CN109468954A - A kind of form of construction work of anchorage anchor system - Google Patents

A kind of form of construction work of anchorage anchor system Download PDF

Info

Publication number
CN109468954A
CN109468954A CN201811272730.1A CN201811272730A CN109468954A CN 109468954 A CN109468954 A CN 109468954A CN 201811272730 A CN201811272730 A CN 201811272730A CN 109468954 A CN109468954 A CN 109468954A
Authority
CN
China
Prior art keywords
anchor
bracket
anchor pole
construction
pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811272730.1A
Other languages
Chinese (zh)
Other versions
CN109468954B (en
Inventor
甄宗标
汪成龙
魏湛力
钟永新
潘桂林
石军
方龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
China Railway Shanghai Group Co Ltd
Original Assignee
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
China Railway Shanghai Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co, CCCC SHEC Fourth Engineering Co Ltd, China Railway Shanghai Group Co Ltd filed Critical CCCC Second Harbor Engineering Co
Priority to CN201811272730.1A priority Critical patent/CN109468954B/en
Publication of CN109468954A publication Critical patent/CN109468954A/en
Application granted granted Critical
Publication of CN109468954B publication Critical patent/CN109468954B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of forms of construction work of anchorage anchor system, the form of construction work includes the following steps, (1) construction open caisson well lid, (2) anchor beam bracket step region subdivision casting concrete, (3) anchor beam bracket is installed, (4) install anchor beam and anchor pole bracket, and (5) install anchor pole, and anchor block concrete layer is successively poured, (6) continue anchor block construction.The construction method forms mixed type anchor support system and uses the form of construction work poured when installing anchor pole simultaneously.This method forms mixed type anchor support system, to enhance anchor support rigidity, eliminates accumulated deformation effect, and effectively preventing deformation of timbering causes to repeat operation, improves construction efficiency, reduces the usage amount of fashioned iron, reduces cost input.

