CN109403517A - A kind of construction of plaster wall - Google Patents

A kind of construction of plaster wall Download PDF

Info

Publication number
CN109403517A
CN109403517A CN201811173632.2A CN201811173632A CN109403517A CN 109403517 A CN109403517 A CN 109403517A CN 201811173632 A CN201811173632 A CN 201811173632A CN 109403517 A CN109403517 A CN 109403517A
Authority
CN
China
Prior art keywords
wall
plaster wall
plaster
construction
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811173632.2A
Other languages
Chinese (zh)
Inventor
刘斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shijiazhuang Jia Jia Energy-Saving Products Technology Co Ltd
Original Assignee
Shijiazhuang Jia Jia Energy-Saving Products Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shijiazhuang Jia Jia Energy-Saving Products Technology Co Ltd filed Critical Shijiazhuang Jia Jia Energy-Saving Products Technology Co Ltd
Priority to CN201811173632.2A priority Critical patent/CN109403517A/en
Publication of CN109403517A publication Critical patent/CN109403517A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/08Forms, which are completely dismantled after setting of the concrete and re-built for next pouring
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/08Forms, which are completely dismantled after setting of the concrete and re-built for next pouring
    • E04G11/085End form panels for walls

Abstract

The invention belongs to the wall construction fields based on gypsum building materials, and in particular to a kind of construction of plaster wall.The present invention builds the wall of plaster wall using the method constructed paragraph by paragraph, a small amount of template is only needed to be had enough to meet the need in work progress, and since the setting rate of gypsum material is fast, template is almost not subject to lateral pressure, therefore aluminium alloy even plastic formwork can be used in template, substantially reduces the cost of template, and template weight reduces, fast and easy is had enough to meet the need while reducing personnel's physical demand, is greatly facilitated the rapid construction of plaster wall.

