CN109441459A - A kind of earth pressure balanced shield separate launching side excavating construction method - Google Patents

A kind of earth pressure balanced shield separate launching side excavating construction method Download PDF

Info

Publication number
CN109441459A
CN109441459A CN201811391499.8A CN201811391499A CN109441459A CN 109441459 A CN109441459 A CN 109441459A CN 201811391499 A CN201811391499 A CN 201811391499A CN 109441459 A CN109441459 A CN 109441459A
Authority
CN
China
Prior art keywords
chute
soil
earth pressure
pressure balanced
gantry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811391499.8A
Other languages
Chinese (zh)
Other versions
CN109441459B (en
Inventor
林辉
吴文彪
谭荣珊
许清
舒翔
杨欢
温彦杰
钟锐华
黄春雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Water Power Urban Rail Transit Construction Co Ltd
Original Assignee
Guangdong Water Power Urban Rail Transit Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Water Power Urban Rail Transit Construction Co Ltd filed Critical Guangdong Water Power Urban Rail Transit Construction Co Ltd
Priority to CN201811391499.8A priority Critical patent/CN109441459B/en
Publication of CN109441459A publication Critical patent/CN109441459A/en
Application granted granted Critical
Publication of CN109441459B publication Critical patent/CN109441459B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A kind of earth pressure balanced shield separate launching side excavating construction method, is connected with chute at the soil-unloading port of interim gantry, and the soil outlet of chute is located at the left and right either side of interim gantry;Before shield machine driving, first soil bucket is hung under the soil outlet position of chute, then shield machine starts broken hole door driving, and quarrel soil is transported on the soil-unloading port of interim gantry by screw conveyor and belt feeder, falls to Tu Douzhong then along chute.This method is suitable for the unearthed construction of all short vertical shaft earth pressure balanced shield, EPBS separate launching stages, working space is required low, no need to increase shield well length, save engineering cost, and this method is unearthed without using hoist engine, the unearthed disadvantage of hoist engine is evaded, has had the characteristics that economical, safe and efficient.

Description

A kind of earth pressure balanced shield separate launching side excavating construction method
Technical field
The present invention relates to shield tunnel construction fields, and in particular to is unearthed a kind of earth pressure balanced shield separate launching side Construction method, this method are suitable for the unearthed construction of all short vertical shaft earth pressure balanced shield, EPBS separate launching stages.
Background technique
The unearthed operation of earth pressure balanced shield, EPBS separate launching is accident prone high risk construction link in shield-tunneling construction, at present Domestic EPB shield tunneling separate launching construction, which is unearthed, mainly takes mode or the electric haulage side of dead astern hoist engine mixed soil bucket Formula carries out construction of being unearthed.
The prior art is unable to reach safety, economy, efficient construction requirement, and mainly dead astern, which is unearthed, needs certain work Industry space need to increase shield well length to increase engineering investment cost;Due to the limitation of working space, dead astern is unearthed can not Soil bucket is transported using gantry crane, can only be in such a way that hoist engine be unearthed, hoist engine is unearthed, and there are higher safety is hidden Suffer from, especially originate the case where section is upward slope section driving, if soil bucket braking control is bad easily to occur car slipping collision and wirerope The accidents such as fracture, meanwhile, dead astern, which is unearthed to be unearthed using hoist engine, has speed slow, low efficiency, construction period long disadvantage.
Summary of the invention
In order to solve the above-mentioned technical problem the present invention, provides a kind of earth pressure balanced shield separate launching side unearthed construction Method, this method is suitable for the unearthed construction of all short vertical shaft earth pressure balanced shield, EPBS separate launching stages, low to working space requirement, No need to increase shield well length, engineering cost is saved, and this method is unearthed without using hoist engine, has evaded what hoist engine was unearthed Disadvantage has the characteristics that economical, safe and efficient.
In order to achieve the object of the present invention, used technical solution are as follows: it is seperated to provide a kind of earth pressure balanced shield Side excavating construction method is originated, interim gantry is equipped in launching shaft, is connected with chute at the soil-unloading port of interim gantry, The chute is arranged diagonally downward, and the soil outlet of the chute is located at the left and right either side of interim gantry;Before shield machine driving, first Soil bucket is hung under the soil outlet position for moving to chute, then shield machine starts broken hole door driving, quarrel soil by screw conveyor and Belt feeder is transported on the soil-unloading port of interim gantry, falls to Tu Douzhong then along chute;It carries out hanging native operation to soil bucket When, by chute disassembly or pull-up, soil bucket is sling into removal, then empty soil bucket is hung and is displaced downwardly under former chute soil outlet position, It reinstalls chute or puts down chute, re-start dress soil;After shield machine completes an endless tube piece headwork, chute is torn open It unloads or pull-up, progress side section of jurisdiction and track lifting job pacifies chute after completing section of jurisdiction and track lifting job again It fills or puts down, continue the unearthed operation in side after waiting for pipe sheet assembling.
As a further improvement of the present invention, the chute is formed by connecting by two sections of front and back chute, and two sections of front and back chute is equal Including bottom wall and the side wall being fixed at left and right sides of bottom wall, the front end of the leading portion chute is fixedly connected with soil-unloading port, described The tail end of back segment chute is equipped with soil outlet, and the objective for implementation of movement or pull-up and the movement put down of disassembly and installation is Back segment chute.
As a further improvement of the present invention, the bottom surface of the bottom wall of the two sections of chutes in front and back is respectively welded along bottom wall length side To the square steel of setting, the bottom surface of the two sidewalls of the two sections of chutes in front and back is respectively welded the square steel along the setting of sidewall width direction, institute The square steel stated on bottom wall is mutually welded with the square steel on side wall.
As a further improvement of the present invention, the square steel on the square steel and side wall on the bottom wall is 30mm square steel.
As a further improvement of the present invention, the leading portion chute is 3 meters long, 1.2 meters wide, and the back segment chute is 2.2 meters long, 1.21 meters wide, the bottom wall and left and right sides wall of two sections of front and back chute are all made of 3mm thick steel plate.
As a further improvement of the present invention, the front end of the back segment chute is connected to the bottom of leading portion chute tail end.
As a further improvement of the present invention, the front end of the tail end of leading portion chute two sidewalls and back segment chute two sidewalls On be equipped with convenient for chute installation and removal and bolt hole.
As a further improvement of the present invention, branch midleg of the interim gantry in side corresponding with chute is equipped with branch Point, and hook gear is set in the lateral roof, the hook gear is hung with chain block, and the chute is clicked through by the branch Row support installation, the chain block are connected on chute.
As a further improvement of the present invention, the gradient of the chute is 30~45%.
As a further improvement of the present invention, during shield machine is pushed ahead, interim gantry and chute promote therewith Identical distance, soil bucket remain stationary.
The invention has the benefit that
One, versatile, it is highly-safe.The method of the invention is suitable for all earth pressure balance separate launchings, especially The short Construction of Silo operating condition of water-conveyance tunnel is sufficiently used through chute in such a way that the left and right either side of interim gantry is unearthed The working space of the left and right sides can solve the problems, such as that small space limits, so that operation of being unearthed can lift up into row handling by Men Long, The unearthed problem for causing risk big of hoist engine is avoided, the security risk of operation in launching shaft is reduced.
Two, efficiently.It is constructed using the method for the invention, ensure that screw machine effectively efficiently unearthed operation, subtract The cost of labor of scaling-off cleaning in well is lacked;The method of the invention widens soil bucket using gantry crane during unearthed and carries out Dress soil, compared with the unearthed mode that hoist engine draws small soil bucket, the method for the invention greatly accelerates shield driving and is unearthed Operating efficiency shortens the shield launching period.
Three, construction quality is ensured.It is constructed using the method for the invention, greatly shortens unearthed duty cycle, Shorten shield launching and tunnel the time, so that shield machine is reinforced section soil body driving quickly through broken hole door and end, to subtract Few surface subsidence and underground water are lost;In addition, improving construction environment in well, guarantee attitude of shield machine and linear control.
Four, high financial profit.It is constructed using the method for the invention, required equipment is simple, and transport is easy;The side Method is low to working space requirement, can effectively adapt to short Construction of Silo operating condition, and no need to increase vertical shaft length, reduces the throwing to vertical shaft Money;The method simple process is feasible, can save certain labour cost and a large amount of duration costs.
Detailed description of the invention
Fig. 1 is the chute structure schematic diagram;
Fig. 2 is the unearthed structural schematic diagram in chute side;
Description of symbols: the interim gantry of 1-, 11- soil-unloading port, 12- fulcrum, 13- hook gear, 14- chain block, 2- chute, 21- leading portion chute, 211- bottom wall, 212- side wall, 213- square steel, 214- square steel, 215- bolt hole, 22- back segment chute, the bottom 221- Wall, 222- side wall, 223- square steel, 224- square steel, 225- bolt hole, 226- soil outlet.
Specific embodiment
Below in conjunction with the accompanying drawings and embodiment the invention will be further described.
Shenzhen City, Guangdong Province water-conveyance tunnel project shield-tunneling construction is using earth pressure balanced shield of the present invention point Body originates side excavating construction method.The project launching shaft, which is served only for shield machine, goes into the well and originates and transport of materials well, engineering It needs to carry out backfill processing after completion;Well design length 30m (actual job space 27.6m), this section of route longitudinal slope 1%, work Armored concrete Symmetric Beam is equipped among well, shield-tunneling construction working space is narrow.Earth pressure balanced shield, EPBS construction need to be begun using seperated Hair, but since narrow space can not be unearthed mode using conventional electric locomotive, if being unearthed again using hoist engine there are certain risk, And inefficiency, the construction period is long, while will affect the handling of section of jurisdiction.
Earth pressure balanced shield separate launching side excavating construction method, including following construction procedure:
(1) preparation of construction: surrounding enviroment investigation, levelling of the land, march into the arena road and construction site hardening, construction water, use The Facilities Constructions such as electricity, ventilation, are inspected for acceptance using plant, materials arrival, and construction drawing examines, confides a technological secret, operation people Member's safety education and training is told somebody what one's real intentions are.
(2) installation of embedded parts, job platform are set up: originating frame ruler according to portal position, shield body before shield well construction of bottom plates Very little, reaction frame structure size carries out pre-embedded steel slab installation in bottom plate in advance, and bottom plate is after the completion again in reaction frame rear I-steel Installation connecting bridge, interim gantry 1 and operation platform are simultaneously laid with track.
(3) shield machine assembly and adjustment: shield mechanism accessory site acceptance first hangs interim gantry, connecting bridge and screw machine It loads well and is moved to and originate frame rear, shield body is then lifted into assembly and connection of going into the well respectively;Secondly assembling machine lifting, spiral shell are carried out The installation of rotation machine, the connection work of connecting bridge and interim gantry 1;The oil pipe that finally ground trolley is connected, circuit are drawn to underground And be attached in shield body, shield machine debugging is carried out after the completion.
(4) the unearthed chute 2 in ground side makes: as shown in Figure 1, processing one in ground workshop during shield machine assembly and adjustment The long 3m of item, the back segment chute 22 of the leading portion chute 21 of wide 1.2m and a long 2.2m, wide 1.21m, the tail end of back segment chute 22 Equipped with soil outlet 226, two sections of front and back chute 21,22 includes bottom wall 211,221 and is fixed at left and right sides of bottom wall 211,221 Side wall 212,222, the bottom wall 211,221 and left and right sides wall 212,222 of two sections of front and back chute 21,22 are all made of 3mm thick steel plate; The bottom surface of the bottom wall 211,221 of two sections of front and back chute 21,22 is respectively welded the 30mm square steel along the setting of bottom wall length direction 213,223, the bottom surface of the two sidewalls 212,222 of two sections of front and back chute 21,22 is respectively welded along the setting of sidewall width direction 30mm square steel 214,224, the square steel 213,223 on bottom wall 211,221 and the square steel 214 on side wall 212,222,224 phases are welded, By square steel 213,214,223,224 setting can reinforce the structural strength of two sections of front and back chute 21,22;Leading portion chute 21 The part tail end 20cm and the every 10cm on the front end part 20cm of 22 two sidewalls 222 of back segment chute of two sidewalls 212 are reserved at one The bolt hole 215,225 of 22mm, in order to the installation and removal between two sections of front and back chute 21,22.
(5) the unearthed chute 2 in side is installed: as shown in Fig. 2, being connected with chute 2 at the soil-unloading port 11 of interim gantry 1, being slipped Slot 2 is arranged diagonally downward, and the soil outlet 226 of chute 2 is located at the left and right either side of interim gantry 1.Consider the self weight and quarrel of chute 2 The impact and weight that soil is fallen weld one of Two bors d's oeuveres 5# channel steel conduct in the middle part of a side leg of the installation of chute 2 on interim gantry 1 Chute intermediate support 12, chute 2 are supported installation by fulcrum 12;Two are welded at the top of the same side of interim gantry 1 to hang Hook device 13, hook gear 13 are hung with chain block 14.By the soil-unloading port 11 of the front end of leading portion chute 21 and interim gantry 1 It being connected and is welded and fixed with steel plate, chain block 14 is connected at the soil outlet 226 of back segment chute 22, two sections of front and back chute 21, 22 are attached fixation by reserved bolt hole 215,225, and when connection, the front end of back segment chute 22 is connected to leading portion chute 21 The bottom of tail end, and guarantee that back segment chute 22 can use 14 pull-up of chain block upwards.Chute 2 should ensure that chute after being installed 2 gradient is 30~45%, to guarantee the mobility of quarrel soil.
(6) shield driving side is unearthed: utilizing the chain block 14 on 22 both sides of back segment chute by back segment chute 22 before driving Soil bucket 3 (soil bucket 36.5m × 1.5m × 2.5m is transported in the normal hole of shield) is then hung to interim gantry by gantry crane by pull-up 1 unearthed side and 226 position of soil outlet for being moved to back segment chute 22 is put well, puts down back segment chute 22;Then shield machine starts brokenly Portal driving.Quarrel soil in shield machine soil storehouse is transported on the soil-unloading port 11 of interim gantry 1 by screw conveyor and belt feeder, so It is fallen in soil bucket 3 along chute 2 afterwards.As shield forward impelling about 30cm (the shield stroke of a pipeful of soil), chute 2 and interim Gantry 1 and then moves forward 30cm, and soil bucket 3 remains stationary.After last soil bucket 3 fills soil, by 22 pull-up of back segment chute, and pass through Gantry crane slings soil bucket 3 translate out 22 range of back segment chute after hang out well head, be finished down after soil to hang empty soil bucket 3 and be displaced downwardly to original and go out Under native 226 position of mouth, back segment chute 22 is put down, repeats the above steps and carries out operation of being unearthed.
(7) after shield completes endless tube piece (1.5m) headwork according to step (6), back segment chute 22 is dismantled, into Back segment chute 22 is reinstalled after completing section of jurisdiction and track handling, is waited for by row side section of jurisdiction and track lifting job Continue the unearthed operation in side by step (6) after pipe sheet assembling.
Earth pressure balanced shield, EPBS separate launching side, which is unearthed, effectively overcomes the short shaft space limitation of water-conveyance tunnel, has saved warp Ji cost.Also, side, which is unearthed, effectively avoids the unearthed existing biggish security risk of hoist engine, meanwhile, side goes out Soil also greatly accelerates shield driving speed, shortens the duration.
In conclusion test is used for multiple times in the present invention, judging from the effect of using the test, the provable present invention can reach it Desired purpose, practical value are unquestionable.Embodiment provided above is only used to conveniently illustrate the present invention, not It is intended that the present invention is limited in any way, any those of ordinary skill in the art, if not departing from the present invention In the range of mentioned technical characteristic, the equivalence enforcement locally changed or modified made by disclosed technology contents is utilized Example, and without departing from technical feature content of the invention, in the range of still falling within the technology of the present invention feature.

Claims (10)

1. a kind of earth pressure balanced shield separate launching side excavating construction method, it is characterised in that: be equipped in launching shaft Interim gantry is connected with chute at the soil-unloading port of interim gantry, and the chute is arranged diagonally downward, the soil outlet of the chute Positioned at the left and right either side of interim gantry;Before shield machine driving, first soil bucket is hung under the soil outlet position for moving to chute, then shield Structure machine starts broken hole door driving, and quarrel soil is transported on the soil-unloading port of interim gantry by screw conveyor and belt feeder, then along Chute falls to Tu Douzhong;When soil bucket carries out hanging native operation, by chute disassembly or pull-up, soil bucket is sling into removal, Then empty soil bucket is hung and is displaced downwardly under former chute soil outlet position, reinstalled chute or put down chute, re-start dress soil; After shield machine completes an endless tube piece headwork, by chute disassembly or pull-up, side section of jurisdiction and track lifting job are carried out, After completing section of jurisdiction and track lifting job, chute is reinstalled or put down, is continued after waiting for pipe sheet assembling Side is unearthed operation;The handling of above-mentioned soil bucket, section of jurisdiction and track is all made of gantry crane progress.
2. a kind of earth pressure balanced shield separate launching side according to claim 1 excavating construction method, feature exist In: the chute is formed by connecting by two sections of front and back chute, and two sections of front and back chute includes bottom wall and is fixed at left and right sides of bottom wall Side wall, the front end of the leading portion chute is fixedly connected with soil-unloading port, and the tail end of the back segment chute is equipped with soil outlet, tears open The objective for implementation of the movement or pull-up unloading and install and the movement put down is back segment chute.
3. a kind of earth pressure balanced shield separate launching side according to claim 2 excavating construction method, feature exist In: the bottom surface of the bottom wall of the two sections of chutes in front and back is respectively welded the square steel along the setting of bottom wall length direction, two sections of front and back chute The bottom surface of two sidewalls is respectively welded the square steel along the setting of sidewall width direction, the square steel on square steel and side wall on the bottom wall Mutually weld.
4. a kind of earth pressure balanced shield separate launching side according to claim 3 excavating construction method, feature exist In: the square steel on square steel and side wall on the bottom wall is 30mm square steel.
5. a kind of earth pressure balanced shield separate launching side according to claim 2 excavating construction method, feature exist In: the leading portion chute is 3 meters long, 1.2 meters wide, and the back segment chute is 2.2 meters long, 1.21 meters wide, the bottom wall of the two sections of chutes in front and back 3mm thick steel plate is all made of with left and right sides wall.
6. a kind of earth pressure balanced shield separate launching side according to claim 2 excavating construction method, feature exist In: the front end of the back segment chute is connected to the bottom of leading portion chute tail end.
7. a kind of earth pressure balanced shield separate launching side according to claim 2 excavating construction method, feature exist In be equipped on: the tail end of leading portion chute two sidewalls and the front end of back segment chute two sidewalls convenient for chute installation and removal with Bolt hole.
8. a kind of earth pressure balanced shield separate launching side according to claim 2 excavating construction method, feature exist In: branch midleg of the interim gantry in side corresponding with chute is equipped with fulcrum, and hook gear, institute is arranged in the lateral roof It states hook gear and is hung with chain block, the chute is supported installation by the fulcrum, and the chain block is connected to On chute, the gradient of the chute is 30~45%.
9. a kind of earth pressure balanced shield separate launching side according to claim 1 excavating construction method, feature exist In: the gradient of the chute is 30~45%.
10. a kind of earth pressure balanced shield separate launching side according to claim 1 excavating construction method, feature exist In: during shield machine is pushed ahead, interim gantry and chute promote identical distance therewith, and soil bucket remains stationary.
CN201811391499.8A 2018-11-21 2018-11-21 Earth pressure balance type shield split starting side unearthing construction method Active CN109441459B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811391499.8A CN109441459B (en) 2018-11-21 2018-11-21 Earth pressure balance type shield split starting side unearthing construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811391499.8A CN109441459B (en) 2018-11-21 2018-11-21 Earth pressure balance type shield split starting side unearthing construction method

Publications (2)

Publication Number Publication Date
CN109441459A true CN109441459A (en) 2019-03-08
CN109441459B CN109441459B (en) 2020-07-28

Family

ID=65554094

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811391499.8A Active CN109441459B (en) 2018-11-21 2018-11-21 Earth pressure balance type shield split starting side unearthing construction method

Country Status (1)

Country Link
CN (1) CN109441459B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110219661A (en) * 2019-07-12 2019-09-10 中铁工程装备集团有限公司 Applied to minimum starting well separate launching corollary apparatus and originate construction method
CN110510367A (en) * 2019-09-16 2019-11-29 粤水电轨道交通建设有限公司 A kind of active belt regulating device
CN111255466A (en) * 2020-01-20 2020-06-09 中铁十二局集团第二工程有限公司 Construction method for single shaft starting by changing tunnel into shield by mining method
CN112682060A (en) * 2020-12-11 2021-04-20 中铁工程服务有限公司 Novel double-slag-hole chute and construction method thereof
CN114215541A (en) * 2021-12-21 2022-03-22 中铁六局集团有限公司 Shield constructs components of a whole that can function independently and starts with interim platform truck frock
CN114412497A (en) * 2022-01-13 2022-04-29 华侨大学 Rapid unearthing and feeding construction method for normal tunneling of interval short shaft shield

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007198080A (en) * 2006-01-30 2007-08-09 Ishikawajima Harima Heavy Ind Co Ltd Master/slave shield machine
CN201605005U (en) * 2010-02-08 2010-10-13 宝山钢铁股份有限公司 Recovery device of fallen mine materials with hopper
CN102616520A (en) * 2012-04-05 2012-08-01 中铁十局集团济南铁路工程有限公司 Auxiliary device for shield single-well integral starting belt conveyor
CN202508557U (en) * 2012-04-05 2012-10-31 中铁十局集团济南铁路工程有限公司 Shield single-well overall originating belt machine auxiliary device
CN204299187U (en) * 2014-12-15 2015-04-29 中建七局建筑装饰工程有限公司 A kind of detachable concrete casting device
CN107269291A (en) * 2017-07-25 2017-10-20 北京建工土木工程有限公司 Material and dregs transportation system in shield separate launching tunnel
CN108071403A (en) * 2018-01-29 2018-05-25 重庆建工集团股份有限公司 A kind of tunneling separate launching equipment
CN207724794U (en) * 2017-12-13 2018-08-14 六盘水康博木塑科技有限公司 A kind of charging lifting device

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007198080A (en) * 2006-01-30 2007-08-09 Ishikawajima Harima Heavy Ind Co Ltd Master/slave shield machine
CN201605005U (en) * 2010-02-08 2010-10-13 宝山钢铁股份有限公司 Recovery device of fallen mine materials with hopper
CN102616520A (en) * 2012-04-05 2012-08-01 中铁十局集团济南铁路工程有限公司 Auxiliary device for shield single-well integral starting belt conveyor
CN202508557U (en) * 2012-04-05 2012-10-31 中铁十局集团济南铁路工程有限公司 Shield single-well overall originating belt machine auxiliary device
CN204299187U (en) * 2014-12-15 2015-04-29 中建七局建筑装饰工程有限公司 A kind of detachable concrete casting device
CN107269291A (en) * 2017-07-25 2017-10-20 北京建工土木工程有限公司 Material and dregs transportation system in shield separate launching tunnel
CN207724794U (en) * 2017-12-13 2018-08-14 六盘水康博木塑科技有限公司 A kind of charging lifting device
CN108071403A (en) * 2018-01-29 2018-05-25 重庆建工集团股份有限公司 A kind of tunneling separate launching equipment

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
季维国: "大连地铁2号线小半径曲线隧道盾构单井口始发技术研究", 《隧道建设》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110219661A (en) * 2019-07-12 2019-09-10 中铁工程装备集团有限公司 Applied to minimum starting well separate launching corollary apparatus and originate construction method
CN110510367A (en) * 2019-09-16 2019-11-29 粤水电轨道交通建设有限公司 A kind of active belt regulating device
CN111255466A (en) * 2020-01-20 2020-06-09 中铁十二局集团第二工程有限公司 Construction method for single shaft starting by changing tunnel into shield by mining method
CN112682060A (en) * 2020-12-11 2021-04-20 中铁工程服务有限公司 Novel double-slag-hole chute and construction method thereof
CN112682060B (en) * 2020-12-11 2023-01-06 中铁工程服务有限公司 Novel double-slag-hole chute and construction method thereof
CN114215541A (en) * 2021-12-21 2022-03-22 中铁六局集团有限公司 Shield constructs components of a whole that can function independently and starts with interim platform truck frock
CN114412497A (en) * 2022-01-13 2022-04-29 华侨大学 Rapid unearthing and feeding construction method for normal tunneling of interval short shaft shield
CN114412497B (en) * 2022-01-13 2024-06-07 华侨大学 Construction method for quick soil discharging and feeding of normal tunneling of shield of short-interval vertical shaft

Also Published As

Publication number Publication date
CN109441459B (en) 2020-07-28

Similar Documents

Publication Publication Date Title
CN109441459A (en) A kind of earth pressure balanced shield separate launching side excavating construction method
CN103225513B (en) Integral pouring construction method of ventilation inclined shaft provided with mid-partition and integral trolleys
CN111852521B (en) Mouth-shaped piece assembling trolley for construction of internal structure of large-section shield tunnel and synchronous construction method
CN109653105A (en) Box girder bridge cantilever construction main truss cradle system and its application method
CN101831888A (en) 1200 tonner water conservancy aqueduct transportation and erection equipment
CN107255188A (en) A kind of lifting pipeline method suitable at pipe gallery intersection node
CN110258352A (en) The steel reinforced concrete combined bridge construction method that two bridgings are done
CN104863374B (en) Large-span steel slipping mechanism and its gliding method
CN106088609A (en) A kind of integral lifting method of large span steel structure vestibule
CN104727833A (en) Method of conducting steel bar installation on bend section through bend-section steel bar trolley
CN107022958A (en) The method in cable-stayed bridge across girder is installed using cable crane
CN106837376B (en) Bind module turnover device for subway tunnel section of jurisdiction
CN102071646A (en) Large-tonnage box girder sea system and construction method
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
CN104532755A (en) Push type beam transporting trolley
CN104372746B (en) The prefabricated post stretching Simple T-Girders note concrete form support of railroad bridge and mounting process thereof
CN209652772U (en) Box girder bridge cantilever construction main truss cradle system
CN209338005U (en) A kind of mobile height leg gantry crane of erecting beam construction
CN110344334A (en) Steel reinforced concrete combined bridge construction method is done using two bridgings of dorsal funciculus formula Bridge Erector
CN204919341U (en) Installing the system of prefabricated decking of dysmorphism on uncovered lattice formula girder steel of arched bridge
CN105781108A (en) Overall transition construction method for large-size steel mould between adjacent field regions
CN206156620U (en) Movable track hoisting trolley of usefulness is demolishd with temporary track to shield tunnel construction
CN102704360A (en) Construction method for ballastless track base plate
CN107988909B (en) Railway is just roof beam rapid transit erects and uses trailer
CN108840060A (en) Cable belt conveying structure and conveyer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant