CN109436191A - The construction total coating process of semisubmersible platform - Google Patents
The construction total coating process of semisubmersible platform Download PDFInfo
- Publication number
- CN109436191A CN109436191A CN201811364004.2A CN201811364004A CN109436191A CN 109436191 A CN109436191 A CN 109436191A CN 201811364004 A CN201811364004 A CN 201811364004A CN 109436191 A CN109436191 A CN 109436191A
- Authority
- CN
- China
- Prior art keywords
- segmentation
- mobile moulding
- ring segment
- several
- self
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B71/00—Designing vessels; Predicting their performance
Abstract
A kind of construction total coating process of semisubmersible platform, using following construction step: one: mobile moulding bed is arranged;Two: mobile moulding bed is put to scene;Three: building segmentation on mobile moulding bed;Four: self-traveling module transport vehicle is moved under mobile moulding bed;Five: self-traveling module transport vehicle being jacked up on several mobile moulding beds, and is sent to place;Six: by each segmentation group pair;Seven: corresponding two-section is closed up as a ring segment;Eight: corresponding in addition two-section is closed up into two ring segments;Nine: self-traveling module transport vehicle is entered under mobile moulding bed;Ten: by a ring segment and two ring segment groups pair;11: a ring segment and two ring segments are closed up into total segmentation;12: by total fragmented transport at semisubmersible platform general assembly;13: by total segmental hoisting;14, total segmentation is mounted on semisubmersible platform.The present invention solves the problems, such as to carry out integration of operation using more loop wheel machines;Moreover, entire work progress is carried out in low level always, the risk of high-altitude construction is reduced.
Description
Technical field
The present invention relates to semisubmersible platform more particularly to a kind of construction total coating process of semisubmersible platform.Belong to ocean stone
Oily engineering field.
Background technique
Currently, traditional flat platform sectional construction general assembly partly latent, is usually segmented each section for platform, has built in workshop
At then, then transporting with transporting equipment that general assembly place is segmented using large caterpillar, ring segment is closed up.But upper
During stating platform sectional construction general assembly, due to needing to carry out integration of operation using more large caterpillars, not only to big
Type loop wheel machine resource quantity and Capability Requirement are higher, and construction efficiency is lower;Moreover, platform segmentation spatial group to the difficulty of operation compared with
Greatly;Meanwhile the risk of lifting operation is larger.
Summary of the invention
It is a primary object of the present invention to overcome disadvantages mentioned above of the existing technology, and provide a kind of improved semi-submersible type
Each segmentation of the construction total coating process of platform, semisubmersible platform is built on pre-designed mobile moulding bed, is built
After, then slideway general assembly domain is transported by self-traveling module transport vehicle and carries out segment folding;It is segmented, the group of ring segment is to logical
Self-traveling module transport vehicle is crossed to complete, not only solves and needs to carry out asking for integration of operation using more large caterpillars
Topic, substantially increases construction efficiency;Moreover, entire work progress is carried out in low level always, after the completion of total segmentation, then transport
Semisubmersible platform general assembly place completes semisubmersible platform general assembly work, greatly reduces the risk of high-altitude construction, improve construction
Safety.
The purpose of the present invention is implemented by the following technical solutions:
A kind of construction total coating process of semisubmersible platform, it is characterised in that: the present invention uses following construction step:
Step 1: several mobile moulding beds are arranged according to the size of segmentation;
Step 2: several mobile moulding beds are put prefabricated place;
Step 3: being respectively completed the construction of several segmentations on several mobile moulding beds;
Step 4: several self-traveling module transport vehicles to be moved to the lower section of mobile moulding bed respectively;
Step 5: several self-traveling module transport vehicles are increased jack-up in several mobile moulding beds respectively and are built in movement
Each segmentation on moulding bed, and be transported to general assembly and close up place;
Step 6: several self-traveling module transport vehicles are slowly moved, and by several mobile moulding beds and it is built in movement
Each segmentation on moulding bed is close, and reaches requirement spacing, completes preliminary group pair;
Step 7: withdrawing from several self-traveling module transport vehicles respectively, accurately adjust corresponding two-section, when reach group pair
After it is required that, corresponding two-section is closed up as the first ring segment;
Step 8: repeating the work of the 7th step, corresponding in addition two-section is closed up as the second ring segment;
Step 9: several self-traveling module transport vehicles to be had respectively entered to the lower section of corresponding mobile moulding bed;
Step 10: several self-traveling module transport vehicles slowly move, and by the first ring segment and the second ring segment close to reaching
It is required that spacing, completes preliminary group pair;
It is accurate to adjust the first ring segment and the second ring segment step 11: withdraw from self-traveling module transport vehicle respectively, when reaching
After group is to requiring, the first ring segment and the second ring segment, which are closed up, becomes total segmentation;
Step 12: by total fragmented transport at semisubmersible platform general assembly;
Step 13: total segmentation is lifted on semisubmersible platform;
Total segmentation is mounted on semisubmersible platform by the 14th step.
The top surface of the mobile moulding bed is crossed grid structure, and the lower section of mobile moulding bed is equipped with several supporting legs, between supporting leg there are
It is able to enter the space of self-traveling module transport vehicle.
Beneficial effects of the present invention: due to the adoption of the above technical scheme, each segmentation of semisubmersible platform is pre- by the present invention
It is first built on designed mobile moulding bed, after construction, then slideway general assembly is transported by self-traveling module transport vehicle
Domain carries out segment folding;Segmentation, ring segment group to being completed by self-traveling module transport vehicle, not only solving needs makes
The problem of carrying out integration of operation with more large caterpillars, substantially increases construction efficiency;Moreover, entire work progress is always
It is carried out in low level, after the completion of total segmentation, then transports semisubmersible platform general assembly place, complete semisubmersible platform general assembly work, greatly
The risk for reducing high-altitude construction greatly, improves the safety of construction.
Detailed description of the invention
Fig. 1 is the mobile jig structure schematic diagram of the present invention.
Fig. 2 is that the mobile moulding bed of the present invention puts schematic diagram.
Fig. 3 is that the present invention builds stepwise schematic views on mobile moulding bed.
Fig. 4 is self-traveling module transport vehicle schematic diagram of the present invention.
Fig. 5 is that self-traveling module transport vehicle of the present invention jacks mobile moulding bed schematic diagram.
Fig. 6 is self-traveling module transport vehicle schematic diagram of the present invention.
Fig. 7 be the present invention by each segmentation group to closing up schematic diagram.
Self-traveling module transport vehicle is entered mobile moulding bed schematic diagram for the present invention by Fig. 8.
Fig. 9 is that two ring segments of the invention are closed up as total stepwise schematic views.
Figure 10 is the total segmentation transport diagram of the present invention.
Figure 11 is that the total segmentation of the present invention is lifted into semisubmersible platform schematic diagram.
Major Symbol illustrates in figure:
1. mobile moulding bed, 2. first segmentations, 3. second segmentations, the segmentation of 4. thirds, 5. the 4th segmentations, 6. self-traveling modules
Transport vehicle, 7. first ring segments, 8. second ring segments, 9. total segmentations, 10. semisubmersible platforms.
Specific embodiment
As shown in Figure 1-Figure 11, the present invention uses following construction step:
Step 1: as shown in Figure 1, several mobile moulding beds 1 are arranged according to the size of segmentation;
The top surface of above-mentioned mobile moulding bed 1 is crossed grid structure, and the lower section of mobile moulding bed 1 is equipped with several using welding manner
Leg, there are the spaces that can enter self-traveling module transport vehicle 6 between supporting leg.
Step 2: as shown in Fig. 2, several mobile moulding beds 1 (the present embodiment is four) are put prefabricated place;
Step 3: as shown in figure 3, being respectively completed the first segmentation 2, second segmentation 3, third point on four mobile moulding beds 1
The construction of the 4, the 4th segmentation 5 of section;
Step 4: as shown in figure 4, several self-traveling module transport vehicles 6 to be moved to the lower section of mobile moulding bed 1 respectively;
Step 5: as shown in figure 5, several self-traveling module transport vehicles 6 to be increased to jack-up respectively in several mobile moulding beds 1
And it is built in each segmentation on mobile moulding bed 1, and be transported to general assembly and close up place;
Step 6: as shown in fig. 6, several self-traveling module transport vehicles 6 are slowly mobile, and by several mobile moulding beds 1
And each segmentation being built on mobile moulding bed 1 is close, and reaches requirement spacing, completes preliminary group pair;
Step 7: accurately being adjusted using three-dimensional adjusting machine as shown in fig. 7, withdraw from several self-traveling module transport vehicles 6 respectively
Whole second segmentation 3 and third segmentation 4 are closed the second segmentation 3 and third segmentation 4 using welding manner after reaching group to requiring
Hold together to become the first ring segment 7;
Step 8: repeating the work of the 7th step, third segmentation 5 and the 4th segmentation 6 are closed up using welding manner as second
Ring segment 8;
Step 9: as shown in figure 8, several self-traveling module transport vehicles 6 are had respectively entered corresponding mobile moulding bed 1
Lower section;
Step 10: several self-traveling module transport vehicles 6 are slowly mobile, and by the first ring segment 7 and the second ring segment 8 close to reaching
To spacing is required, preliminary group pair is completed;
Step 11: accurately being adjusted using three-dimensional adjusting machine as shown in figure 9, withdraw from self-traveling module transport vehicle 6 respectively
First ring segment 7 and the second ring segment 8 are closed up the first ring segment 7 and the second ring segment 8 using welding manner after reaching group to requiring
As total segmentation 9;
Step 12: as shown in Figure 10, will always be segmented 9 and transport at semisubmersible platform general assembly;
Step 13: as shown in figure 11, total segmentation 9 is lifted on semisubmersible platform 10 using crawler crane;
Total segmentation 9 is mounted on semisubmersible platform 10 by the 14th step.
The above described is only a preferred embodiment of the present invention, be not intended to limit the present invention in any form, it is all
It is any simple modification, equivalent change and modification to the above embodiments according to the technical essence of the invention, still falls within
In the range of technical solution of the present invention.
Claims (2)
1. a kind of construction total coating process of semisubmersible platform, it is characterised in that: the present invention uses following construction step:
Step 1: several mobile moulding beds are arranged according to the size of segmentation;
Step 2: several mobile moulding beds are put prefabricated place;
Step 3: being respectively completed the construction of several segmentations on several mobile moulding beds;
Step 4: several self-traveling module transport vehicles to be moved to the lower section of mobile moulding bed respectively;
Step 5: several self-traveling module transport vehicles are increased jack-up in several mobile moulding beds respectively and are built in mobile moulding bed
On each segmentation, and be transported to general assembly and close up place;
Step 6: several self-traveling module transport vehicles are slowly moved, and by several mobile moulding beds and it is built in mobile moulding bed
On each segmentation it is close, and reach requirement spacing, complete preliminary group pair;
Step 7: withdrawing from several self-traveling module transport vehicles respectively, corresponding two-section is accurately adjusted, when reaching group to requiring
Afterwards, corresponding two-section is closed up as the first ring segment;
Step 8: repeating the work of the 7th step, corresponding in addition two-section is closed up as the second ring segment;
Step 9: several self-traveling module transport vehicles to be had respectively entered to the lower section of corresponding mobile moulding bed;
Step 10: several self-traveling module transport vehicles slowly move, and by the first ring segment and the second ring segment close to reaching requirement
Spacing completes preliminary group pair;
It is accurate to adjust the first ring segment and the second ring segment step 11: withdraw from self-traveling module transport vehicle respectively, when reaching group pair
After it is required that, the first ring segment and the second ring segment, which are closed up, becomes total segmentation;
Step 12: by total fragmented transport at semisubmersible platform general assembly;
Step 13: total segmentation is lifted on semisubmersible platform;
Total segmentation is mounted on semisubmersible platform by the 14th step.
2. the construction total coating process of semisubmersible platform according to claim 1, it is characterised in that: the top of the mobile moulding bed
Face is crossed grid structure, and the lower section of mobile moulding bed is equipped with several supporting legs, and there are be able to enter self-traveling moduleization transport between supporting leg
The space of vehicle.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811364004.2A CN109436191A (en) | 2018-11-16 | 2018-11-16 | The construction total coating process of semisubmersible platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811364004.2A CN109436191A (en) | 2018-11-16 | 2018-11-16 | The construction total coating process of semisubmersible platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109436191A true CN109436191A (en) | 2019-03-08 |
Family
ID=65553023
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811364004.2A Pending CN109436191A (en) | 2018-11-16 | 2018-11-16 | The construction total coating process of semisubmersible platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109436191A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109909631A (en) * | 2019-03-20 | 2019-06-21 | 海洋石油工程(青岛)有限公司 | The building technology of super large wall thickness overlength multiple tube manifold |
CN111114710A (en) * | 2019-12-20 | 2020-05-08 | 海洋石油工程(青岛)有限公司 | Semi-submersible platform structure and block segmentation method thereof |
CN114802621A (en) * | 2022-03-30 | 2022-07-29 | 广州文冲船舶修造有限公司 | Construction method of deep-sea semi-submersible type breeding tourism platform |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1955068A (en) * | 2005-10-27 | 2007-05-02 | 山海关船厂 | Construction method for ship making on land and its moving device |
CN201296361Y (en) * | 2008-10-14 | 2009-08-26 | 无锡华联科技集团有限公司 | Trolley for translating hull sections |
CN204236739U (en) * | 2014-07-31 | 2015-04-01 | 江苏宏强船舶重工有限公司 | A kind of segmentation berth combination device |
CN106184615A (en) * | 2016-06-30 | 2016-12-07 | 海阳中集来福士海洋工程有限公司 | The method of construction of semisubmersible platform |
CN206485539U (en) * | 2016-11-25 | 2017-09-12 | 海洋石油工程(青岛)有限公司 | Tension leg platform (TLP) segmentation is prefabricated to transport multi-purpose pad pier of weighing |
-
2018
- 2018-11-16 CN CN201811364004.2A patent/CN109436191A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1955068A (en) * | 2005-10-27 | 2007-05-02 | 山海关船厂 | Construction method for ship making on land and its moving device |
CN201296361Y (en) * | 2008-10-14 | 2009-08-26 | 无锡华联科技集团有限公司 | Trolley for translating hull sections |
CN204236739U (en) * | 2014-07-31 | 2015-04-01 | 江苏宏强船舶重工有限公司 | A kind of segmentation berth combination device |
CN106184615A (en) * | 2016-06-30 | 2016-12-07 | 海阳中集来福士海洋工程有限公司 | The method of construction of semisubmersible platform |
CN206485539U (en) * | 2016-11-25 | 2017-09-12 | 海洋石油工程(青岛)有限公司 | Tension leg platform (TLP) segmentation is prefabricated to transport multi-purpose pad pier of weighing |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109909631A (en) * | 2019-03-20 | 2019-06-21 | 海洋石油工程(青岛)有限公司 | The building technology of super large wall thickness overlength multiple tube manifold |
CN109909631B (en) * | 2019-03-20 | 2021-04-27 | 海洋石油工程(青岛)有限公司 | Construction process of super-thick-wall super-long composite pipe manifold |
CN111114710A (en) * | 2019-12-20 | 2020-05-08 | 海洋石油工程(青岛)有限公司 | Semi-submersible platform structure and block segmentation method thereof |
CN114802621A (en) * | 2022-03-30 | 2022-07-29 | 广州文冲船舶修造有限公司 | Construction method of deep-sea semi-submersible type breeding tourism platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109436191A (en) | The construction total coating process of semisubmersible platform | |
CN104775364B (en) | The installation method of Cable-stayed Bridge Pylon king-post reinforcing bar | |
CN103287555B (en) | A kind of movable hydraulic pressure docking block and using method thereof | |
CN102285616B (en) | Walking type shield machine lateral sway system and lateral sway method | |
AU2019209726B2 (en) | Construction method for spar platform cylindrical deck and upper facilities, and spar platform | |
CN104805907A (en) | Jacking method and device of steel structure module | |
CN110053932A (en) | A kind of multi-faceted built-in type segmentation transport small car | |
CN204690960U (en) | A kind of lift-up device of steel structure module | |
CN106089560A (en) | Seat bottom type liftable tidal current energy generating equipment and elevating method | |
CN113942620A (en) | Ship position arrangement method for improving dock utilization rate | |
CN110253045A (en) | A kind of truss-like hydraulic lift wedge bracket method for boring hole | |
CN103911950A (en) | Large-scale combination joist steel girder complete hole and manufacture method thereof | |
CN203788007U (en) | Electric automobile battery replacing station | |
CN104290866B (en) | Split type dock construction method of self-elevating production platform and oil storing and discharging platform | |
CN109484586A (en) | The mobile moulding bed built for semisubmersible platform | |
CN102561289A (en) | Around synchronization hydraumatic jacking process of upper module of ultra-large marine oil platform | |
CN102101629B (en) | Hierarchical synchronous hydraulic jacking process for large-tonnage ocean engineering structure | |
CN206485367U (en) | A kind of board migration device of accommodation module peculiar to vessel | |
CN107399412A (en) | MOPU method of construction | |
CN105667709A (en) | Hull manufacturing method | |
CN207044026U (en) | A kind of round bottom pallet special tooling | |
CN108487212A (en) | Jacket skirt pile sleeve combines sheet of hoisting | |
CN109625174A (en) | Semisubmersible platform upper chunk and lower float structure slideway jack the technique closed up | |
CN109625172A (en) | Semisubmersible platform upper chunk and lower float structure slideway promote the technique closed up | |
CN203807012U (en) | Climbing device used in internal climbing tower-type crane |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20190308 |