Description

A kind of construction of plaster wall
Technical field
The invention belongs to the wall construction fields based on gypsum building materials, and in particular to a kind of construction of plaster wall.
Background technique
Using gypsum as construction material, especially using the tailing ardealite of chemical fertilizer production as construction material, can either solve It certainly the problem of ardealite exhaust emission environment, and can solve the high problem of construction material cost, be to kill two birds with one stone, Using the construction method of conventional concrete material because of length the time required to concrete setting, large area formwork is needed, concrete is whole Body pour after maintenance the long period could demoulding, the turn around time of template is long, and the template number disposably occupied is more, construction cost It is higher, and the setting rate block of gypsum material, according to construction technology identical with conventional concrete, it is difficult to it is superior to embody its Property.
Summary of the invention
The present invention is in order to solve above-mentioned problems of the prior art, and the present invention provides a kind of construction works of plaster wall Method can effectively improve construction efficiency, and form cycling rate is accelerated, and the dosage of template is greatly reduced, and reduce construction cost.
The specific technical solution that the present invention uses is:
A kind of construction of plaster wall, includes the following steps:
A, wall position is determined on ground according to design planning and formwork forms wall and pours chamber,
B, to wall pour it is intracavitary pour gypsum slurry,
C, demoulding after the completion of gypsum slurry pours, demoulding gypsum slurry initial set simultaneously form plaster wall section,
D, the template removed using step c and the plaster wall section are surrounded next section of wall jointly and pour chamber,
E, above-mentioned a is repeated to Step d, is constructed paragraph by paragraph, and whole plaster wall is completed.
The plaster wall section and next section of wall pour and are provided with connecting structure on the face of plugging into of chamber.
The connecting structure is concave convex groove structure.
The forming method of the concave convex groove structure is,
It is poured in the step a in formwork formation wall and adds tongue and groove module in chamber, which is set to stone In template corresponding to the face of plugging into of cream wall section, concave convex groove structure is formed after step b is poured.
It is previously provided on the ground and leads wall construction for carry plaster wall.
Described leads the positioning structure for formwork for having additional on wall and being laid with along plaster wall design direction.
The connecting structure is the hole of plugging into for the group pattern formula arrangement horizontally dug on the face of plugging into.
Unilateral or bilateral linear queue shape setting of the positioning structure for formwork in plaster wall, the Template Location Structure includes the locating piece of multiple spaced L-shaped structures, and the horizontal position of the locating piece is on the inside of plaster wall, institute The vertical portion for the locating piece stated is coplanar with plaster wall metope, and the locating piece is fixedly connected by peg with wall is led.
Staggeredly portion is overlapped to form between the template and plaster wall section, forms sealing knot by template clamping plaster wall section Structure.
The wall, which pours, intracavitary is provided with Screw arbor with nut at both-ends casing.
The beneficial effects of the present invention are:
The present invention builds the wall of plaster wall using the method constructed paragraph by paragraph, and a small amount of template is only needed to carry out in work progress Turnover, and since the setting rate of gypsum material is fast, template is almost not subject to lateral pressure, therefore aluminium can be used in template Alloy even plastic formwork, substantially reduces the cost of template, and template weight reduces, and facilitates while reducing personnel's physical demand fast Speed turnover, is greatly facilitated the rapid construction of plaster wall.
Detailed description of the invention
Fig. 1 is that wall of the invention pours the structural schematic diagram after chamber assembling;
Fig. 2 is the structural schematic diagram after splitting at template in Fig. 1;
In attached drawing, 1, wall pour chamber, 2, plaster wall section, 3, template, 4, lead wall, 201, face of plugging into, 202, hole of plugging into, 301, tongue and groove module, 302, staggeredly portion, 303, Screw arbor with nut at both-ends casing, 401, locating piece.
Specific embodiment
With reference to the accompanying drawing and specific embodiment the invention will be further described:
Specific embodiment, as shown in Figures 1 and 2, the present invention are a kind of construction of plaster wall, are included the following steps:
A, wall position is determined on ground according to design planning and formwork forms wall and pours chamber 1,
B, it is poured in chamber 1 to wall and pours gypsum slurry,
C, demoulding after the completion of gypsum slurry pours, demoulding gypsum slurry initial set simultaneously forms plaster wall section, because of gypsum itself Setting rate Quickly, that is, demoulding pours and completes the gypsum that pours in chamber 1 of back wall and largely solidify, and demoulding while is surplus The slurry that remaining top finally pours also gradually solidifies, thus can demoulding immediately, or for guarantee solidification completely also stand wait, the time Less than or equal to 5 minutes,
D, the template 3 and the plaster wall section 2 removed using step c is surrounded next section of wall jointly and pours chamber 1,
E, above-mentioned a is repeated to Step d, is constructed paragraph by paragraph, and whole plaster wall is completed.
Formwork way uses common formwork way in the present invention, and template is by 303 formation width size of Screw arbor with nut at both-ends casing Stable wall pours chamber 1, and construction site carries out the stirring of land plaster, and by expecting that the gypsum slurry being stirred is pumped by pump Wall pours in chamber 1, since gypsum slurry solidifies rapid feature, while being pumped into wall and pour in chamber 1, and the gypsum of lower layer Just gradually solidification upwards can almost be set about preparing form removal 3, by template slurry simultaneously after wall, which pours chamber 1, to be filled After 3 remove, next section of plaster wall section is poured by this plaster wall section 2 formed, to gradually pour the whole gypsum of completion Wall does not need a large amount of template 3 in work progress, only needs the template of enough plaster wall sections, template turnover rapidly, greatly Production cost has been saved greatly, using gradually pouring, the mode formed paragraph by paragraph, between the time formed between adjacent plaster wall section 2 Every short, the cementability at seam of plugging into is good and each plaster wall section it is dry the time required to it is close, wall integrity can be excellent, is not easy There is crack.
Further, as shown in Figures 1 and 2, the plaster wall section 2 and next section of wall pour the plugging on face 201 of chamber 1 It is provided with connecting structure.The connecting structure is concave convex groove structure.
The forming method of the concave convex groove structure is,
It is poured in the step a in formwork formation wall and adds tongue and groove module 301 in chamber 1, which sets It is placed in the plugging into template 3 corresponding to face 201 of plaster wall section 2, forms concave convex groove structure after step b is poured.
The connecting structure of setting is used to connect the adjacent plaster wall section 2 in front and back, and the setting of concave convex groove structure is so that seam of plugging into Contact area increase, improve the effect of bonding, the moisture of front-back wall section, which exchanges, to be increased, the rate of drying both enable compared with To be consistent, it is located in the plaster wall section 2 of the preceding paragraph additionally, due to concave convex groove structure further groove, and next section of plaster wall section 2 is suitable Gesture is formed as tongue structure, and still than the tongue position of rear solidification drying shrinkage can occur earlier for the groove position solidified first, so that The nesting of tongue and groove is even closer, and switching performance is further promoted.
In addition, using tongue and groove module 301 formed groove structure, the two contact area is small, and can by template 3 separate after again Rod-shaped tongue and groove module 301 is taken out, tongue and groove module 301 is separated with wall easily, wall is avoided to damage, so that wall The pouring quality of body gets a promotion.
Further, it is previously provided on the ground and leads 4 structure of wall for carry plaster wall.Lead wall 4 on the one hand Carrying basis is provided for plaster wall, the plaster wall more to absorb water is on the other hand pulled away into ground, the moisture in ground is avoided to infect Plaster wall guarantees the durable of plaster wall.
Further, the connecting structure is plugging into for the group pattern formula arrangement horizontally dug on the face of plugging into Hole 202.The linear array equally of hole 202 of plugging into or the multiple lines and multiple rows formula array of matrix form arrangement, when next section of plaster wall The gypsum slurry of liquid fills up hole 202 of plugging into when section pours, and forms the horse tooth trough structure of similar traditional brick wall, improves two successively The switching performance of the wall section of formation, since plaster wall section is merely through initial set, hardness at this time is lower, homogeneous, using electric drill The mode of punching can be obtained pore structure of plugging into, and operation is more convenient, can promote working efficiency.
Further, described to lead the positioning structure for formwork for having additional on wall 4 and being laid with along plaster wall design direction.Described For positioning structure for formwork in the linear queue shape setting of unilateral or bilateral of plaster wall, the positioning structure for formwork includes multiple Every the locating piece 401 of the L-shaped structure of setting, the horizontal position of the locating piece 401 is on the inside of plaster wall, the positioning The vertical portion of block 401 is coplanar with plaster wall metope, and the locating piece 401 is fixedly connected by peg with wall 4 is led.
Locating piece 401 is followed closely on leading wall 4 by peg, locating piece 401 is sleeved on wall in formwork and is poured in chamber 1 Portion, the vertical portion of locating piece 401 is bonded with the inside of template 3 at this time, is formed position-limiting action to template 3, is avoided pouring middle because of stone The template 3 for pouring into and causing quality lighter of cream slurry is displaced, and when pouring completion and needing demoulding or moving die plate, is borrowed The barrier effect for helping locating piece 401 avoids sharp template edge and scratches the plaster wall not yet solidified completely, in this way can Shorten the waiting time, improve the turnaround speed of template, when template 3 is mobile, it is to be poured to next section that template 3 is pulled from worker Wall position is mobile, ensure that the straight of front-back wall section, locating piece 401 reduce template by the guiding role of locating piece 401 Friction between plaster wall enables worker more easily to carry out the movement of template, greatly improves construction efficiency.
Further, staggeredly portion 302 are overlapped to form between the template 3 and plaster wall section 2, clamps stone by template 3 Cream wall section 2 forms sealing structure.Soon, quality is softer for the just solidification of plaster wall section 2 at this time, forms such as Fig. 1 by the clamping of template 3 Shown in staggeredly behind portion 302, on the one hand prevent the gypsum slurry newly poured from strutting groove position, on the other hand by it is this compared with Crevice place is sealed for soft wall section, avoids slurry from leaking out, ensure that the planarization of front-back wall section, substantially reduces later period finishing Cost.

Claims (10)

1. a kind of construction of plaster wall, characterized by the following steps:
A, wall position is determined on ground according to design planning and formwork forms wall and pours chamber,
B, to wall pour it is intracavitary pour gypsum slurry,
C, demoulding after the completion of gypsum slurry pours, demoulding gypsum slurry initial set simultaneously form plaster wall section,
D, the template removed using step c and the plaster wall section are surrounded next section of wall jointly and pour chamber,
E, above-mentioned a is repeated to Step d, is constructed paragraph by paragraph, and whole plaster wall is completed.
2. a kind of construction of plaster wall according to claim 1, it is characterised in that: the plaster wall section and next section Wall pours and is provided with connecting structure on the face of plugging into of chamber.
3. a kind of construction of plaster wall according to claim 2, it is characterised in that: the connecting structure is bumps Slot structure.
4. a kind of construction of plaster wall according to claim 3, it is characterised in that: the concave convex groove structure at Type method is,
It is poured in the step a in formwork formation wall and adds tongue and groove module in chamber, which is set to plaster wall In template corresponding to the face of plugging into of section, concave convex groove structure is formed after step b is poured.
5. a kind of construction of plaster wall according to claim 2, it is characterised in that: the connecting structure is to connect Refute the hole of plugging into for the group pattern formula arrangement horizontally dug on face.
6. a kind of construction of plaster wall according to claim 1, it is characterised in that: preset on the ground Have and leads wall construction for carry plaster wall.
7. a kind of construction of plaster wall according to claim 6, it is characterised in that: described leading has additional edge on wall The positioning structure for formwork that plaster wall design direction is laid with.
8. a kind of construction of plaster wall according to claim 7, it is characterised in that: the positioning structure for formwork exists The linear queue shape setting of the unilateral or bilateral of plaster wall, the positioning structure for formwork includes multiple spaced L-shaped The locating piece of structure, the horizontal position of the locating piece is on the inside of plaster wall, the vertical portion of the locating piece and plaster wall Metope is coplanar, and the locating piece is fixedly connected by peg with wall is led.
9. a kind of construction of plaster wall according to claim 1, it is characterised in that: the template and plaster wall section Between overlap to form staggeredly portion, by template clamping plaster wall section formed sealing structure.
10. a kind of construction of plaster wall according to claim 1, it is characterised in that: the wall pours intracavitary It is provided with Screw arbor with nut at both-ends casing.
CN201811173632.2A 2018-10-09 2018-10-09 A kind of construction of plaster wall Pending CN109403517A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811173632.2A CN109403517A (en) 2018-10-09 2018-10-09 A kind of construction of plaster wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811173632.2A CN109403517A (en) 2018-10-09 2018-10-09 A kind of construction of plaster wall

Publications (1)

Publication Number Publication Date
CN109403517A true CN109403517A (en) 2019-03-01

Family

ID=65466875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811173632.2A Pending CN109403517A (en) 2018-10-09 2018-10-09 A kind of construction of plaster wall

Country Status (1)

Country Link
CN (1) CN109403517A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110206139A (en) * 2019-06-05 2019-09-06 贵州百胜工程建设咨询有限公司 A kind of mass concrete construction method
CN112727072A (en) * 2020-12-24 2021-04-30 天蓬智慧建造(广东)科技有限公司 Construction method of cast-in-place wall

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090249725A1 (en) * 2008-04-03 2009-10-08 Mcdonagh Greg Wall forming system and method thereof
EP2221425A1 (en) * 2009-02-20 2010-08-25 Algemene Participatie Kerkhofs, afgekort APK Wall frame
CN101886402A (en) * 2010-07-13 2010-11-17 中铁三局集团有限公司 Diaphragm wall seam waterproof method and diaphragm wall construction method based on same
CN101914991A (en) * 2010-04-02 2010-12-15 曾周亮 Gypsum wall in-situ concreting equipment system and construction method thereof
CN104074285A (en) * 2014-06-30 2014-10-01 浙江省二建建设集团有限公司 ultra-long concrete wall body structure and method for controlling structural cracks by constructing wall body
CN105804294A (en) * 2016-05-10 2016-07-27 天津城建大学 Composite rammed-earth wall, template device adopted in construction thereof and construction method thereof
CN106013086A (en) * 2016-06-23 2016-10-12 程华清 Construction method for processing underground continuous wall joint through boss type I-steel joint box

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090249725A1 (en) * 2008-04-03 2009-10-08 Mcdonagh Greg Wall forming system and method thereof
EP2221425A1 (en) * 2009-02-20 2010-08-25 Algemene Participatie Kerkhofs, afgekort APK Wall frame
CN101914991A (en) * 2010-04-02 2010-12-15 曾周亮 Gypsum wall in-situ concreting equipment system and construction method thereof
CN101886402A (en) * 2010-07-13 2010-11-17 中铁三局集团有限公司 Diaphragm wall seam waterproof method and diaphragm wall construction method based on same
CN104074285A (en) * 2014-06-30 2014-10-01 浙江省二建建设集团有限公司 ultra-long concrete wall body structure and method for controlling structural cracks by constructing wall body
CN105804294A (en) * 2016-05-10 2016-07-27 天津城建大学 Composite rammed-earth wall, template device adopted in construction thereof and construction method thereof
CN106013086A (en) * 2016-06-23 2016-10-12 程华清 Construction method for processing underground continuous wall joint through boss type I-steel joint box

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110206139A (en) * 2019-06-05 2019-09-06 贵州百胜工程建设咨询有限公司 A kind of mass concrete construction method
CN112727072A (en) * 2020-12-24 2021-04-30 天蓬智慧建造(广东)科技有限公司 Construction method of cast-in-place wall
CN112727072B (en) * 2020-12-24 2023-02-28 广东天凛高新科技有限公司 Construction method of cast-in-place wall

Similar Documents

Publication Publication Date Title
CN109403517A (en) A kind of construction of plaster wall
CN105971160A (en) Method for preventing 3D printing reinforced masonry shear wall being unshelled
CN106593468B (en) Tunnel inverted arch concrete lining sliding formwork and construction method
CN206256914U (en) Tunnel inverted arch concrete lining sliding formwork
CN203007762U (en) Hole sealing locating device for karst treatment
CN208594572U (en) Single layer double cabin pipe galleries in underground are hydraulic from walking formwork jumbo
CN207260636U (en) Pipe die reinforced column supporting member
CN106703377A (en) Automatic floor tile paving machine
CN109763399A (en) A kind of one body swimming ditch construction mould and construction method
CN203808082U (en) Slope-cast planting eco-concrete anti-overflow device
CN109162461B (en) Lower chord plate pouring equipment for arch plate concrete pouring construction
CN205875451U (en) Prefabricated festival of brickwork wall constructional column
CN109356161B (en) Low-layer high-frequency inclined surface layered concrete pouring method for large-scale hydropower well bent pipe section
CN209425771U (en) A kind of six rib brick automatic demoulding machine of new and effective concrete hollow
CN201168996Y (en) Gridding cloth press-in device for gypsum decorative line
CN213352889U (en) Concrete slab pouring device
CN206825628U (en) A kind of Construction of Civil Engineering pours device with concrete slab
CN103590371A (en) Concrete pouring machine for U-shaped trench
CN106337509A (en) Prefabricated segment of masonry wall constructional column
CN207194439U (en) Cornerite plywood form
CN107366425B (en) Facilitate the concrete blinding of installation
CN206607606U (en) A kind of combined type piping lane moving lifting support day face die plate
CN203654242U (en) Concrete pouring machine for U-shaped ditch
CN205637571U (en) Do not have outside secret building wall who is detained pipe and pour template
CN106193420A (en) A kind of ceramic tile building block

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190301

RJ01 Rejection of invention patent application after publication