CN109457693A - A kind of mixing pile working ship waterborne - Google Patents

A kind of mixing pile working ship waterborne Download PDF

Info

Publication number
CN109457693A
CN109457693A CN201811385414.5A CN201811385414A CN109457693A CN 109457693 A CN109457693 A CN 109457693A CN 201811385414 A CN201811385414 A CN 201811385414A CN 109457693 A CN109457693 A CN 109457693A
Authority
CN
China
Prior art keywords
hull
pile
working ship
pile body
lantern ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811385414.5A
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Zhuwei Technology Co.,Ltd.
Original Assignee
Xinye Jiujiu Global Science And Technology (beijing) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinye Jiujiu Global Science And Technology (beijing) Co Ltd filed Critical Xinye Jiujiu Global Science And Technology (beijing) Co Ltd
Priority to CN201811385414.5A priority Critical patent/CN109457693A/en
Publication of CN109457693A publication Critical patent/CN109457693A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Structural Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Combustion & Propulsion (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The present invention provides a kind of mixing pile working ship waterborne, comprising: hull, opposite sides are provided with buoyancy tank, and the stem of hull is provided with piling machine;Guide pile, it is set to the mounting structure of buoyancy tank and/or hull, including pile body and it is installed on the upright driving mechanism of mounting structure, pile body vertical motion under the driving of upright driving mechanism has the second position for separating and withdrawing hull inside insertion soft base with the first position of fixed hull and with soft base.Above-mentioned working ship drives pile body to can be inserted into inside soft base by upright driving mechanism, since pile body is rigid structure, the flowing for protruding into water behind soft base inside can not be such that pile body is displaced, stability with higher, this allows working ship is stable to rest on the water surface, increases stability of the working ship in piling on the water surface.Upright driving mechanism driving pile body separates with soft base and withdraws hull, and the drag effect that can avoid soft base and water hinders working ship normal walking on the water.

Description

A kind of mixing pile working ship waterborne
Technical field
The present invention relates to the technical fields of pile driving equipment, and in particular to a kind of mixing pile working ship waterborne.
Background technique
It is American-European-Japanese to begin to reclaim fields from the sea early in eighties of last century in order to solve the problems, such as coastal area land used anxiety, I State also reclaims fields from the sea since the beginning of this century on a large scale.China has been the big country to reclaim fields from the sea at present, builds using face increasing Also related problem has been caused while product.Due to reclaiming fields from the sea on a large scale, sandstone exhaustive exploitation is caused, is greatly destroyed Ecological environment, country has put into effect relevant policies thus, forbids employing sandstone and reclaim fields from the sea.It follows that adopting new technology, green wood Material and new equipment substitution sandstone reclaim fields from the sea being particularly important.In coastal area, sandstone is substituted using cement mixing pile Carrying out treatment of soft foundation is one of solution to the problem.
Cement mixing pile is a kind of using cement as the host agent of curing agent, and cement is sprayed into soft base using mixing pile working ship And be sufficiently stirred, make cement and soft base that a series of physical chemical reaction occur, weak soil is made to harden and improve foundation strength.
Currently, as water transport engineering project cause continues to develop, under the drive of the Belt and Road economy, at China's underwater It is more and more to manage engineering project.Engineering project needs are handled to adapt to underwater, the country has had developed some mixing piles waterborne Working ship.However mixing pile working ship waterborne in the prior art on the water operation when, need first to fix hull, fix master If hoist engine is arranged on hull, an anchor is fixed on the wirerope of hoist engine, anchor, which is dished out, makes it fix underwater mud In soil, hull is fixed to realize.Since wirerope is easily influenced by water flow etc., thus keep the position of hull mobile, ship The stability of body is poor, and leading to the installation site of cement mixing pile, there are deviations, influences going on smoothly for engineering.
Summary of the invention
Therefore, the technical problem to be solved in the present invention is that overcoming mixing pile working ship waterborne in the prior art on the water Stability difference defect, to provide a kind of mixing pile working ship waterborne.
In order to solve the above technical problem, the present invention provides a kind of mixing pile working ships waterborne, comprising:
Hull, opposite sides are provided with buoyancy tank, and the stem of the hull is provided with piling machine;
Guide pile, is set to the mounting structure of the buoyancy tank and/or the hull, including pile body and is installed on the peace The upright driving mechanism of assembling structure, pile body vertical motion under the driving of the upright driving mechanism have insertion soft base Inside is with the first position of the fixation hull and separates and withdraw the second position of the hull with the soft base.
Optionally, the upright driving mechanism includes the first lantern ring for being sheathed on the pile body, and, it is set to the peace The first hydraulic cylinder between assembling structure and first lantern ring, first hydraulic cylinder drive institute by first lantern ring State pile body vertical motion.
Optionally, mounting base is provided on the mounting structure, the mounting base, which is provided with, is sheathed on the pile body periphery The second lantern ring, second lantern ring other side is equipped with first hydraulic cylinder.
Optionally, second lantern ring is detachably connected with the mounting base, and the mounting base is additionally provided with pitch drives Mechanism, the tilt drive mechanism include the bracket for being fixedly installed in the mounting base, are sheathed on the third lantern ring of the pile body And third hydraulic cylinder;The third, which is covered, is pivotally mounted to the bracket around first axle, has relative to described the The swing arm that one axis radially extends;Third hydraulic cylinder both ends are hinged with the mounting base and the swing arm respectively, in institute State drives the pile body to rotate around the first axle when the second lantern ring is separated with the mounting base by the third lantern ring, turns The pile body has the third place perpendicular to the hull and is parallel to the 4th position of the hull during dynamic.
Optionally, the guide pile includes sliding guide pile and stationary positioned stake, the installation of the sliding guide pile Structure includes pedestal and the horizontal drive mechanism for being set to the pedestal;The mounting base is installed on the base along linear slide Seat, the horizontal drive mechanism drive the mounting base to slide relative to the pedestal, the installation of the stationary positioned stake Structure is fixedly installed in the buoyancy tank and/or the hull.
Optionally, the sliding guide pile includes at least two connected installations for being slideably positioned in the pedestal Seat, the mounting base are correspondingly arranged on the pile body, the upright driving mechanism and the tilt drive mechanism;The horizontal drive Motivation structure is the 4th hydraulic cylinder connecting with mounting base described in one of them.
Optionally, the hull tail end is provided with the stationary positioned stake, and it is fixed that the buoyancy tank tail end is provided with the sliding Position stake;The glide direction of the sliding guide pile is parallel to the ship length direction.
Optionally, the piling machine, the buoyancy tank and the hull are detachably connected.
It optionally, further include the driver's cabin for being located at the stem of the buoyancy tank and the power list positioned at the hull aft Member, the power unit provide electric power and hydraulic power for the mixing pile working ship waterborne.
It optionally, further include grouting pump and storage bin on the hull, the storage bin and the grouting pump connect It connects, curing agent is filled in the storage bin and fixative can be made to mortar, the mortar in the storage bin passes through the slip casting Pump injects in the stirring-head of the piling machine.
Technical solution of the present invention has the advantages that
1. a kind of mixing pile working ship waterborne provided by the invention, by the way that buoyancy tank is arranged in hull opposite sides, in hull Stem be arranged piling machine, so that working ship is walked on the water and carry out piling work.There is installation on buoyancy tank and/or hull Structure, guide pile include pile body and the upright driving mechanism that is mounted on mounting structure, and upright driving mechanism can drive pile body It moves in the vertical direction, can be inserted into pile body inside soft base.Since pile body is rigid structure, the stream of water behind soft base inside is protruded into Dynamic pile body to be made to be displaced, stability with higher, this allows working ship is stable to rest on the water surface, increases Stability of the working ship in piling on the water surface.Upright driving mechanism can also drive pile body to separate with soft base and withdraw ship Body will not hinder working ship on the water because of soft base and the drag effect of water in this way when working ship needs to continue to walk on the water Normal walking.
2. a kind of mixing pile working ship waterborne provided by the invention, after the second lantern ring is disassembled from mounting base, the After three hydraulic cylinders drive pile body to turn to the 4th position parallel with hull around first axle by third lantern ring, reduce in this way The space occupancy volume of pile body in the vertical direction, i.e. reduction working ship occupy space, convenient for the navigation and transport of working ship, Bracket is installed between third lantern ring and mounting base, when pile body is parallel with hull, can be used for supporting pile body, reduce pile body and apply The pressure being added on third hydraulic cylinder, when pile body turns to the position perpendicular to hull, bracket is available and supports pile body, makes Pile body is stablized in upright position.
3. a kind of mixing pile working ship waterborne provided by the invention, guide pile includes sliding guide pile and stationary positioned Stake, slides and is provided with horizontal drive mechanism on the mounting structure of guide pile, horizontal drive mechanism can drive installation seat opposite base Sliding, mounting base are provided with the second lantern ring for being sheathed on pile body periphery, such horizontal drive mechanism drive installation seat opposite base When sliding, pile body and the second lantern ring, upright driving mechanism and tilt drive mechanism follow mounting base synchronous slide, are reached with this and are pushed away The mobile purpose of dynamic hull.Further, the synergy of horizontal drive mechanism and the second lantern ring can fix pile body, prevent stake Body is deviated towards the direction of the first hydraulic cylinder, can be toggled between the first position and the second position.
4. a kind of mixing pile working ship waterborne provided by the invention, the tail end of hull are provided with stationary positioned stake, buoyancy tank tail End is provided with sliding guide pile;The glide direction of sliding guide pile is parallel to ship length direction, in this way when stationary positioned stake Pile body is in the second position and slides the pile body of guide pile when be in first position, and horizontal drive mechanism can drive shifting before and after buoyancy tank It is dynamic, so that hull be driven to be moved forward and backward;Second is in when the pile body of stationary positioned stake is in first position and slides guide pile When setting, horizontal drive mechanism can drive buoyancy tank to rotate around stationary positioned stake, thus drive hull that can also rotate around stationary positioned stake, The traffic direction of working ship adjustable in this way, while can increase the piling range of working ship.
5. a kind of mixing pile working ship waterborne provided by the invention, piling machine, buoyancy tank and hull are detachably connected, in work When the piling of journey ship is completed to need to carry out hauling operation, can piling machine and buoyancy tank be unloaded and are placed on hull from hull, this Sample can reduce working ship horizontal footprint and vertical duty space, convenient for the transport of working ship.
6. driver's cabin, is arranged in the stem of buoyancy tank, piling machine is set by a kind of mixing pile working ship waterborne provided by the invention The stem in hull is set, is conducive to drive the condition of construction that indoor driver observes piling machine in time in this way, it is problematic It is easy to adjustment in time.
Detailed description of the invention
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art Embodiment or attached drawing needed to be used in the description of the prior art be briefly described, it should be apparent that, it is described below Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor It puts, is also possible to obtain other drawings based on these drawings.
Fig. 1 is the schematic diagram of the mixing pile working ship waterborne provided of the invention;
Fig. 2 is the enlarged drawing at the A in Fig. 1;
Fig. 3 is the top view of mixing pile working ship waterborne provided by the invention;
Fig. 4 is the schematic diagram that mixing pile working ship waterborne provided by the invention is rotated around the stationary positioned stake of hull.
Description of symbols:
1, hull;
2, guide pile;21, upright driving mechanism;211, the first hydraulic cylinder;212, the first lantern ring;22, the second lantern ring; 23, tilt drive mechanism;231, bracket;232, third lantern ring;233, third hydraulic cylinder;24, horizontal drive mechanism;25, stake Body;
3, buoyancy tank;
4, piling machine;
5, driver's cabin;
6, power unit;
7, grouting pump;
8, storage bin.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with attached drawing, it is clear that described implementation Example is a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill Personnel's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to Convenient for description the present invention and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation, It is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.In addition, term " first ", " second ", " third " is used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can To be mechanical connection, it is also possible to be electrically connected;It can be directly connected, can also can be indirectly connected through an intermediary Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood at this with concrete condition Concrete meaning in invention.
As long as in addition, the non-structure each other of technical characteristic involved in invention described below different embodiments It can be combined with each other at conflict.
A kind of specific embodiment of mixing pile working ship waterborne as shown in Figures 1 to 4, the mixing pile working ship waterborne Including hull 1 and guide pile 2, the opposite sides of hull 1 is provided with buoyancy tank 3, and the stem of hull 1 is provided with piling machine 4, makes engineering Ship can walk on the water and carry out piling work.
Guide pile 2 is set to the mounting structure of buoyancy tank 3 and/or hull 1, including pile body 25 and is installed on mounting structure Upright driving mechanism 21.Upright driving mechanism 21 includes the first lantern ring 212 for being sheathed on pile body 25, and, it is set to installation knot The first hydraulic cylinder 211 between structure and the first lantern ring 212.First hydraulic cylinder 211 drives pile body 25 by the first lantern ring 212 Vertical motion has pile body 25 inside insertion soft base to separate with the first position of fixed hull 1 and with soft base and withdraw hull 1 The second position.
The output elongate axis of first hydraulic cylinder 211 can be such that pile body 25 separates with soft base and be retracted to hull 1, same with this When, hull 1 sinks, and in this way when working ship needs to continue to walk on the water, will not hinder work because of soft base and the drag effect of water Journey ship normal walking on the water.The output shaft of first hydraulic cylinder 211 shortens, and can make 2 vertical motion of guide pile until being inserted into soft It, can be with fixed hull 1 inside base.Since pile body 25 is rigid structure, the flowing for protruding into water behind soft base inside can not make pile body 25 It is displaced, stability with higher, this allows working ship is stable to rest on the water surface, increases working ship piling When stability on the water surface.
Mounting base is provided on mounting structure, mounting base detachably connects with the second lantern ring 22 for being sheathed on 25 periphery of pile body It connects, the other side of the second lantern ring 22 is equipped with the first hydraulic cylinder 211.Mounting base is additionally provided with tilt drive mechanism 23.Inclination Driving mechanism 23 includes the bracket 231 for being fixedly installed in mounting base, and third lantern ring 232 and the third for being sheathed on pile body 25 are hydraulic Oil cylinder 233.Third lantern ring 232 is pivotally mounted to bracket 231 around first axle, with what is radially extended relative to first axle Swing arm.233 both ends of third hydraulic cylinder are hinged with mounting base and swing arm respectively, pass through when the second lantern ring 22 is separated with mounting base Third lantern ring 232 drives pile body 25 to rotate around first axle, and pile body 25 has the third place perpendicular to hull 1 in rotation process With the 4th position for being parallel to hull 1.
After second lantern ring 22 is disassembled from mounting base, third hydraulic cylinder 233 drives stake by third lantern ring 232 After body 25 turns to the 4th position parallel with hull 1 around first axle, the sky of pile body 25 in the vertical direction is reduced in this way Between occupancy volume, i.e. reduction working ship occupies space, can be convenient for the navigation and transport of working ship, in third lantern ring 232 and installation Bracket 231 is installed between seat, when pile body 25 is parallel with hull 1, can with support pile body 25, reduction pile body 25 is applied to the Pressure on three hydraulic cylinders 233, when pile body 25 turns to the position perpendicular to hull 1, bracket 231 can with support pile body 25, stablize pile body 25 in upright position.
With no restriction for the mode being detachably connected between the second lantern ring 22 and mounting base, it is, for example, possible to use spiral shells It tethers and connects, also just using the retaining mechanism with locking and release conditions.
Guide pile 2 includes sliding guide pile and stationary positioned stake, and the mounting structure for sliding guide pile includes pedestal and setting In the horizontal drive mechanism 24 of pedestal;Mounting base is installed on pedestal, 24 drive installation seat phase of horizontal drive mechanism along linear slide Pedestal is slided.At least two connected mounting bases for being slideably positioned in pedestal are correspondingly arranged on pile body 25, vertical driving machine Structure 21 and tilt drive mechanism 23.Horizontal drive mechanism 24 is the 4th hydraulic cylinder connecting with one of mounting base.In this way When the output elongate axis of the 4th hydraulic cylinder, mounting base, pile body 25, upright driving mechanism 21 and tilt drive mechanism 23 are slided backward It is dynamic, so that hull 1 be pushed to move ahead forward;When the output shaft of 4th hydraulic cylinder shortens, mounting base, pile body 25, vertical driving machine 23 forward slip of structure 21 and tilt drive mechanism, so that hull 1 be pushed to retreat backward.Further, horizontal drive mechanism 24 with The synergy of second lantern ring 22 can fix pile body 25, prevent pile body 25 from deviating towards the direction of the first hydraulic cylinder 211, make It can be toggled between the first position and the second position.
The mounting structure of stationary positioned stake is fixedly installed in buoyancy tank 3 and/or hull 1.
In the present embodiment, the tail end of hull 1 is provided with stationary positioned stake, and 3 tail end of buoyancy tank is provided with sliding guide pile;Sliding The glide direction of guide pile is parallel to 1 length direction of hull.In this way when the pile body 25 of stationary positioned stake is in the second position and cunning When the pile body 25 of shifting guide pile is in first position, horizontal drive mechanism 24 can drive buoyancy tank 3 to be moved forward and backward, to drive hull 1 is moved forward and backward;When the pile body 25 of stationary positioned stake is in first position and sliding guide pile is in the second position, horizontal drive Mechanism 24 can drive buoyancy tank 3 to rotate around stationary positioned stake, in this way can be with to drive hull 1 that can also rotate around stationary positioned stake The traffic direction of working ship is adjusted, while can increase the piling range of working ship.
As another embodiment, sliding guide pile includes a mounting base, and pile body 25, vertical is provided in mounting base Driving mechanism 21 and tilt drive mechanism 23 may also comprise three with upper mounting seat and corresponding pile body 25, upright driving mechanism 21 and tilt drive mechanism 23.The quantity of mounting base in sliding guide pile can be arranged according to actual needs.
As another embodiment, it can be equipped with simultaneously on buoyancy tank 3 and slide guide pile and stationary positioned stake, on hull 1 Sliding guide pile and stationary positioned stake can also be installed simultaneously.Alternatively, installing stationary positioned stake on buoyancy tank 3, installed on hull 1 Slide guide pile.
Mixing pile working ship waterborne further include the stem positioned at buoyancy tank 3 driver's cabin 5 and positioned at hull 1 stern it is dynamic Power unit 6, power unit 6 provide electric power and hydraulic power for mixing pile working ship waterborne.Because hull 1 is arranged in piling machine 4 Stem is conducive to the condition of construction that the driver in driver's cabin 5 observes piling machine 4 in time in this way, problematic convenient for timely Adjustment.
Mixing pile working ship waterborne further includes the grouting pump 7 and storage bin 8 on hull 1, storage bin 8 and grouting pump 7 It connects, fill curing agent in storage bin 8 and fixative can be made to mortar, the mortar in storage bin 8 is beaten by the injection of grouting pump 7 In the stirring-head of stake machine 4.Mortar in this way in stirring-head can be injected inside soft base by the effect of piling machine 4, and mixed with soft base Conjunction is formed uniformly mixing pile.
Piling machine 4, buoyancy tank 3 and hull 1 are detachably connected.It needs to carry out hauling operation after the completion of working ship piling When, piling machine 4 and buoyancy tank 3 can be unloaded from hull 1 and are placed on hull 1, the level that can reduce working ship in this way accounts for With space and vertical duty space, convenient for the transport of working ship.
As another embodiment, the stem of hull 1 is arranged in the stern for the buoyancy tank 3 being oppositely arranged, so that opposite set Accommodation space is formed between the buoyancy tank 3 set, when needing Transportation Engineering ship time, the top half of piling machine 4 can be contained in receiving Space reduces the space occupancy volume of working ship, convenient for the transport of working ship.
The working principle of above-mentioned mixing pile working ship waterborne is as follows:
When mixing pile working ship waterborne navigates by water arrival piling construction position on the water, the output shaft contracting of the first hydraulic cylinder 211 It is short with by buoyancy tank 3 and hull 1 pile body 25 be inserted into soft base inside, to working ship is fixed on the water surface, then by storing Mortar is made in fixative in storehouse 8, and the mortar in storage bin 8 is injected by grouting pump 7 in the stirring-head of piling machine 4, carries out soft The piling work of base, after the completion of piling, when needing to expand piling range or adjusting the navigation direction of engineering department, by buoyancy tank 3 On the first hydraulic cylinder 211 output elongate axis so that it separates with soft base and withdraws on hull 1, the 4th hydraulic cylinder Output shaft shortens, and pile body 25 of the working ship on hull 1 can be made to rotate certain angle, then the first hydraulic oil on buoyancy tank 3 The output shaft of cylinder 211 shortens again is inserted into pile body 25 inside soft base, piling work is then proceeded to, after the completion of piling;Working ship When needing to move back and forth certain distance, by the output elongate axis of the first hydraulic cylinder 211 on hull 1, so that the stake on hull 1 Body 25 is separated with soft base and is withdrawn on hull 1, then the output shaft of the 4th hydraulic cylinder is stretched out or withdrawn, and makes mounting base, pile body 25, upright driving mechanism 21 and tilt drive mechanism 23 slide together, so that working ship be pushed to be moved forward and backward;Hull 1 needs to navigate When row is more remote, the bolt between the second lantern ring 22 and mounting base can be unscrewed, the second lantern ring 22 is torn open from mounting base It unloads down, then the output shaft of third hydraulic cylinder 233 is shortened, pile body 25 is made to drive the first lantern ring 212, the second lantern ring 22 and the Three lantern rings 232 turn to parallel with hull 1, navigate by water on the water convenient for working ship.
Obviously, the above embodiments are merely examples for clarifying the description, and does not limit the embodiments.It is right For those of ordinary skill in the art, can also make on the basis of the above description it is other it is various forms of variation or It changes.There is no necessity and possibility to exhaust all the enbodiments.And it is extended from this it is obvious variation or It changes still within the protection scope of the invention.

Claims (10)

1. a kind of mixing pile working ship waterborne characterized by comprising
Hull (1), opposite sides are provided with buoyancy tank (3), and the stem of the hull (1) is provided with piling machine;
Guide pile (2) is set to the mounting structure of the buoyancy tank (3) and/or the hull (1), including pile body (25) and peace Upright driving mechanism (21) loaded on the mounting structure, the pile body (25) is under the driving of the upright driving mechanism (21) Vertical motion has and is inserted into inside soft base with the first position of the fixation hull (1) and separates with the soft base and withdraw institute State the second position of hull (1).
2. mixing pile working ship waterborne according to claim 1, which is characterized in that the upright driving mechanism (21) includes It is sheathed on the first lantern ring (212) of the pile body (25), and, it is set to the mounting structure and first lantern ring (212) Between the first hydraulic cylinder (211), first hydraulic cylinder (211) passes through first lantern ring (212) and drives the stake Body (25) vertical motion.
3. mixing pile working ship waterborne according to claim 2, which is characterized in that be provided with installation on the mounting structure Seat, the mounting base are provided with the second lantern ring (22) for being sheathed on the pile body (25) periphery, and second lantern ring (22) is another Side is equipped with first hydraulic cylinder (211).
4. mixing pile working ship waterborne according to claim 3, which is characterized in that second lantern ring (22) and the peace Dress seat is detachably connected, and the mounting base is additionally provided with tilt drive mechanism (23), and the tilt drive mechanism (23) includes solid Dingan County is loaded on the bracket (231) of the mounting base, is sheathed on the third lantern ring (232) and third hydraulic oil of the pile body (25) Cylinder (233);The third lantern ring (232) is pivotally mounted to the bracket (231) around first axle, has relative to described the The swing arm that one axis radially extends;Third hydraulic cylinder (233) both ends are hinged with the mounting base and the swing arm respectively, Drive the pile body (25) around institute by the third lantern ring (232) when second lantern ring (22) separates with the mounting base First axle rotation is stated, pile body described in rotation process (25) has the third place perpendicular to the hull (1) and is parallel to 4th position of the hull (1).
5. mixing pile working ship waterborne according to claim 4, which is characterized in that the guide pile (2) includes that sliding is fixed Position stake and stationary positioned stake, the mounting structure of the sliding guide pile include pedestal and the horizontal drive for being set to the pedestal Motivation structure (24);The mounting base is installed on the pedestal along linear slide, and the horizontal drive mechanism (24) drives the peace Dress seat slided relative to the pedestal, the mounting structure of the stationary positioned stake be fixedly installed in the buoyancy tank (3) and/or The hull (1).
6. mixing pile working ship waterborne according to claim 5, which is characterized in that the sliding guide pile includes that sliding is set It is placed in at least two connected mounting bases of the pedestal, the mounting base is correspondingly arranged on the pile body (25), described Upright driving mechanism (21) and the tilt drive mechanism (23);The horizontal drive mechanism (24) be and peace described in one of them Fill the 4th hydraulic cylinder of seat connection.
7. mixing pile working ship waterborne according to claim 5 or 6, which is characterized in that hull (1) tail end is provided with The stationary positioned stake, the buoyancy tank tail end are provided with the sliding guide pile;The glide direction of the sliding guide pile is parallel In the hull (1) length direction.
8. mixing pile working ship waterborne described in any one of -7 according to claim 1, which is characterized in that the piling machine (4), The buoyancy tank (3) and the hull (1) are detachably connected.
9. mixing pile working ship waterborne according to claim 1 to 8, which is characterized in that further include positioned at described The driver's cabin (5) of the stem of buoyancy tank (3) and the power unit (6) for being located at the hull (1) stern, the power unit (6) Electric power and hydraulic power are provided for the mixing pile working ship waterborne.
10. mixing pile working ship waterborne according to claim 1 to 8, which is characterized in that further include being located at institute The grouting pump (7) and storage bin (8) on hull (1) are stated, the storage bin (8) connect with the grouting pump (7), the storage bin (8) it fills curing agent in and fixative can be made to mortar, the mortar in the storage bin (8) is infused by the grouting pump (7) In the stirring-head for entering the piling machine.
CN201811385414.5A 2018-11-20 2018-11-20 A kind of mixing pile working ship waterborne Pending CN109457693A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811385414.5A CN109457693A (en) 2018-11-20 2018-11-20 A kind of mixing pile working ship waterborne

