CN106836202A - Bored in efficient pile tube soil, piling, dust, whitewash all-in-one and its construction technology - Google Patents

Bored in efficient pile tube soil, piling, dust, whitewash all-in-one and its construction technology Download PDF

Info

Publication number
CN106836202A
CN106836202A CN201710086464.2A CN201710086464A CN106836202A CN 106836202 A CN106836202 A CN 106836202A CN 201710086464 A CN201710086464 A CN 201710086464A CN 106836202 A CN106836202 A CN 106836202A
Authority
CN
China
Prior art keywords
pile
pile tube
hollow drill
segment
dust
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710086464.2A
Other languages
Chinese (zh)
Inventor
沈国勤
姚锋祥
沈飞
杭旭亚
沈蕾
钱沈霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANJI CONSTRUCTION GROUP CO Ltd
Original Assignee
JIANJI CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANJI CONSTRUCTION GROUP CO Ltd filed Critical JIANJI CONSTRUCTION GROUP CO Ltd
Priority to CN201710086464.2A priority Critical patent/CN106836202A/en
Publication of CN106836202A publication Critical patent/CN106836202A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses bored in efficient pile tube soil, piling, dust, whitewash all-in-one and its construction technology, including Static pressure pile driver:There are Static pressure pile driver base and microscope carrier;Column:Column bottom rear side is provided with twin drum winch and rear fixed pulley, lower front installs preceding fixed pulley group, upper fixed pulley group is arranged at top, twin drum winch is connected by the first steel wire rope with rear fixed pulley, upper fixed pulley group with power set top, power set bottom centre is provided with joint screw socket, two bottom sides have pressurization running block, and twin drum winch is connected with preceding fixed pulley group, pressurization running block by the second steel wire rope;Some section hollow drills:There is joint screw socket top and bottom, and apex point is arranged at bottom, and pressure injection powder high, slip casting interface tube are arranged at top;Some section pile tubes:Pile tube is hung in Pile holding mechanism.The present invention realizes a tractor serves several purposes function, solve due to Geological Reasons piling do not reach projected depth generation cut stake, draw hole, the low problem of single pile bearing, it is to avoid the differential settlement of building.

Description

Bored in efficient pile tube soil, piling, dust, whitewash all-in-one and its construction technology
Technical field
Bored the present invention relates to the realm of building construction, in specifically efficient pile tube soil, piling, dust, whitewash all-in-one and its Construction technology.
Background technology
Static pressure pile driver is widely used in China's construction foundation working, due to its using the static pressure of the oil cylinder that pressurizes by coagulation Native pile tube has the advantages that without friction, noiselessness, speed of application are fast in being directly vertically pressed into stratum, therefore work progress.However, Geological conditions is not quite similar in construction, often due to the reason such as geology layer of sand is thicker, packing is high, causes stake to reach and set Meter absolute altitude, or even cut stake.Additionally, the factor such as muck soil moisture content is high, bearing capacity of single pile is low, cohesive soil soil extrusion in construction effect is big Also the development prospect of Static pressure pile driver is seriously constrained.
Accordingly, it would be desirable to a kind of efficient pile tube in bore soil, piling, dust, all-in-one of whitewashing.
The content of the invention
To solve above-mentioned problem, it is an object of the invention to provide brill soil, piling, spray in a kind of efficient pile tube Powder, whitewashing all-in-one and its construction technology.Bore in efficient pile tube of the present invention soil, piling, dust, all-in-one of whitewashing, tie Rationally, easy construction realizes the function of a tractor serves several purposes to structure, reduces machine cost, improves the service efficiency of machine, has Field is widely applied, and only needs the working procedure can just to reach design and construction depth, both improve efficiency of construction, and Ensure that bearing capacity of single pile, and the pile body periphery soil body and stake bottom are dusted, after spray operation, a footpath and formation is expanded Stake bottom enlarged footing, it is to avoid produce differential settlement, reliable in quality, security performance is high.
To reach above-mentioned purpose, the technical scheme is that:
Bored in efficient pile tube soil, piling, dust, all-in-one of whitewashing, including:
Static pressure pile driver:The Static pressure pile driver includes Static pressure pile driver base, and Static pressure pile driver base top is provided with microscope carrier, Static pressure pile driver Hydraulic traveling mechanism is provided between base and microscope carrier, Pile holding mechanism and mechanism of pile are provided with microscope carrier;
Column:Column is erect and is fixed on microscope carrier, and column bottom rear side is provided with twin drum winch and rear fixed pulley, column bottom Installed in front has a preceding fixed pulley group, and column top is provided with fixed pulley group, rear fixed on rear side of twin drum winch and column bottom Upper fixed pulley group at the top of pulley, column is connected by the first steel wire rope with power set top center, in the power set Motor and reductor are installed, power set bottom centre is provided with joint screw socket, and two bottom sides are additionally provided with pressurization movable pulley Group, the twin drum winch is connected with the preceding fixed pulley group on front side of column bottom, pressurization running block by the second steel wire rope, shape Into pressue device, microscope carrier surface is fixed in one end of the second steel wire rope;
Some section hollow drills:Often section hollow drill top and bottom are provided with joint screw socket, are used between adjacent hollow drilling rod Threaded connection, the hollow drill lower end base be provided with bipyramid shape dust, whitewash, the apex point of automatic open close, hollow drill top Portion is additionally provided with pressure injection powder high, slip casting interface tube, and is connected with outside note powder, grouting equipment by noting powder, Grouting Pipe;
Some section pile tubes:The pile tube is hollow tubular structures, often saves pile tube and is hung in Pile holding mechanism through microscope carrier, described hollow Drill rod sleeve is embedded in inside pile tube.Bore in a kind of pile tube soil, dust, whitewash, piling all-in-one machine structure rationally, easy construction, The function of a tractor serves several purposes is realized, machine cost is reduced, the service efficiency of machine is improved, solved due to Geological Reasons piling What is do not reached projected depth and produce cuts stake, draws hole, the problems such as bearing capacity of single pile is low, by pile tube internal drilling, dusts, whitewashes Function, both improves efficiency of construction, in turn ensures that the bearing capacity of single pile of pile tube, and the pile body periphery soil body and stake bottom are sprayed A footpath is expanded after powder, spray operation and base expanding and base expanding effect is formd, it is to avoid the differential settlement of building, with widely should Use field.
Further, the height of the column is 26-32m.Steel wire rope drives the distance of drilling rod movement also up to 26-32m, Meet the requirement of 12 meters to 15 meters of single-unit pile tube maximum length, it is ensured that drilling rod has room for promotion, improves efficiency of construction.
Further, the hollow drill surface soldered has spiral blade.Can will be unnecessary during rod boring Soil discharge, reduce pressure, be conducive to construction.
Further, the first steel wire rope drive motor, reductor and hollow drill move up and down.
Further, when the hollow drill is moved upwards, apex point disengages 2-3cm with hollow drill, and hollow drill is downward During motion, apex point is closed with hollow drill.When hollow drill is moved upwards so that hollow apex point is disengaged with drilling rod, outside note Powder, grouting equipment carry out high pressure dust, gunite work, fully the soft soil consolidation around pile body, improve bearing capacity of single pile, it is to avoid Produce differential settlement;When hollow drill is moved downward, apex point and hollow drill are closed, and are dusted, pause of whitewash, continuation next step Work.
Further, the joint screw socket at the top of the hollow drill is public screw socket, and the joint screw socket of bottom is female screw socket.
Further, it is additionally provided with crane on vehicle on the microscope carrier.
Bored in efficient pile tube soil, piling, dust, the construction technology of all-in-one of whitewashing, comprise the following steps:
(1)Apply utilization of hour crane on vehicle hang in first segment pile tube into Static pressure pile driver Pile holding mechanism in, be aligned terrestrial positioning Next stroke is pressed into after point, each stroke 1.6-2m;
(2)Start twin drum winch, it is by the motion of rear fixed pulley, upper fixed pulley group and the first steel wire rope, first segment is hollow Drilling rod is inserted in first segment pile tube, until first segment hollow drill exceedes first segment pile tube bottom 20-50mm;
(3)Hollow drill is lifted up, the note powder, grouting equipment outside startup are dusted, gunite work;
(4)First segment pile tube synchronously presses downward to next stroke, keeps first segment hollow drill all the time than first segment pile tube The low 20-50mm in bottom, and persistently dusted, gunite work, now, when hollow drill deadweight is lower bores difficult, open pressurization Device, carries out back-pressure and buries using stake machine own wt, it is ensured that drilling depth and dust, gunite effect;
(5)When first segment pile tube is depressed into welding position, the threaded connection at the top of first segment hollow drill is unclamped, hung with crane on vehicle Enter second section pile tube, and be inserted in first segment drilling rod, then second section drilling rod is inserted in second section pile tube;
(6)Second section pile tube is lifted into 0.5-1.0m followed by crane on vehicle, and by female spiral shell of second section hollow drill bottom Mouth is docked with the public screw socket of first segment hollow drill, puts down second section pile tube welded after being aligned with first segment pile tube solid in addition It is fixed;
(7)Repeat step(1)- step(6), until pile tube reaches projected depth, now, high pressure is dusted, time lengthening of whitewashing 3- 5min, Stress control, fully the soft soil consolidation around pile body, forms pile body and stake end bottom soil cement expands at 3-5 MPas Head, whole pile operational procedure is completed.
The beneficial effects of the present invention are:
Bore in efficient pile tube of the present invention soil, piling, dust, all-in-one of whitewashing, rational in infrastructure, easy construction realizes The function of a tractor serves several purposes, reduces machine cost, improves the service efficiency of machine, solves because Geological Reasons piling is not reached Projected depth and produce cut stake, draw hole, the problems such as bearing capacity of single pile is low, by pile tube internal drilling, dust, whitewashing function, Both efficiency of construction is improve, the bearing capacity of single pile of pile tube is in turn ensured that, and the pile body periphery soil body and stake bottom are dusted, is sprayed A footpath is expanded after slurry operation and form base expanding and base expanding effect, it is to avoid the differential settlement of building, have a wide range of applications neck Domain.
Brief description of the drawings
In order to illustrate more clearly of the embodiment of the present application or technical scheme of the prior art, below will be to embodiment or existing The accompanying drawing to be used needed for having technology description is briefly described, it should be apparent that, drawings in the following description are only this Some embodiments described in application, for those of ordinary skill in the art, on the premise of not paying creative work, Other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 be bore in efficient pile tube provided by the present invention soil, piling, dust, the structural representation of all-in-one of whitewashing.
Fig. 2 be bore in efficient pile tube provided by the present invention soil, piling, dust, structure for amplifying shows at the M of all-in-one of whitewashing It is intended to.
Fig. 3 be bore in efficient pile tube provided by the present invention soil, piling, dust, structure for amplifying shows at the N of all-in-one of whitewashing It is intended to.
Fig. 4 be efficient pile tube provided by the present invention in bore soil, piling, dust, all-in-one of whitewashing is moved upwards in drilling rod When, the view of apex point.
Fig. 5 be efficient pile tube provided by the present invention in bore soil, piling, dust, all-in-one of whitewashing is moved downward in drilling rod When, the view of apex point.
Wherein:1 is Static pressure pile driver base, and 2 is microscope carrier, and 3 is hydraulic traveling mechanism, and 4 is Pile holding mechanism, and 5 is mechanism of pile, 6 is column, and 7 is twin drum winch, and 8 is rear fixed pulley, and 9 is preceding fixed pulley group, and 10 is upper fixed pulley group, and 11 is the first steel wire Rope, 12 is power set, and 13 is motor, and 14 is reductor, and 15 is joint screw socket, and 16 is pressurization running block, and 17 is the second steel Cord, 18 is hollow drill, and 19 is apex point, and 20 is pressure injection powder high, slip casting interface tube, and 21 is note powder, Grouting Pipe, 22 be note powder, Grouting equipment, 23 is pile tube, and 24 is spiral blade, and 25 is crane on vehicle.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with the accompanying drawings to specific reality of the invention The mode of applying is described in detail.The example of these preferred embodiments is illustrated in the accompanying drawings.Shown in accompanying drawing and according to What the embodiments of the present invention of Description of Drawings were merely exemplary, and the present invention is not limited to these implementation methods.
Here, also, it should be noted that in order to avoid having obscured the present invention because of unnecessary details, in the accompanying drawings only Structure and/or the process step closely related with scheme of the invention is shown, and is eliminated little with relation of the present invention Other details.
Referring to Fig. 1, Fig. 1 be efficient pile tube in bore soil, piling, dust, all-in-one of whitewashing, including:
Static pressure pile driver:The Static pressure pile driver includes Static pressure pile driver base 1, and the top of Static pressure pile driver base 1 is provided with microscope carrier 2, static pressure Hydraulic traveling mechanism 3 is provided between stake machine base 1 and microscope carrier 2, Pile holding mechanism 4 and mechanism of pile 5 are provided with microscope carrier 2;
Column 6:Column 6 is erect and is fixed on microscope carrier 2, and the bottom rear of column 6 is provided with twin drum winch 7 and rear fixed pulley 8, stands The lower front of post 6 is provided with preceding fixed pulley group 9, and the top of column 6 is provided with fixed pulley group 10, twin drum winch 7 and the bottom of column 6 The upper fixed pulley group 10 of rear fixed pulley 8, the top of column 6 on rear side of portion is by the first steel wire rope 11 and the top center of power set 12 Connection, as shown in Fig. 2 being provided with motor 13 and reductor 14 in the power set 12, the bottom centre of power set 12 is set There is joint screw socket 15, two bottom sides are additionally provided with pressurization running block 16, the twin drum winch 7 and the lower front of column 6 Preceding fixed pulley group 9, pressurization running block 16 are connected by the second steel wire rope 17, form pressue device, the one of the second steel wire rope 17 The surface of microscope carrier 2 is fixed at end, participates in Fig. 3;
Some section hollow drills 18:Often the top and bottom of section hollow drill 18 are provided with joint screw socket 15, adjacent hollow drilling rod 18 Between using threaded connection, the lower end base of the hollow drill 18 be provided with bipyramid shape dust, whitewash, the apex point of automatic open close 19, the top of hollow drill 18 is additionally provided with pressure injection powder high, slip casting interface tube 20, and by noting the note of powder, Grouting Pipe 21 and outside Powder, grouting equipment 22 are connected;
Some section pile tubes 23:The pile tube 23 is hollow tubular structures, often saves pile tube 23 and is hung in Pile holding mechanism 4 through microscope carrier 2, 18 sets of the hollow drill is embedded in inside pile tube 23.
Further, the height of the column 6 is 26-32m.
Further, the surface soldered of the hollow drill 18 has spiral blade 24.
Further, the drive motor 13 of first steel wire rope 11, reductor 14 and hollow drill 18 move up and down.
As illustrated in figures 4-5, further, when the hollow drill 18 is moved upwards, apex point 19 is disengaged with hollow drill 18 2-3cm, when hollow drill 18 is moved downward, apex point 19 is closed with hollow drill 18.
Further, the joint screw socket 15 at the top of the hollow drill 18 is public screw socket, and the joint screw socket 15 of bottom is mother Screw socket.
Further, it is additionally provided with crane on vehicle 25 on the microscope carrier 2.
Bored in efficient pile tube soil, piling, dust, the construction technology of all-in-one of whitewashing, comprise the following steps:
(1)Apply utilization of hour crane on vehicle 25 to hang in the Pile holding mechanism 4 of the entrance Static pressure pile driver of first segment pile tube 23, be directed at ground Next stroke is pressed into after anchor point, each stroke 1.6-2m;
(2)Start twin drum winch 7, by rear fixed pulley 8, the motion of the steel wire rope 11 of upper fixed pulley group 10 and first, by first Section hollow drill 18 is inserted in first segment pile tube 23, until first segment hollow drill 18 exceedes the bottom 20- of first segment pile tube 23 50mm;
(3)Hollow drill 18 is lifted up, the note powder, grouting equipment 22 outside startup are dusted, gunite work;
(4)First segment pile tube 23 is synchronous to press downward to next stroke, keeps first segment hollow drill 18 to compare first segment all the time The low 20-50mm in the bottom of pile tube 23, and persistently dusted, gunite work, now, when the deadweight of hollow drill 18 is lower bores difficult, Open pressue device, carry out back-pressure using stake machine own wt and bury, it is ensured that drilling depth and dust, gunite effect;
(5)When first segment pile tube 23 is depressed into welding position, the threaded connection at the top of first segment hollow drill 18 is unclamped, use truck-mounted crane Machine 25 hangs in second section pile tube 23, and is inserted in first segment drilling rod 18, then second section drilling rod 18 is inserted in second section pile tube 23;
(6)Second section pile tube 23 is lifted into 0.5-1.0m followed by crane on vehicle 25, and by the bottom of second section hollow drill 18 Female screw socket docked with the male screw socket of first segment hollow drill 18, second section pile tube 23 is put down and first segment pile tube 23 pairs in addition It is welded and fixed after standard;
(7)Repeat step(1)- step(6), until pile tube 23 reaches projected depth, now, high pressure is dusted, time lengthening of whitewashing 3-5min, Stress control, fully the soft soil consolidation around pile body, forms pile body and stake end bottom soil cement expands at 3-5 MPas Major part, whole pile operational procedure is completed.
Bore in efficient pile tube of the present invention soil, piling, dust, all-in-one of whitewashing, rational in infrastructure, easy construction, reality The function of a tractor serves several purposes is showed, has reduced machine cost, improved the service efficiency of machine, solved because Geological Reasons piling reaches Produced less than projected depth cut stake, draw hole, the problems such as bearing capacity of single pile is low, by pile tube internal drilling, dust, work(of whitewashing Can, efficiency of construction is both improve, the bearing capacity of single pile of pile tube is in turn ensured that, and the pile body periphery soil body and stake bottom are sprayed A footpath is expanded after powder, spray operation and base expanding and base expanding effect is formd, it is to avoid the differential settlement of building, with widely should Use field.
Finally, in addition it is also necessary to explanation, term " including ", "comprising" or its any other variant be intended to it is non-exclusive Property include so that process, method, article or equipment including a series of key elements not only include those key elements, and Also include other key elements being not expressly set out, or also include intrinsic for this process, method, article or equipment Key element.

Claims (8)

1. bore in efficient pile tube soil, piling, dust, all-in-one of whitewashing, it is characterised in that including:
Static pressure pile driver:The Static pressure pile driver includes Static pressure pile driver base, and Static pressure pile driver base top is provided with microscope carrier, Static pressure pile driver Hydraulic traveling mechanism is provided between base and microscope carrier, Pile holding mechanism and mechanism of pile are provided with microscope carrier;
Column:Column is erect and is fixed on microscope carrier, and column bottom rear side is provided with twin drum winch and rear fixed pulley, column bottom Installed in front has a preceding fixed pulley group, and column top is provided with fixed pulley group, rear fixed on rear side of twin drum winch and column bottom Upper fixed pulley group at the top of pulley, column is connected by the first steel wire rope with power set top center, in the power set Motor and reductor are installed, power set bottom centre is provided with joint screw socket, and two bottom sides are additionally provided with pressurization movable pulley Group, the twin drum winch is connected with the preceding fixed pulley group on front side of column bottom, pressurization running block by the second steel wire rope, shape Into pressue device, microscope carrier surface is fixed in one end of the second steel wire rope;
Some section hollow drills:Often section hollow drill top and bottom are provided with joint screw socket, are used between adjacent hollow drilling rod Threaded connection, the hollow drill lower end base be provided with bipyramid shape dust, whitewash, the apex point of automatic open close, hollow drill top Portion is additionally provided with pressure injection powder high, slip casting interface tube, and is connected with outside note powder, grouting equipment by noting powder, Grouting Pipe;
Some section pile tubes:The pile tube is hollow tubular structures, often saves pile tube and is hung in Pile holding mechanism through microscope carrier, described hollow Drill rod sleeve is embedded in inside pile tube.
2. bore in efficient pile tube according to claim 1 soil, piling, dust, all-in-one of whitewashing, it is characterised in that it is described The height of column is 26-32m.
3. bore in efficient pile tube according to claim 1 soil, piling, dust, all-in-one of whitewashing, it is characterised in that it is described Hollow drill surface soldered has spiral blade.
4. bore in efficient pile tube according to claim 1 soil, piling, dust, all-in-one of whitewashing, it is characterised in that it is described First steel wire rope drive motor, reductor and hollow drill move up and down.
5. bore in efficient pile tube according to claim 4 soil, piling, dust, all-in-one of whitewashing, it is characterised in that it is described When hollow drill is moved upwards, apex point and hollow drill disengage 2-3cm, when hollow drill is moved downward, apex point and hollow drill Closure.
6. bore in efficient pile tube according to claim 1 soil, piling, dust, all-in-one of whitewashing, it is characterised in that it is described Joint screw socket at the top of hollow drill is public screw socket, and the joint screw socket of bottom is female screw socket.
7. bore in efficient pile tube according to claim 1 soil, piling, dust, all-in-one of whitewashing, it is characterised in that it is described Crane on vehicle is additionally provided with microscope carrier.
8. bore in efficient pile tube soil, piling, dust, the construction technology of all-in-one of whitewashing, it is characterised in that comprise the following steps:
(1)Apply utilization of hour crane on vehicle hang in first segment pile tube into Static pressure pile driver Pile holding mechanism in, be aligned terrestrial positioning Next stroke is pressed into after point, each stroke 1.6-2m;
(2)Start twin drum winch, it is by the motion of rear fixed pulley, upper fixed pulley group and the first steel wire rope, first segment is hollow Drilling rod is inserted in first segment pile tube, until first segment hollow drill exceedes first segment pile tube bottom 20-50mm;
(3)Hollow drill is lifted up, the note powder, grouting equipment outside startup are dusted, gunite work;
(4)First segment pile tube synchronously presses downward to next stroke, keeps first segment hollow drill all the time than first segment pile tube The low 20-50mm in bottom, and persistently dusted, gunite work, now, when hollow drill deadweight is lower bores difficult, open pressurization Device, carries out back-pressure and buries using stake machine own wt, it is ensured that drilling depth and dust, gunite effect;
(5)When first segment pile tube is depressed into welding position, the threaded connection at the top of first segment hollow drill is unclamped, hung with crane on vehicle Enter second section pile tube, and be inserted in first segment drilling rod, then second section drilling rod is inserted in second section pile tube;
(6)Second section pile tube is lifted into 0.5-1.0m followed by crane on vehicle, and by female spiral shell of second section hollow drill bottom Mouth is docked with the public screw socket of first segment hollow drill, puts down second section pile tube welded after being aligned with first segment pile tube solid in addition It is fixed;
(7)Repeat step(1)- step(6), until pile tube reaches projected depth, now, high pressure is dusted, time lengthening of whitewashing 3- 5min, Stress control, fully the soft soil consolidation around pile body, forms pile body and stake end bottom soil cement expands at 3-5 MPas Head, whole pile operational procedure is completed.
CN201710086464.2A 2017-02-17 2017-02-17 Bored in efficient pile tube soil, piling, dust, whitewash all-in-one and its construction technology Pending CN106836202A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710086464.2A CN106836202A (en) 2017-02-17 2017-02-17 Bored in efficient pile tube soil, piling, dust, whitewash all-in-one and its construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710086464.2A CN106836202A (en) 2017-02-17 2017-02-17 Bored in efficient pile tube soil, piling, dust, whitewash all-in-one and its construction technology

Publications (1)

Publication Number Publication Date
CN106836202A true CN106836202A (en) 2017-06-13

Family

ID=59127733

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710086464.2A Pending CN106836202A (en) 2017-02-17 2017-02-17 Bored in efficient pile tube soil, piling, dust, whitewash all-in-one and its construction technology

Country Status (1)

Country Link
CN (1) CN106836202A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107386977A (en) * 2017-07-20 2017-11-24 建华建材(江苏)有限公司 A kind of interior rig and its construction method
CN109881675A (en) * 2018-10-29 2019-06-14 山东君宏基础工程有限公司 A kind of pile-sinking device and its construction method
CN110410019A (en) * 2019-08-30 2019-11-05 宁波中淳高科股份有限公司 A kind of pile-driving machine configuring the double drilling machines of double guide rails

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383431A (en) * 2011-04-21 2012-03-21 上海城地建设发展有限公司 Sinking device and novel sinking method of center dug prestressed centrifuge pipe pile (square pile)
CN102400465A (en) * 2010-09-10 2012-04-04 湖北毅力机械有限公司 Static pressure moderately-excavated pile pressing machine and static pressure moderately-excavated pile pressing construction method
CN104947652A (en) * 2015-07-02 2015-09-30 浙江新曙光建设有限公司 Long auger drilling cement mortar retaining wall type implanted pile tube construction device and construction method
CN206635747U (en) * 2017-02-17 2017-11-14 建基建设集团有限公司 One kind is bored soil, piling in pile tube, dusted, all-in-one of whitewashing

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102400465A (en) * 2010-09-10 2012-04-04 湖北毅力机械有限公司 Static pressure moderately-excavated pile pressing machine and static pressure moderately-excavated pile pressing construction method
CN102383431A (en) * 2011-04-21 2012-03-21 上海城地建设发展有限公司 Sinking device and novel sinking method of center dug prestressed centrifuge pipe pile (square pile)
CN104947652A (en) * 2015-07-02 2015-09-30 浙江新曙光建设有限公司 Long auger drilling cement mortar retaining wall type implanted pile tube construction device and construction method
CN206635747U (en) * 2017-02-17 2017-11-14 建基建设集团有限公司 One kind is bored soil, piling in pile tube, dusted, all-in-one of whitewashing

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107386977A (en) * 2017-07-20 2017-11-24 建华建材(江苏)有限公司 A kind of interior rig and its construction method
CN107386977B (en) * 2017-07-20 2023-06-20 建华建材(中国)有限公司 Internal drilling machine and construction method thereof
CN109881675A (en) * 2018-10-29 2019-06-14 山东君宏基础工程有限公司 A kind of pile-sinking device and its construction method
CN110410019A (en) * 2019-08-30 2019-11-05 宁波中淳高科股份有限公司 A kind of pile-driving machine configuring the double drilling machines of double guide rails
CN110410019B (en) * 2019-08-30 2024-02-27 宁波中淳高科股份有限公司 Drilling pile machine with double guide rails and double drilling machines

Similar Documents

Publication Publication Date Title
CN105649083B (en) The clear stake device of the disposable rotary-cutting type of full-sleeve and its clear piling method
CN104763328A (en) Hydraulic reaming circulation drilling machine and reaming pile construction technology thereof
CN102383431B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN103603342A (en) Construction method of ultra-long bored concrete pile with large-diameter casing combination
CN106836202A (en) Bored in efficient pile tube soil, piling, dust, whitewash all-in-one and its construction technology
CN107120058A (en) It is a kind of to be used for gravelly soil, the pore-forming grouting method of viscous soil horizon
CN205387708U (en) Clear stake device of disposable rotary -cut formula of a complete set of pipe
CN102182180B (en) Rotary extrusion sleeve anchor rod and construction method thereof
CN103572770B (en) A kind of stake case hydraulic structures and construction method thereof
CN104213554A (en) Construction method of slip-casting variable-cross section steel pipe pile and expansion and extrusion device of slip-casting variable-cross section steel pipe pile
CN212129131U (en) Crowded native pore-forming stock construction structures
CN206635747U (en) One kind is bored soil, piling in pile tube, dusted, all-in-one of whitewashing
CN111749231A (en) Double-sleeve double-drive full-rotation pile forming device and pile forming process
CN102296597A (en) Construction method of steel pipe piles in shallow soil layer
CN102758434B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN112252312B (en) Construction method for enhancing integral stress performance of PHC pipe pile
CN206246052U (en) Soil compaction rotary-jetting bottom-expanding pile shaped device
CN107558469A (en) Pin and the stake with pin of pile body
CN103821137A (en) Construction method and device for long auger drilling, rock embedding, bottom expanding and press-casting pile
CN106567386A (en) Pouring type pile driver and pile driving method therefor
CN209244499U (en) Link combination drill tool for more power guide positions
CN204627406U (en) A kind of hydraulic pressure reaming circulation drilling machine
CN209244498U (en) More Power compound drilling tools
CN105178315A (en) Pouring type pile driver and pile driving method using pile driver
CN205012337U (en) Pour formula pile driver

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170613