CN109372421A CN201811186080.9A CN201811186080A CN109372421A CN 109372421 A CN109372421 A CN 109372421A CN 201811186080 A CN201811186080 A CN 201811186080A CN 109372421 A CN109372421 A CN 109372421A
Authority
CN
China
Prior art keywords
drilling tool
power
drilling
compound
power head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811186080.9A
Other languages
Chinese (zh)
Inventor
李广信
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811186080.9A priority Critical patent/CN109372421A/en
Publication of CN109372421A publication Critical patent/CN109372421A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B3/00Rotary drilling
    • E21B3/02Surface drives for rotary drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B17/00Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
    • E21B17/22Rods or pipes with helical structure
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling

Abstract

The present invention relates to technical field of civil engineering, more particularly, to a kind of more Power compound drilling tools, preparation method and type stake.More Power compound drilling tools include the lower power drilling tool, middle power drilling tool and upper power drilling tool being sequentially coaxially nested;The lower power drilling tool, middle power drilling tool and upper power drilling tool are respectively equipped with a power mechanism, and the power mechanism can be operated alone its correspondence drilling tool and be rotated.When more Power compound drilling tools are constructed, each drilling tool is converted into the driving method of active by traditional linked manner, can disposably complete pore-forming and concrete pressure fills pile, high degree of automation realizes the raising of work efficiency;The variable diameter of pile body, reasonable engineering method, so that bearing capacity of single pile is further to be improved, to reduce costs;The above composite factor shortens the duration.