Description

A kind of form of construction work of anchorage anchor system
Technical field
The present invention relates to field of bridge construction, the form of construction work of specifically a kind of anchorage anchor system.
Background technique
In bridge construction process, the anchoring of anchorage generally uses fashioned iron anchoring system and prestress anchorage system, fashioned iron Although anchoring system steel using amount is big, fabrication and installation and construction precision require height, and project amount is big, and the system is not with after needing Phase maintenance does not have to later period investment, belongs to disposable investment, therefore permanent usage type considers, type from bridge life-cycle angle Steel anchor system has stronger advantage relative to prestress anchoraging system, but the anchor support of fashioned iron anchoring system is usually Using steel construction, it is in turn mounted to position, however, steel structure support is led by not disconnecting height in fashioned iron anchor system installation process Integral fastening stent flexibility is caused to increase, while support force constantly increases, accumulated deformation increases, and anchor system is caused to be installed Part precision repeatedly changes, and repeats to adjust, extreme influence installation progress expends a large amount of manpower and material resources.
Summary of the invention
In view of the above-mentioned problems, the present invention provides a kind of form of construction work of anchorage anchor system, which forms mixed Mould assembly anchor support system uses the form of construction work poured when installing anchor pole simultaneously.This method forms mixed type anchor support system System eliminates accumulated deformation effect to enhance anchor support rigidity, and effectively preventing deformation of timbering causes to repeat operation, improves Construction efficiency reduces the usage amount of fashioned iron, reduces cost input.
The technical solution that the present invention uses in order to solve the above problem:
A kind of form of construction work of anchorage anchor system, includes the following steps:
(1) Step 1: construction open caisson well lid:
1) open caisson well lid is poured, anchor beam upport installation portion position, after open caisson well lid pours, institute are reserved above the well lid poured Stating anchor beam upport installation portion position two sides is respectively anchor beam bracket stepped area and anchor pole bracket stepped area, the anchor pole trestle table Rank region is divided into middle anchor pole stent area and preceding anchor face anchor pole bracket stepped area;
2) anchor beam bracket built-in fitting is set at anchor beam upport installation portion position, anchor pole branch is equipped in middle anchor pole stent area Frame built-in fitting;
(2) step 2: anchor beam bracket step region subdivision casting concrete:
1) concreting in lifts is carried out in anchor beam bracket stepped area form anchor beam bracket ladder;
2) anchor beam bracket built-in fitting is buried on every layer of anchor beam bracket ladder;
(3) step 3: installation anchor beam bracket and anchor beam:
1) on the anchor beam bracket built-in fitting and anchor beam bracket ladder anchor beam bracket being mounted at anchor beam upport installation portion position Anchor beam bracket built-in fitting on, while anchor beam bracket is reinforced;
2) anchor beam is installed on anchor beam bracket, and adjusts position, is uniformly provided with and several connect with anchor pole on the anchor beam Bracket tie point;
3) it is mixed to form anchor pole bracket in anchor pole bracket stepped area for the concrete block for anchor pole bracket stepped area of constructing simultaneously Solidifying earthen platform rank, buries anchor pole bracket built-in fitting on every layer of anchor pole bracket concrete step;
(4) step 4: installation anchor beam and anchor pole bracket:
1) continue that anchor beam is installed, and adjust position;
2) anchor being simultaneously mounted on the first anchor pole bracket at the middle anchor pole stent area on anchor pole bracket concrete step On bar bracket built-in fitting, the second anchor pole bracket is mounted on to the preceding anchor face anchor pole bracket stepped region on anchor pole bracket concrete step On anchor pole bracket built-in fitting at domain;
(5) step 5: installation anchor pole, and successively pour anchor block concrete layer:
1) anchor pole is installed in batches, each batch anchor pole carries out a point root and installs, and the bracket of the anchor pole rear end is installed The anchor pole is connected on the first anchor pole bracket and the second anchor pole bracket simultaneously on the bracket tie point of the anchor beam, and is adjusted Position is fixed temporarily, and completes anchor bolt construction;
2) after the completion of anchor bolt construction described in each batch, anchor block concrete layer of successively constructing, the anchor block concrete layer Horizontal plane to the anchor beam bracket tie point for being equipped with anchor pole bracket connects with the anchor beam bracket for being not installed with anchor pole bracket Between contact;
3) it after the completion of anchor bolt construction described in a batch, successively constructs after anchor block concrete layer, carries out the anchor pole of next batch Construction and construction anchor block concrete layer;
4) N batch anchor bolt construction complete and construct complete anchor block concrete layer after, N+1 batch installation anchor pole it Before, high first anchor pole bracket or the second anchor pole bracket are connect, the N+1 times anchor bolt construction is carried out;The N is anchor pole batch number, is Integer more than or equal to 1;
(6) step 6: continue anchor block construction:
After the completion of rockbolt installation, continue the construction of anchor block concrete layer.
The present invention uses new anchorage anchor system construction technology, in anchor system construction, using concrete ladder and Shape steel bracket forms mixed type support system, which includes anchor beam bracket, the first anchor pole bracket and the second anchor pole bracket, Anchor beam bracket ladder is formed using concreting in lifts, the anchor beam bracket ladder connect to form mixing with the anchor beam bracket Type anchor beam bracket;Anchor pole bracket concrete step, the anchor pole bracket concrete step point are formed using concreting in lifts Do not connect to form mixed type anchor pole bracket with the first anchor pole bracket and the second anchor pole bracket, the mixed type anchor beam bracket and The mixed type anchor pole bracket forms mixed type support system and is used to support steel construction anchor pole, while when installing anchor pole, uses The form of construction work of casting concrete layer when filling anchor pole.It is big, demanding to support stability that the construction technology is suitable for weight The installation effectiveness of anchor system can be improved in the installation of large-scale anchor system, enhances stability, reduces security risk, while shape At mixed type support system can reduce accumulated deformation effect, can effectively avoid repetition adjustment, greatly improve installation essence Degree, reduces workload, while reducing the dosage of steel, save the cost.
Preferably, construction open caisson well lid in the step 1, pours open caisson well lid by the way of piecemeal, layering.According to Temperature controlled requirement, to prevent from cracking, using piecemeal, placement layer by layer.
Preferably, for the anchor block concrete layer in addition to the last layer, every layer height is identical.It is fixed according to concrete-pouring template System, every layer height of template is identical, therefore, every layer pour height it is identical, do not have to every time adjustment, facilitate construction.
Preferably, the first anchor pole bracket and the second anchor pole bracket include several segments truss list interconnected Member.Truss element interconnected can realize segmentation installation in order to the first anchor pole bracket and the second anchor pole bracket, so as to basis The installation situation of practical anchor pole adjusts the height of the first anchor pole bracket and the second anchor pole bracket.
Preferably, the first anchor pole bracket is fixedly connected with the second anchor pole bracket using fashioned iron.By the first anchor pole Bracket and the second anchor pole bracket are fixedly connected using fashioned iron, so that the first anchor pole bracket and the second anchor pole bracket form entirety, are made It is more securely and stable to obtain entire anchor pole bracket.
Detailed description of the invention
Fig. 1 is the construction schematic diagram after open caisson well lid pours;
Fig. 2 is the construction schematic diagram after the completion of anchor beam bracket ladder;
Fig. 3 is that anchor beam completes the construction schematic diagram after installation and the completion of anchor pole bracket concrete step;
Fig. 4 is the construction schematic diagram after the installation of anchor pole bracket;
Fig. 5 is the construction schematic diagram that first anchor pole completes installation after-pouring first layer anchor block concrete layer;
Fig. 6 is the construction schematic diagram that second batch anchor pole completes installation second and third layer of anchor block concrete layer of after-pouring;
Fig. 7 is the construction schematic diagram that third batch anchor pole completes installation after-pouring third to five layers of anchor block concrete layer;
Fig. 8 is the construction schematic diagram that the 4th batch of anchor pole completes installation the six to nine layer of anchor block concrete layer of after-pouring;
Fig. 9 is the schematic diagram after the completion of anchor block construction;
Marked in the figure: 1- anchor beam upport installation portion position, 2- anchor beam bracket stepped area, 3- anchor block concrete layer, 4- anchor beam Bracket built-in fitting, 5- anchor pole bracket built-in fitting, 6- anchor beam bracket ladder, 7- anchor beam bracket, 71- the first anchor pole bracket, 72- second Anchor pole bracket, 8- anchor beam, 81- bracket tie point, 9- anchor pole bracket concrete step, 10- anchor pole, 11- anchor pole bracket stepped region Domain, bracket stepped area in 111-, anchor face bracket stepped area before 112-;12- saddle, 15- fashioned iron.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawing and specific implementation The present invention is described in detail for example.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, not For limiting the present invention.
Embodiment 1
A kind of form of construction work of anchorage anchor system, includes the following steps:
(1) Step 1: construction open caisson well lid:
1) open caisson well lid is poured, anchor beam upport installation portion position 1 is reserved above the well lid poured, as shown in Figure 1, open caisson well After lid pours, 1 two sides of anchor beam upport installation portion position are respectively anchor beam bracket stepped area 2 and anchor pole bracket stepped area 11, the anchor pole bracket stepped area 11 is divided for middle anchor pole stent area 111 and preceding anchor face anchor pole bracket stepped area 112, such as Fig. 1, shown in 3,4;Different regions is distinguished in reserved anchor beam upport installation portion position 1 after well lid pours, so as in construction in later period shape At mixed type support system;In the present embodiment, pour open caisson well lid mode be those skilled in the art common knowledge with And therefore customary means herein no longer repeats the mode for pouring open caisson well lid.In addition, anchor pole bracket stepped area 11 other side is saddle 12, and in the present embodiment, saddle form of construction work and saddle structure are well known to those skilled in the art Common knowledge, therefore, here and subsequent construction procedure no longer carries out detailed repeat to the construction of saddle and structure.
2) anchor beam bracket built-in fitting 4 is set at anchor beam upport installation portion position 1, is equipped in middle anchor pole stent area 111 Anchor pole bracket built-in fitting 5, such as Fig. 1, shown in 3,4;Anchor beam bracket built-in fitting 4 is for loading anchor beam bracket 7, anchor pole bracket built-in fitting 5 for loading anchor pole bracket;In the present embodiment, the structure of anchor beam bracket built-in fitting 4 and the structure of anchor pole bracket built-in fitting 5 are The common knowledge of this book field technical staff, anchor beam bracket built-in fitting 4 are used for loading anchor beam bracket 7, anchor pole bracket built-in fitting 5 In loading anchor pole bracket, those skilled in the art can be realized the anchor beam branch of above-mentioned loading effect according to the content that this programme is recorded Frame built-in fitting 4 and anchor pole bracket built-in fitting 5 can be used, therefore, no longer pre- to anchor beam bracket built-in fitting 4 and anchor pole bracket herein The structure of embedded part 5, which is done, specifically to be repeated.
(2) step 2: 2 concreting in lifts of anchor beam bracket stepped area:
1) concreting in lifts is carried out in anchor beam bracket stepped area 2 and form anchor beam bracket ladder 6, as shown in figs. 2-9;
2) anchor beam bracket built-in fitting 4 is buried on every layer of anchor beam bracket ladder 6, as shown in figs. 2-9;
(3) step 3: installation anchor beam bracket 7 and anchor beam 8:
1) anchor beam bracket 7 is mounted on at anchor beam upport installation portion position 1 anchor beam bracket built-in fitting 4 and anchor beam bracket ladder On anchor beam bracket built-in fitting 4 on 6, while reinforcing, as shown in figs. 3-9, anchor beam bracket ladder 2 and anchor to anchor beam bracket 7 Boom support 6 forms mixed type anchor beam bracket, as shown in figs. 3-9;
2) anchor beam 8 is installed on anchor beam bracket 7, and adjusts position, several bracket tie points are uniformly provided on the anchor beam 8 81, as shown in figs. 3-9;
3) concrete block for anchor pole bracket stepped area 11 of constructing simultaneously forms anchor pole branch in anchor pole bracket stepped area 11 Frame concrete step 9 buries anchor pole bracket built-in fitting 5 as shown in figs. 3-9 on every layer of anchor pole bracket concrete step 9, As shown in figs. 3-9;
(4) step 4: installation anchor beam and anchor pole bracket:
1) continue that anchor beam 8 is installed, and adjust position;
2) the first anchor pole bracket 71 is mounted at the middle anchor pole stent area on anchor pole bracket concrete step 11 simultaneously On 111 anchor pole bracket built-in fitting 5, the preceding anchor face anchor that 72 bracket of the second anchor pole is mounted on anchor pole bracket concrete step 11 On anchor pole bracket built-in fitting 5 at bar bracket stepped area 112, the first anchor pole bracket 71 and the second anchor pole bracket 72 respectively with anchor The connection of bar bracket mixed mud step 11 forms mixed type anchor pole bracket, as shown in figures 4-9;
Construction procedure one to four, construction form mixed type support system, the support system include by anchor beam bracket ladder 6 with The mixed type anchor beam bracket that anchor beam bracket 7 is formed, the first anchor pole bracket 71 and the second anchor pole bracket 72 are mixed with anchor pole bracket respectively Solidifying earthen platform rank 9 connects the mixed type anchor pole bracket formed, the anchor beam bracket ladder 6 in the mixed type support system, anchor pole bracket Support force is born based on concrete step 9, and anchor beam bracket 7, the first anchor pole bracket 71 and the second anchor pole bracket 72 are to be positioned as It is main, and concrete is transmitted the force to, to reduce the deformation of steel construction, the rigidity of bracket can be enhanced, eliminate accumulated deformation, prevented Operation is only repeated caused by deformation of timbering, improves construction efficiency, reduces the usage amount of steel, reduces cost input.In this implementation In example, anchor beam bracket 7 is mounted on anchor beam bracket built-in fitting 4 at anchor beam bracket ladder 6 and anchor beam upport installation portion position 1 and the One anchor pole bracket 71 and the second anchor pole bracket 72 are mounted on the anchor pole bracket built-in fitting 5 on anchor pole bracket concrete step 9 Mounting means is the customary means of art technology, therefore, the mounting means no longer to anchor beam bracket 7 and anchor pole bracket herein It is specifically repeated with needing tool to be used to do.In the present embodiment, the reinforcing of anchor beam bracket 7, the installation and adjustment of anchor beam 8 It is the routine operation of art technology, therefore, the reinforcing no longer to anchor beam bracket 7 herein, the installation of anchor beam 8 and adjustment Mode, which is done, specifically to be repeated.
(5) step 5: installation anchor pole 10, and successively pour anchor block concrete layer 3:
1) as viewed in figures 5-8, anchor pole 10 is installed in batches, each batch anchor pole carries out a point root and installs, by the anchor pole The bracket of 10 rear ends is mounted on the bracket tie point 81 of the anchor beam 8 anchor pole 10 simultaneously and is connected to the first anchor pole bracket 71 On the second anchor pole bracket 72, and position is adjusted, be fixed temporarily, completed anchor pole 10 and construct;
2) after the completion of the construction of anchor pole 10 described in each batch, anchor block concrete layer 3 of successively constructing, the anchor block concrete layer 3 horizontal plane to the anchor beam 8 for being equipped with 10 bracket of anchor pole bracket tie point 81 be not installed with the institute of 10 bracket of anchor pole It states between the bracket tie point 81 of anchor beam 8;
3) it after the completion of the construction of anchor pole 10 described in a batch, successively constructs after anchor block concrete layer 3, carries out the anchor of next batch The construction of bar 10 and construction anchor block concrete layer 3;
4) after N batch anchor pole 10 constructs and completes and construct completion anchor block concrete layer 3, anchor is installed in N+1 batch Before bar, high first anchor pole bracket 71 or the second anchor pole bracket 72 are connect, the N+1 times anchor pole 10 is carried out and installs;The N is anchor pole 10 batch number, is greater than or equal to 1 integer;