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811385414.5A CN109457693A (en) 2018-11-20 2018-11-20 A kind of mixing pile working ship waterborne

Publications (1)

Publication Number Publication Date
CN109457693A true CN109457693A (en) 2019-03-12

Family

ID=65611121

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811385414.5A Pending CN109457693A (en) 2018-11-20 2018-11-20 A kind of mixing pile working ship waterborne

Country Status (1)

Country Link
CN (1) CN109457693A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110576942A (en) * 2019-09-29 2019-12-17 泸州市巨力液压有限公司 Pile pressing type offshore platform positioning device
CN116084409A (en) * 2022-09-07 2023-05-09 中交第四航务工程局有限公司 Cement mixing pile construction system and construction method under offshore navigation limited condition

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203142979U (en) * 2013-03-18 2013-08-21 熔盛机械有限公司 Location mechanism for dredger
JP2015058861A (en) * 2013-09-20 2015-03-30 ジャパンマリンユナイテッド株式会社 Spud carriage device and method for movement of hull
CN105464160A (en) * 2013-11-27 2016-04-06 卜建余 Double-bucket-wheel type underwater mud suction silt remover
CN207433756U (en) * 2017-09-06 2018-06-01 江苏润林船舶科技有限公司 A kind of stepless speed regulation formula amplitude-variable guide pile
CN209368812U (en) * 2018-11-20 2019-09-10 新叶九九全域科技(北京)有限公司 A kind of mixing pile working ship waterborne

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203142979U (en) * 2013-03-18 2013-08-21 熔盛机械有限公司 Location mechanism for dredger
JP2015058861A (en) * 2013-09-20 2015-03-30 ジャパンマリンユナイテッド株式会社 Spud carriage device and method for movement of hull
CN105464160A (en) * 2013-11-27 2016-04-06 卜建余 Double-bucket-wheel type underwater mud suction silt remover
CN207433756U (en) * 2017-09-06 2018-06-01 江苏润林船舶科技有限公司 A kind of stepless speed regulation formula amplitude-variable guide pile
CN209368812U (en) * 2018-11-20 2019-09-10 新叶九九全域科技(北京)有限公司 A kind of mixing pile working ship waterborne

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
徐纯武;: "中小型新式绞吸挖泥船的研究", 水利电力机械, no. 05, pages 17 - 18 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110576942A (en) * 2019-09-29 2019-12-17 泸州市巨力液压有限公司 Pile pressing type offshore platform positioning device
CN116084409A (en) * 2022-09-07 2023-05-09 中交第四航务工程局有限公司 Cement mixing pile construction system and construction method under offshore navigation limited condition
CN116084409B (en) * 2022-09-07 2023-11-03 中交第四航务工程局有限公司 Cement mixing pile construction system and construction method under offshore navigation limited condition

Similar Documents

Publication Publication Date Title
CN102653308B (en) Wind turbine is transported to ship and the method to set up thereof in " offshore " place
US20110129301A1 (en) Piling barge
CN109457693A (en) A kind of mixing pile working ship waterborne
CN109312552A (en) The unit and method of the sea bed support of shallow water probing terminal are provided
CN106677257B (en) A kind of mounting process of power plant sea taking and discharging immersed tube
CN103270221B (en) For drilling and/or exploit offshore structure and the method thereof of submarine well
CN101837929B (en) Operation method for lifting fan for barge in shoal area
CN103103972A (en) Prefabricate type nautical fixed platform and installing method
WO2010143967A2 (en) Tripod foundation
CN209368812U (en) A kind of mixing pile working ship waterborne
CN108265708A (en) Stake construction equipment
CN103119222A (en) Surface-breaking re-usable submergeable template for installing one or more submerged columns/piles
NO20092241L (en) Subsoil foundations, as well as methods for installing the foundation
CN219710296U (en) Shallow sea is from removing construction ship
CN208328938U (en) Rubble leveling device
CN208578032U (en) Stake construction equipment
CN207143999U (en) A kind of underwater immersed tube and the device for setting up underwater immersed tube
CN214530756U (en) Combined structure system of multi-pile foundation and floating type fan
CN113897848B (en) Grouting reinforcement construction method for old concrete pavement void slab
JP2024509809A (en) Undersea fixed object installation system
CN214695710U (en) Combined structure system of single-pile foundation and floating type fan
JPS5812409B2 (en) Basic equipment for boring platform
CN112814015A (en) Combined structure system of multi-pile foundation and floating type fan and single-ship installation method
JP5352002B1 (en) Ground improvement device
CN112814014A (en) Combined structure system of single-pile foundation and floating type fan and double-ship installation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20230309

Address after: 315040 Room 201, Building 9, Baolong Square, High-tech Zone, Ningbo City, Zhejiang Province

Applicant after: Zhejiang Zhuwei Technology Co.,Ltd.

Address before: 3027B, Floor 3, Building 9, No. 16, Fengguan Road, Fengtai District, Beijing, 100071

Applicant before: XINYE 99 QUANYU TECHNOLOGY (BEIJING) Co.,Ltd.