CN109403324A - A kind of diesel hammer hammer body and pile cover buffer control method and it connect buffer structure - Google Patents

A kind of diesel hammer hammer body and pile cover buffer control method and it connect buffer structure Download PDF

Info

Publication number
CN109403324A
CN109403324A CN201811545407.7A CN201811545407A CN109403324A CN 109403324 A CN109403324 A CN 109403324A CN 201811545407 A CN201811545407 A CN 201811545407A CN 109403324 A CN109403324 A CN 109403324A
Authority
CN
China
Prior art keywords
hammer
connection
diesel
pile cover
diesel hammer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811545407.7A
Other languages
Chinese (zh)
Inventor
赵波
周天辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG LIYUAN HYDRAULIC MACHINERY Co Ltd
Original Assignee
GUANGDONG LIYUAN HYDRAULIC MACHINERY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG LIYUAN HYDRAULIC MACHINERY Co Ltd filed Critical GUANGDONG LIYUAN HYDRAULIC MACHINERY Co Ltd
Priority to CN201811545407.7A priority Critical patent/CN109403324A/en
Publication of CN109403324A publication Critical patent/CN109403324A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers
    • E02D7/12Drivers with explosion chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/10Follow-blocks of pile-drivers or like devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a kind of diesel hammer hammer bodies and pile cover buffer control method comprising following steps: (1) connecting buffer structure with pile cover junction setting one in diesel hammer hammer body;(2) connection buffer structure is set in the movable rail of piston, is connected and fixed by the first connection bolt with hammer body, is connected and fixed by the second connection bolt with pile cover;(3) diesel hammer lower piston is made to move reciprocatingly.The present invention pushes lower piston to move back and forth using fuel oil explosion, and lower piston is directly acted on drill rod in a manner of impacting, then returned;Lower piston and drill rod produced strong vibration wave when colliding first are passed to connection buffer structure by hammer body and pass to pile cover again, to avoid the damage for causing hammer body or pile cover.The present invention also provides it is a kind of implement the above method connection buffer structure, by optimizing structure design, separate inertia system achieve the purpose that improve piling machine power, reduce failure rate, extend bulk life time.

