CN109386298B - Prefabricated tunnel steel arch with monitoring facilities - Google Patents

Prefabricated tunnel steel arch with monitoring facilities Download PDF

Info

Publication number
CN109386298B
CN109386298B CN201811371994.2A CN201811371994A CN109386298B CN 109386298 B CN109386298 B CN 109386298B CN 201811371994 A CN201811371994 A CN 201811371994A CN 109386298 B CN109386298 B CN 109386298B
Authority
CN
China
Prior art keywords
steel arch
testing device
internal force
surrounding rock
rock pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811371994.2A
Other languages
Chinese (zh)
Other versions
CN109386298A (en
Inventor
常帅斌
陈明
谢卓吾
刘世平
李国平
张双龙
史凌杰
谢腾飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Science and Technology
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
Xian University of Science and Technology
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Science and Technology, China Railway 12th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical Xian University of Science and Technology
Priority to CN201811371994.2A priority Critical patent/CN109386298B/en
Publication of CN109386298A publication Critical patent/CN109386298A/en
Application granted granted Critical
Publication of CN109386298B publication Critical patent/CN109386298B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01LMEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
    • G01L5/00Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes
    • G01L5/0028Force sensors associated with force applying means
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01LMEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
    • G01L5/00Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes
    • G01L5/0028Force sensors associated with force applying means
    • G01L5/0033Force sensors associated with force applying means applying a pulling force
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Mining & Mineral Resources (AREA)
  • Analytical Chemistry (AREA)
  • Structural Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

The invention belongs to the technical field of tunnel engineering, and particularly relates to a prefabricated tunnel steel arch with monitoring equipment. According to the invention, various monitoring devices are integrated in advance on the existing designed arch frame, so that construction stagnation caused by on-site installation of various devices is avoided and surrounding rock pressure born by the section of the lining structure at the bottom layer can be systematically measured while the stress and the distribution characteristics of the primary support structure are truly obtained, and the radial and axial internal force of the primary support structure and the internal force of the steel arch frame can obtain more accurate results; the invention can also adapt to the requirements of different arches by adjusting the installation equipment, and expands the application range of the invention.