Description

More Power compound drilling tools, preparation method and type stake
Technical field
The present invention relates to technical field of civil engineering, more particularly, to a kind of more Power compound drilling tools, preparation method and type Stake.
Background technique
In the tide of reform and opening-up, construction industry has rapid development, and design, the construction of foundation are wanted in architectural engineering Ask higher and higher, concrete stake and reinforced concrete pile basis and composite foundation are in skyscraper, bridge, harbour, railway, highway, airport, water It is used widely in the engineerings such as sharp hydroelectric facility, in order to make concrete stake and reinforced concrete pile meet bending resistance, anti-shearing, raising bearing capacity Constantly the shape of concrete stake and reinforced concrete pile is improved with design requirements, people such as antidetonations, is wanted to further satisfaction design It asks, save material dosage, improves construction quality and shortens construction speed.With traditional pile-type that existing equipment and technique are built, Its in length and breadth section be usually it is not long with stake and change cylinder or square column type stake, bearing capacity mainly by stake side frictional resistance and The end resistance composition at stake end.Existing equipment function is more single, and automation degree of equipment is low, is unable to adaptation to local conditions Ground Treatment Soil causes certain cost waste, affects bearing capacity of single pile and play effect.
The extruding and removing soil combination drill tool technology reference that this patent is related to: utility model patent: 201820124401.1, invention name Claim: a kind of extruding and removing soil combination drill tool and CFG extruding and removing soil stake.(patent of invention is in the substantive examination stage)
The information disclosed in the background technology section is intended only to deepen understanding of the general background technology to the present invention, and It is not construed as recognizing or implying in any form that the information constitutes the prior art known to those skilled in the art.
Summary of the invention
The purpose of the present invention is to provide a kind of more Power compound drilling tools, preparation method and type stakes, to solve the prior art Present in the automatic degree of equipment it is low, engineering method is single, and pile-type is single, and bad adaptability and the not high technology of bearing capacity of single pile are asked Topic.
To achieve the goals above, the invention adopts the following technical scheme:
In a first aspect, the present invention provides a kind of more Power compound drilling tools comprising: the lower power drill being sequentially coaxially nested Tool, middle power drilling tool and upper power drilling tool;It is dynamic that the lower power drilling tool, middle power drilling tool and upper power drilling tool are respectively equipped with one Force mechanisms, the power mechanism can be operated alone its correspondence drilling tool and be rotated.
As a kind of further technical solution, the lower power drilling tool includes: lower power head and outer sleeve drilling tool;It is described Lower power head is set to the upper end of the outer sleeve drilling tool, for driving the outer sleeve drilling tool to carry out spinning movement.
As a kind of further technical solution, the lower power drilling tool further include: lower casting slot;The lower casting slot is set It is placed in the upper end of the lower power head.
As a kind of further technical solution, the middle power drilling tool include: middle power head, intermediate sleeve drilling tool and in Lifting device;The middle power head is set to the upper end of the intermediate sleeve drilling tool, for drive the intermediate sleeve drilling tool into Row spinning movement;The middle lifting device is set to the lower end of the middle power head, for driving the lower power drilling tool to carry out Lifting action.
As a kind of further technical solution, the middle power drilling tool further include: middle casting slot and middle limiting device, institute State the upper end that middle casting slot is set to the middle power head;The middle limiting device is set to the lower end of the middle power head.
As a kind of further technical solution, the upper power drilling tool includes: upper power head, center drilling tool and upper promotion Device;The upper power head is set to the upper end of the center drilling tool, for driving the center drilling tool to carry out spinning movement;Institute The lower end that lifting device is set to the upper power head is stated, for driving the middle power drilling tool to carry out lifting action.
As a kind of further technical solution, the upper power drilling tool further include: position limit device;The upper limit dress Install the lower end for being placed in the upper power head.
As a kind of further technical solution, further includes: pressurizing device, the pressurizing device are set to the upper power Any one among drilling tool and the middle power drilling tool.
Second aspect, the present invention also provides a kind of type stakes according to more Power compound drilling tool preparations comprising: main body Pile body;
At least two back taper stepped ramp type bodies are provided on the main body pile body;
The inverted cone disk inclined-plane extended line of the back taper stepped ramp type body and the included angle of the main body pile body central axis Range are as follows: 5 °~90 °.
The third aspect, the present invention provide again it is a kind of according to more Power compound drilling tools in the method for preparative stake, packet Include: the demand according to stratum to engineering method, the upper power drilling tool, middle power drilling tool and lower power drilling tool are successively drilled into respectively successively Projected depth, so as to form multiple back taper stepped ramp type drillings;Start concrete pump, starts pressure concrete injecting, successively mentioned in pressure concrete injecting Go up power drilling tool, middle power drilling tool and lower power drilling tool, Synchronous lifting after each power drilling tool bottom end is successively concordant, until mentioning To aperture absolute altitude, while concrete also presses and fills pile to designed elevation, realizes that disposable completion pore-forming and concrete pressure fill pile.
By adopting the above technical scheme, the invention has the following beneficial effects:
The present invention provides a kind of more Power compound drilling tools, which includes lower power drilling tool, middle power drilling tool and upper dynamic Power drilling tool, lower power drilling tool, middle power drilling tool and upper power drilling tool are respectively equipped with a power mechanism, more Power compound drilling tools When being constructed, each drilling tool is converted into the driving method of active by traditional linked manner, can disposably complete pore-forming and concrete Pressure fills pile, and high degree of automation realizes the raising of work efficiency, and the raising of bearing capacity of single pile is reduced costs simultaneously, shortened Duration;It is adaptable, it is conducive to promote and applies.
The present invention provides a kind of type stakes prepared according to more Power compound drilling tools, and bearing capacity not only includes traditional pile body Pile side friction and stake end bottom bearing, and the back taper disk inclined-plane of back taper stepped ramp type body can be vertical vertically downwards part Power be decomposed into the tangential force and normal force of the conical surface, soil around pile forms passive compression chord state and squeezed state, increases stake All frictional resistances improve the bearing capacity of single pile, can reduce settling amount.This superficial part inversed taper platform part bearing capacity Ke Yong Tai Shaji (Terzaghi) shallow water oil field formula calculates.It is superimposed the combination construction that is nested by the combination drill tool, can disposably be completed Pore-forming and concrete pressure fill pile, realize the raising of work efficiency, and bearing capacity of single pile further improves, and reduces costs simultaneously, contract The short duration.
The present invention provides a kind of preparation methods according to more Power compound drilling tools, and this method is according to stratum to the need of engineering method It asks, upper power drilling tool, middle power drilling tool and lower power drilling tool are successively drilled into respective projected depth successively, multiple so as to be formed The drilling of back taper stepped ramp type;Start concrete pump, start pressure concrete injecting, successively promotes upper power drilling tool, middle power drill successively in pressure concrete injecting Tool and lower power drilling tool, Synchronous lifting after each power drilling tool bottom end is successively concordant, until mentioning aperture absolute altitude, while concrete also presses filling Pile realizes that disposable completion pore-forming and concrete pressure fill pile, to form the type with above structure and function to designed elevation Stake.
Detailed description of the invention
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art Embodiment or attached drawing needed to be used in the description of the prior art be briefly described, it should be apparent that, it is described below Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor It puts, is also possible to obtain other drawings based on these drawings.
Fig. 1 is the structural schematic diagram of more Power compound drilling tool original states provided in an embodiment of the present invention;
Fig. 2 is the structural schematic diagram that more Power compound drilling tools provided in an embodiment of the present invention creep into state;
Fig. 3 is the structural schematic diagram of upper power drilling tool provided in an embodiment of the present invention;
Fig. 4 is the positive structure schematic of upper power head provided in an embodiment of the present invention;
Fig. 5 is the structural schematic diagram of middle power drilling tool provided in an embodiment of the present invention;
Fig. 6 is the positive structure schematic of middle power head provided in an embodiment of the present invention;
Fig. 7 is the structural schematic diagram of middle casting slot provided in an embodiment of the present invention;
Fig. 8 is the structural schematic diagram of lower power drilling tool provided in an embodiment of the present invention;
Fig. 9 is the positive structure schematic of lower power head provided in an embodiment of the present invention;
Figure 10 to Figure 14 is the construction procedure schematic diagram of drilling tool provided in an embodiment of the present invention;
Figure 15 to Figure 24 is different types of pile-type schematic diagram provided in an embodiment of the present invention.
Icon: the upper power drilling tool of 1-;Power drilling tool in 2-;Power drilling tool under 3-;4- type stake;5- concrete pump;The upper power of 11- Head;The center 12- drilling tool;The upper lifting device of 13-;14- position limit device;15- pressurizing device;Power head in 21-;22- intermediate sleeve Cylinder drilling tool;Lifting device in 23-;Limiting device in 24-;Casting slot in 26-;Power head under 31-;32- outer sleeve drilling tool;36- Lower casting slot;41- main body pile body;42- back taper stepped ramp type body.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with attached drawing, it is clear that described implementation Example is a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill Personnel's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to Convenient for description the present invention and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation, It is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.In addition, term " first ", " second ", " third " is used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can To be mechanical connection, it is also possible to be electrically connected;It can be directly connected, can also can be indirectly connected through an intermediary Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood as the case may be Concrete meaning in the present invention.
Below in conjunction with attached drawing, detailed description of the preferred embodiments.It should be understood that this place is retouched The specific embodiment stated is merely to illustrate and explain the present invention, and is not intended to restrict the invention.
Embodiment one
Shown in Fig. 1 to Fig. 9, the present embodiment provides a kind of more Power compound drilling tools comprising: what is be sequentially coaxially nested is lower dynamic Power drilling tool 3, middle power drilling tool 2 and upper power drilling tool 1 (ecto-entad, which is sequentially overlapped, to be nested);The lower power drilling tool 3, middle power Drilling tool 2 and upper power drilling tool 1 are respectively equipped with a power mechanism, and the power mechanism can be operated alone it and correspond to drilling tool progress Rotation.As it can be seen that each drilling tool is converted into the driving method of active by passively linked manner, high degree of automation is adaptable, Conducive to promoting and apply.
Preferably, the lower power drilling tool 3 includes: lower power head 31 and outer sleeve drilling tool 32;The lower power head 31 is set It is placed in the upper end of the outer sleeve drilling tool 32, for driving the outer sleeve drilling tool 32 to carry out spinning movement.
Further, the lower power drilling tool 3 further include: lower casting slot 36;The lower casting slot 36 be set to it is described under The upper end of power head 31.
Preferably, the concrete form of the lower power head 31 is not limited to, can is fluid pressure drive device, it can also be with For Vidacare corp.For the structure of lower power head 31, the shell of the lower power head 31 can be hollow cylindrical, in Portion has the casting space communicated with lower casting slot 36.Specifically, the lower casting slot 36 includes a casting case and the row of being set to Native case side and what is be inclined to set lead soil box.The bottom of casting case can pass through the shell and outer sleeve drilling tool 32 of lower power head 31 It is connected, i.e. the part rotation casting of middle sleeve drilling tool 22 is led through 32 inside of outer sleeve drilling tool, lower power head 31, lower casting slot 36 Out.Outer sleeve drilling tool 32 revolves casting and is immediately discharged to aperture.
For outer sleeve drilling tool 32, third helical blade, the third helical-blade are provided on outer sleeve drilling tool 32 Piece is axially set on the outer wall of the outer sleeve drilling tool 32 along the outer sleeve drilling tool 32.The size of outer sleeve drilling tool 32 and Concrete shape can flexible setting according to actual needs.
Preferably, the middle power drilling tool 2 includes: middle power head 21, intermediate sleeve drilling tool 22 and middle lifting device 23;Institute The upper end that middle power head 21 is set to the intermediate sleeve drilling tool 22 is stated, for driving the intermediate sleeve drilling tool 22 to be rotated Movement;The middle lifting device 23 is set to the lower end of the middle power head 21, for driving the lower power drilling tool 3 to be risen Drop movement.
For middle power head 21, structure can refer to the description of above-mentioned lower power head 31.
It, can be there are many mode for middle lifting device 23.
Such as: lifting device 23 includes: hoist engine in this, which is set to the lower end of the middle power head 21, should The traction rope of hoist engine is connected with lower power drilling tool 3 (preferably descending power head 31).
Another example is: lifting device 23 includes: telescoping cylinder (oil cylinder) in this, telescoping cylinder is set under the middle power head 21 End, the telescopic rod of the telescoping cylinder are connected with lower power drilling tool 3 (preferably descending power head 31).
For intermediate sleeve drilling tool 22, which is provided with the second helical blade, second spiral shell Vane piece is axially set on the outer wall of the first sleeve drilling tool along the first sleeve drilling tool.
Preferably, the middle power drilling tool 2 further include: middle casting slot 26 and middle limiting device 24, the middle casting slot 26 It is set to the upper end of the middle power head 21;The middle limiting device 24 is set to the lower end of the middle power head 21.
For middle casting slot 26, casting slot 26 includes a casting case and is set to casting case side and is in incline in this What is be tiltedly arranged leads soil box.The bottom of casting case can be connected by the shell of middle power head 21 with intermediate sleeve drilling tool 22, i.e., in The part rotation casting of heart drilling tool 12 is exported through 22 inside of intermediate sleeve drilling tool, lower power head 21, middle casting slot 26.
It, can be there are many mode for middle limiting device 24.Such as: limiting device 24 can be rigid connection in this Bar, the length of the rigid connecting rod is according to practical flexible setting.It may be telescopic connection rod, length is any according to requiring It adjusts.