Description

A kind of diesel hammer hammer body and pile cover buffer control method and it connect buffer structure
Technical field
The present invention relates to piling machine equipment manufacturing technology field, in particular to a kind of diesel hammer hammer body and pile cover cushioning control Method and connection buffer structure.
Background technique
Diesel hammer is one kind of building machinery, is the conventional machinery equipment in construction, is mainly pushed away using fuel oil explosion Piston moves back and forth and impact pile driving, and piston weight is from several hundred kilograms to several tons.With the suitable weight tap of hammer piling.If weight Bang then hammers function and is largely absorbed by pile body, and stake is not easy to squeeze into, and pile crown is easily broken.Hammer weight preferably has certain with stake weight Ratio, or control hammering stress, are broken to prevent stake.Pile frame is to support pile body and pile monkey, and the direction of stake is guided in pile driving process, And enable pile monkey along the pile driving equipment of desired direction impact.
Current hammer class building machinery is to solve hydraulic hammer hammer body to be easy to hammer the vibration generated after effective object effect The problem of body itself damages, application for a patent for invention " a kind of hydraulic hammer protection that number of patent application is 201710735454.7 Device and the means of defence that hydraulic hammer is buffered ", by the way that buffer gear is arranged between oil cylinder and weight, by spring and The double buffering of bolster is combined, and buffers the entire action process of weight effectively;In the time that weight falls, rebounds Section, has enough or necessary space and technical measures, guarantees that cylinder piston rod continues deceleration downlink, piston rod is made to have neither part nor lot in weight The later period rebound acceleration in rebound process or the later period for being only involved in rebound process, the process that rebounds significantly is decayed, or even is tended to 0, simultaneously because evade or significantly reduce the adverse effect that weight rebounds to cylinder piston rod or the parts for being mounted on piston rod, Cylinder piston rod and the parts for being mounted on piston rod do not rebound or slightly rebound, and not only protect oil cylinder, also protect rack and With the associated equipment other parts of rack, the stability of whole device is significantly improved, that improves each part of appliance indirectly uses the longevity Life.Above-mentioned buffer structure protects hookup, spring, washer, connecting piece, gland, fastener, bolster, washer, lock washer Etc. more spare part, each spare part assists work to provide pooling feature for hydraulic hammer hammer body simultaneously, and structure design is also more multiple It is miscellaneous.It should be worked in high speed, the piling of high frequency time since its spare part quantity is more, assembly relation is complicated, overall weight is also larger Cheng Zhong, part spare part is easy to appear fatigue, damage, so as to cause the global failure of the buffer structure, easily to the whole of hydraulic hammer Body structure damages, while being also unfavorable for the maintenance and replacement in later period.
Summary of the invention
Present invention aims at provide a kind of diesel hammer hammer body and pile cover buffering controlled for the above-mentioned deficiency of the prior art Method processed and the connection buffer structure for implementing this method focus on the structure design for optimizing the prior art and control step Suddenly, inertia system is separated, structure design and control technique is made to reach Synchronous fluorimetry.Especially by diesel hammer hammer body and diesel hammer Pile cover junction setting connection buffer structure, the diesel hammer hammer body for connecting the connection of buffer structure two sides and diesel hammer pile cover are divided At two different inertia systems, vibration wave and noise because of piston and drill rod collision are absorbed, substantially reduces vibration wave to bavin The damage of oil hammer hammer body and pile cover avoids each spare part from failing, avoids diesel oil to avoid local lesion caused by vibration wave Internal component is hammered into shape because of component aging or damage caused by colliding the vibration wave generated, that improves diesel hammer internal component uses the longevity Life.
To achieve the above object, the technical scheme adopted by the invention is that:
A kind of diesel hammer hammer body and pile cover buffer control method comprising following steps:
(1) buffer structure is connect with diesel hammer pile cover junction setting one in diesel hammer hammer body;
(2) the connection buffer structure is set in the movable rail of diesel hammer lower piston, by first connection bolt with Diesel hammer hammer body is connected and fixed, and is connected and fixed by the second connection bolt with diesel hammer pile cover;