Description

Prefabricated tunnel steel arch with monitoring facilities
Technical Field
The invention belongs to the technical field of tunnel engineering, and particularly relates to a prefabricated tunnel steel arch with monitoring equipment.
Background
At present, tunnel lining structure design is carried out according to a reconnaissance result, and design change is carried out through advanced geological radar and convergence deformation observation in an actual construction process. The existing test methods are all passive or indirect measurement methods, the method has low precision and delayed test effect, and meanwhile, the installation of force measuring equipment often causes the sealing delay of tunnel face grouting, so that potential safety hazards are caused.
Disclosure of Invention
The invention aims to provide a prefabricated tunnel steel arch frame which integrates various monitoring devices and can avoid construction stagnation caused by on-site installation of various devices while truly obtaining the stress and distribution characteristics of an initial supporting structure.
In order to achieve the above purpose, the invention adopts the following technical scheme:
the prefabricated tunnel steel arch with the monitoring equipment at least comprises a steel arch, and further comprises a surrounding rock pressure testing device, a surrounding rock pressure axial concrete internal force testing device, a surrounding rock pressure radial concrete internal force testing device, a steel arch flange internal force testing device, a line collecting groove and a first line collector; the steel arch consists of an upper baffle plate, a lower baffle plate and a support plate perpendicular to the two parallel baffle plates, and a first through hole is formed in the bottom of the lower baffle plate of the steel arch; the surrounding rock pressure testing device is contacted with the steel arch through a base fixedly arranged on the upper baffle of the steel arch; the surrounding rock pressure axial concrete internal force testing device and the surrounding rock pressure radial concrete internal force testing device are respectively detachably connected with the steel arch through fixing frames vertically arranged on the lower surface of the upper baffle of the steel arch and the side surface of the supporting plate; the lower surface and the upper surface of the upper baffle plate and the lower baffle plate are respectively detachably connected with a steel arch flange internal force testing device; the line collecting groove is arranged on the side surface of the steel arch supporting plate; the first concentrator is connected to the lower surface of the lower part of the lower baffle of the steel arch, and is respectively connected with the surrounding rock pressure testing device, the surrounding rock pressure axial concrete internal force testing device, the surrounding rock pressure radial concrete internal force testing device and the steel arch flange internal force testing device through first through holes formed in the bottom of the lower baffle of the steel arch.
End plates are fixedly connected to two ends of the steel arch; the end plate is a rectangular steel plate, and a second through hole for bolting is formed in the rectangular steel plate.
The second through holes are a pair of strip-shaped through holes parallel to the long sides of the rectangle, and the two ends of the second through holes are arc-shaped.
The base and the upper baffle of the steel arch are integrated; the line collecting groove is a tubular or square groove.
The fixing frame is a ruler with a length-adjustable lantern ring.
The second concentrator is arranged at the bottom end of the steel arch and is connected with the surrounding rock pressure testing device, the surrounding rock pressure axial concrete internal force testing device and the surrounding rock pressure radial concrete internal force testing device in a wire mode.
The steel arch is of an I-shaped steel structure.
The surrounding rock pressure testing device is a soil pressure box.
The surrounding rock pressure axial concrete internal force testing device is a first concrete strain gauge, and the radial concrete internal force testing device is a second concrete strain gauge.
The steel arch flange internal force testing device comprises an outer arch surface strain gauge and an inner arch surface strain gauge, wherein the outer arch surface strain gauge and the inner arch surface strain gauge are detachably connected to the lower surface and the upper surface of the upper baffle plate and the lower surface of the lower baffle plate respectively.
The beneficial effects are that: according to the invention, various monitoring devices are integrated in advance on the existing designed arch frame, so that construction stagnation caused by on-site installation of various devices is avoided and surrounding rock pressure born by the section of the lining structure at the bottom layer can be systematically measured while the stress and the distribution characteristics of the primary support structure are truly obtained, and the radial and axial internal force of the primary support structure and the internal force of the steel arch frame are obtained to obtain relatively systematic and accurate results; the invention can also adapt to the test requirements of installing different arches by adjusting the installation fixing frame of the radial concrete strain gauge, and expands the application range of the invention.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings that are needed in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
FIG. 1 is a three-dimensional view of the present invention;
FIG. 2 is a left side view of the present invention;
FIG. 3 is a top view of the present invention;
fig. 4 is a front view of the present invention.
In the figure, a 1-steel arch; 2-line collecting grooves; 3-a first hub; 4-baffle plates; 5-supporting plates; 6-a first through hole; 7-a base; 8-fixing frames; 9-end plates; 10-a second through hole; 11-soil pressure box; 12-a first concrete strain gauge; 13-a second concrete strain gauge; 14-outboard arch surface strain gauges; 15-inner arch surface strain gauge; 16-a second hub.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and fully with reference to the accompanying drawings, in which it is evident that the embodiments described are only some, but not all embodiments of the invention. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Embodiment one:
a prefabricated tunnel steel arch with monitoring equipment as shown in fig. 1-4, comprising at least a steel arch 1, characterized in that: the device also comprises a surrounding rock pressure testing device, a surrounding rock pressure axial concrete internal force testing device, a surrounding rock pressure radial concrete internal force testing device, a steel arch flange internal force testing device, a line collecting groove 2 and a first line collector 3; the steel arch 1 consists of an upper baffle plate 4, a lower baffle plate 4 and a support plate 5 perpendicular to the two baffle plates 4, wherein a first through hole 6 is formed in the bottom of the lower baffle plate of the steel arch 1; the surrounding rock pressure testing device is contacted with the steel arch 1 through a base 7 fixedly arranged on the upper baffle of the steel arch 1; the surrounding rock pressure axial concrete internal force testing device and the surrounding rock pressure radial concrete internal force testing device are respectively detachably connected with the steel arch 1 through fixing frames 8 vertically arranged on the lower surface of the upper baffle plate of the steel arch 1 and the side surface of the supporting plate 5; the lower surface and the upper surface of the upper baffle plate and the lower baffle plate are respectively detachably connected with a steel arch flange internal force testing device; the line collecting groove 2 is formed in the side face of the supporting plate 5 of the steel arch 1; the first concentrator 3 is connected to the lower surface of the lower part of the lower baffle of the steel arch 1, and the first concentrator 3 is respectively connected with the surrounding rock pressure testing device, the surrounding rock pressure axial concrete internal force testing device, the surrounding rock pressure radial concrete internal force testing device and the steel arch flange internal force testing device through a first through hole 6 formed in the bottom of the lower baffle of the steel arch 1.
Preferably, the fixing frame 8 is a ruler with a length-adjustable collar.
When in actual use, the installation process of the arch is the same as the installation process of a common tunnel steel arch in the prior art. Only in the installation process, the soil pressure box 11 on the outer surface of the prefabricated steel arch 1 is required to be tightly attached to surrounding rock, and if the soil pressure box 11 cannot be tightly attached to the surrounding rock, a steel backing plate with the same area as the soil pressure box can be arranged; the surrounding rock pressure axial concrete internal force testing device is provided with a length-adjustable ruler with a lantern ring, and the concrete internal force testing device can be supported between the concrete internal force testing device and a common arch frame; the contact soil pressure box is prevented from being stained with sprayed concrete, namely, for installation, all test equipment connecting wires are concentrated in the hub through the line collecting groove 2, the connecting part is prefabricated with the line collecting groove to lead out test wires, and later-stage reading test data is obtained through the hub in a manual reading or mechanical reading mode. The prefabricated steel arch 1 can be provided with different equipment groups according to different development modes. Different test equipment of steel bow member is through plug quick connect for equipment connection is convenient. After the installation is completed, the installation initial parameters are obtained at the first hub 3. The fixing frame 8 is a ruler with a length-adjustable lantern ring, and the fixing frame 8 with different lengths can be matched for adjustment to adapt to the test requirements of installing different arches, so that the application range of the invention is enlarged.
According to the invention, through the arrangement of the surrounding rock pressure testing device, the surrounding rock pressure axial concrete internal force testing device, the surrounding rock pressure radial concrete internal force testing device and the steel arch flange internal force testing device, the stress magnitude and the distribution characteristics of the primary support structure can be truly obtained, meanwhile, construction stagnation caused by on-site installation of various devices is avoided, the surrounding rock pressure born by the section of the lining structure at the bottom layer can be systematically measured, and the radial and axial internal force of the primary support structure and the internal force of the steel arch are obtained, so that a relatively systematic and accurate result is obtained.
Embodiment two:
a prefabricated tunnel steel arch with monitoring equipment as shown in fig. 1-4 differs from the first embodiment in that: end plates 9 are fixedly connected to two ends of the steel arch 1; the end plate 9 is a rectangular steel plate, and a second through hole 10 for bolting is formed in the rectangular steel plate.
Preferably, the second through hole 10 is a pair of elongated through holes parallel to the long side of the rectangle, and two ends of the second through hole 10 are arc-shaped.
Preferably, the base 7 is integrated with the upper baffle of the steel arch 1; the line collecting groove 2 is a tubular or square groove.
When in actual use, the end plates 9 are fixedly connected to the two ends of the steel arch 1, the steel arch 1 is convenient to install, the end plates 9 are rectangular steel plates and are provided with second through holes 10 for bolting, so that the connection can be completed only by bolts, and the steel arch is convenient and fast to install. The second through holes 10 are a pair of long strip-shaped through holes parallel to the long sides of the rectangle, so that the adjustment during installation is convenient; the two ends of the second through hole 10 are arc-shaped, so as to be matched with the bolts well, and the installation of the steel arch is more stable.
The base 7 and the upper baffle of the steel arch 1 are integrated, and the base 7 can be sunken in the upper surface of the upper baffle of the steel arch 1 during prefabrication, so that the base 7 is arranged, the rigidity of the steel arch 1 is not affected, the distance between the steel arch and a surrounding rock piece is reduced, and the installation safety of the steel arch 1 is ensured; the line collecting groove 2 adopts a tubular or square groove, and can meet the requirements of various testing devices.
Embodiment III:
a prefabricated tunnel steel arch with monitoring equipment as shown in fig. 1-4 differs from the first embodiment in that: the second concentrator 16 is arranged at the bottom end of the steel arch 1 and is in line connection with a surrounding rock pressure testing device, a surrounding rock pressure axial concrete internal force testing device, a surrounding rock pressure radial concrete internal force testing device and a steel arch flange internal force testing device.
Preferably, the steel arch 1 is of an I-steel structure.
Preferably, the surrounding rock pressure testing device is a soil pressure box 11.
It is preferable that the surrounding rock pressure axial concrete internal force testing device is a first concrete strain gauge 12, and the radial concrete internal force testing device is a second concrete strain gauge 13.
Preferably, the steel arch flange internal force testing device comprises an outer arch surface strain gauge 14 and an inner arch surface strain gauge 15, and the outer arch surface strain gauge 14 and the inner arch surface strain gauge 15 are detachably connected to the lower surface and the upper surface of the upper baffle plate and the lower baffle plate respectively.
When the steel arch centering device is actually used, a plurality of adjacent steel arches 1 can be connected with a link through the second hub 16 when the plurality of steel arches 1 are required to be arranged according to construction requirements, and then the plurality of adjacent steel arches 1 are linked for a plurality of times through the second hub 16, so that test data of test equipment on all the steel arches 1 are read; by adjusting the radial concrete internal force testing device of the adjacent steel arches 1, namely the fixing frame of the second concrete strain gauge 13, the arch testing requirements of different intervals are ensured. The steel arch 1 adopts an I-steel structure, which is convenient for selecting materials and reduces the increase of cost caused by adopting special materials. When a plurality of steel arches 1 are arranged, the number of wiring terminals at the joint positions of the thickness of the concentrator and the arches is correspondingly increased. All the test devices are installed at the corresponding positions to be tested.
In summary, by integrating various monitoring devices in advance on an existing designed arch frame, the invention can truly obtain the stress and distribution characteristics of the primary support structure, meanwhile, construction stagnation caused by on-site installation of various devices is avoided, and the surrounding rock pressure, the radial and axial internal force of the primary support structure and the internal force of the steel arch frame can be systematically measured, so that a more accurate result is obtained; the invention can also adapt to the requirements of different arches by adjusting the installation equipment, and expands the application range of the invention.
The foregoing description of the preferred embodiments of the invention is not intended to be limiting, but rather is intended to cover all modifications, equivalents, alternatives, and improvements that fall within the spirit and scope of the invention.
It should be noted that all directional indicators (such as up, down, left, right, front, and rear … …) in the embodiments of the present invention are merely used to explain the relative positional relationship, movement, etc. between the components in a particular posture (as shown in the drawings), and if the particular posture is changed, the directional indicator is changed accordingly.
Furthermore, the description of "first," "second," etc. in this disclosure is for descriptive purposes only and is not to be construed as indicating or implying a relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defining "a first" or "a second" may explicitly or implicitly include at least one such feature.
The technical solutions between the embodiments may be combined with each other, but it is necessary to base the implementation on the basis of those skilled in the art that when the combination of technical solutions contradicts or cannot be implemented, it should be considered that the combination of technical solutions does not exist and is not within the scope of protection claimed by the present invention.