It is formed it is worth noting that middle power drilling tool 2 can be nested according to design requirement by multiple superpositions.Middle power drilling tool 2 When being nested by multiple superpositions, in addition to sleeve diameter and length are different, structure is all the same.
Preferably, the upper power drilling tool 1 includes: upper power head 11, center drilling tool 12 and upper lifting device 13;On described Power head 11 is set to the upper end of the center drilling tool 12, for driving the center drilling tool 12 to carry out spinning movement;On described Lifting device 13 is set to the lower end of the upper power head 11, for driving the middle power drilling tool 2 to carry out lifting action.
For upper power head 11, structure, form and its power head 21,31 are substantially similar outer, in addition add slip casting (bend pipe one end communicates (concrete) union elbow with center drilling tool core pipe, the other end and concrete conveyance high-pressure hose phase Connect), power top head is additionally provided with suspension centre, is connect with drilling machine master winch by wirerope, no casting slot setting.
It, can be there are many mode for upper lifting device 13.
Such as: lifting device 13 includes: hoist engine on this, which is set to the lower end of the upper power head 11, should The traction rope of hoist engine is connected with middle power drilling tool 2 (power head 21 in preferably).
Another example is: lifting device 13 includes: telescoping cylinder (oil cylinder) on this, telescoping cylinder is set under the upper power head 11 End, the telescopic rod of the telescoping cylinder are connected with middle power drilling tool 2 (power head 21 in preferably).
Further, the upper power drilling tool 1 further include: position limit device 14;The position limit device 14 is set to institute State the lower end of power head 11.
It, can be there are many mode for position limit device 14.Such as: the position limit device 14 can be rigid connection Bar.The length of the rigid connecting rod is according to practical flexible setting.It may be telescopic connection rod, length is any according to requiring It adjusts.
In addition, the present embodiment further include: pressurizing device 15, the pressurizing device 15 are set to 1 He of upper power drilling tool Any one among the middle power drilling tool 2.
Certainly, for pressurizing device 15, can be self-possessed according to power mechanism, geological conditions and design requirement are flexibly set It sets, it is preferred that the pressurizing device 15 can be hoist engine, and hoist engine is set on drilling machine platform, and the traction rope of hoist engine is logical Cross times among a directive wheel and the upper power drilling tool 1 (upper power head 11) and the middle power drilling tool 2 (middle power head 21) One of anticipating connection.Pressurizing device 15 or hydraulic cylinder, cylinder tube are fixedly installed on boring tower suitable position, oil cylinder piston Bar top with it is any one among the upper power drilling tool 1 (upper power head 11) and the middle power drilling tool 2 (middle power head 21) Person's connection.
Embodiment two
Shown in Figure 10 to Figure 14, the present embodiment two provides a kind of Power compound drilling tools more according to embodiment one again to make The method of standby type stake 4 comprising: the demand according to stratum to engineering method, the upper power drilling tool 1, middle power drilling tool 2 and lower power Drilling tool 3 is successively drilled into respective projected depth successively;Start concrete pump 5, start pressure concrete injecting, upper power drill is successively promoted in pressure concrete injecting Tool 1, middle power drilling tool 2 and lower power drilling tool 3, until successively concordant rear Synchronous lifting goes out aperture absolute altitude for each power drilling tool bottom end, Concrete, which is also pressed, simultaneously fills pile to designed elevation.
In the treatments of soft foundation such as building structure or railway, highway, need to carry out the foundation soil of disposal field soil from shallow to deep According to mean shear wave velocity value changing rule can generally be divided into Soft site soil (soil layer average clearance method≤140m/s), in Soft Site Soil (140m/s < soil layer average clearance method≤250m/s), native (the 250m/s < soil layer average shear wave of Moderate stiff soil sites Speed≤500m/s), hard ground it is native (500m/s < soil layer shear wave velocity).
For diameter-variable pile:
Such as: it is Moderate stiff soil sites soil (or the overwhelming majority is Moderate stiff soil sites soil) for stratum in the processing long range of stake, adopts With casting engineering method, casting pore-forming is successively crept by center drilling tool 12-intermediate sleeve, 22-outer sleeve of drilling tool drilling tool 32 respectively.Into One step, this kind of 15 pressure point of process flow pressurizing device is set on power head 11 most preferably.
Such as: for stratum in the processing long range of stake be it is weak, in soft Site Soil (or the overwhelming majority it is weak, in soft field Ground soil), using soil compaction engineering method, soil compaction is successively crept by center drilling tool 12-intermediate sleeve, 22-outer sleeve of drilling tool drilling tool 32 respectively Pore-forming.Further, this kind of 15 pressure point of process flow pressurizing device is set on power head 11 most preferably.The first variable diameter of stake top Casting mode (mainly seeing intermediate sleeve drilling tool 22 to the compacted degree of hole wall soil) also can be used in pile body pore-forming engineering method.
Such as: handling stratum top in the long range of stake is soft Site Soil in weakness-, and lower part is Moderate stiff soil sites soil, using crowded Engineering method is had both in casting, and by intermediate sleeve drilling tool 22, (drilling tool 12 drill bit in center stretches out 22 bottom end of intermediate sleeve drilling tool at this time, when drilling For reversion, spin-ended casting is prevented, only play as the positioning of intermediate sleeve drilling tool 22, break ground and creep into function)-outer sleeve drilling tool 32 is successively Soft Site Soil drilling soil compaction pore-forming (or 22 bottom end of intermediate sleeve drilling tool slightly penetrates soil compaction area) in weakness-respectively, stops boring, so It is rotated forward afterwards by center drilling tool 12, continues drilling rotation casting into stake holes, reach projected depth in Moderate stiff soil sites soil.Further, Stake top the first variable diameter pile body pore-forming engineering method also can be used casting mode and (mainly see intermediate sleeve drilling tool 22 to the compacted journey of stake holes wall soil Degree).This kind of 15 pressure point of process flow pressurizing device is set on middle power head 21.
For screw thread diameter-variable pile:
Such as: in the processing long range of stake stratum be it is weak, in soft Site Soil (or the overwhelming majority it is weak, in soft place Soil), using screw thread soil compaction engineering method, successively it is respectively adopted together by center drilling tool 12-intermediate sleeve, 22-outer sleeve of drilling tool drilling tool 32 Step technology creeps into soil compaction into screw thread stake holes.Further, this kind of 15 pressure point of process flow pressurizing device is set to power head On 11.Stake top the first variable diameter pile body pore-forming engineering method also can be used casting mode, formed equal diameter stake holes (stake top stress is concentrated, Increase stake top cross section forced area).
Such as: stratum top is soft Site Soil in weakness-in the processing long range of stake, and lower part is that Moderate stiff soil sites are native, in use Portion's screw thread soil compaction lower part casting, crowded row have both engineering method, and by intermediate sleeve drilling tool 22, (drilling tool 12 drill bit in center stretches out intermediate sleeve at this time Cylinder drilling tool 22 bottom end is reversion when drilling, prevents spin-ended casting, only play as the positioning of intermediate sleeve drilling tool 22, break ground and creep into function Can)-outer sleeve drilling tool 32 be successively respectively adopted simultaneous techniques drilling soil compaction at screw thread stake holes, 22 bottom end of intermediate sleeve drilling tool is not Stop after soft Site Soil in penetrating or slightly penetrating, main story, drilling rotation casting are continued at stake holes, in firmly by center drilling tool 12 at this time Reach projected depth in Site Soil.Further, casting mode also can be used in the first variable diameter of stake top pile body pore-forming engineering method, formed etc. Diameter stake holes (stake top stress is concentrated, and stake top cross section forced area is increased).This kind of 15 pressure point of process flow pressurizing device is set It is placed on power head 21.
Embodiment three
Shown in Figure 15 to Figure 24, the present embodiment also provides a kind of type stake 4 according to more Power compound drilling tool preparations, It include: main body pile body 41;At least two back taper stepped ramp type bodies 42 are provided on the main body pile body 41;The back taper stepped ramp type body The included angle range of place inclined-plane extended line and 41 central axis of main body pile body at 42 variable diameter are as follows: 5 °~90 °.Example Such as: being located at pile body superficial part at the variable diameter of the back taper stepped ramp type body 42, the place at the variable diameter of the back taper stepped ramp type body 42 is oblique The included angle value range of face extended line and 41 central axis of main body pile body is preferably 30 °~45 °.Another example is: the back taper It is located at pile body deep, place inclined-plane extended line and institute at the variable diameter of the back taper stepped ramp type body 42 at the variable diameter of stepped ramp type body 42 The included angle range for stating 41 central axis of main body pile body is 5 °~90 °, (such as: 30 °, 45 °, 60 °, 75 °).
In addition, for main body pile body 41, it can also be there are many form.
For example, non-threaded type diameter-variable pile: there are two back taper stepped ramp type body 42, the back tapers for setting on the main body pile body 41 The angle 5 °~900 of place inclined-plane extended line and 41 central axis of main body pile body at the variable diameter of stepped ramp type body 42.
In another example screw-type diameter-variable pile: there are two back taper stepped ramp type bodies 42 for setting on the main body pile body 41, from top to bottom It is divided into the first pile body, the second pile body and third pile body, wherein at least one has among the first pile body, the second pile body and third pile body There is helicitic texture.Place inclined-plane extended line and 41 central axis of main body pile body at the variable diameter of the back taper stepped ramp type body 42 Angle 5 °~900.
Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;To the greatest extent Pipe present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: its according to So be possible to modify the technical solutions described in the foregoing embodiments, or to some or all of the technical features into Row equivalent replacement;And these are modified or replaceed, various embodiments of the present invention technology that it does not separate the essence of the corresponding technical solution The range of scheme.

Claims (10)

1. a kind of more Power compound drilling tools characterized by comprising lower power drilling tool, the middle power drilling tool being sequentially coaxially nested With upper power drilling tool;The lower power drilling tool, middle power drilling tool and upper power drilling tool are respectively equipped with a power mechanism, described dynamic Force mechanisms can be operated alone its correspondence drilling tool and be rotated.
2. more Power compound drilling tools according to claim 1, which is characterized in that the lower power drilling tool includes: lower power Head and outer sleeve drilling tool;The lower power head is set to the upper end of the outer sleeve drilling tool, for driving the outer sleeve drilling tool Carry out spinning movement.
3. more Power compound drilling tools according to claim 2, which is characterized in that the lower power drilling tool further include: lower row Soil box;The lower casting slot is set to the upper end of the lower power head.
4. more Power compound drilling tools according to claim 1, which is characterized in that the middle power drilling tool includes: middle power Head, intermediate sleeve drilling tool and middle lifting device;The middle power head is set to the upper end of the intermediate sleeve drilling tool, for driving The intermediate sleeve drilling tool carries out spinning movement;The middle lifting device is set to the lower end of the middle power head, for driving The lower power drilling tool carries out lifting action.
5. more Power compound drilling tools according to claim 4, which is characterized in that the middle power drilling tool further include: middle row Soil box and middle limiting device, the middle casting slot are set to the upper end of the middle power head;The middle limiting device is set to institute State the lower end of middle power head.
6. more Power compound drilling tools according to claim 1, which is characterized in that the upper power drilling tool includes: upper power Head, center drilling tool and upper lifting device;The upper power head is set to the upper end of the center drilling tool, for driving the center Drilling tool carries out spinning movement;The upper lifting device is set to the lower end of the upper power head, for driving the middle power drill Tool carries out lifting action.
7. more Power compound drilling tools according to claim 6, which is characterized in that the upper power drilling tool further include: the upper limit Position device;The position limit device is set to the lower end of the upper power head.
8. more Power compound drilling tools described in any one of -7 according to claim 1, which is characterized in that further include: pressurizing device, The pressurizing device is set to any one among the upper power drilling tool and the middle power drilling tool.
9. a kind of type stake of more Power compound drilling tool preparations described in any one of -8 according to claim 1, which is characterized in that packet It includes: main body pile body;
At least two back taper stepped ramp type bodies are provided on the main body pile body;
The inverted cone disk inclined-plane extended line of the back taper stepped ramp type body and the included angle range of the main body pile body central axis Are as follows: 5 °~90 °.
10. a kind of more Power compound drilling tools described in any one of -8 according to claim 1 are with the method for preparative stake, feature It is, comprising:
Demand according to stratum to engineering method, the upper power drilling tool, middle power drilling tool and lower power drilling tool are successively drilled into respectively successively From projected depth, so as to form multiple back taper stepped ramp type drillings;Start concrete pump, starts pressure concrete injecting, successively in pressure concrete injecting Power drilling tool, middle power drilling tool and lower power drilling tool in promotion, Synchronous lifting after each power drilling tool bottom end is successively concordant, until Aperture absolute altitude is mentioned, while concrete also presses and fills pile to designed elevation, realizes that disposable completion pore-forming and concrete pressure fill pile.
CN201811186080.9A 2018-10-11 2018-10-11 More Power compound drilling tools, preparation method and type stake Pending CN109372421A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811186080.9A CN109372421A (en) 2018-10-11 2018-10-11 More Power compound drilling tools, preparation method and type stake

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811186080.9A CN109372421A (en) 2018-10-11 2018-10-11 More Power compound drilling tools, preparation method and type stake

Publications (1)

Publication Number Publication Date
CN109372421A true CN109372421A (en) 2019-02-22

Family

ID=65403485

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811186080.9A Pending CN109372421A (en) 2018-10-11 2018-10-11 More Power compound drilling tools, preparation method and type stake

Country Status (1)

Country Link
CN (1) CN109372421A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0892956A (en) * 1994-09-29 1996-04-09 Chiyoda Koei Kk Square type post steel pipe pile with multi-stage spiral blade
JP2002105954A (en) * 2000-09-28 2002-04-10 Nippon Steel Corp Rotary penetration steel pipe pile
CN1632237A (en) * 2004-12-29 2005-06-29 天津市华达商贸有限公司 Construction machinery for long spiral press pouring concrete lock pin combination piles
CN104763328A (en) * 2015-04-02 2015-07-08 宁波易和桩基工程技术开发有限公司 Hydraulic reaming circulation drilling machine and reaming pile construction technology thereof
CN207296871U (en) * 2017-06-23 2018-05-01 刘淼 The structure-improved of full-sleeve twist bit
CN108035341A (en) * 2018-01-24 2018-05-15 李广信 Extruding and removing soil complex superposition is nested drilling tool, the back taper stepped ramp type stake of CFG reducings and method
CN209244498U (en) * 2018-10-11 2019-08-13 李广信 More Power compound drilling tools

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0892956A (en) * 1994-09-29 1996-04-09 Chiyoda Koei Kk Square type post steel pipe pile with multi-stage spiral blade
JP2002105954A (en) * 2000-09-28 2002-04-10 Nippon Steel Corp Rotary penetration steel pipe pile
CN1632237A (en) * 2004-12-29 2005-06-29 天津市华达商贸有限公司 Construction machinery for long spiral press pouring concrete lock pin combination piles
CN104763328A (en) * 2015-04-02 2015-07-08 宁波易和桩基工程技术开发有限公司 Hydraulic reaming circulation drilling machine and reaming pile construction technology thereof
CN207296871U (en) * 2017-06-23 2018-05-01 刘淼 The structure-improved of full-sleeve twist bit
CN108035341A (en) * 2018-01-24 2018-05-15 李广信 Extruding and removing soil complex superposition is nested drilling tool, the back taper stepped ramp type stake of CFG reducings and method
CN209244498U (en) * 2018-10-11 2019-08-13 李广信 More Power compound drilling tools

Similar Documents

Publication Publication Date Title
CN103556625B (en) Complex squeezed pile forming construction method and complex squeezed pile forming device
CN104763328B (en) A kind of hydraulic pressure reaming circulation drilling machine and its reaming pile constructing process
CN110043187A (en) The fluid pressure type reducing reaming bit and filling pile construction engineering method of long-spiral drilling machine
CN102226342B (en) Multi-functional piling machine for jet grouting pile-sinking
CN208293568U (en) Extruding and removing soil complex superposition is nested drilling tool
CN102182180B (en) Rotary extrusion sleeve anchor rod and construction method thereof
CN102312427A (en) Half soil squeezing screw expansion pile forming method
CN106192996A (en) The construction method of a kind of T-shaped stake and the T-shaped drilling tool of T-shaped cast pile driving construction
CN108035341A (en) Extruding and removing soil complex superposition is nested drilling tool, the back taper stepped ramp type stake of CFG reducings and method
CN109098655B (en) Multi-power composite drilling tool, preparation method and pile
CN209244498U (en) More Power compound drilling tools
CN109025809B (en) Multi-power guide linkage composite drilling tool, preparation method and pile type
CN209244499U (en) Link combination drill tool for more power guide positions
CN205025364U (en) Dig drilling tool soon
CN202039369U (en) Multifunctional pilling machine for jet grouting pile sinking
CN209244509U (en) More Power compound drilling tools
CN109372421A (en) More Power compound drilling tools, preparation method and type stake
CN106836202A (en) Bored in efficient pile tube soil, piling, dust, whitewash all-in-one and its construction technology
CN210343236U (en) Thread matching type multi-power composite drilling tool and profile pile
CN210105746U (en) Thread fit type composite drilling tool and profile pile
CN210858571U (en) Thread matching type multi-power guide composite drilling tool and profile pile
CN204627406U (en) A kind of hydraulic pressure reaming circulation drilling machine
CN209228300U (en) Link combination drill tool for more power guide positions
CN106978974A (en) The stake of CFG reducing back tapers stepped ramp type and preparation method and drilling tool
CN109025808B (en) Multi-power guide linkage composite drilling tool, preparation method and pile type

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20190222

Assignee: Hebei cone base civil engineering Co., Ltd.

Assignor: Li Guangxin

Contract record no.: 2019990000261

Denomination of invention: Multi-power compound drilling tool, production method thereof and pile

License type: Exclusive License

Record date: 20190801