(3) so that diesel hammer lower piston is moved reciprocatingly: pushing lower piston to move back and forth using fuel oil explosion, it is living under diesel hammer Plug is directly acted in a manner of impacting on the drill rod of diesel hammer, by the direct effect between diesel hammer lower piston and drill rod, To after diesel hammer lower piston hits drill rod, return up movement initial position in injection rock;
When fuel oil explodes, and diesel hammer lower piston and drill rod is pushed to be collided, strong vibration wave can be generated, the vibration is made Dynamic wave is first passed to connection buffer structure by hammer body, is absorbed by it, is passed to pile cover again after delay, stays to avoid the vibration wave It stays on hammer body while also the vibration wave being avoided to be directly delivered on pile cover, cause the damage of hammer body or pile cover.
As a further improvement of the present invention, further comprising the steps of:
(4) after diesel hammer lower piston and drill rod occur to hit acting, diesel hammer lower piston returns up activity initial bit When setting, diesel hammer lower piston can collide to generate shock wave again with hammer body, so that the vibration wave is first passed to connection slow Structure is rushed, absorbed by it, pass to hammer body again after delay, avoided the vibration wave from being directly delivered to hammer body, cause the damage of hammer body Wound.
As a further improvement of the present invention, the step (2) is further comprising the steps of:
(21) cushion and outer cushion in being arranged in the structure, the interior cushion and outer cushion are multilayer The structural adhesive layer of double-sides belt iron plate, according to the size and speed of piling stroke and produced vibration wave in the buffer structure The rigidity of cushion and outer cushion is adjusted: by the glue-line quantity in increase and decrease cushion, and/or adjusting glue-line simultaneously Pre compressed magnitude, so that the rigidity of the cushion structure is reached the range of setting and is buffered to diesel hammer lower piston.
It is a kind of implement the above method diesel hammer hammer body connect buffer structure with pile cover, be set to diesel hammer hammer body and stake It between cap and is set in the movable rail of diesel hammer lower piston, including the first connection bolt, the second connection bolt, method in connection Blue, semicircle baffle ring and connection outward flange, the connection inner flange are sheathed on diesel hammer lower piston and are connected with semicircle baffle ring It connects, the connection outward flange is connected and fixed with the connection inner flange having connected with semicircle baffle ring, on the connection outward flange It is provided with the through-hole for placing and fixing the first connection bolt and the second connection bolt, the first connection bolt passes through institute It states connection outward flange and will be attached fixed semicircle baffle ring with diesel hammer hammer body, connect inner flange and connected outward flange and consolidate Due on the diesel hammer hammer body, the first connection bolt passes through the connection outward flange will connect with diesel hammer pile cover Fixed semicircle baffle ring, connection inner flange and connection outward flange is connect to be fixed on the diesel hammer pile cover.
It as a further improvement of the present invention, further include interior cushion and outer cushion, the interior cushion is set to Connect inner flange on, the outer cushion is set on the connection outward flange, respectively with diesel hammer lower piston, connect outer method Blue and semicircle baffle ring is connected.
As a further improvement of the present invention, the interior cushion and outer cushion are the glue of the double-sides belt iron plate of multilayer Layer structure is adjusted the overall stiffness of inside and outside cushion according to the size and speed of piling stroke and produced vibration wave: By the glue-line quantity in increase and decrease glue-line, and/or the pre compressed magnitude of glue-line is adjusted simultaneously, reach the rigidity of the connection buffer structure To the range of setting.
As a further improvement of the present invention, the outer connecting flange is integrated the molding flange workpiece of forging process.
As a further improvement of the present invention, the interior connecting flange carries out processing point after being integrated forging process molding again For the flange workpiece of two halves.
Above-mentioned diesel hammer hammer body connect the erection sequence of buffer structure with pile cover:
1) cushion in installing;
2) connection inner flange is inserted in lower piston;
3) connection inner flange is connect with semicircle baffle ring;
4) mounted connection inner flange and semicircle baffle ring are mounted on connection outward flange;
5) by it is above-mentioned have connected fixed workpiece the first connection bolt integrally used to connect bolt with second be mounted on bavin On oil hammer hammer body and diesel hammer pile cover;
6) outer cushion is installed;
7) pile cover and drill rod are installed.
It has the advantage that compared with prior art:
1, diesel hammer hammer body of the present invention and pile cover buffer control method and it is connect buffer structure, focuses on optimizing structure Design and rate-determining steps, separate different inertia systems, so that structure design and control technique is reached Synchronous fluorimetry: by diesel oil Hammer hammer body connect buffer structure with diesel hammer pile cover junction setting one, which is set to the activity of diesel hammer lower piston On track, connection and buffering are provided between diesel hammer hammer body and diesel hammer pile cover, after acting on diesel hammer lower piston to drill rod The vibration wave of generation is quickly exported to the buffer structure first, is absorbed using the buffer structure, after delay, to diesel hammer hammer body And pile cover conduction, the rigid connection inside diesel hammer is improved to elastic connection, it can be by the connection of connection buffer structure two sides Diesel hammer hammer body and diesel hammer the pile cover inertia system that be divided into two different, absorb the vibration wave because of piston and drill rod collision And noise, substantially reduce damage of the vibration wave to diesel hammer hammer body and pile cover, to avoid locally damaging caused by vibration wave Evil avoids each spare part from failing, and avoids component aging or damage caused by vibration wave of the diesel hammer internal component because colliding generation, Improve the service life of diesel hammer internal component;
2, the interior cushion in present invention connection buffer structure and outer cushion are the glue-line of the double-sides belt iron plate of multilayer Structure is adjusted the overall stiffness of the buffer structure according to the size and speed of piling stroke and produced vibration wave: logical The glue-line quantity in increase and decrease glue-line is crossed, and/or adjusts the pre compressed magnitude of glue-line simultaneously, reaches the rigidity of the connection buffer structure The range of setting;
3, the interior connecting flange in present invention connection buffer structure is used with outer connecting flange and is used in the prior art Split flange different Integral flange structures, China and foreign countries' connecting flange is completed by integrated forging process, interior By dimidiation after the completion of integrated forging process, for split type structure flange, on the one hand connecting flange is The intensity of flanged joint is strengthened, on the other hand more preferable fixed hammer body, connecting flange, outer cushion are connected with pile cover.
The present invention separates inertia system by the Synchronous fluorimetry to structure and control technique, enhances buffering effect, reaches and mention High piling machine power, the purpose for reducing failure rate, extending the service life.
In order to explain the structural features and functions of the invention more clearly, come with reference to the accompanying drawing with specific embodiment to its into Row is described in detail.
Detailed description of the invention
Fig. 1 is the overall structure diagram that diesel hammer hammer body of the present invention connect buffer structure with pile cover.
In attached drawing: 1, hammer body;2, pile cover;3, lower piston;4, the first connection bolt;5, the second connection bolt;6, drill rod 6; 7, interior cushion;8, outer cushion;9, inner flange is connected;10, semicircle baffle ring;11, outward flange is connected.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Referring to Fig. 1, a kind of diesel hammer hammer body and pile cover buffer control method provided by the invention comprising following steps:
(1) buffer structure is connect with 2 junction of diesel hammer pile cover setting one in diesel hammer hammer body 1;
(2) the connection buffer structure is set in the movable rail of diesel hammer lower piston 3, passes through the first connection bolt 4 It is connected and fixed with diesel hammer hammer body 1, is connected and fixed by the second connection bolt 5 with diesel hammer pile cover 2;
(3) so that diesel hammer lower piston 3 is moved reciprocatingly: pushing lower piston to move back and forth using fuel oil explosion, under diesel hammer Piston 3 is directly acted in a manner of impact on the drill rod 6 of diesel hammer, by direct between diesel hammer lower piston 3 and drill rod 6 Effect, to after diesel hammer lower piston 3 hits drill rod 6, return up movement initial position in injection rock;
When fuel oil explodes, and diesel hammer lower piston 3 and drill rod 6 is pushed to be collided, strong vibration wave can be generated, this is made Vibration wave first passes to connection buffer structure by hammer body 1, absorbs by it, passes to pile cover 2 again after delay, to avoid the vibration Wave resides on hammer body 1 while also the vibration wave being avoided to be directly delivered to the damage for causing hammer body 1 or pile cover 22 on pile cover.
