool tower upper cylinder
CN207863437U (en) * 2017-12-25 2018-09-14 中国化学工程第三建设有限公司 Indirect cool tower direct tube section installation platform

Also Published As

Publication number Publication date
CN109488103A (en) 2019-03-19

Similar Documents

Publication Publication Date Title
US8863474B2 (en) Main work construction method for reinforced concrete building and building construction machine
WO2022048321A1 (en) Steel tower single-sided climbing-type lifting formwork and application in inclined single-column steel cable tower
CN102530732B (en) Hydraulic hoisting, slipping and emplacing method and equipment for large scale press components
CN103790234A (en) Large-span truss hydraulic multi-point synchronous lifting construction method
CN105692470A (en) Internal climbing tower crane and operating method thereof
CN201367728Y (en) Derrick-less hydraulic slip form device used for reinforced concrete water tower supporting tube construction
CN102786004B (en) Integrally moving on-load hydraulic lifting system without mooring rope and lifting method
CN101723286B (en) Large gas holder top lifting device and method
CN109488103B (en) Hydraulic lifting construction method for large all-steel structure intercooling tower
CN1057973C (en) Four-bar frame self-lifting type door-base crane
CN107142954B (en) Steel hanging box lifting system for integral lifting and lifting method thereof
CN112456348B (en) Heat absorber hoisting method
CN203486787U (en) Integral lifting device for cabinet top of Wiggins coal gas cabinet
CN104555833B (en) Method for hoisting steel inner cylinder of chimney
CN110424808B (en) Skin construction method of steel structure indirect cooling tower
CN210482577U (en) A prop up top circulation system for three-dimensional prefabricated full assembled concrete structure
CN102040174B (en) Integral hoisting device and method for large-scale equipment and member
RU2442743C2 (en) Double-girder crane with number of supports
CN109306938B (en) Tower drum of wind generating set, installation method of tower drum and wind generating set
CN215670930U (en) Integral hydraulic mold moving device serving high-rise chimney quality safety control
CN204752102U (en) Door derrick crane pylon standard festival equipment relay formula is vertical from jacking device
CN215210908U (en) Square steel structure assembled type hydropower station stator maintenance platform capable of being lifted integrally
CN205077876U (en) Machine and stressing jack linkage are worn to restraint by prestress wire
CN114046083B (en) Construction method for building steel inner cylinder chimney
CN110616842B (en) Construction method of purline assembly in steel structure coal shed

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
CB02 Change of applicant information

Address after: 230000 East Fozhang Road and North Tingyun Road Office Building, Hefei Economic and Technological Development Zone, Anhui Province

Applicant after: China National Chemical Engineering Third Construction Co., Ltd.

Address before: 232038 No. 98 Dongshan Road, Tianjiaan District, Huainan City, Anhui Province

Applicant before: China National Chemical Engineering Third Construction Co., Ltd.

CB02 Change of applicant information
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Wang De

Inventor after: Luo Huitian

Inventor after: Cheng Zhi

Inventor after: Fu Yingxi

Inventor after: Ma Biao

Inventor after: Luo Sheng

Inventor before: Wang De

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant