CN109424191A - Based on to marble, the granite laying process in building - Google Patents
Based on to marble, the granite laying process in building Download PDFInfo
- Publication number
- CN109424191A CN109424191A CN201710788960.2A CN201710788960A CN109424191A CN 109424191 A CN109424191 A CN 109424191A CN 201710788960 A CN201710788960 A CN 201710788960A CN 109424191 A CN109424191 A CN 109424191A
- Authority
- CN
- China
- Prior art keywords
- brush
- marble
- mortar
- cement
- granite
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
The invention discloses based on to marble, the granite laying process in building, including base treatment, sorting, brush cement slurry, paving screed-coat, it is laid with surface layer, the cementation of fissures, maintenance, edge patch these steps of skirting board, first plate brush water-wet is moistened before edge patch, base's watering is drenched, uniform brushing plain-water slurry, 1 ︰, 2 cement mortar edge patch is used in brush, the dimensions of skirting board should be consistent with earth material, and plate seam should be penetrated through with ground.This invention ensures that marble, granite are laid with efficiency and quality, the requirement of service life is met.
Description
Technical field
The present invention relates to a kind of architectural construction technologies, and in particular to a kind of based on to marble, the granite in building
Laying process.
Background technique
Building is based on timber buildings, and the traditional architecture in west is based on masonry structure.Modern building is then with steel
Based on reinforced concrete.
Chinese ancient architecture has simple simple and elegant style, is knot with yoke structure mainly using cogongrass, timber as construction material
Structure mode (components such as column, beam, a tree, used in making timber for boats, purlin, rafter) is combined according to actual size, shape and the spacing that structure needs.It is this
Building structure mode reflects the clear, orderly of ancient times patriarchal society structure and stablizes.Due to wooden material production beam column not
Huge inner space is easily formed, ancient architecture just dexterously using outport place, forms garden.Garden is the base of building
Our unit, it is both closed and open;Be both it is artificial and naturally, can bow and plant flowers, plants and trees, face upward and serve as a lookout
Cloud life becomes the another performance of ancients " harmony between man and nature " idea, also embodies Chinese's not only implicit introversion, but also pioneer and keep forging ahead
National character.The groups of building that ancient times somewhat larger building is all made of several gardens, single building and garden are along one
Move towards to arrange calmly, it is A distinction should be made between what is primary and what is secondary, there is climax to have transition, become the space for the depth that has levels, has, shows a kind of Chinese and chased after
The integrated beauty and deep beauty asked.Wherein palace, the building that temple one kind is more solemn, often one by one along central axes
It is longitudinally arranged key construction, monosymmetric arrangement secondary structure, arrangement balancing is unfolded, fascinating.
Ancients can achieve the effect that beauty with the design techniques such as balance, harmonious, symmetrical, light and shade axis very early.Ancient times
Weight artistic decoration is built, but uncomplicated, only makees emphasis decoration, such as window hood, lintel, ridge in main portions, layout is mostly to weigh
Square to development, skyscraper is not weighed, until there is building pagoda, high building is just able to prevailing after Buddhism is incoming.The one of building
Cutting art processing is also all processing to structural system and component, if color, decoration are in conjunction with component, constitute enrich it is gorgeous
Art achievements, carved beams and painted rafter, body are graceful and colorful;Couplet written on scrolls and hung on the pillars of a hall horizontal inscribed board, excites interest and charm and reverie is infinite, ancient architecture category
It is flouring, including palace, cemetery park, monastery, palace sight, gardens, bridge, tower brake etc..
Prior art low efficiency when being laid with marble, granite, and cause the laying quality of marble, granite
Difference can not be aligned and hollowing occurs.
Summary of the invention
The technical problem to be solved by the present invention is to prior arts when being laid with marble, granite low efficiency, Er Qiezao
Laying quality at marble, granite is poor, can not be aligned and hollowing occurs, and it is an object of the present invention to provide a kind of based on in building
Marble, granite laying process, solve prior art low efficiency when being laid with marble, granite, and cause Dali
Stone, the laying quality of granite are poor, can not be aligned and the problem of hollowing occur.
The present invention is achieved through the following technical solutions:
Based on to marble, the granite laying process in building, comprising the following steps:
(1) base treatment: it is real that the various hole gaps of flooring should fill packing with pea gravel concreten in advance, and on inspection without infiltration
Leak phenomenon, the clean no-sundries of base, no ponding;
(2) sorting: same room, the standard width of a room in an old-style house should be clear and coherent by almost the same size, uniform color, texture is selected with flower, kind
Plate carry out walkthrough to number, store classifiedly;
(3) brush cement slurry: wet base of watering, 0.5 plain-water slurry of the brush ratio of mud, cement slurry should with brush with mortar laying, and
There must not be air-dried phenomenon;
(4) it spreads screed-coat: spreading screed-coat with 1 ︰, 3 dry cement mortar, virtual resurfacing thickness is advisable with 25-30mm, is smeared with iron
Son makes real floating;
(5) it is laid with surface layer: carrying out stone by walkthrough to number when laying and overlay, T-joining should be directed at, put forth effort to tap with wooden mallet
In the middle part of plate, jolt ramming mortar starts slabstone to after being laid with height, after checking that mortar surface matches with slabstone bottom, in mortar table
Face is first sprinkled water with watering can in right amount, then uniformly spills one layer of cement powder, and slabstone block alignment paving, quadrangle will land simultaneously when paving,
Put forth effort to tap to plain with wooden mallet again, it is desirable that quadrangle is smooth, and gap is aligned in length and breadth, gap width such as without design requirement when, it is right
It should not exceed 1mm in granite, marble;
(6) cementation of fissures: paving it is complete for 24 hours after, block faces are without fracture, after hollowing on inspection, crammed with dilute cement paint brush seam it is full, and
It uses cloth to wipe with immediately net until without residual ash, stain, completes in rear plate two days and forbid pedestrian and stacked items;
(7) conserve: after topping laying, surface should cover, moisten, and curing time should not be less than 7d;
(8) edge patch skirting board: first moistening plate brush water-wet before edge patch, base is watered drenched, uniform brushing plain-water slurry,
1 ︰, 2 cement mortar edge patch is used in brush, the dimensions of skirting board should be consistent with earth material, and plate seam should be passed through with ground
It is logical.
Compared with prior art, the present invention having the following advantages and benefits: this invention ensures that marble, Hua Gang
Rock is laid with efficiency and quality, meets the requirement of service life.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, below with reference to embodiment, the present invention is made
Further to be described in detail, exemplary embodiment of the invention and its explanation for explaining only the invention, are not intended as to this
The restriction of invention.
Embodiment:
Based on to marble, the granite laying process in building, comprising the following steps:
(1) base treatment: it is real that the various hole gaps of flooring should fill packing with pea gravel concreten in advance, and on inspection without infiltration
Leak phenomenon, the clean no-sundries of base, no ponding;
(2) sorting: same room, the standard width of a room in an old-style house should be clear and coherent by almost the same size, uniform color, texture is selected with flower, kind
Plate carry out walkthrough to number, store classifiedly;
(3) brush cement slurry: wet base of watering, 0.5 plain-water slurry of the brush ratio of mud, cement slurry should with brush with mortar laying, and
There must not be air-dried phenomenon;
(4) it spreads screed-coat: spreading screed-coat with 1 ︰, 3 dry cement mortar, virtual resurfacing thickness is advisable with 25-30mm, is smeared with iron
Son makes real floating;
(5) it is laid with surface layer: carrying out stone by walkthrough to number when laying and overlay, T-joining should be directed at, put forth effort to tap with wooden mallet
In the middle part of plate, jolt ramming mortar starts slabstone to after being laid with height, after checking that mortar surface matches with slabstone bottom, in mortar table
Face is first sprinkled water with watering can in right amount, then uniformly spills one layer of cement powder, and slabstone block alignment paving, quadrangle will land simultaneously when paving,
Put forth effort to tap to plain with wooden mallet again, it is desirable that quadrangle is smooth, and gap is aligned in length and breadth, gap width such as without design requirement when, it is right
It should not exceed 1mm in granite, marble;
(6) cementation of fissures: paving it is complete for 24 hours after, block faces are without fracture, after hollowing on inspection, crammed with dilute cement paint brush seam it is full, and
It uses cloth to wipe with immediately net until without residual ash, stain, completes in rear plate two days and forbid pedestrian and stacked items;
(7) conserve: after topping laying, surface should cover, moisten, and curing time should not be less than 7d;
(8) edge patch skirting board: first moistening plate brush water-wet before edge patch, base is watered drenched, uniform brushing plain-water slurry,
1 ︰, 2 cement mortar edge patch is used in brush, the dimensions of skirting board should be consistent with earth material, and plate seam should be passed through with ground
It is logical.
This invention ensures that marble, granite are laid with efficiency and quality, the requirement of service life is met.
Above-described specific embodiment has carried out further the purpose of the present invention, technical scheme and beneficial effects
It is described in detail, it should be understood that being not intended to limit the present invention the foregoing is merely a specific embodiment of the invention
Protection scope, all within the spirits and principles of the present invention, any modification, equivalent substitution, improvement and etc. done should all include
Within protection scope of the present invention.
Claims (1)
1. based on to marble, the granite laying process in building, which comprises the following steps:
(1) base treatment: it is real that the various hole gaps of flooring should fill packing with pea gravel concreten in advance, and ne-leakage is existing on inspection
As, the clean no-sundries of base, no ponding;
(2) sorting: same room, the standard width of a room in an old-style house should be by the plates for selecting almost the same size, uniform color, texture smoothness with flower, kind
Material carries out walkthrough to number, stores classifiedly;
(3) brush cement slurry: wet base of watering, 0.5 plain-water slurry of the brush ratio of mud, cement slurry should be with brushes with mortar laying, and must not
There is air-dried phenomenon;
(4) it spreads screed-coat: spreading screed-coat with 1 ︰, 3 dry cement mortar, virtual resurfacing thickness is advisable with 25-30mm, is clapped with plasterer's trowel
It is real to smooth out;
(5) it is laid with surface layer: carrying out stone by walkthrough to number when laying and overlay, T-joining should be directed at, puted forth effort in tapping board with wooden mallet
Portion, jolt ramming mortar start slabstone to after being laid with height, after checking that mortar surface matches with slabstone bottom, in mortar surface elder generation
It is sprinkled water in right amount with watering can, then uniformly spills one layer of cement powder, slabstone block alignment paving, quadrangle will land simultaneously when paving, then use
Wooden mallet is puted forth effort to tap to plain, it is desirable that quadrangle is smooth, and gap is aligned in length and breadth, gap width such as without design requirement when, for flower
Gang Yan, marble should not exceed 1mm;
(6) cementation of fissures: paving it is complete for 24 hours after, block faces are without fracture, after hollowing on inspection, crammed with dilute cement paint brush seam it is full, and immediately
It uses cloth to wipe with net until without residual ash, stain, completes in rear plate two days and forbid pedestrian and stacked items;
(7) conserve: after topping laying, surface should cover, moisten, and curing time should not be less than 7d;
(8) edge patch skirting board: first moistening plate brush water-wet before edge patch, base is watered drenched, uniform brushing plain-water slurry, side brush
Side is inlayed with 1 ︰, 2 cement mortar and is pasted, and the dimensions of skirting board should be consistent with earth material, and plate seam should be penetrated through with ground.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710788960.2A CN109424191A (en) | 2017-09-05 | 2017-09-05 | Based on to marble, the granite laying process in building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710788960.2A CN109424191A (en) | 2017-09-05 | 2017-09-05 | Based on to marble, the granite laying process in building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109424191A true CN109424191A (en) | 2019-03-05 |
Family
ID=65513905
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710788960.2A Withdrawn CN109424191A (en) | 2017-09-05 | 2017-09-05 | Based on to marble, the granite laying process in building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109424191A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111155740A (en) * | 2020-01-06 | 2020-05-15 | 佛山宏润美嘉建材有限公司 | Marble ground construction process |
-
2017
- 2017-09-05 CN CN201710788960.2A patent/CN109424191A/en not_active Withdrawn
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111155740A (en) * | 2020-01-06 | 2020-05-15 | 佛山宏润美嘉建材有限公司 | Marble ground construction process |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Malacrino | Constructing the ancient world: Architectural techniques of the Greeks and Romans | |
CN103375000B (en) | A kind of water-soluble metal fluorocarbon coatings is coated with the construction technology on plucking surface in elasticity | |
Orlenko et al. | Conservation of the residential and public architecture of the 19th-early 20th centuries (on the examples of Kyiv and Cracow) | |
Dumarçay | Construction techniques in South and Southeast Asia: A history | |
Bonapace et al. | Traditional materials and construction technologies used in the Kathmandu valley | |
Orlenko et al. | Modern technologies in restoration of architectural monuments (on the example of St. Volodymyr's Cathedral in Chersonesos) | |
Ivashko et al. | Ways of performance and preservation of monumental art works on the facades of architectural monuments of the 19th-early 20th century | |
CN103147562A (en) | Construction method of ground cement mortar leveling | |
Ivashko et al. | Finishing Materials for Facades and Interiors of Art Nouveau Buildings. Examples of Ukraine and Poland | |
CN109424191A (en) | Based on to marble, the granite laying process in building | |
CN109424188A (en) | The technique of pouring exposed concrete is used in construction | |
CN109424189A (en) | The technique constructed in construction to rolled roofing material waterproof | |
CN109424152A (en) | The technique that ground ornamental slab for paving the floor is laid in construction | |
Baruch et al. | Excavations near the Triple Gate of the Temple Mount, Jerusalem | |
Turner et al. | The Great Tower, Chepstow Castle, Wales | |
CN107152103A (en) | A kind of clear water brick decorative wall | |
Adam | Building materials, construction techniques and chronologies | |
CN206220388U (en) | A kind of engraving structure of plastering of landscape metope | |
Marchante et al. | Characterization of traditional coatings in earthen vernacular architecture in the Limarí Valley: their role in the conservation of built heritage in Chile | |
Sweek et al. | Architectural conservation of an Amun temple in Sudan | |
Lowther | Report on Excavations at Verulamium in 1934 | |
Orlenko et al. | RESTORATION AND PRESERVATION PROCEDURE OF ARCHITECTURAL MONUMENTS. RAILWAY STATIONS WITH MONUMENTAL ART OF THE SOCIALIST PERIOD (ON THE EXAMPLES OF UKRAINE AND POLAND). | |
Ashurst | Methods of repairing and consolidating stone buildings | |
Orlenko et al. | The role of the tenement housing development in the urban structure of Western and Central Ukraine during the Secession era | |
CN109424149A (en) | Based on the method to brick wall tiling in building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20190305 |