Claims (7)

1. Prefabricated tunnel steel arch with monitoring facilities includes steel arch (1) at least, its characterized in that: the device also comprises a surrounding rock pressure testing device, a surrounding rock pressure axial concrete internal force testing device, a surrounding rock pressure radial concrete internal force testing device, a steel arch flange internal force testing device, a line collecting groove (2) and a first line collector (3); the steel arch (1) consists of an upper baffle plate (4) and a lower baffle plate (4) which are parallel and a support plate (5) which is perpendicular to the two baffle plates (4), and a first through hole (6) is formed in the bottom of the lower baffle plate of the steel arch (1); the surrounding rock pressure testing device is contacted with the steel arch (1) through a base (7) fixedly arranged on the upper baffle of the steel arch (1); the surrounding rock pressure axial concrete internal force testing device and the surrounding rock pressure radial concrete internal force testing device are respectively detachably connected with the steel arch (1) through fixing frames (8) vertically arranged on the lower surface of the upper baffle of the steel arch (1) and the side surface of the supporting plate (5); the lower surface and the upper surface of the upper baffle plate and the lower baffle plate are respectively detachably connected with a steel arch flange internal force testing device; the line collecting groove (2) is arranged on the side surface of the supporting plate (5) of the steel arch (1); the first concentrator (3) is connected to the lower surface of the lower part of the lower baffle of the steel arch (1), and the first concentrator (3) is respectively connected with the surrounding rock pressure testing device, the surrounding rock pressure axial concrete internal force testing device, the surrounding rock pressure radial concrete internal force testing device and the steel arch flange internal force testing device through a first through hole (6) formed in the bottom of the lower baffle of the steel arch (1);
the base (7) and the upper baffle of the steel arch (1) are integrated; the line collecting groove (2) is a tubular or square groove;
the fixing frame (8) is a ruler with a length-adjustable collar;
the device further comprises a second concentrator (16), wherein the second concentrator (16) is arranged at the bottom end of the steel arch (1) and is in wire connection with the surrounding rock pressure testing device, the surrounding rock pressure axial concrete internal force testing device, the surrounding rock pressure radial concrete internal force testing device and the steel arch flange internal force testing device.
2. A prefabricated tunnel steel arch with monitoring device according to claim 1, characterized in that: end plates (9) are fixedly connected to two ends of the steel arch (1); the end plate (9) is a rectangular steel plate, and a second through hole (10) for bolting is formed in the rectangular steel plate.
3. A prefabricated tunnel steel arch with monitoring device according to claim 2, characterized in that: the second through holes (10) are a pair of strip-shaped through holes parallel to the long sides of the rectangle, and two ends of the second through holes (10) are arc-shaped.
4. A prefabricated tunnel steel arch with monitoring device according to claim 1 or 2, characterized in that: the steel arch (1) is of an I-shaped steel structure.
5. A prefabricated tunnel steel arch with monitoring device according to claim 1, characterized in that: the surrounding rock pressure testing device is a soil pressure box (11).
6. A prefabricated tunnel steel arch with monitoring device according to claim 1, characterized in that: the surrounding rock pressure axial concrete internal force testing device is a first concrete strain gauge (12), and the radial concrete internal force testing device is a second concrete strain gauge (13).
7. A prefabricated tunnel steel arch with monitoring device according to claim 1, characterized in that: the steel arch flange internal force testing device comprises an outer arch surface strain gauge (14) and an inner arch surface strain gauge (15), wherein the outer arch surface strain gauge (14) and the inner arch surface strain gauge (15) are detachably connected to the lower surface and the upper surface of the upper baffle plate and the lower baffle plate respectively.
CN201811371994.2A 2018-11-16 2018-11-16 Prefabricated tunnel steel arch with monitoring facilities Active CN109386298B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811371994.2A CN109386298B (en) 2018-11-16 2018-11-16 Prefabricated tunnel steel arch with monitoring facilities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811371994.2A CN109386298B (en) 2018-11-16 2018-11-16 Prefabricated tunnel steel arch with monitoring facilities

Publications (2)

Publication Number Publication Date
CN109386298A CN109386298A (en) 2019-02-26
CN109386298B true CN109386298B (en) 2024-03-01

Family

ID=65428783

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811371994.2A Active CN109386298B (en) 2018-11-16 2018-11-16 Prefabricated tunnel steel arch with monitoring facilities

Country Status (1)

Country Link
CN (1) CN109386298B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110778340B (en) * 2019-09-18 2021-01-05 中国矿业大学(北京) Steel arch strain gauge embedded structure and construction method thereof
CN112983540B (en) * 2021-03-16 2021-12-28 中国科学院武汉岩土力学研究所 Construction method and protection tool for tunnel deformation monitoring points
CN114235034A (en) * 2021-11-29 2022-03-25 山东大学 Tunnel surrounding rock stress and steel arch frame strain integrated measurement auxiliary device and method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015081425A (en) * 2013-10-22 2015-04-27 清水建設株式会社 Steel support and structure of lining concrete
CN105332739A (en) * 2015-10-14 2016-02-17 同济大学 Tunnel supporting structure stress monitoring device and method
CN106499397A (en) * 2016-11-14 2017-03-15 西安科技大学 A kind of soft rock tunnel deformation control method that is analyzed based on rockbolt stress
CN108019222A (en) * 2017-11-20 2018-05-11 三峡大学 A kind of tunnel lining structure filled using haydite and construction method
CN108397217A (en) * 2018-01-09 2018-08-14 山东大学 The tunnel steel arch frame transport fitting machine and method that achievable monitoring element is laid in advance
CN209469445U (en) * 2018-11-16 2019-10-08 中铁十二局集团有限公司 A kind of prefabricated tunnel steel arch frame with monitoring device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015081425A (en) * 2013-10-22 2015-04-27 清水建設株式会社 Steel support and structure of lining concrete
CN105332739A (en) * 2015-10-14 2016-02-17 同济大学 Tunnel supporting structure stress monitoring device and method
CN106499397A (en) * 2016-11-14 2017-03-15 西安科技大学 A kind of soft rock tunnel deformation control method that is analyzed based on rockbolt stress
CN108019222A (en) * 2017-11-20 2018-05-11 三峡大学 A kind of tunnel lining structure filled using haydite and construction method
CN108397217A (en) * 2018-01-09 2018-08-14 山东大学 The tunnel steel arch frame transport fitting machine and method that achievable monitoring element is laid in advance
CN209469445U (en) * 2018-11-16 2019-10-08 中铁十二局集团有限公司 A kind of prefabricated tunnel steel arch frame with monitoring device

Also Published As

Publication number Publication date
CN109386298A (en) 2019-02-26

Similar Documents

Publication Publication Date Title
CN109386298B (en) Prefabricated tunnel steel arch with monitoring facilities
CN104897479B (en) A kind of composite support insulator mechanical property comprehensive detection system
CN102914282A (en) Monitoring and measuring method using displacement sensor to measure tunnel deformation
CN209670980U (en) A kind of tunneling shield section of jurisdiction site monitoring system
CN106759547B (en) Integral Abutment, pile foundation and soil interaction pseudo-static experimental measuring device and its installation method
CN102207366B (en) Strain transducer structure and mounting methods
KR20090071102A (en) Load test apparatus for pile type structure
CN210741454U (en) Bridge pier deformation monitoring system
KR101317635B1 (en) Displacement monitoring device of discontinuities in the rock masses and method thereof
CN104568279A (en) Multi-axis force sensor
CN205562101U (en) Stay cable force change testing device
CN106088171B (en) Combined testing method for horizontal displacement of pile top and stress of pile body of precast pile
CN201387325Y (en) Verticality and parallelism measuring device for metallurgical equipment by acoustic control method
CN113740163A (en) Intelligent self-sensing double-block sleeper calibration system and calibration method thereof
CN106226177B (en) Extra-high voltage direct current composite wall bushing internal and external anti-seismic testing device and testing method
CN102175357B (en) Method for directly measuring bearing force based on structure micro-strain
CN202255731U (en) Low-height resistance strain type pressure sensor
CN209945590U (en) Integrated steel pipe support stress testing device
CN208367029U (en) A kind of mobile wind measuring device for Along Railway
CN208282973U (en) The vertical load power system of high-precision pivoted arm force-measuring framework tests structure
CN209469445U (en) A kind of prefabricated tunnel steel arch frame with monitoring device
CN203298907U (en) Soil pressure box fixing device
CN107131985B (en) Spoke type grading pressure detection device
CN112113692B (en) Long-term stress monitoring system and method based on perforated underground continuous wall
CN104089602A (en) Method for measuring dynamic deflection through fiber grating differential pressure gauges

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant