CN109430134A CN201910037697.2A CN201910037697A CN109430134A CN 109430134 A CN109430134 A CN 109430134A CN 201910037697 A CN201910037697 A CN 201910037697A CN 109430134 A CN109430134 A CN 109430134A
Authority
CN
China
Prior art keywords
anchor chain
scaffold
mooring system
round
marine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910037697.2A
Other languages
Chinese (zh)
Inventor
石福明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow Fish Island Marine Fisheries Co Ltd
Original Assignee
Yellow Fish Island Marine Fisheries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow Fish Island Marine Fisheries Co Ltd filed Critical Yellow Fish Island Marine Fisheries Co Ltd
Priority to CN201910037697.2A priority Critical patent/CN109430134A/en
Publication of CN109430134A publication Critical patent/CN109430134A/en
Pending legal-status Critical Current

Links

Classifications

    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01KANIMAL HUSBANDRY; AVICULTURE; APICULTURE; PISCICULTURE; FISHING; REARING OR BREEDING ANIMALS, NOT OTHERWISE PROVIDED FOR; NEW BREEDS OF ANIMALS
    • A01K61/00Culture of aquatic animals
    • A01K61/60Floating cultivation devices, e.g. rafts or floating fish-farms
    • A01K61/65Connecting or mooring devices therefor
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/80Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in fisheries management
    • Y02A40/81Aquaculture, e.g. of fish

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Environmental Sciences (AREA)
  • Marine Sciences & Fisheries (AREA)
  • Zoology (AREA)
  • Animal Husbandry (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Cultivation Of Seaweed (AREA)

Abstract

The present invention relates to a kind of mooring systems of marine round floating net cultivation, relate generally to marine floating net cultivation field.The device includes round scaffold 3, railing head 1, upright fence post 2, purse seine 4, purse seine pendant block drawstring 5, purse seine pendant block 6, scaffold fixed pulling rope 7, mooring system;Mooring system includes outer drawing anchor chain 8, anchoring pile 9, cyclic annular anchor chain 10.Each anchor chain of mooring system is laid in seabed, and each outer 8 inner end of drawing anchor chain is to be fixedly connected with cyclic annular anchor chain 10.The mooring system of the invention has buffer function, so that each 7 uniform force of scaffold fixed pulling rope, to enhance the reliability of whole system.Meanwhile the assembly of entire net cage scaffold monomer or multiple monomers can be made greatly, and infinity theoretically may be implemented, to enhance the scale and benefit of cultivation.In addition, the invention also proposes targetedly solution to the mooring system in the case of cultivation by massif, there is very strong practicability.

Description

A kind of mooring system for marine round floating net cultivation
Technical field
The present invention relates to a kind of mooring systems of marine floating net cultivation, relate generally to marine floating net cultivation field.
Background technique
The floating net cultivation in sea is exactly the semiclosed purse seine that open top is at sea formed using the net cage floating to fence up, benefit With the method for corresponding waters cultured fishes.Currently, the technology that floating net cultivation uses has scaffold, purse seine, purse seine pendant block and solid Fixed whole anchor chain and anchoring pile, drawstring etc..Circle net cage floating body in the prior art is frequently with multiple individual anchor chains and anchoring pile It fixes respectively.Since maritime environment is changeable, due to the effect of stormy waves, part anchor chain and anchoring pile may be damaged since stress is excessive It is bad, and other anchor chains and anchoring pile are almost without stress.There is no buffer gear to lead to each anchor chain and anchoring pile unbalance stress, reliably Property is not high.So this individual anchor chain and anchoring pile fixed structure are merely able to adaptation diameter or the lesser scaffold net cage of area, Because big net cage anchor chain local after by Lidar Equation and anchoring pile stress can be bigger.In addition, by the influence of topography, some farms Around cast anchor inconvenience there are situations such as island, hillside, influence the fixation of entire cultivation equipment.
Summary of the invention
In order to overcome the above problem, the present invention provides a kind of mooring system for marine round floating net cultivation.As Fig. 1, Fig. 2, the device include round scaffold 3, railing head 1, upright fence post 2, purse seine 4, purse seine pendant block drawstring 5, purse seine pendant block 6, float Frame fixed pulling rope 7, mooring system;Mooring system includes outer drawing anchor chain 8, anchoring pile 9, cyclic annular anchor chain 10.Each anchor chain of mooring system is flat It is layered on seabed, each outer 8 inner end of drawing anchor chain is to be fixedly connected, and have corresponding hinge joint, outer drawing anchor chain 8 with cyclic annular anchor chain 10 Outer end is fixedly connected with anchoring pile 9, and anchoring pile 9 is fixed on seabed.3 top of at least one circle scaffold, one week fixed setting railing head 1, Upright fence post 2,4 top of purse seine are fixed on 2 top of upright fence post, and bottom surrounding connects purse seine pendant block drawstring 5 and purse seine falls block 6.Several 7 one end of scaffold fixed pulling rope connect round scaffold 3, and the other end is connected on cyclic annular anchor chain 10, can thus pass through Mooring system fixes whole scaffold.Purse seine 4 has closed net bottom, prevents cultured product excessive.Round scaffold 3 is independent floating The structures such as PE pipe welding can be used in body.
Due to mooring system integrally criss-cross hinged formation one it is netted, therefore it is whole have it is certain rigid Degree, while each anchor chain itself is made of iron hoop all linked with one another again, whole rate of tension is fitted adjustable more moderate.This Outside, such as Fig. 2, mooring system is integrally to be laid in seabed, and the generally inclined direction of scaffold fixed pulling rope 7, therefore Impact direction is not It is directly, thus to bring biggish buffering.Entire mooring system can according to the force-bearing situation of scaffold fixed pulling rope 7 from Dynamic adjustment (when stress is big, outer drawing anchor chain 8 and the angle of scaffold fixed pulling rope 7 become larger, thus cut down scaffold fixed pulling rope 7 by Power, stress hour, above-mentioned angle become smaller) so that each 7 uniform force of scaffold fixed pulling rope.On the contrary, multiple in the prior art Individual anchor chain and anchoring pile are directly connected with each scaffold, and Impact direction directly transmits, and thus brings certain stress on anchor chain Excessive the problem of damaging.
The horizontal direction of round scaffold 3, such as Fig. 1 are fixed to make the scaffold fixed pulling rope 7 preferably provide the power of side direction Shown in top view, the shape of cyclic annular anchor chain 10 on projecting direction for relative to round 3 outer circle of scaffold it is whole it is outer move it is polygon Shape.
It as seen from Figure 1, Figure 2, is preferably fixed function of the performance scaffold fixed pulling rope 7 to scaffold, scaffold fixed pulling rope 7 Lower end is preferably attached on a hinge joint of mooring system, and upper end is connected on round scaffold 3.It is of course also possible to by scaffold The tie point of 7 lower end of fixed pulling rope and the hinge joint of mooring system are staggered, in this way since the deformation of cyclic annular anchor chain 10 is so that scaffold Fixed pulling rope 7 obtains additional buffering.Such as Fig. 3, the case where being combined for multiple round scaffolds 3, due to each scaffold it Between need to keep a suitable distance, be convenient for the operation of personnel's ship, therefore buffer should be appropriate, found between buffering and fixation One balance.
Such as Fig. 5, when culturing area nearby has massif, which may also include mountainous region anchoring pile 13, inclination anchor chain 14, iron thallium 15.Fix mountainous region anchoring pile 13 on hillslope, inclination 14 one end of anchor chain is fixed on mountainous region anchoring pile 13, lower end and mooring system Draw anchor chain 8 hinged outside one, hinge joint is also connected with the iron thallium 15 naturally drooped.The tension of anchor chain is drawn since this is outer Effect, iron thallium 15 are outstanding in the seawater;When the outer drawing anchor chain tenses, iron thallium 15 is moved up, when the outer drawing slack away chain, iron Thallium 15 moves down, to play buffer function.
The mooring system of the invention has buffer function, so that each 7 uniform force of scaffold fixed pulling rope, to enhance The reliability of whole system.Meanwhile the assembly of entire net cage scaffold monomer or multiple monomers can be made greatly, theoretically Infinity may be implemented, to enhance the scale and benefit of cultivation.In addition, the invention is also to the anchoring in the case of cultivation by massif System proposes targetedly solution, has very strong practicability.
Detailed description of the invention
Fig. 1, Fig. 2, Fig. 5 are the schematic diagrames of first embodiment of the invention, and wherein Fig. 1 is top view, and Fig. 2 is rearview, Fig. 5 It is the partial schematic diagram of mooring system at massif;Fig. 3, Fig. 4 are the schematic diagrames of second embodiment of the invention, and wherein Fig. 3 is to bow View, Fig. 4 are rearview;Fig. 6 is the schematic diagram of third embodiment of the invention.
Specific embodiment
First embodiment
A kind of mooring system for marine round floating net cultivation.As shown in Figure 1, Figure 2, which includes round scaffold 3, fence Handrail 1, upright fence post 2, purse seine 4, purse seine pendant block drawstring 5, purse seine fall block 6, scaffold fixed pulling rope 7, mooring system;Mooring system Including outer drawing anchor chain 8, anchoring pile 9, cyclic annular anchor chain 10.Each anchor chain of mooring system is laid in seabed, each outer 8 inner end of drawing anchor chain and ring-type Anchor chain 10 is to be fixedly connected, and have corresponding hinge joint, and outer 8 outer end of drawing anchor chain is fixedly connected with anchoring pile 9, and anchoring pile 9 is fixed on Seabed.1 round 3 top of scaffold one week fixed setting railing head 1, upright fence post 2,4 top of purse seine is fixed on upright fence post 2 Top, is fixed on each scaffold and plays main load-bearing effect in the middle part of purse seine 4, and 4 bottom surrounding of purse seine connects purse seine and falls block drawstring 5 And purse seine falls block 6.Several 7 one end of scaffold fixed pulling rope connect round scaffold 3, and the other end is connected on cyclic annular anchor chain 10, this Sample can fix whole scaffold by mooring system.Purse seine 4 has closed net bottom, prevents cultured product excessive.It is round Scaffold 3 is independent floating body, using PE pipe welding structure.
Top view as shown in Figure 1, the shape of cyclic annular anchor chain 10 is on projecting direction for relative to the outer rounding of round scaffold 3 The polygon moved in vitro.
It as seen from Figure 1, Figure 2, is preferably fixed function of the performance scaffold fixed pulling rope 7 to scaffold, scaffold fixed pulling rope 7 Lower end is connected on a hinge joint of mooring system, and upper end is connected on round scaffold 3.Entire mooring system and scaffold are fixed Drawstring 7 is center symmetrical structure (center of circle relative to round scaffold 3), can balance the stress in all directions in this way.
Such as Fig. 5, when culturing area nearby has massif, which may also include mountainous region anchoring pile 13, inclination anchor chain 14, iron thallium 15.Fix mountainous region anchoring pile 13 on hillslope, inclination 14 one end of anchor chain is fixed on anchoring pile, and one of lower end and mooring system is outer It draws anchor chain 8 hinged, the iron thallium 15 naturally drooped is also connected under hinge joint.The tension of anchor chain is drawn to make since this is outer With iron thallium 15 is outstanding in the seawater;When the outer drawing anchor chain tenses, iron thallium 15 is moved up, when the outer drawing slack away chain, iron thallium 15 move down.To play buffer function.
Second embodiment
A kind of mooring system for marine round floating net cultivation.Such as Fig. 3, Fig. 4, which includes round scaffold 3, fence Handrail 1, upright fence post 2, purse seine 4, purse seine pendant block drawstring 5, purse seine fall block 6, scaffold fixed pulling rope 7, mooring system;Mooring system Including outer drawing anchor chain 8, anchoring pile 9, cyclic annular anchor chain 10, vertical drawing anchor chain 11 and horizontal drawing anchor chain 12.Each anchor chain of mooring system is laid in sea Bottom, each outer 8 inner end of drawing anchor chain is fixedly connected with corresponding cyclic annular anchor chain 10, and has corresponding hinge joint, outer 8 outer end of drawing anchor chain It is fixedly connected with anchoring pile 9 or is connected on neighbouring vertical drawing anchor chain 11 and horizontal drawing anchor chain 12, anchoring pile 9 is fixed on seabed.It is vertical to draw anchor chain 11 and horizontal drawing anchor chain 12 respectively have two, connect anchoring pile 9 in end.9 round scaffolds 3 are equal along the direction of two square crossings Cloth.Round 3 top of scaffold one week fixed setting railing head 1, upright fence post 2,4 top of purse seine are fixed on 2 top of upright fence post, Be fixed on each scaffold and play main load-bearing effect in the middle part of purse seine 4,4 bottom surrounding of purse seine connect purse seine pendant block drawstring 5 and Purse seine falls block 6.Several 7 one end of scaffold fixed pulling rope connect round scaffold 3, and the other end is connected on cyclic annular anchor chain 10, thus Whole scaffold can be fixed by mooring system.Purse seine 4 has closed net bottom, prevents cultured product excessive.It is each round floating Frame 3 can provide enough buoyancy using PE pipe welding structure for independent floating body.
Top view as shown in Figure 3, the shape of each ring-type anchor chain 10 is on projecting direction for relative to corresponding round floating The whole outer regular polygon moved of 3 outer circle of frame.The number of edges of regular polygon is 8 multiple or 12 multiple, can occur two groups in this way Vertical drawing anchor chain 11 and horizontal 12 joint of drawing anchor chain and centrosymmetric outer drawing anchor chain 8 are crossed, the outer drawing anchor chain 8 and neighbouring vertical drawing anchor Chain 11 and horizontal 12 angle of drawing anchor chain are 45 °, so that whole stress more balances.
By Fig. 3, Fig. 4 it is found that preferably to play fixed function of the scaffold fixed pulling rope 7 to scaffold, scaffold fixed pulling rope 7 Lower end is connected on a hinge joint of mooring system, and upper end is connected on round scaffold 3.
For the draw for preferably playing outer 8 pairs of drawing anchor chain cyclic annular anchor chains 10, force balance, each circle 3 surrounding of scaffold Outer 8 distributed architecture of drawing anchor chain it is equal towards outer 8 outer end of drawing anchor chain in the center of circle of the circle scaffold 3 and each round scaffold 3 The outer end of anchor chain 8 is drawn to coincide with a bit outside corresponding with adjacent circular scaffold 3, i.e., about adjacent vertical drawing anchor chain 11 and horizontal drawing anchor Chain 12 is symmetrical.
Preferably 3 diameter of each round scaffold is identical, is conducive to whole stress balance and reduces the spare part number of replacement purse seine 4 Amount improves versatility.
The mooring system of the floating net cultivation of the circle has significant buffer function, so that each 7 stress of scaffold fixed pulling rope is equal It is even, to enhance the reliability of whole system.Simultaneously as entire scaffold assembly stress balance, overall dimensions can be done It is very big, infinity theoretically may be implemented, to enhance the scale and benefit of cultivation.
3rd embodiment
A kind of mooring system for marine round floating net cultivation, such as Fig. 6, unique area of the embodiment and first embodiment It is not that the tie point of 7 lower end of scaffold fixed pulling rope is located at the midpoint of the two neighboring hinge joint of mooring system, in this way due to ring The deformation of shape anchor chain 10 is so that scaffold fixed pulling rope 7 obtains additional buffering and two sides stress balance.

Claims (10)

1. a kind of mooring system of marine round floating net cultivation, including round scaffold (3), railing head (1), upright fence post (2), Purse seine (4), purse seine pendant block drawstring (5), purse seine fall block (6), scaffold fixed pulling rope (7), mooring system;The mooring system includes Outer drawing anchor chain (8), anchoring pile (9), cyclic annular anchor chain (10);Each anchor chain of mooring system is laid in seabed, and each outer drawing anchor chain (8) is interior End is to be fixedly connected, and have corresponding hinge joint with cyclic annular anchor chain (10), and outer drawing anchor chain (8) outer end is fixedly connected with anchoring pile (9), anchoring pile (9) is fixed on seabed;One week fixed setting railing head (1), fence of circle scaffold (3) top described at least one Column (2), purse seine (4) top are fixed on upright fence post (2) top, bottom surrounding connect purse seine pendant block drawstring (5) and Purse seine falls block (6);Several scaffold fixed pulling rope (7) one end connect round scaffold (3), and the other end is connected to cyclic annular anchor chain (10) On, purse seine (4) has closed net bottom;It is characterized in that it is described ring-type anchor chain (10) shape on projecting direction for relative to The whole outer polygon moved of round scaffold (3) outer circle.
2. the mooring system of marine round floating net cultivation according to claim 1, it is characterised in that the scaffold is fixed to be drawn Rope (7) lower end is preferably attached on a hinge joint of mooring system, and upper end is connected on round scaffold (3).
3. the mooring system of marine round floating net cultivation according to claim 1, it is characterised in that the scaffold is fixed to be drawn The tie point of rope (7) lower end and the hinge joint of mooring system are staggered.
4. the mooring system of marine round floating net cultivation according to claim 1, it is characterised in that the system further includes mountain Ground anchor peg (13), inclination anchor chain (14), iron thallium (15);It is fixed on hillslope mountainous region anchoring pile (13), tilts anchor chain (14) one end It is fixed on mountainous region anchoring pile (13), draws anchor chain (8) hinged outside one of lower end and mooring system, hinge joint connects one The iron thallium (15) naturally drooped.
5. the mooring system of marine round floating net cultivation according to claim 1, it is characterised in that the system has 1 circle Shape scaffold (3), the mooring system and scaffold fixed pulling rope (7) are center symmetrical structure.
6. the mooring system of marine round floating net cultivation according to claim 1, it is characterised in that the system has 9 circles Shape scaffold (3), the circle scaffold (3) are uniformly distributed along the direction of two square crossings;The mooring system includes outer drawing anchor chain (8), anchoring pile (9), cyclic annular anchor chain (10), vertical drawing anchor chain (11) and horizontal drawing anchor chain (12);Each outer drawing anchor chain (8) inner end with it is corresponding Cyclic annular anchor chain (10) is fixedly connected, and has corresponding hinge joint, and outer drawing anchor chain (8) outer end is fixedly connected with anchoring pile (9) or connection In on neighbouring vertical drawing anchor chain (11) and horizontal drawing anchor chain (12).
7. the mooring system of marine round floating net cultivation according to claim 6, it is characterised in that each cyclic annular anchor chain (10) shape on projecting direction for relative to the whole outer regular polygon moved of corresponding round scaffold (3) outer circle, it is described just The number of edges of polygon is 8 multiple or 12 multiple.
8. the mooring system of marine round floating net cultivation according to claim 6, it is characterised in that each round scaffold (3) outer drawing anchor chain (8) distributed architecture of surrounding towards the center of circle of the circle scaffold (3) and each round scaffold (3) it is outer Draw 8 outer end of anchor chain is corresponding with adjacent circular scaffold (3) to draw the outer end of anchor chain (8) to coincide with a bit outside.
9. the mooring system of marine round floating net cultivation according to claim 1, it is characterised in that each round scaffold (3) diameter is identical.
10. the mooring system of marine round floating net cultivation according to claim 1, it is characterised in that the scaffold is fixed to be drawn The tie point of rope (7) lower end is located at the midpoint of the two neighboring hinge joint of mooring system.
CN201910037697.2A 2019-01-16 2019-01-16 A kind of mooring system for marine round floating net cultivation Pending CN109430134A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910037697.2A CN109430134A (en) 2019-01-16 2019-01-16 A kind of mooring system for marine round floating net cultivation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910037697.2A CN109430134A (en) 2019-01-16 2019-01-16 A kind of mooring system for marine round floating net cultivation

Publications (1)

Publication Number Publication Date
CN109430134A true CN109430134A (en) 2019-03-08

Family

ID=65544297

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910037697.2A Pending CN109430134A (en) 2019-01-16 2019-01-16 A kind of mooring system for marine round floating net cultivation

Country Status (1)

Country Link
CN (1) CN109430134A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111006826A (en) * 2019-11-05 2020-04-14 中国水产科学研究院南海水产研究所 Installation and adjustment method of deepwater net cage anchoring system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0146518A2 (en) * 1983-12-19 1985-06-26 Viking Fish Ab Fish breeding plant comprising at least one tank submergible to the desired depth and having an air chamber
EP0393276A1 (en) * 1989-04-18 1990-10-24 Ocean Spar Technologies, L.L.C. Spar buoy pen system
WO2005117573A1 (en) * 2004-06-02 2005-12-15 Aquaculture Engineering Group Ltd. An offshore aquaculture system
CN104351103A (en) * 2014-11-27 2015-02-18 浙江大学宁波理工学院 Large-scale shallow sea purse net culture device
CN204949111U (en) * 2015-07-27 2016-01-13 广东联塑科技实业有限公司 Box with a net mooring system breeds
CN204949099U (en) * 2015-07-27 2016-01-13 广东联塑科技实业有限公司 Centralized mooring system of box with a net breeds
CN205409140U (en) * 2016-03-04 2016-08-03 古国维 From mooring gridLayout box with a net mooring system along with fluctuation in stage heave

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0146518A2 (en) * 1983-12-19 1985-06-26 Viking Fish Ab Fish breeding plant comprising at least one tank submergible to the desired depth and having an air chamber
EP0393276A1 (en) * 1989-04-18 1990-10-24 Ocean Spar Technologies, L.L.C. Spar buoy pen system
WO2005117573A1 (en) * 2004-06-02 2005-12-15 Aquaculture Engineering Group Ltd. An offshore aquaculture system
CN104351103A (en) * 2014-11-27 2015-02-18 浙江大学宁波理工学院 Large-scale shallow sea purse net culture device
CN204949111U (en) * 2015-07-27 2016-01-13 广东联塑科技实业有限公司 Box with a net mooring system breeds
CN204949099U (en) * 2015-07-27 2016-01-13 广东联塑科技实业有限公司 Centralized mooring system of box with a net breeds
CN205409140U (en) * 2016-03-04 2016-08-03 古国维 From mooring gridLayout box with a net mooring system along with fluctuation in stage heave

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111006826A (en) * 2019-11-05 2020-04-14 中国水产科学研究院南海水产研究所 Installation and adjustment method of deepwater net cage anchoring system

Similar Documents

Publication Publication Date Title
ES2718934T3 (en) Floating wind turbine base with flare-type tension legs, marine wind turbine and construction method
JP7417000B2 (en) Floating wind power platform with tension leg device
CN103786837B (en) Asymmetric anchoring system for supporting offshore wind turbine
US9003631B2 (en) Power generation assemblies and apparatus
KR101786063B1 (en) Support structure for an offshore wind turbine
ES2444950T3 (en) Floating offshore wind turbine
WO2015181424A1 (en) Floating structure and method of installing same
CN104816797B (en) A kind of offshore wind turbine and its installation method
JP6505840B2 (en) Floating platform for utilizing wind energy
CN104186381B (en) There is the deep water mesh cage of single point mooring system
SE2000207A1 (en) Mooring system
CN107593552A (en) A kind of twin columns flexibility culture pure seine used in shallow sea
DK202070363A1 (en) Fish farming structure
JP2022542995A (en) Ocean aquaculture fish pen
CN109430134A (en) A kind of mooring system for marine round floating net cultivation
CN106719218A (en) A kind of single-point anchoring type circular deep water net cage
KR20230135643A (en) mooring system
CN213127636U (en) Novel ship-shaped net cage structure
CN109430135A (en) A kind of mooring system for marine floating net cultivation
CN106672170B (en) Assembled A type float islands
SE2000206A1 (en) Floating wind power plant
CN111670852A (en) Net cage floating body system and purse net type net cage
CN105432532A (en) Anti-wind-wave soft deep sea net cage
NO338758B1 (en) pontoon bridge
GB2617686A (en) Mooring systems and methods for floating offshore wind turbines

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190308

RJ01 Rejection of invention patent application after publication