As a further improvement of the present invention, further comprising the steps of:
(4) after diesel hammer lower piston 3 and drill rod 6 occur to hit acting, diesel hammer lower piston 3 returns up movable initial When position, diesel hammer lower piston 3 can collide to generate shock wave again with hammer body 1, make the vibration wave first company of passing to Buffer structure is connect, absorbed by it, pass to hammer body 1 again after delay, avoided the vibration wave from being directly delivered to hammer body 1, cause to hammer into shape The damage of body 1.
As a further improvement of the present invention, the step (2) is further comprising the steps of:
(21) cushion and outer cushion in being arranged in the structure, the interior cushion 7 and outer cushion 8 are multilayer Double-sides belt iron plate structural adhesive layer, according to piling stroke and produced vibration wave size and speed in the buffer structure The rigidity of interior cushion 7 and outer cushion 8 is adjusted: by the glue-line quantity in increase and decrease cushion, and/or adjusting simultaneously The pre compressed magnitude of glue-line makes the rigidity of the cushion structure reach the range of setting and buffer to diesel hammer lower piston 3.
It is a kind of implement the above method diesel hammer hammer body connect buffer structure with pile cover, be set to diesel hammer hammer body 1 and It between pile cover 2 and is set in the movable rail of diesel hammer lower piston 3, including the first connection bolt 4, second connects bolt 5, connects Connect inner flange 9, semicircle baffle ring 10 and connection outward flange 11, the connection inner flange 9 be sheathed on diesel hammer lower piston 3 and with Semicircle baffle ring is connected, and the connection outward flange 11 is connected and fixed with the connection inner flange 9 having connected with semicircle baffle ring 10, The through-hole for placing and fixing the first connection bolt 4 and the second connection bolt 5, institute are provided on the connection outward flange 11 State the first connection bolt 4 across the connection outward flange 11 and diesel hammer hammer body 1 will be attached fixed semicircle baffle ring 10, Connection inner flange 9 and connection outward flange 11 are fixed on the diesel hammer hammer body 1, and the first connection bolt 4 passes through described Fixed semicircle baffle ring 10 will be attached, connect inner flange 9 and has connected outer method with diesel hammer pile cover 2 by connecting outward flange 9 Orchid 11 is fixed on the diesel hammer pile cover 2.
It as a further improvement of the present invention, further include interior cushion 7 and outer cushion 8, the interior cushion 7 is arranged In connection inner flange 9 on, the outer cushion 8 is set on the connection outward flange 11, respectively with diesel hammer lower piston 3, Connection outward flange 11 and semicircle baffle ring 10 are connected.
As a further improvement of the present invention, the interior cushion 7 and outer cushion 8 are the double-sides belt iron plate of multilayer Structural adhesive layer adjusts the overall stiffness of inside and outside cushion according to the size and speed of piling stroke and produced vibration wave Section: by the glue-line quantity in increase and decrease glue-line, and/or the pre compressed magnitude of glue-line is adjusted simultaneously, make the rigid of the connection buffer structure Degree reaches the range of setting.
As a further improvement of the present invention, the outer connecting flange is integrated the molding flange workpiece of forging process.
As a further improvement of the present invention, the interior connecting flange carries out processing point after being integrated forging process molding again For the flange workpiece of two halves.
Above-mentioned diesel hammer hammer body connect the erection sequence of buffer structure with pile cover:
1) cushion 7 in installing;
2) connection inner flange 9 is inserted in lower piston 9;
3) connection inner flange 9 is connect with semicircle baffle ring 10;
4) mounted connection inner flange 11 and semicircle baffle ring 10 are mounted on connection outward flange 11;
5) by it is above-mentioned have connected fixed workpiece the first connection bolt 4 integrally used to connect bolt 5 with second be mounted on On diesel hammer hammer body 1 and diesel hammer pile cover 2;
6) outer cushion 8 is installed;
7) pile cover 2 and drill rod 6 are installed.
The present invention separates inertia system by the Synchronous fluorimetry to structure and control technique, enhances buffering effect, reaches and mention High piling machine power, the purpose for reducing failure rate, extending the service life.
The present invention has been described in detail with reference to the accompanying drawings, those skilled in the art can be according to upper It states and bright many variations example is made to the present invention.Thus, certain details in embodiment should not constitute limitation of the invention, this Invention will be using the range that the appended claims define as protection scope of the present invention.

Claims (8)

1. a kind of diesel hammer hammer body and pile cover buffer control method, which is characterized in that it includes the following steps:
(1) buffer structure is connect with diesel hammer pile cover (2) junction setting one in diesel hammer hammer body (1);
(2) the connection buffer structure is set in the movable rail of diesel hammer lower piston (3), passes through the first connection bolt (4) It is connected and fixed with diesel hammer hammer body (1), is connected and fixed by the second connection bolt (5) with diesel hammer pile cover (2);
(3) so that diesel hammer lower piston (3) is moved reciprocatingly: pushing lower piston (3) to move back and forth using fuel oil explosion, under diesel hammer Piston (3) is directly acted in a manner of impact on the drill rod (6) of diesel hammer, by diesel hammer lower piston (3) and drill rod (6) it Between direct effect after diesel hammer lower piston (3) hit drill rod, return up movement initial position thus in injection rock;
When fuel oil explodes, and diesel hammer lower piston (3) and drill rod (6) is pushed to be collided, strong vibration wave can be generated, this is made Vibration wave first passes to connection buffer structure by hammer body (1), absorbs by it, passes to pile cover (2) again after delay, to avoid this Vibration wave resides on hammer body (1) while the vibration wave also being avoided to be directly delivered on pile cover (2), causes hammer body (1) or pile cover (2) damage.
2. diesel hammer hammer body according to claim 1 and pile cover buffer control method, which is characterized in that further include following step It is rapid:
(4) after diesel hammer lower piston (3) and drill rod (6) occur to hit acting, at the beginning of diesel hammer lower piston (3) returns up activity When beginning position, diesel hammer lower piston (3) can collide to generate shock wave again with hammer body (1), pass the vibration wave first Connection buffer structure is passed, absorbed by it, pass to hammer body (1) again after delay, the vibration wave is avoided to be directly delivered to hammer body (1), the damage of hammer body (1) is caused.
3. diesel hammer hammer body according to claim 1 and pile cover buffer control method, which is characterized in that the step (2) It is further comprising the steps of:
(21) cushion (7) and outer cushion (8), the interior cushion (7) and outer cushion (8) in being arranged in the structure For the structural adhesive layer of the double-sides belt iron plate of multilayer, according to the size and speed of piling stroke and produced vibration wave to the buffering knot The rigidity of interior cushion (7) and outer cushion (8) in structure is adjusted: by the glue-line quantity in increase and decrease cushion, and/ Or adjust the pre compressed magnitude of glue-line simultaneously, make the rigidity of the cushion structure reach setting range and to diesel hammer lower piston into Row buffering.
4. a kind of diesel hammer hammer body for implementing one of claims 1 to 33 the method connect buffer structure with pile cover, feature exists In, it is set between diesel hammer hammer body (1) and pile cover (2) and is set in the movable rail of diesel hammer lower piston (3), including First connection bolt (4), the second connection bolt (5), connection inner flange (9), semicircle baffle ring (10) and connection outward flange (11), The connection inner flange (9) is sheathed on diesel hammer lower piston (3) and is connected with semicircle baffle ring (10), the connection outward flange (11) it is connected and fixed with the connection inner flange (9) having connected with semicircle baffle ring (10), is set on the connection outward flange (11) It is equipped with the through-hole for placing and fixing the first connection bolt (4) and the second connection bolt (5), the first connection bolt (4) it passes through in the connection outward flange (11) will be attached fixed semicircle baffle ring (10), connect with diesel hammer hammer body (1) Flange (9) and connection outward flange (11) are fixed on the diesel hammer hammer body (1), and first connection bolt (4) passes through institute State connection outward flange (11) and diesel hammer pile cover (2) will be attached fixed semicircle baffle ring (10), connect inner flange (9) with And connection outward flange (11) is fixed on the diesel hammer pile cover (2).
5. diesel hammer hammer body connect buffer structure with pile cover according to claim 4, which is characterized in that further include interior cushion (7) and outer cushion (8), the interior cushion (7) are set in connection inner flange (9), and the outer cushion (8) is set to On the connection outward flange (11), respectively with diesel hammer lower piston (3), connect outward flange (11) and semicircle baffle ring (10) phase Connection.
6. diesel hammer hammer body connect buffer structure with pile cover according to claim 5, which is characterized in that the interior cushion (7) and outer cushion (8) be multilayer double-sides belt iron plate structural adhesive layer, according to piling stroke and produced vibration wave it is big The overall stiffness of inside and outside cushion is adjusted in small and speed: by the glue-line quantity in increase and decrease glue-line, and/or adjusting simultaneously The pre compressed magnitude of whole glue-line makes the rigidity of the connection buffer structure reach the range of setting.
7. diesel hammer hammer body connect buffer structure with pile cover according to claim 6, which is characterized in that the outer connecting flange (11) it is integrated the molding flange workpiece of forging process.
8. diesel hammer hammer body connect buffer structure with pile cover according to claim 6, which is characterized in that the interior connecting flange (8) it is integrated the flange workpiece for carrying out processing dimidiation after forging process forms again.
CN201811545407.7A 2018-12-17 2018-12-17 A kind of diesel hammer hammer body and pile cover buffer control method and it connect buffer structure Pending CN109403324A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811545407.7A CN109403324A (en) 2018-12-17 2018-12-17 A kind of diesel hammer hammer body and pile cover buffer control method and it connect buffer structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811545407.7A CN109403324A (en) 2018-12-17 2018-12-17 A kind of diesel hammer hammer body and pile cover buffer control method and it connect buffer structure

Publications (1)

Publication Number Publication Date
CN109403324A true CN109403324A (en) 2019-03-01

Family

ID=65460651

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811545407.7A Pending CN109403324A (en) 2018-12-17 2018-12-17 A kind of diesel hammer hammer body and pile cover buffer control method and it connect buffer structure

Country Status (1)

Country Link
CN (1) CN109403324A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10298987A (en) * 1997-04-22 1998-11-10 Nippon Sharyo Seizo Kaisha Ltd Hydraulic drop hammer
CN2649650Y (en) * 2003-09-27 2004-10-20 佛山市顺德区力源液压机械有限公司 Diesel hammer starting device
CN2869130Y (en) * 2005-03-28 2007-02-14 上海工程机械厂有限公司 Buffer cushion combination for drum-type diesel piling hammer
CN108561471A (en) * 2018-03-22 2018-09-21 广东力源液压机械有限公司 A kind of hydraulic hammer hammer body connect buffer structure with pile cover buffer control method and annular

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10298987A (en) * 1997-04-22 1998-11-10 Nippon Sharyo Seizo Kaisha Ltd Hydraulic drop hammer
CN2649650Y (en) * 2003-09-27 2004-10-20 佛山市顺德区力源液压机械有限公司 Diesel hammer starting device
CN2869130Y (en) * 2005-03-28 2007-02-14 上海工程机械厂有限公司 Buffer cushion combination for drum-type diesel piling hammer
CN108561471A (en) * 2018-03-22 2018-09-21 广东力源液压机械有限公司 A kind of hydraulic hammer hammer body connect buffer structure with pile cover buffer control method and annular

Similar Documents

Publication Publication Date Title
CN108561471B (en) Hydraulic hammer body and pile cap buffer control method and annular connection buffer structure
CN107956834B (en) Combined type multi-cylinder linkage buffer and application thereof
CN204430105U (en) A kind of forging hammer machine
KR102035799B1 (en) Piston for hydraulic breaker
CN107283909A (en) A kind of strong stamping machine of shock resistance
CN101466503A (en) Percussion mechanism with a striking pin and an associated catching mechanism
CN104968513A (en) Jounce bumper assembly
CN209457000U (en) A kind of diesel hammer hammer body connect buffer structure with pile cover
CN103047335A (en) Inertial resistance type vibration absorber
CN109403324A (en) A kind of diesel hammer hammer body and pile cover buffer control method and it connect buffer structure
CN209211441U (en) A kind of hydraulic hammer elastic connection and buffer damping structure
CN205834087U (en) A kind of forging hammer vibration absorber
CN109024588A (en) A kind of hydraulic hammer elastic connection and buffer control method and shock-damping structure
CN208041034U (en) A kind of annular connection buffer structure of hydraulic hammer hammer body and pile cover
CN104404959B (en) A kind of hydraulic pile hammer combination tup
CN202162319U (en) Stamping hammer base
CN201384964Y (en) Hydraulic cylinder used for breaking hammer
CN2893301Y (en) Damper with function of reducing secondary impact
CN208323277U (en) A kind of cylinder interior buffer damping structure and its electric hammer or hammer brick
CN202377469U (en) Anvil block for forging machine
KR20220105411A (en) Vibration damping device for hydraulic breaker
CN104512210B (en) Automotive suspension buffering block assembly
KR102331165B1 (en) Piston for hydraulic breaker
CN216180269U (en) Rebound rubber hammer with shockproof handle
CN218258053U (en) Anti-collision buffer device utilizing multistage energy absorption

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination