CN109371987A - Pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course - Google Patents

Pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course Download PDF

Info

Publication number
CN109371987A
CN109371987A CN201811209726.0A CN201811209726A CN109371987A CN 109371987 A CN109371987 A CN 109371987A CN 201811209726 A CN201811209726 A CN 201811209726A CN 109371987 A CN109371987 A CN 109371987A
Authority
CN
China
Prior art keywords
anchor cable
anchor
cable
pile
tensioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811209726.0A
Other languages
Chinese (zh)
Inventor
江家强
隗合新
李奥博
侯放
潘子龙
赵光宇
顾佳亮
刘金鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Installation Engineering Co Ltd
Original Assignee
China Construction Sixth Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Installation Engineering Co Ltd filed Critical China Construction Sixth Installation Engineering Co Ltd
Priority to CN201811209726.0A priority Critical patent/CN109371987A/en
Publication of CN109371987A publication Critical patent/CN109371987A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses pre-stress anti-slide pile supporting comprehensive construction methods in a kind of back fill course, this method comprises: work surface is excavated and levelling of the land;Construction friction pile and breast boards, pre-buried anchor cable perforation casing;After stake below backfill to anchor cable face;Anchor cable drilling, lashing and slip casting;Anchor cable wears rigid protective casing;Anchorage cable stretching;Rank backfilling of earthwork on anchor cable;Anchor cable mends tensioning, detection and sealing off and covering anchorage;The present invention solve collapse hole when constructing anchor cable in backfill cause anchor cable can not the problems such as lashing and slip casting is discontented, anchor cable hole deviations, longer anchor rope grouting tensioning period, guarantee anchor cable construction quality, shorten construction period, save the cost.

Description

Pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course
Technical field
The present invention relates to pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course, be particularly suitable for by Place limitation carries out backfill after needing excavation slope construction friction pile again, or height difference is usually larger up and down, and operation side is relatively narrow Pre-stress anti-slide pile engineering.
Background technique
Currently, mountain area tableland slope retaining form is more, the scale of construction is larger, especially by place limited can not slope processing forever Long property side slope generallys use pre-stress anti-slide pile slope retaining, such supporting shape if road is other, narrow landform equipotential is set Formula is limited by place, need excavation slope construct friction pile after carry out backfill again, upper and lower height difference is usually larger, operation side compared with It is narrow, it is affected to road traffic and surrounding enviroment.
Conventional construction technology is that crosshead construction anchor cable is set up on the outside of friction pile after constructing friction pile and backfill, This construction technology need to set up a large amount of crossheads, and prestress anchorage cable of constructing in back fill course after stake, face since collapse hole causes The problems such as drilling can not be crept into, anchor cable lashing is difficult, slip casting is discontented, while by anchor rope grouting technique intermittent effects, anchorage cable stretching It cannot be inserted into time, influence subsequent handling construction;Before anchor cable work, backfill earth lateral pressure is also possible to damage pile body.
If backfill anchor cable work after carry out, by anchor cable effect of distance, backfill work surface becomes smaller, be unfavorable for anchor cable at Product protection and backfill construction, and backfill can disturb the generation of stretch-draw anchor during being backfilling and compacted, construction quality It is difficult to control.
Summary of the invention
It is an object of the invention to solve the key problem in above-mentioned construction technology, prestressing force in a kind of back fill course is provided Anchor anti-slide piles supporting comprehensive construction method.
The purpose of the present invention is achieved by following technical proposals:
Pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course, which includes following Step:
(1) it carries out excavating smooth formation work surface in natural hill side slope;
(2) support bracket is built in side slope work surface carry out friction pile, bulkhead construction;Anchor cable is perforated sleeve pipe pre-embedding simultaneously In friction pile:
(3) anchor cable lashing, mortar depositing construction are completed after the opposite side slope work surface of friction pile is drilled;
(4) backfill construction is carried out under anchor cable face;
(5) the exposed anchor cable free end of side slope is passed through and reserves perforation casing in stake and carries out anchorage cable stretching process;
(6) one layer of anchor cable face is judged whether there is, if there is then return step (3);Otherwise enter in next step;
(7) anchor cable mends tensioning, detection and sealing off and covering anchorage.
The friction pile work progress:
2.1 since place limits, and friction pile generallys use manual pore-forming's rectangular pile, and primary concreting is completed;Below ground Using reinforced concrete core-tube manually digging hole pore-forming;
The used ratio of reinforcement of 2.2 friction piles is higher, and bar diameter is larger, and quantity is more, therefore carries out main reinforcement in the venue Processing connection, is hung in hole using truck crane by root, framework of steel reinforcement welding installation is carried out in hole, while binding compound stirrup, Pre-buried breast boards horizontal reinforcement;
2.3, in design height position, install anchor cable casing, casing uses seamless steel pipe, with level or tape measure in antiskid Telltale mark casing absolute altitude in stake main reinforcement adjusts casing tilt angle with dedicated angle measurement device, and casing and reinforcement welding are solid It is fixed, and sealed casing two sides hole with cystosepiment;
2.4 after reinforcing bar binding, from friction pile fore shaft position, set up double crosshead, pacify according to design size Decking, template use set shaped steel formwork, interior plus 2~3 M16 split bolts, the double steel pipe anchor ear clamping die of external application spacing 250 Plate;
2.5 pour antiskid pile concrete, and one-time-concreting batch is not less than 3 piles, and every pile answers placement layer by layer, one-time-concreting Depth is no more than 2m, and concreting should be continuous, there is not allowed that construction joint;
2.6 concrete reach after some strength (>=1.5Mpa), can remove friction pile template, and watering is covered in time after demoulding Lid maintenance, while the breast boards that can construct according to design drawing.
When antiskid pile driving construction, pre-buried anchor cable perforation casing, angular deviation is no more than 2 °, and deviations are no more than 5mm.
The anchor cable drilling, lashing and slip casting process:
4.1 set up anchor cable drilling platform in back fill course, project anchor cable hole location in slope surface with anchor cable angle positioning device, Drilling machine is set up, bore angle is adjusted, is drilled into weathered rock formation in work surface according to design;
4.2 anchor cables use 6 beamsSteel strand wires composition, anchors 6~8m of segment length, and anchor cable front end adds guiding cap, with Anchor cable is welded and fixed, interior packing reality cement mortar, and centering bracket and lock ring ring is arranged every the interval 0.4m~0.6m in anchoring section, will Centering bracket of the Grouting Pipe in the middle part of anchor cable passes through, and extends to anchoring section front end;Free section of anchor cable smears Huang after carrying out preservative treatment Oil, then housing PVC bellows, anchor cable are intercepted according to actual borehole depth scene, need to lengthen on theoretical length 70cm so as to Anchorage cable stretching;
4.3 bind after the assay was approved to anchor cable length, straight degree, centering bracket, Grouting Pipe, carry out anchor cable and enter hole, anchor cable It is promoted by anchor hole inclination angle, it is smooth when propulsion, if being unable to reach projected depth in progradation, anchor cable steadily be extracted Afterwards, borehole cleaning again, until being installed in place;
After 4.4 anchor cables are installed, borehole cleaning slip casting is carried out immediately, and grouting material presses M35 cement mortar mix ratio ingredient, uses Stop grouting plug is arranged in slip casing by pressure, the preceding aperture of slip casting, and grouting pressure is 0.5~1Mpa, until fresh slurry is overflowed in slip casting to aperture; A slurries are mended after slip casting 30~45 minutes again.
Anchor cable drills hole location deviation no more than 5mm, and angular deviation is no more than 2 °;Anchor rope grouting slurry uses cement mortar, Appropriate early strength agent and micro-expanding agent can be mixed;Preservative treatment is done in anchor cable free end, and passes through soap-free emulsion polymeization PVC hose protection sleeve pipe.
Described sleeve pipe is the seamless steel pipe of DN100, and casing is laid in backfill face, and casing central axes and anchor cable central axes exist Same vertical plane, height are higher than anchor cable central axes 10mm, and tilt angle is embedded to primary side with anchor cable tilt angle, protection sleeve pipe It is not less than 100mm in the soil layer of slope and in friction pile service sleeve.
The anchorage cable stretching process: when slip casting slurry and friction pile reach design strength 75% after carry out tensioning, use Hand oil pump and jack system are loaded, and pre- tensioning is carried out before formal tensioning, take 10%~20% design tensile load, To anchorage cable stretching 1~2 time, keeping its each location contacts close, keep steel strand wires totally straight, uniform force, tensioning should be loaded gently, Loading speed is not preferably greater than 0.1Nk/min.
5 applications of anchorage cable stretching load point, successively take 0.2,0.5,0.75,1.00,1.1 times of design value to be opened step by step It draws, preceding level Four holds lotus 5 minutes, and afterbody holds lotus 15 minutes, and every grade of load tensioning answers off-load 10% after holding lotus.
The anchor cable mends stretching process: after the completion of backfill, checking anchorage cable anchoring situation by root, carries out anchor cable benefit It draws;Anchor cable detection determines that qualification rate, detection method detect tensioning value with anchorage cable stretching process, anchor cable using on-site measurement latching force For 1.2~1.4 times for designing latching force;After detection is qualified, anchorage exposed parts steel strand wires are reserved using abrasive wheel cutting machine It is cut off after 50mm, to anchor pier brushing antirust paint, finally formwork pours C35 concrete sealing off and covering anchorage again.
Beneficial effect
1, the present invention can be inserted into construction in advance by anchor cable, it is ensured that the slip casting intensity before anchorage cable stretching meets design and wants It asks, so as to shorten construction period.
2, the present invention can effectively solve after friction pile when constructing prestress anchorage cable in back fill course, since collapse hole causes to bore The problems such as hole can not be crept into, anchor cable lashing is difficult, slip casting is discontented;Backfill can effectively be solved during being backfilling and compacted to The disturbance of stretch-draw anchor can effectively control the anchoring effect of anchor cable.
3, prestress anchorage cable can work before comprehensive backfill in the present invention, reduce backfill earth lateral pressure to cantilever The influence of friction pile;Setting up for crosshead on the outside of stake, the safety wind for reducing cost and constructing on high crosshead are reduced simultaneously Danger reduces the influence to external environment.
4, using this construction technology, speed of application is fast, applicability and strong operability, and safety reliability is high, reduces labour Intensity saves human and material resources.
Detailed description of the invention
Fig. 1 is pre-stress anti-slide pile supporting comprehensive construction method flow diagram in a kind of back fill course of the present invention.
Fig. 2 is applicable elements schematic diagram of the invention.
Fig. 3 is supporting sectional schematic diagram provided by the present invention.
Fig. 4 is supporting section drawing provided by the present invention.
Fig. 5 is the flat schematic diagram in slope excavating field provided by the present invention.
Fig. 6 is friction pile and service sleeve construction schematic diagram provided by the present invention.
Fig. 7 is the first rank anchor cable lashing provided by the present invention and slip casting schematic diagram.
Fig. 8 is the first rank backfill schematic diagram provided by the present invention.
Fig. 9 is the first rank anchor cable sleeve-penetrating schematic diagram provided by the present invention.
Figure 10 is anchor second-order cable drilling hole provided by the present invention and the first rank anchorage cable stretching schematic diagram.
Figure 11 is second-order anchor cable lashing provided by the present invention and slip casting schematic diagram.
Figure 12 is second-order backfill schematic diagram provided by the present invention.
Figure 13 is second-order anchor cable sleeve-penetrating schematic diagram provided by the present invention.
Figure 14 is second-order anchorage cable stretching schematic diagram provided by the present invention.
Figure 15 is second-order backfill schematic diagram provided by the present invention.
Figure 16 is anchor cable sealing off and covering anchorage schematic diagram provided by the present invention.
Specific embodiment
Technical solution of the present invention is described further in conjunction with attached drawing 1.
As shown in Figure 1, the present invention provides pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course,
(1) 101 carries out excavating smooth formation work surface in natural hill side slope;
(2) 102, which build support bracket in side slope work surface, carries out friction pile, bulkhead construction;Anchor cable is perforated casing simultaneously It is embedded in friction pile: the friction pile work progress:
2.1 since place limits, and friction pile generallys use manual pore-forming's rectangular pile, and primary concreting is completed;Below ground Using reinforced concrete core-tube manually digging hole pore-forming;
The used ratio of reinforcement of 2.2 friction piles is higher, and bar diameter is larger, and quantity is more, therefore carries out main reinforcement in the venue Processing connection, is hung in hole using truck crane by root, framework of steel reinforcement welding installation is carried out in hole, while binding compound stirrup, Pre-buried breast boards horizontal reinforcement;
2.3, in design height position, install anchor cable casing, casing uses seamless steel pipe, with level or tape measure in antiskid Telltale mark casing absolute altitude in stake main reinforcement adjusts casing tilt angle with dedicated angle measurement device, and casing and reinforcement welding are solid It is fixed, and sealed casing two sides hole with cystosepiment;
2.4 from friction pile fore shaft position, setting up double crosshead after reinforcing bar binding, pacifying according to design size Decking, template use set shaped steel formwork, interior plus 2~3 M16 split bolts, the double steel pipe anchor ear clamping die of external application spacing 250 Plate;
2.5 pour antiskid pile concrete, and one-time-concreting batch is not less than 3 piles, and every pile answers placement layer by layer, one-time-concreting Depth is no more than 2m, and concreting should be continuous, there is not allowed that construction joint;
2.6 concrete reach after some strength (>=1.5Mpa), can remove friction pile template, and watering is covered in time after demoulding Lid maintenance, while the breast boards that can construct according to design drawing.
(3) 103 complete anchor cable lashing, mortar depositing construction after the opposite side slope work surface of friction pile is drilled;
The anchor cable drilling, lashing and slip casting process:
4.1 set up anchor cable drilling platform in back fill course, project anchor cable hole location in slope surface with anchor cable angle positioning device, Drilling machine is set up, bore angle is adjusted, is drilled into middle weathered rock formation according to design;
4.2 anchor cables use 6 beamsSteel strand wires composition, anchors 6~8m of segment length, and anchor cable front end adds guiding cap, with Anchor cable is welded and fixed, interior packing reality cement mortar, and centering bracket and lock ring ring is arranged every the interval 0.4m~0.6m in anchoring section, will Centering bracket of the Grouting Pipe in the middle part of anchor cable passes through, and extends to anchoring section front end;Free section of anchor cable smears Huang after carrying out preservative treatment Oil, then housing PVC bellows, anchor cable are intercepted according to actual borehole depth scene, need to lengthen on theoretical length 70cm so as to Anchorage cable stretching;
4.3 bind after the assay was approved to anchor cable length, straight degree, centering bracket, Grouting Pipe, carry out anchor cable and enter hole, anchor cable It is promoted by anchor hole inclination angle, it is smooth when propulsion, if being unable to reach projected depth in progradation, anchor cable steadily be extracted Afterwards, borehole cleaning again, until being installed in place;
After 4.4 anchor cables are installed, borehole cleaning slip casting is carried out immediately, and grouting material presses M35 cement mortar mix ratio ingredient, uses Stop grouting plug is arranged in slip casing by pressure, the preceding aperture of slip casting, and grouting pressure is 0.5~1Mpa, until fresh slurry is overflowed in slip casting to aperture; A slurries are mended after slip casting 30~45 minutes again.Anchor cable drills hole location deviation no more than 5mm, and angular deviation is no more than 2 °;Anchor cable Slip casting slurry uses cement mortar, can mix appropriate early strength agent and micro-expanding agent;Preservative treatment is done in anchor cable free end, and passes through nothing Bond PVC hose protection sleeve pipe.
(4) 104 carry out backfill construction under anchor cable face;The backfill process: it is filled to anchor cable central axes or less 50mm 10mm is reserved as settling amount in place, it is desirable that be backfilling and compacted coefficient not less than design value.
The exposed anchor cable free end of side slope is passed through reserved perforation casing in stake and carries out anchorage cable stretching process by (5) 105;
The anchorage cable stretching process: when slip casting slurry and friction pile reach design strength 75% after carry out tensioning, use Hand oil pump and jack system are loaded, and pre- tensioning is carried out before formal tensioning, take 10%~20% design tensile load, To anchorage cable stretching 1~2 time, keeping its each location contacts close, keep steel strand wires totally straight, uniform force, tensioning should be loaded gently, Loading speed is not preferably greater than 0.1Nk/min.5 applications of anchorage cable stretching load point, successively take 0.2,0.5,0.75,1.00,1.1 times Design value carries out tensioning step by step, and preceding level Four holds lotus 5 minutes, and afterbody holds lotus 15 minutes, and every grade of load tensioning should unload after holding lotus Lotus 10%.
(6) 106 judge whether there is one layer of anchor cable face, if there is then return step (3);Otherwise enter in next step;
(7) 107 anchor cables mend tensioning, detection and sealing off and covering anchorage.The anchor cable mends stretching process: after the completion of backfill, examining by root Anchorage cable anchoring situation is looked into, anchor cable is carried out and mends tensioning;Anchor cable detection determines that qualification rate, detection method are same using on-site measurement latching force Anchorage cable stretching process, anchor cable detection tensioning value are 1.2~1.4 times for designing latching force;After detection is qualified, using abrasive wheel cutting machine It is cut off after anchorage exposed parts steel strand wires are reserved 50mm, to anchor pier brushing antirust paint, finally formwork pours C35 coagulation grave again Anchor.
As shown in Fig. 2, in a kind of back fill course pre-stress anti-slide pile supporting comprehensive construction method applicable elements.
As shown in figure 3, pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course, supporting construction packet Containing friction pile 10, backfill 11, anchor cable 1, centering bracket 2, tighten hoop, guiding cap 4, PVC hose 5, seamless steel pipe 6, pre-buried set Pipe 7, anchor plate 8, anchorage 9.
As shown in figure 4, diagram full-page proof node is supporting construction full-page proof.
As shown in figure 5, place excavate smooth, naturally stable side slope is formed after excavation.
As shown in fig. 6, construction friction pile and breast boards, require pre-buried anchor cable perforation casing according to design drawing.
As shown in fig. 7, setting up crosshead, anchor cable drilling construction is carried out;And anchor cable production, lashing, mortar depositing construction are carried out, and Exposed parts anchor cable is temporarily fixed in side slope, prevents backfill from disturbing.
As shown in figure 8, carrying out the construction of the first rank backfill, backfill is filled to the first rank anchor cable face or less.
As shown in figure 9, anchor cable is passed through seamless steel pipe protection sleeve pipe, protection sleeve pipe is embedded in the soil layer of primary side slope and friction pile It is not less than 100mm in service sleeve.
As shown in Figure 10, after slip casting intensity reaches design tensioning requirement, anchorage cable stretching is carried out;Operation is set up simultaneously, into Row second-order anchor cable drilling construction.
As shown in figure 11, the production of second-order anchor cable, lashing, mortar depositing construction are carried out;And exposed parts anchor cable is fixed temporarily In in side slope.
As shown in figure 12, the construction of second-order backfill is carried out, backfill is filled to second-order anchor cable face or less.
As shown in figure 13, second-order anchor cable is passed through into seamless steel pipe protection sleeve pipe, protection sleeve pipe is embedded in the soil layer of primary side slope And it is not less than 100mm in friction pile service sleeve.
As shown in figure 14, after slip casting intensity reaches design tensioning requirement, anchorage cable stretching is carried out.
As shown in figure 15, remaining backfill earthen backfill is carried out.
As shown in figure 16, it carries out anchor cable and mends tensioning and detection, sealing off and covering anchorage is carried out after detection is qualified, construction is completed.
In practical operation, process adjustment can be carried out according to scene, as anchor cable drilling, lashing, slip casting can be same with friction pile When construct, shorten technique interval;After can also carrying out lower rank backfill, anchor cable drilling is carried out on back fill course, is reduced anchor cable and is applied Work crosshead is set up.

Claims (10)

1. pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course, which is characterized in that the integrated construction side Method the following steps are included:
(1) it carries out excavating smooth formation work surface in natural hill side slope;
(2) support bracket is built in side slope work surface carry out friction pile, bulkhead construction;Simultaneously by anchor cable perforation sleeve pipe pre-embedding anti- In sliding pile:
(3) anchor cable lashing, mortar depositing construction are completed after the opposite side slope work surface of friction pile is drilled;
(4) backfill construction is carried out under anchor cable face;
(5) the exposed anchor cable free end of side slope is passed through and reserves perforation casing in stake and carries out anchorage cable stretching process;
(6) one layer of anchor cable face is judged whether there is, if there is then return step (3);Otherwise enter in next step;
(7) anchor cable mends tensioning, detection and sealing off and covering anchorage.
2. pre-stress anti-slide pile supporting comprehensive construction method, feature exist in back fill course according to claim 1 In: the friction pile work progress:
2.1 since place limits, and friction pile generallys use manual pore-forming's rectangular pile, and primary concreting is completed;Below ground uses Reinforced concrete core-tube manually digging hole pore-forming;
The used ratio of reinforcement of 2.2 friction piles is higher, and bar diameter is larger, and quantity is more, therefore carries out the processing of main reinforcement in the venue Connection, is hung in hole using truck crane by root, framework of steel reinforcement welding installation is carried out in hole, while binding compound stirrup, pre-buried Breast boards horizontal reinforcement;
2.3, in design height position, install anchor cable casing, casing uses seamless steel pipe, with level or tape measure in friction pile master Telltale mark casing absolute altitude on muscle adjusts casing tilt angle with dedicated angle measurement device, and casing is fixed with reinforcement welding, and Casing two sides hole is sealed with cystosepiment;
2.4 after reinforcing bar binding, from friction pile fore shaft position, set up double crosshead, install mould according to design size Plate, template use set shaped steel formwork, and the double steel pipe anchor ear of interior plus 2~3 M16 split bolts, external application spacing 250 clamps template;
2.5 pour antiskid pile concrete, and one-time-concreting batch is not less than 3 piles, and every pile answers placement layer by layer, one-time-concreting depth No more than 2m, concreting should be continuous, there is not allowed that construction joint;
2.6 concrete reach after some strength (>=1.5Mpa), can remove friction pile template, and watering covering in time is supported after demoulding Shield, while the breast boards that can construct according to design drawing.
3. pre-stress anti-slide pile supporting comprehensive construction method, feature exist in back fill course according to claim 2 In: when antiskid pile driving construction, pre-buried anchor cable perforation casing, angular deviation is no more than 2 °, and deviations are no more than 5mm.
4. pre-stress anti-slide pile supporting comprehensive construction method, feature exist in back fill course according to claim 1 In: the anchor cable drilling, lashing and slip casting process:
4.1 set up anchor cable drilling platform in back fill course, project anchor cable hole location in slope surface with anchor cable angle positioning device, set up Drilling machine adjusts bore angle, is drilled into middle weathered rock formation according to design;
4.2 anchor cables are formed using steel strand wires, anchor 6~8m of segment length, anchor cable front end adds guiding cap, is welded and fixed with anchor cable, interior Packing reality cement mortar, centering bracket and lock ring ring is arranged every the interval 0.4m~0.6m in anchoring section, by Grouting Pipe from anchor cable The centering bracket in portion passes through, and extends to anchoring section front end;Free section of anchor cable carries out coating butter after preservative treatment, then housing PVC Bellows, anchor cable are intercepted according to actual borehole depth scene;
4.3 bind after the assay was approved to anchor cable length, straight degree, centering bracket, Grouting Pipe, carry out anchor cable and enter hole, anchor cable presses anchor Hole inclination angle promotes, smooth when propulsion, if being unable to reach projected depth in progradation, after anchor cable is steadily extracted, weighs New borehole cleaning, until being installed in place;
After 4.4 anchor cables are installed, borehole cleaning slip casting is carried out immediately, grouting material presses M35 cement mortar mix ratio ingredient, using pressure Stop grouting plug is arranged in slip casting, the preceding aperture of slip casting, and grouting pressure is 0.5~1Mpa, until fresh slurry is overflowed in slip casting to aperture;Slip casting A slurries are mended after 30~45 minutes again.
5. pre-stress anti-slide pile supporting comprehensive construction method, feature exist in back fill course according to claim 4 In: anchor cable drills hole location deviation no more than 5mm, and angular deviation is no more than 2 °;Anchor rope grouting slurry uses cement mortar, can mix Appropriate early strength agent and micro-expanding agent;Preservative treatment is done in anchor cable free end, and passes through soap-free emulsion polymeization PVC bellows.
6. pre-stress anti-slide pile supporting comprehensive construction method, feature exist in back fill course according to claim 1 In: the backfill process: being filled at the 40mm~60mm of anchor cable central axes or less, reserves 8mm~12mm as settling amount, it is desirable that Coefficient is backfilling and compacted not less than design value.
7. pre-stress anti-slide pile supporting comprehensive construction method, feature exist in back fill course according to claim 1 In: described sleeve pipe is seamless steel pipe, and casing is laid in backfill face, casing central axes and anchor cable central axes same vertical flat Face, height are higher than anchor cable central axes 10mm, tilt angle with anchor cable tilt angle, protection sleeve pipe be embedded in the soil layer of primary side slope and It is greater than 100mm in friction pile service sleeve.
8. pre-stress anti-slide pile supporting comprehensive construction method, feature exist in back fill course according to claim 1 In the anchorage cable stretching process: when slip casting slurry and friction pile reach design strength 75% after carry out tensioning, using manual oil Pump and jack system are loaded, and pre- tensioning is carried out before formal tensioning, 10%~20% design tensile load is taken, to anchor cable Tensioning 1~2 time, keep its each location contacts close, keep steel strand wires totally straight, uniform force, tensioning should be loaded gently, load speed Rate is less than 0.1Nk/min.
9. pre-stress anti-slide pile supporting comprehensive construction method, feature exist in back fill course according to claim 8 In 5 applications of: anchorage cable stretching load point, 0.2,0.5,0.75,1.00,1.1 times of design value is successively taken to carry out tensioning step by step, preceding four Grade holds lotus 5 minutes, and afterbody holds lotus 15 minutes, and every grade of load tensioning answers off-load 10% after holding lotus.
10. pre-stress anti-slide pile supporting comprehensive construction method, feature exist in back fill course according to claim 1 In: the anchor cable mends stretching process: after the completion of backfill, checking anchorage cable anchoring situation by root, carries out anchor cable and mend tensioning;Anchor cable Detection determines qualification rate using on-site measurement latching force, and for detection method with anchorage cable stretching process, it is design that anchor cable, which detects tensioning value, 1.2~1.4 times of latching force;After detection is qualified, cut after anchorage exposed parts steel strand wires are reserved 50mm using abrasive wheel cutting machine It removes, to anchor pier brushing antirust paint, finally formwork pours C35 concrete sealing off and covering anchorage again.
CN201811209726.0A 2018-10-17 2018-10-17 Pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course Pending CN109371987A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811209726.0A CN109371987A (en) 2018-10-17 2018-10-17 Pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811209726.0A CN109371987A (en) 2018-10-17 2018-10-17 Pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course

Publications (1)

Publication Number Publication Date
CN109371987A true CN109371987A (en) 2019-02-22

Family

ID=65400682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811209726.0A Pending CN109371987A (en) 2018-10-17 2018-10-17 Pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course

Country Status (1)

Country Link
CN (1) CN109371987A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158497A (en) * 2019-05-30 2019-08-23 中铁二院工程集团有限责任公司 A kind of high cantilever rock-fall protection structure and construction method
CN110670605A (en) * 2019-09-16 2020-01-10 中冶交通建设集团有限公司 Mountain road slope reinforcing method
CN110761292A (en) * 2019-09-27 2020-02-07 中国二十冶集团有限公司 Prestressed anchor cable structure and prestressed anchor cable construction method
CN112195942A (en) * 2020-09-23 2021-01-08 贵州建工集团第一建筑工程有限责任公司 Building foundation slope stepped supporting method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201671108U (en) * 2010-04-27 2010-12-15 中国科学院武汉岩土力学研究所 Riverside shoulder prestressing anchor cable sheet-pile wall
CN102352632A (en) * 2011-07-29 2012-02-15 重庆大学 Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope
CN103603369A (en) * 2013-12-09 2014-02-26 中国石油集团工程设计有限责任公司 Construction method of anchor pile counterfort retaining wall
CN105421485A (en) * 2015-10-30 2016-03-23 杭州江润科技有限公司 Construction method of high-fill prefabricated cast-in-situ combined pile slab wall protection structure
CN108468341A (en) * 2018-05-24 2018-08-31 杭州昂创科技有限公司 Friction pile-ripple steel arch-drawing anchor combination slope protection structure and construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201671108U (en) * 2010-04-27 2010-12-15 中国科学院武汉岩土力学研究所 Riverside shoulder prestressing anchor cable sheet-pile wall
CN102352632A (en) * 2011-07-29 2012-02-15 重庆大学 Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope
CN103603369A (en) * 2013-12-09 2014-02-26 中国石油集团工程设计有限责任公司 Construction method of anchor pile counterfort retaining wall
CN105421485A (en) * 2015-10-30 2016-03-23 杭州江润科技有限公司 Construction method of high-fill prefabricated cast-in-situ combined pile slab wall protection structure
CN108468341A (en) * 2018-05-24 2018-08-31 杭州昂创科技有限公司 Friction pile-ripple steel arch-drawing anchor combination slope protection structure and construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
成都建筑工程集团总公司: "《工程建设施工工法汇编(2008-2014年度 上册)》", 29 February 2016 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158497A (en) * 2019-05-30 2019-08-23 中铁二院工程集团有限责任公司 A kind of high cantilever rock-fall protection structure and construction method
CN110670605A (en) * 2019-09-16 2020-01-10 中冶交通建设集团有限公司 Mountain road slope reinforcing method
CN110761292A (en) * 2019-09-27 2020-02-07 中国二十冶集团有限公司 Prestressed anchor cable structure and prestressed anchor cable construction method
CN112195942A (en) * 2020-09-23 2021-01-08 贵州建工集团第一建筑工程有限责任公司 Building foundation slope stepped supporting method

Similar Documents

Publication Publication Date Title
CN106958256B (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN109371987A (en) Pre-stress anti-slide pile supporting comprehensive construction method in a kind of back fill course
CN102031784B (en) Slope protection pile pouring and cable bolting construction method for deep foundation pit
CN111733828A (en) Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
CN107130607B (en) Building basement supporting
CN104032758A (en) Reinforcement construction method for ultrahigh slope in abandoned pit
CN101886393B (en) Construction method of combined foundation ditch support
CN106498943A (en) Disposable high-pressure rotary-spray type enlarged footing Prestressed Soil anchor pole construction method
CN105926667A (en) Retaining wall
CN111894641B (en) Treatment and construction process for tunnel to penetrate through super-huge water-containing cavity karst cave
CN114215042A (en) Miniature steel pipe pile for reinforcing foundation and construction method thereof
CN110106889A (en) A kind of deep basal pit perfusion slope protection pile adds cable bolting construction
CN211421169U (en) Fill side slope gravity type retaining wall reinforced structure
CN110552371A (en) Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
CN104453915B (en) Big cross section vertical shaft pre-pouring grout reinforces Rapid Excavation method
CN113293773A (en) Foundation pit supporting system and construction method thereof
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN107191196A (en) Through the anti-skidding shearing resistance administration structure of the inter-laminar dislocation band of great burying underground chamber and construction method
CN111395375A (en) Open caisson construction method based on thixotropic slurry drag reduction
KR20190072213A (en) Method Of Ground Half-Openning For Tunnel Excavation
CN211171922U (en) Construction structure for improving stability of groove wall
CN207582473U (en) Foundation pit supporting construction
CN109826066A (en) A kind of road structure and construction method of light soil roadbed combination steel-pipe pile
CN217601402U (en) Miniature steel pipe pile for reinforcing foundation
CN111576435B (en) Construction method and structure of column control slip surface of inter-pile soil steel structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190222

WD01 Invention patent application deemed withdrawn after publication