After step 1 is finished to step 4, mixed type support system is formd in anchorage structures, it is therefore, next Step installs anchor pole 10 in support system, and anchor pole 10 is installed in batches, and each batch divides root to install, and the installation of anchor pole 10 is to pass through The bracket of 10 rear end of anchor pole is mounted on the bracket tie point 81 of the anchor beam 8 anchor pole 10 simultaneously and is connected to the first anchor pole branch On frame 71 and the second anchor pole bracket 72, in the present embodiment, dividing root installation 10 concrete mode of anchor pole is the conventional means of this field, It no longer specifically repeats herein, after first anchor pole 10 is installed, carries out pouring for anchor block concrete layer 3, anchor block coagulation The horizontal plane that soil layer 3 pours to the anchor beam 8 for being equipped with 10 bracket of anchor pole bracket tie point 81 and 10 bracket of anchor pole is not installed Between the bracket tie point 81 of anchor beam 8, so as not to interfere next group anchor pole 10 to be mounted on anchor beam 8, anchor block concrete layer 3 is poured After the completion;The installation of anchor pole 10 of next batch and pouring for anchor block concrete layer 3 are carried out again, until anchor pole 10 is installed.? In work progress of the invention, using the form of construction work of the casting concrete layer 3 when filling anchor pole 10, which is suitable for weight The installation of big, demanding to the support stability large-scale anchor system of amount, can be improved the installation effectiveness of anchor system, enhancing is steady It is qualitative.In addition, in the present embodiment, in the installation process of anchor pole 10, the height of the first anchor pole bracket 71 and the second anchor pole bracket 72 Degree connects high installation with the carry out scene of increasing of 10 installation number of anchor pole, and buries anchor in anchor block concrete layer 3 before connecing height Bar bracket built-in fitting 5 connects height so as to the first anchor pole bracket 71 and the second anchor pole bracket 72, is mixed due to installing a collection of anchor pole Solidifying soil pours, and therefore, when connecing high first anchor pole bracket 71 and the second anchor pole bracket 72, is equipped with the first anchor pole bracket of anchor pole 71 and 72 part of the second anchor pole bracket become whole with the anchor block concrete layer 3 of casting, this part anchor pole bracket will not be because It is deformed to connect high, therefore, the first anchor pole bracket 71 or the second anchor pole bracket 72 after connecing height will not be because of the first anchors The not disconnecting of bar bracket 71 or the second anchor pole bracket 72 is high and overall flexibility is caused to increase, so as to cause the first anchor pole bracket 71 Increase with 72 accumulated deformation of the second anchor pole bracket.
(6) step 6: continue anchor block construction:
As shown in figure 9, continuing the construction of anchor block concrete layer 3 after anchor pole 10 is installed.
Above-mentioned construction technology is applied to specific anchorage anchor system, the anchorage high 56.6m of anchor body, Hawser dissipates cable saddle point Elevation is+50.0m, and Hawser direction across bridge upstream and downstream distance is 43m.Entire anchor body is in U-shape, the laterally wide 70.2m in tail portion, front end point Laterally wide from, every side is 10m, and anchor body is along bridge to overall length 83.3m.Anchor system is made of rear anchor beam and anchor pole.Material is Q345qD, two systems are about 7000 tons total.Specific construction is as follows, constructs schematic diagram as shown in figs 1-9:
(1) Step 1: construction open caisson well lid:
1) open caisson well lid is poured, 1 after-pouring of anchor beam upport installation portion position is reserved above well lid, after open caisson well lid pours, 1 two sides of anchor beam upport installation portion position are respectively anchor beam bracket stepped area 2 and anchor pole bracket stepped area 11, the anchor pole Bracket stepped area 11 is divided for middle anchor pole stent area 111 and preceding anchor face anchor pole bracket stepped area 112;
(2) step 2: 2 concreting in lifts of anchor beam bracket stepped area:
1) concreting in lifts is carried out in anchor beam bracket stepped area 2 form anchor beam bracket ladder 6;
2) anchor beam bracket built-in fitting 4 is buried on every layer of anchor beam bracket ladder 2;
(3) step 3: installation anchor beam bracket 7 and anchor beam 8:
1) the anchor beam bracket built-in fitting 4 and anchor beam bracket ladder being mounted on anchor beam bracket 7 at anchor beam upport installation portion position 1 On anchor beam bracket built-in fitting 4 on 6, while anchor beam bracket 7 is reinforced;
2) anchor beam 8 is installed on anchor beam bracket 7, and adjusts position, several bracket tie points are uniformly provided on the anchor beam 8 81;
3) concrete block for anchor pole bracket stepped area 11 of constructing simultaneously forms anchor pole branch in anchor pole bracket stepped area 11 Frame concrete step 9 buries anchor pole bracket built-in fitting 5 on every layer of anchor pole bracket concrete step 9;
(4) step 4: installation anchor beam 8 and anchor pole bracket:
1) continue that anchor beam 8 is installed, and adjust position;
2) the middle anchor pole stent area 111 being simultaneously mounted on the first anchor pole bracket 71 on anchor pole bracket concrete step 9 On the anchor pole bracket built-in fitting 5 at place, the preceding anchor face anchor pole that 72 bracket of the second anchor pole is mounted on anchor pole bracket concrete step 9 On anchor pole bracket built-in fitting 5 at bracket stepped area 112;
(5) step 5: installing first anchor pole 10, pours first layer anchor block concrete layer 3:
1) anchor pole 10 is installed in batches, each batch anchor pole 10 carries out a point root and installs, by first 10 rear end of anchor pole Bracket is mounted on the bracket tie point 81 of the anchor beam 8 anchor pole 10 simultaneously and is connected to the first anchor pole bracket 71 and the second anchor On bar bracket 72, and position is adjusted, completes the construction of first anchor pole 10;
2) construction first layer anchor block concrete layer 3, first layer anchor block concrete layer 3-1 ' as shown in Figure 5;
(6) step 6: installation second batch anchor pole 10 pours second and third layer of anchor block concrete layer 3:
1) high second anchor pole bracket 72 is connect;
2) bracket of 10 rear end of second batch anchor pole is mounted on on the bracket tie point 81 of the anchor beam 8 anchor pole simultaneously 10 are connected on the first anchor pole bracket 71 and the second anchor pole bracket 72, and adjust position, complete second batch anchor pole 10 and construct;
3) construction second and third layer concrete layer 3 of anchor block, the second layer anchor block concrete layer 3-2 ' as shown in FIG. 6, institute State third layer anchor block concrete layer 3-3 ' as shown in FIG. 6;
(7) step 7: installation third batch anchor pole 10 pours third to five layers of anchor block concrete layer 3;
1) high first anchor pole bracket 71 and the second anchor pole bracket 72 are connect, the first anchor pole bracket 71 and the second anchor pole bracket 72 are used Fashioned iron welding;
2) bracket of third batch 10 rear end of anchor pole is mounted on the bracket tie point 81 of the anchor beam 8 anchor pole simultaneously 10 are connected on the first anchor pole bracket 71 and the second anchor pole bracket 72, and adjust position, complete third batch anchor pole 10 and construct;
3) construction-five layer concrete layer 3 of anchor block third, third layer anchor block concrete layer 3-3 ' as shown in Figure 7, institute State the 4th layer of anchor block concrete layer 3-4 ' as shown in Figure 5, layer 5 anchor block concrete layer 3-5 ' as shown in Figure 8;
(8) step 8: the 4th batch of anchor pole 10 of installation pours the six to nine layer of anchor block concrete layer 3;
1) bracket of the 4th batch of 10 rear end of anchor pole is mounted on on the bracket tie point 81 of the anchor beam 8 anchor pole simultaneously 10 are connected on the first anchor pole bracket 71 and the second anchor pole bracket 72, and adjust position, complete the 4th batch of anchor pole 10 and construct;
3) construction the 6th-nine layer concrete layer of anchor block, layer 6 anchor block concrete layer 3-6 ' as shown in Figure 8, institute State layer 7 anchor block concrete layer 3-7 ' as shown in Figure 8, the 8th layer of anchor block concrete layer 3-8 ' as shown in Figure 8, institute State the 9th layer of anchor block concrete layer 3-9 ' as shown in Figure 8;
(9) step 9: continue anchor block construction:
1) after the completion of rockbolt installation, continue the tenth-ten eight layer of anchor block concrete layer of construction, the described ten layer of anchor block concrete Layer 3-10 ' as shown in Figure 9, eleventh floor anchor block concrete layer 3-11 ' as shown in Figure 9, the Floor 12 anchor block Concrete layer 3-12 ' as shown in Figure 9, the 13rd layer of anchor block concrete layer 3-13 ' as shown in Figure 9, the described 14th Layer anchor block concrete layer 3-14 ' as shown in Figure 9, the 15th layer of anchor block concrete layer 3-15 ' as shown in Figure 9, it is described 16th layer of anchor block concrete layer 3-16 ' as shown in Figure 9, the 17th layer of anchor block concrete layer 3- as shown in Figure 9 17 ', the 18th layer of anchor block concrete layer 3-18 ' as shown in Figure 9, anchor block concrete layer is constructed to 18 layers, construction The height of anchor block concrete layer 3 is 51.66m.
Embodiment 2
Based on the above embodiment 1, as shown in Figure 1, open caisson well lid of constructing in the step 1, using piecemeal, the side of layering Formula pours open caisson well lid.It can prevent the well lid poured from opening using piecemeal, placement layer by layer well lid according to temperature controlled requirement It splits.In the present embodiment, other contents not described are same as the previously described embodiments, and details are not described herein again.
Embodiment 3
Based on the above embodiment 1, as shown in figures 5-9, the anchor block concrete layer 3 is in addition to the last layer, every layer height phase Together.The every layer height customized according to concrete-pouring template is identical, and therefore, the every layer of construction height of anchor block concrete layer 3 is identical, no With each adjustment, facilitate construction.Under normal circumstances, every layer height of concrete-pouring template customization is 3m.In the present embodiment, The content that it is not described is same as the previously described embodiments, and details are not described herein again.
Embodiment 4
Based on the above embodiment 1, the first anchor pole bracket 71 and the second anchor pole bracket 72 include interconnected Several segments truss element.First anchor pole bracket 71 and the second anchor pole bracket 72 include several truss elements can be in order to the first anchor pole Bracket 71 and the second anchor pole bracket 72 realize segmentation installation, the case where so as to according to practical rockbolt installation, adjust the first anchor pole branch The height of frame 71 and the second anchor pole bracket 72.Several segments truss element can in such a way that flanged joint etc. is detachably connected, Mode can also be fixedly connected with using welding etc..In the present embodiment, several segments truss element can be used and is detachably connected such as method Orchid connection, is fixedly connected with mode such as welding manner, these connection types customary means known to those skilled in the art, because This, is no longer carried out to means required for its connection type and using tool required for the connection type detailed superfluous herein It states.In the present embodiment, other contents not described are same as the previously described embodiments, and details are not described herein again.
Embodiment 5
Based on the above embodiment 1 or 4, as Figure 7-9, the first anchor pole bracket 71 and the second anchor pole bracket 72 are adopted It is fixedly connected with fashioned iron 15.Can making the first anchor pole bracket 71 and the second anchor pole bracket 72, more securely entirety is more The stabilization added.In the present embodiment, other contents not described are same as the previously described embodiments, and details are not described herein again.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, it is noted that all Made any modifications, equivalent replacements, and improvements etc. within the spirit and principles in the present invention should be included in guarantor of the invention Within the scope of shield.

Claims (5)

1. a kind of form of construction work of anchorage anchor system, which comprises the steps of:
(1) Step 1: construction open caisson well lid:
1) open caisson well lid is poured, anchor beam upport installation portion position, after open caisson well lid pours, the anchor are reserved above the well lid poured Boom support installation position two sides are respectively anchor beam bracket stepped area and anchor pole bracket stepped area, anchor pole bracket stepped region Domain is divided into middle anchor pole stent area and preceding anchor face anchor pole bracket stepped area;
2) anchor beam bracket built-in fitting is set at anchor beam upport installation portion position, it is pre- that anchor pole bracket is equipped in middle anchor pole stent area Embedded part;
(2) step 2: anchor beam bracket step region subdivision casting concrete:
1) concreting in lifts is carried out in anchor beam bracket stepped area form anchor beam bracket ladder;
2) anchor beam bracket built-in fitting is buried on every layer of anchor beam bracket ladder;
(3) step 3: installation anchor beam bracket and anchor beam:
1) anchor on anchor beam bracket built-in fitting and anchor beam bracket ladder anchor beam bracket being mounted at anchor beam upport installation portion position On boom support built-in fitting, while anchor beam bracket is reinforced;
2) anchor beam is installed on anchor beam bracket, and adjusts position, several brackets connecting with anchor pole are uniformly provided on the anchor beam Tie point;
3) concrete block for anchor pole bracket stepped area of constructing simultaneously forms anchor pole bracket concrete in anchor pole bracket stepped area Step buries anchor pole bracket built-in fitting on every layer of anchor pole bracket concrete step;
(4) step 4: installation anchor beam and anchor pole bracket:
1) continue that anchor beam is installed, and adjust position;
2) the anchor pole branch being simultaneously mounted on the first anchor pole bracket at the middle anchor pole stent area on anchor pole bracket concrete step On frame built-in fitting, the second anchor pole bracket is mounted at the preceding anchor face anchor pole bracket stepped area on anchor pole bracket concrete step Anchor pole bracket built-in fitting on;
(5) step 5: installation anchor pole, and successively pour anchor block concrete layer:
1) anchor pole is installed in batches, each batch anchor pole carries out a point root and installs, and the bracket of the anchor pole rear end is mounted on institute It states on the bracket tie point of anchor beam while the anchor pole being connected on the first anchor pole bracket and the second anchor pole bracket, and adjust position It sets, is fixed temporarily, complete anchor bolt construction;
2) after the completion of anchor bolt construction described in each batch, anchor block concrete layer of successively constructing, the level of the anchor block concrete layer Face the anchor beam bracket tie point of anchor pole bracket and is not installed with the anchor beam bracket tie point of anchor pole bracket to being equipped with Between;
3) it after the completion of anchor bolt construction described in a batch, successively constructs after anchor block concrete layer, carries out the anchor bolt construction of next batch With construction anchor block concrete layer;
4) after completion anchor block concrete layer is completed and constructed to N batch anchor bolt construction, before N+1 batch installs anchor pole, High first anchor pole bracket or the second anchor pole bracket are connect, the N+1 times anchor bolt construction is carried out;The N is anchor pole batch number, is greater than Or the integer equal to 1;
(6) step 6: continue anchor block construction:
After the completion of rockbolt installation, continue the construction of anchor block concrete layer.
2. a kind of form of construction work of anchorage anchor system according to claim 1, which is characterized in that applied in the step 1 Work open caisson well lid, pours open caisson well lid by the way of piecemeal, layering.
3. a kind of form of construction work of anchorage anchor system according to claim 1, which is characterized in that the anchor block concrete For layer in addition to the last layer, every layer height is identical.
4. a kind of form of construction work of anchorage anchor system according to claim 1, which is characterized in that the first anchor pole branch Frame and the second anchor pole bracket include several segments truss element interconnected.
5. a kind of form of construction work of anchorage anchor system according to claim 1 or 4, which is characterized in that first anchor Bar bracket is fixedly connected with the second anchor pole bracket using fashioned iron.
CN201811272730.1A 2018-10-29 2018-10-29 Construction mode of anchorage anchoring system Active CN109468954B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811272730.1A CN109468954B (en) 2018-10-29 2018-10-29 Construction mode of anchorage anchoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811272730.1A CN109468954B (en) 2018-10-29 2018-10-29 Construction mode of anchorage anchoring system

Publications (2)

Publication Number Publication Date
CN109468954A true CN109468954A (en) 2019-03-15
CN109468954B CN109468954B (en) 2021-01-05

Family

ID=65666443

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811272730.1A Active CN109468954B (en) 2018-10-29 2018-10-29 Construction mode of anchorage anchoring system

Country Status (1)

Country Link
CN (1) CN109468954B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080110A (en) * 2019-04-17 2019-08-02 中交二航局第四工程有限公司 A kind of extra-long rod element multiple spot space-location method
CN110886218A (en) * 2019-12-02 2020-03-17 湖北省路桥集团有限公司 Main cable profile steel anchoring system of large-span suspension bridge and construction method
CN111501548A (en) * 2020-04-22 2020-08-07 中交一公局集团有限公司 Anchor block structure and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000054321A (en) * 1998-08-07 2000-02-22 Sumitomo Constr Co Ltd Installation of oblique cable
WO2001004039A1 (en) * 1999-07-13 2001-01-18 Bouygues Batiment Method and device for stabilising a mast constructed by successive platforms and applications
CN101260651A (en) * 2008-04-25 2008-09-10 中交第二航务工程局有限公司 Method and device for accomplishing self-balancing load and anchoring temporarily between main beam and platform
JP4329212B2 (en) * 2000-03-14 2009-09-09 鹿島建設株式会社 Anchoring structure of main cable of suspension bridge to anchorage
CN102425115A (en) * 2011-11-11 2012-04-25 中铁大桥局股份有限公司 Control method for actively overcoming dead weight and line shape of vice cable saddle buttress concrete
CN204455823U (en) * 2015-01-30 2015-07-08 中交二公局第二工程有限公司 A kind of suspension bridge push-and-pull rod anchor system
CN106087710A (en) * 2016-08-08 2016-11-09 上海市政工程设计研究总院(集团)有限公司 A kind of king-post steel reinforced concrete transition structure
CN205711746U (en) * 2016-06-02 2016-11-23 中铁第四勘察设计院集团有限公司 A kind of mixing cable beam anchoring structure
CN108316148A (en) * 2018-03-19 2018-07-24 湖南路桥建设集团有限责任公司 A kind of construction method and support construction of suspension bridge shaped steel anchor system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000054321A (en) * 1998-08-07 2000-02-22 Sumitomo Constr Co Ltd Installation of oblique cable
WO2001004039A1 (en) * 1999-07-13 2001-01-18 Bouygues Batiment Method and device for stabilising a mast constructed by successive platforms and applications
JP4329212B2 (en) * 2000-03-14 2009-09-09 鹿島建設株式会社 Anchoring structure of main cable of suspension bridge to anchorage
CN101260651A (en) * 2008-04-25 2008-09-10 中交第二航务工程局有限公司 Method and device for accomplishing self-balancing load and anchoring temporarily between main beam and platform
CN102425115A (en) * 2011-11-11 2012-04-25 中铁大桥局股份有限公司 Control method for actively overcoming dead weight and line shape of vice cable saddle buttress concrete
CN204455823U (en) * 2015-01-30 2015-07-08 中交二公局第二工程有限公司 A kind of suspension bridge push-and-pull rod anchor system
CN205711746U (en) * 2016-06-02 2016-11-23 中铁第四勘察设计院集团有限公司 A kind of mixing cable beam anchoring structure
CN106087710A (en) * 2016-08-08 2016-11-09 上海市政工程设计研究总院(集团)有限公司 A kind of king-post steel reinforced concrete transition structure
CN108316148A (en) * 2018-03-19 2018-07-24 湖南路桥建设集团有限责任公司 A kind of construction method and support construction of suspension bridge shaped steel anchor system

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
涂哲: "清水河大桥锚碇总体施工技术", 《公路》 *
肖仕周: "海外大型悬索桥型钢锚固系统安装定位技术", 《公路》 *
葛文璇: "南京长江四桥北锚碇工程锚体及锚固系统施工技术", 《施工技术》 *
贾红兵: "海上大跨径悬索桥锚固板锚固系统关键施工技术", 《公路交通科技 应用技术版》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080110A (en) * 2019-04-17 2019-08-02 中交二航局第四工程有限公司 A kind of extra-long rod element multiple spot space-location method
CN110886218A (en) * 2019-12-02 2020-03-17 湖北省路桥集团有限公司 Main cable profile steel anchoring system of large-span suspension bridge and construction method
CN111501548A (en) * 2020-04-22 2020-08-07 中交一公局集团有限公司 Anchor block structure and construction method thereof
CN111501548B (en) * 2020-04-22 2021-11-19 中交一公局集团有限公司 Anchor block structure and construction method thereof

Also Published As

Publication number Publication date
CN109468954B (en) 2021-01-05

Similar Documents

Publication Publication Date Title
CN109468954A (en) A kind of form of construction work of anchorage anchor system
CN108660935B (en) A kind of construction method of reinforced concrete arch bridge
CN101117795A (en) Mounting method for steel case basket arch single-frame segment
CN106120568A (en) Cross a river Main Bridge bridge pier secondary locking temporary consolidation structure and construction method
CN107905124B (en) A kind of symmetrical expression rigid frame-continuous girder construction technology
CN105568870B (en) For the triangle hanging basket method cantilever device and its construction method of cross-line bridge construction
CN107905111B (en) A kind of rigid frame-continuous girder end bay construction technology
CN102230313A (en) Bridge thin-wall hollow-pier chain block hoisting operation platform and construction method thereof
CN209211279U (en) A kind of strutting system of pier top Cast-in-situ Beam
CN109505243A (en) Cable-stayed bridge combination beam bridge floor anti-cracking method
CN208668279U (en) Pier cap beam anchor ear girder steel template system
CN107326816A (en) A kind of method for improving of prefabricated pinner and bridge
CN106121249B (en) A kind of plug-in board construction method of the overall assembled building based on BIM technology
CN106012849B (en) A kind of cantilever casting beam straightway steel bar overall binding construction method for hanging and bridge
CN108661169A (en) A kind of assembled marginal frame beam component and design method
CN108018781A (en) A kind of big segment double-template system of self-crawling type and its construction method for bridge tower construction
CN105672568A (en) Stratified casting construction method of super-large-section stiffened concrete transfer beam
CN209128892U (en) A kind of mixed type support system
CN112482188B (en) Arch bridge reinforced structure and construction method thereof
CN109162437A (en) Integral steel platform and its construction method for more steel plate shear force walls
CN111519530A (en) Pier head type tunnel anchor and construction method
CN207296399U (en) Continuous placing is molded overall assembled stair template system
CN207727438U (en) A kind of big segment double-template system of self-crawling type for bridge tower construction
CN217106190U (en) High-low grade beam column node concrete interception structure
CN109267489A (en) A kind of Anchorage Zone of Cable-stayed Bridge Pylon construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant