CN109347543A - Communications equipment room - Google Patents

Communications equipment room Download PDF

Info

Publication number
CN109347543A
CN109347543A CN201811377085.XA CN201811377085A CN109347543A CN 109347543 A CN109347543 A CN 109347543A CN 201811377085 A CN201811377085 A CN 201811377085A CN 109347543 A CN109347543 A CN 109347543A
Authority
CN
China
Prior art keywords
cabinet
communication
subregion
placing
power supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811377085.XA
Other languages
Chinese (zh)
Other versions
CN109347543B (en
Inventor
孙少华
杨林慧
杨有霞
朱靖
张燕燕
肖华
麻佳琪
郭磊
刘生成
李智年
唐玉萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Qinghai Electric Power Co Ltd
Information and Telecommunication Branch of State Grid Qinghai Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Qinghai Electric Power Co Ltd
Information and Telecommunication Branch of State Grid Qinghai Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Qinghai Electric Power Co Ltd, Information and Telecommunication Branch of State Grid Qinghai Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201811377085.XA priority Critical patent/CN109347543B/en
Publication of CN109347543A publication Critical patent/CN109347543A/en
Application granted granted Critical
Publication of CN109347543B publication Critical patent/CN109347543B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04BTRANSMISSION
    • H04B10/00Transmission systems employing electromagnetic waves other than radio-waves, e.g. infrared, visible or ultraviolet light, or employing corpuscular radiation, e.g. quantum communication
    • H04B10/03Arrangements for fault recovery
    • H04B10/038Arrangements for fault recovery using bypasses
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04BTRANSMISSION
    • H04B10/00Transmission systems employing electromagnetic waves other than radio-waves, e.g. infrared, visible or ultraviolet light, or employing corpuscular radiation, e.g. quantum communication
    • H04B10/03Arrangements for fault recovery
    • H04B10/032Arrangements for fault recovery using working and protection systems
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L41/00Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
    • H04L41/06Management of faults, events, alarms or notifications
    • H04L41/0654Management of faults, events, alarms or notifications using network fault recovery
    • H04L41/0668Management of faults, events, alarms or notifications using network fault recovery by dynamic selection of recovery network elements, e.g. replacement by the most appropriate element after failure
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L41/00Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
    • H04L41/06Management of faults, events, alarms or notifications
    • H04L41/0677Localisation of faults
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L65/00Network arrangements, protocols or services for supporting real-time applications in data packet communication
    • H04L65/10Architectures or entities
    • H04L65/1016IP multimedia subsystem [IMS]

Abstract

The invention discloses a kind of communications equipment rooms.Wherein, which may include: spare communication region, be disposed adjacent with principal communication region, for placing spare communication line and spare communication detection device;Premise equipment, wherein premise equipment includes: communication power supply, distribution plant, IP multimedia subsystem IMS equipment, transmission device and server;Principal communication region, for placing premise equipment, wherein principal communication region includes multiple subregions, is spaced a predetermined distance between each adjacent two subregion;Wherein, whether the communication power supply that spare communication detection device is used to detect in premise equipment breaks down, and when testing result breaks down for the communication power supply in premise equipment, control spare communication line is connected serially to principal communication region, so that the normal communication of principal communication region.The present invention solves the technical problem for arranging that the reliability of unreasonable caused communication site is lower of communication site in the related technology.

Description

Communications equipment room
Technical field
The present invention relates to communication equipment fields, in particular to a kind of communications equipment room.
Background technique
Telematic services website is the core node of Utilities Electric Co.'s communication network, be mainly used for data information calculating, The exchange of data information and the storage of data information.However, the construction of communication site at present is not especially rationally, there is communication The region division of website is more chaotic, and then causes the placement location of the various equipment in communication site also to compare and mix, when logical When believing that the equipment component in website breaks down, maintenance personal can not be quickly found out the position of the equipment to break down in time, greatly The maintenance efficiency for reducing faulty equipment greatly, has also seriously affected the normal communication of entire communication site, to give communication site The work and life of the user of coverage brings big inconvenience.
For above-mentioned communication site in the related technology arrangement it is unreasonable caused by the reliability of communication site lower ask Topic, currently no effective solution has been proposed.
Summary of the invention
The embodiment of the invention provides a kind of communications equipment rooms, are not conformed to at least solving the arrangement of communication site in the related technology The lower technical problem of the reliability of communication site caused by managing.
According to an aspect of an embodiment of the present invention, a kind of communications equipment room is provided, comprising: spare communication region, with master Communication zone is disposed adjacent, for placing spare communication line and spare communication detection device;Premise equipment, wherein described predetermined Equipment includes: communication power supply, distribution plant, IP multimedia subsystem IMS equipment, transmission device and server;The master is logical Region is believed, for placing the premise equipment, wherein the principal communication region includes multiple subregions, each adjacent two sub-district It is spaced a predetermined distance between domain;Wherein, the spare communication detection device is used to detect the communication power supply in the premise equipment Whether break down, when testing result breaks down for the communication power supply in the premise equipment, controls the spare communication Line is connected serially to the principal communication region, so that principal communication region normal communication.
Optionally, the multiple subregion is eight, and eight sub-regions are according to the orientation of target geographic position by south To north successively are as follows: the first subregion, the second subregion, third subregion, the 4th subregion, the 5th subregion, the 6th subregion, 7th subregion and the 8th subregion.
Optionally, each subregion is provided with the cabinet of predetermined quantity in eight sub-regions in the principal communication region, In, the cabinet includes at least one of: for placing the communication power supply cabinet of the communication power supply, being set for placing wiring Standby cable distribution cabinet, for placing the transmission device cabinet of transmission device, for placing the server cabinet of server, Yi Jiyong In the IMS cabinet for placing the IMS equipment, the cable distribution cabinet includes at least one of: digital wiring cabinet, optical fiber distributing Cabinet, comprehensive cable distribution cabinet.
Optionally, first subregion is for placing the communication power supply cabinet, wherein the communication power supply cabinet is Multiple, the section communication power supply cabinet in multiple communication power supply cabinets is for placing communication power supply display screen.
Optionally, second subregion is for placing the digital wiring cabinet, wherein the digital wiring cabinet is Multiple, the part number cable distribution cabinet in multiple digital wiring cabinets is for placing digital wiring display screen.
Optionally, the third subregion and the 4th subregion are for placing the transmission device cabinet, wherein institute State transmission device cabinet be it is multiple, fractional transmission equipment enclosure in multiple transmission device cabinets is for placing transmission device With operator's display screen.
Optionally, the 5th subregion is for placing the optical fiber distributing cabinet, wherein the optical fiber distributing cabinet is Multiple, the part fiber cable distribution cabinet in multiple optical fiber distributing cabinets is for placing optical fiber distributing display screen.
Optionally, the 6th subregion is for placing the comprehensive cable distribution cabinet, wherein the comprehensive cable distribution cabinet is Multiple, the part comprehensive cable distribution cabinet in multiple comprehensive cable distribution cabinets is used for placed comprehensive wiring display screen.
Optionally, the 7th subregion is for placing the server cabinet, wherein the server cabinet is more A, the part server cabinet in multiple server cabinets is used to place the display screen of particular device, the particular device Including at least one of: transmission network management server, IMS service device, Network Management Equipment, carrier network.
Optionally, the 8th subregion is for placing the IMS cabinet, wherein the IMS cabinet be it is multiple, it is multiple Part IMS cabinet in the IMS cabinet is used to place the display screen of the IMS equipment.
In embodiments of the present invention, communications equipment room is divided into principal communication region and spare communication region, wherein spare logical Letter region is disposed adjacent with principal communication region, for placing spare communication line and spare communication detection device;Premise equipment, In, premise equipment includes: communication power supply, distribution plant, IP multimedia subsystem IMS equipment, transmission device and server;It is main Communication zone, for placing premise equipment, wherein principal communication region includes multiple subregions, between each adjacent two subregion It is spaced a predetermined distance;Wherein, whether the communication power supply that spare communication detection device is used to detect in premise equipment breaks down, When testing result is that the communication power supply in premise equipment breaks down, control spare communication line is connected serially to principal communication region, so that The normal communication of principal communication region.The communications equipment room provided through the embodiment of the present invention, which is realized, carries out reasonable Arrangement to communications equipment room Target, reached the technical effect for improving the reliability of communications equipment room, and then solved the cloth of communication site in the related technology Set the lower technical problem of the reliability of unreasonable caused communication site.
Detailed description of the invention
The drawings described herein are used to provide a further understanding of the present invention, constitutes part of this application, this hair Bright illustrative embodiments and their description are used to explain the present invention, and are not constituted improper limitations of the present invention.In the accompanying drawings:
Fig. 1 is the schematic diagram of communications equipment room 10 according to an embodiment of the present invention;
Fig. 2 is the preferred schematic diagram of communications equipment room according to an embodiment of the present invention;
Fig. 3 is the gantry schematic diagram in principal communication region according to an embodiment of the present invention.
Specific embodiment
In order to enable those skilled in the art to better understand the solution of the present invention, below in conjunction in the embodiment of the present invention Attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is only The embodiment of a part of the invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill people The model that the present invention protects all should belong in member's every other embodiment obtained without making creative work It encloses.
It should be noted that description and claims of this specification and term " first " in above-mentioned attached drawing, " Two " etc. be to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that using in this way Data be interchangeable under appropriate circumstances, so as to the embodiment of the present invention described herein can in addition to illustrating herein or Sequence other than those of description is implemented.In addition, term " includes " and " having " and their any deformation, it is intended that cover Cover it is non-exclusive include, for example, the process, method, system, product or equipment for containing a series of steps or units are not necessarily limited to Step or unit those of is clearly listed, but may include be not clearly listed or for these process, methods, product Or other step or units that equipment is intrinsic.
For ease of description, below in the embodiment of the present invention part noun or term be described in detail.
Light current well: belonging to electric shaft, is the electric shaft for laying light current route, also referred to as cable shaft, be it is high-rise or For laying the channel of vertical main line communication cable etc. in tier building.
IP multimedia subsystem (IP Mult imedia Subsystem, abbreviation IMS): it is IP multimedia subsystem, is A kind of completely new multimedia service form, it can satisfy the demand of present terminal client diverse multimedia business.
Synchronous digital system (synchronous digital hierarchy, abbreviation SDH): being the numerical digit of friction speed The transmission of signal provides corresponding message structure, including multiplexing method and mapping method and relevant synchronous method group At a technical system.
According to an aspect of an embodiment of the present invention, a kind of communications equipment room is provided, Fig. 1 is according to an embodiment of the present invention The schematic diagram of communications equipment room 10, as shown in Figure 1, the communications equipment room 10 may include: spare communication region 11, with principal communication region 15 are disposed adjacent, for placing spare communication line 111 and spare communication detection device 113;Premise equipment 13, wherein predetermined to set Standby 13 include: communication power supply 131, distribution plant 133, IP multimedia subsystem IMS equipment 135, transmission device 137 and service Device 138;Principal communication region 15, for placing premise equipment 13, wherein principal communication region 15 includes multiple subregions, per adjacent It is spaced a predetermined distance between two sub-regions;Wherein, spare communication detection device 113 is used to detect the communication in premise equipment 13 Whether power supply 131 breaks down, and when testing result breaks down for the communication power supply 131 in premise equipment 13, controls spare Communication line 111 is connected serially to principal communication region 15, so that 15 normal communication of principal communication region.What is provided through the embodiment of the present invention is logical Letter computer room realizes the target that reasonable Arrangement is carried out to communications equipment room, has reached the technology effect for the reliability for improving communications equipment room Fruit, and then the lower technology of reliability for the unreasonable caused communication site of arrangement for solving communication site in the related technology is asked Topic.
Composition an optional embodiment of the present invention, multiple subregions are eight, and eight sub-regions are according to target geographic position The orientation set by Nan Zhibei successively are as follows: the first subregion, the second subregion, third subregion, the 4th subregion, the 5th sub-district Domain, the 6th subregion, the 7th subregion and the 8th subregion.
Fig. 2 is the preferred schematic diagram of communications equipment room according to an embodiment of the present invention, as shown in Fig. 2, the communications equipment room is by south Eight rows are put altogether to north, i.e., ten cabinets are set in above-mentioned eight sub-regions, every arrangement, and every row's rack room is every 1.2m as passageway.
Wherein, each subregion is provided with the cabinet of predetermined quantity in eight sub-regions in principal communication region, wherein cabinet It may include at least one of: for placing the communication power supply cabinet of communication power supply, for placing the wiring machine of distribution plant Cabinet, for placing the transmission device cabinet of transmission device, for placing the server cabinet of server, and for placing IMS The IMS cabinet of equipment, cable distribution cabinet includes at least one of: digital wiring cabinet, optical fiber distributing cabinet, comprehensive cable distribution machine Cabinet.
As an optional embodiment of the present invention, above-mentioned first subregion is for placing communication power supply cabinet, wherein logical Believe power supply cabinet be it is multiple, section communication power supply cabinet in multiple communication power supply cabinets is for placing communication power supply display screen. As shown in Fig. 2, the first subregion (i.e. first row) be communication power supply cabinet, for placing communication power supply, wherein No.1 cabinet and No. two cabinets are for placing communication power supply display screen, reserved cabinet of the remaining cabinet as communication power supply.
As an optional embodiment of the present invention, above-mentioned second subregion is for placing digital wiring cabinet, wherein number Word cable distribution cabinet be it is multiple, part number cable distribution cabinet in multiple digital wiring cabinets is for placing digital wiring display screen.
As an optional embodiment of the present invention, third subregion and the 4th subregion are for placing transmission device machine Cabinet, wherein transmission device cabinet be it is multiple, fractional transmission equipment enclosure in multiple transmission device cabinets is set for placing transmission Standby and operator's display screen.
As an optional embodiment of the present invention, the 5th subregion is for placing optical fiber distributing cabinet, wherein optical fiber is matched Line cabinet be it is multiple, part fiber cable distribution cabinet in multiple optical fiber distributing cabinets is for placing optical fiber distributing display screen.
Preferably, the 6th subregion be used for placed comprehensive cable distribution cabinet, wherein comprehensive cable distribution cabinet be it is multiple, it is multiple comprehensive The part comprehensive cable distribution cabinet closed in cable distribution cabinet is used for placed comprehensive wiring display screen.
As shown in Fig. 2, the second subregion (i.e. second row) is digital wiring cabinet, wherein ride on Bus No. 11 and ten No. two cabinets For placing digital wiring display screen, reserved cabinet of remaining cabinet as digital wiring.Third subregion and the 4th sub-district Domain is for placing transmission device cabinet, wherein two ride on Bus No. 11s and 20 No. two cabinets for placing transmission device, 20 No. nine and Three No. ten are used to place operator's display screen, reserved cabinet of remaining cabinet as transmission device.5th subregion is for placing Optical fiber distributing cabinet, wherein four ride on Bus No. 11s are to 40 No. five for placing optical fiber distributing display screen, 40 No. nine and five No. ten machines Cabinet is for placing operator's optical fiber distributing screen, reserved cabinet of the remaining cabinet as optical fiber distributing.6th subregion is for putting Set comprehensive cable distribution cabinet, wherein five ride on Bus No. 11s and 50 No. two cabinets are used for placed comprehensive wiring display screen, match by the synthesis Line display screen administrative staff can learn wiring situation clear and intuitively, remaining as pre- convenient for the maintenance and maintenance in later period Stay cabinet.
As an optional embodiment of the present invention, the 7th subregion is for placing server cabinet, wherein server machine Cabinet be it is multiple, part server cabinet in multiple server cabinets is used to place the display screen of particular device, particular device packet Include at least one of: transmission network management server, IMS service device, Network Management Equipment, carrier network.As shown in Fig. 2, the 7th son Region is for placing server cabinet, wherein six ride on Bus No. 11s are for placing transmission network management server display, 60 No. two cabinets For placing the display screen of IMS service device, 60 No. three and 60 No. four cabinets are for placing Network Management Equipment display screen, and 69 Number and seven No. ten cabinets for placing carrier network display screen;Remaining part cabinet can be used as the reserving machine of the network equipment Cabinet.
In addition, the 8th subregion is for placing IMS cabinet, wherein IMS cabinet is multiple, the part in multiple IMS cabinets IMS cabinet is used to place the display screen of IMS equipment.As shown in Fig. 2, seven ride on Bus No. 11s are set to 70 No. five cabinets for placing IMS Standby display screen, reserved cabinet of the remaining cabinet as IMS equipment.
In addition, it is necessary to explanation, Fig. 3 is the gantry schematic diagram in principal communication region according to an embodiment of the present invention, such as Fig. 3 It is shown, upward wiring mode is used for carrying out the paving location of the comprehensive cable distribution system of comprehensive cable distribution in principal communication region, that is, is existed A line gantry is laid with above every row's cabinet, each one column of laying are by the gantry of Nan Zhibei as cable above computer room east and west sides Switching.Wherein, the gantry in west side extends to the left side wall between gateway operation, installs wire casing from top to bottom along wall and gateway is grasped Underground wire casing connects between work, and entire computer room arranges eight rows, two column gantries in total.The gantry in principal communication region is divided into three layers, under It is supreme to be divided into forceful electric power layer, light current layer, optical fiber layer.The upward wiring module in principal communication region guarantees that underground cold wind rationally conveys, and does not have Resistance is the same as energy saving;The laminated reason of the forceful electric power layer and light current of gantry avoids electromagnetic interference, and the special optical fiber layer that is arranged ensure that light Fine safety, and make that the wiring of computer room is more beautiful, is easier to manage.
The serial number of the above embodiments of the invention is only for description, does not represent the advantages or disadvantages of the embodiments.
In the above embodiment of the invention, it all emphasizes particularly on different fields to the description of each embodiment, does not have in some embodiment The part of detailed description, reference can be made to the related descriptions of other embodiments.
In several embodiments provided herein, it should be understood that disclosed technology contents can pass through others Mode is realized.Wherein, the apparatus embodiments described above are merely exemplary, such as the division of the unit, Ke Yiwei A kind of logical function partition, there may be another division manner in actual implementation, for example, multiple units or components can combine or Person is desirably integrated into another system, or some features can be ignored or not executed.Another point, shown or discussed is mutual Between coupling, direct-coupling or communication connection can be through some interfaces, the INDIRECT COUPLING or communication link of unit or module It connects, can be electrical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple On unit.It can some or all of the units may be selected to achieve the purpose of the solution of this embodiment according to the actual needs.
It, can also be in addition, the functional units in various embodiments of the present invention may be integrated into one processing unit It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list Member both can take the form of hardware realization, can also realize in the form of software functional units.
If the integrated unit is realized in the form of SFU software functional unit and sells or use as independent product When, it can store in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially The all or part of the part that contributes to existing technology or the technical solution can be in the form of software products in other words It embodies, which is stored in a storage medium, including some instructions are used so that a computer Equipment (can for personal computer, server or network equipment etc.) execute each embodiment the method for the present invention whole or Part steps.And storage medium above-mentioned includes: that USB flash disk, read-only memory (ROM, Read-OnlyMemory), arbitrary access are deposited Reservoir (RAM, Random Access Memory), mobile hard disk, magnetic or disk etc. be various to can store program code Medium.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (10)

1. a kind of communications equipment room characterized by comprising
Spare communication region is disposed adjacent with principal communication region, for placing spare communication line and spare communication detection device;
Premise equipment, wherein the premise equipment includes: communication power supply, distribution plant, IP multimedia subsystem IMS equipment, biography Transfer device and server;
The principal communication region, for placing the premise equipment, wherein the principal communication region includes multiple subregions, often It is spaced a predetermined distance between two neighboring subregion;
Wherein, whether the communication power supply that the spare communication detection device is used to detect in the premise equipment breaks down, Testing result is communication power supply in the premise equipment when breaking down, and controlling the spare communication line, to be connected serially to the master logical Region is believed, so that principal communication region normal communication.
2. communications equipment room according to claim 1, which is characterized in that the multiple subregion is eight, eight sons Region according to the orientation of target geographic position by Nan Zhibei successively are as follows: the first subregion, the second subregion, third subregion, Four subregions, the 5th subregion, the 6th subregion, the 7th subregion and the 8th subregion.
3. communications equipment room according to claim 2, which is characterized in that each in eight sub-regions in the principal communication region Subregion is provided with the cabinet of predetermined quantity, wherein the cabinet includes at least one of: for placing the communication power supply Communication power supply cabinet, for placing the transmission device cabinet of transmission device, be used for for placing the cable distribution cabinet of distribution plant The server cabinet of server is placed, and the IMS cabinet for placing the IMS equipment, the cable distribution cabinet include following At least one: digital wiring cabinet, optical fiber distributing cabinet, comprehensive cable distribution cabinet.
4. communications equipment room according to claim 3, which is characterized in that first subregion is for placing the communication electricity Source cabinet, wherein the communication power supply cabinet is multiple, the section communication power supply cabinet use in multiple communication power supply cabinets In placement communication power supply display screen.
5. communications equipment room according to claim 3, which is characterized in that second subregion is matched for placing the number Line cabinet, wherein the digital wiring cabinet is multiple, the part number cable distribution cabinet use in multiple digital wiring cabinets In placement digital wiring display screen.
6. communications equipment room according to claim 3, which is characterized in that the third subregion and the 4th subregion are used In the placement transmission device cabinet, wherein the transmission device cabinet is multiple, the portion in multiple transmission device cabinets Divide transmission device cabinet for placing transmission device and operator's display screen.
7. communications equipment room according to claim 3, which is characterized in that the 5th subregion is matched for placing the optical fiber Line cabinet, wherein the optical fiber distributing cabinet is multiple, the part fiber cable distribution cabinet use in multiple optical fiber distributing cabinets In placement optical fiber distributing display screen.
8. communications equipment room according to claim 3, which is characterized in that the 6th subregion is matched for placing the synthesis Line cabinet, wherein the comprehensive cable distribution cabinet is multiple, the part comprehensive cable distribution cabinet use in multiple comprehensive cable distribution cabinets In placed comprehensive wiring display screen.
9. communications equipment room according to claim 3, which is characterized in that the 7th subregion is for placing the server Cabinet, wherein the server cabinet be it is multiple, part server cabinet in multiple server cabinets is for placing spy The display screen of locking equipment, the particular device includes at least one of: transmission network management server, IMS service device, and network management is set It is standby, carrier network.
10. communications equipment room according to claim 3, which is characterized in that the 8th subregion is for placing the IMS machine Cabinet, wherein the IMS cabinet be it is multiple, part IMS cabinet in multiple IMS cabinets is for placing the IMS equipment Display screen.
CN201811377085.XA 2018-11-19 2018-11-19 Communication machine room Active CN109347543B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811377085.XA CN109347543B (en) 2018-11-19 2018-11-19 Communication machine room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811377085.XA CN109347543B (en) 2018-11-19 2018-11-19 Communication machine room

Publications (2)

Publication Number Publication Date
CN109347543A true CN109347543A (en) 2019-02-15
CN109347543B CN109347543B (en) 2020-10-09

Family

ID=65316309

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811377085.XA Active CN109347543B (en) 2018-11-19 2018-11-19 Communication machine room

Country Status (1)

Country Link
CN (1) CN109347543B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110139528A (en) * 2019-05-05 2019-08-16 深圳供电局有限公司 A kind of comprehensive wiring method suitable for computer room
CN110650048A (en) * 2019-09-24 2020-01-03 中国人民解放军61623部队 Intelligent digital wiring system based on IMS

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1450821A (en) * 2002-04-11 2003-10-22 华为技术有限公司 Radio communication system
CN202055582U (en) * 2011-04-27 2011-11-30 浙江和勤通信工程有限公司 Intelligentized energy-saving communication machine room
CN203034847U (en) * 2013-01-30 2013-07-03 韩燕� Communication machine room
US20150236921A1 (en) * 2008-12-22 2015-08-20 Panduit Corp. Physical Infrastructure Management System
CN206655511U (en) * 2017-02-23 2017-11-21 中国移动通信集团贵州有限公司 A kind of communications equipment room structure
CN108222570A (en) * 2018-03-21 2018-06-29 中国联合网络通信集团有限公司 A kind of communications equipment room
CN208039931U (en) * 2018-01-02 2018-11-02 文成永 A kind of compact communications equipment room
CN208564072U (en) * 2018-05-22 2019-03-01 国家电网公司 Communications equipment room

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1450821A (en) * 2002-04-11 2003-10-22 华为技术有限公司 Radio communication system
US20150236921A1 (en) * 2008-12-22 2015-08-20 Panduit Corp. Physical Infrastructure Management System
CN202055582U (en) * 2011-04-27 2011-11-30 浙江和勤通信工程有限公司 Intelligentized energy-saving communication machine room
CN203034847U (en) * 2013-01-30 2013-07-03 韩燕� Communication machine room
CN206655511U (en) * 2017-02-23 2017-11-21 中国移动通信集团贵州有限公司 A kind of communications equipment room structure
CN208039931U (en) * 2018-01-02 2018-11-02 文成永 A kind of compact communications equipment room
CN108222570A (en) * 2018-03-21 2018-06-29 中国联合网络通信集团有限公司 A kind of communications equipment room
CN208564072U (en) * 2018-05-22 2019-03-01 国家电网公司 Communications equipment room

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110139528A (en) * 2019-05-05 2019-08-16 深圳供电局有限公司 A kind of comprehensive wiring method suitable for computer room
CN110650048A (en) * 2019-09-24 2020-01-03 中国人民解放军61623部队 Intelligent digital wiring system based on IMS
CN110650048B (en) * 2019-09-24 2022-03-18 中国人民解放军61623部队 Intelligent digital wiring system based on IMS

Also Published As

Publication number Publication date
CN109347543B (en) 2020-10-09

Similar Documents

Publication Publication Date Title
CN102714372B (en) data center network distribution system
CN106849997A (en) Mixed networking method based on power wire broadband carrier
CN109347543A (en) Communications equipment room
CN110392001A (en) The chassis level network switch
CN104080095B (en) Method for networking wireless 3G/LTE base station carrying network in subway stations
CN108777640A (en) A kind of server detection method, device, system and storage medium
CN103138990A (en) Virtual machine management method under cloud computing network and cloud computing network management device
CN210444305U (en) Wireless private network system
CN110224977A (en) A kind of composite defense policy conflict digestion procedure and system
CN106897162A (en) The communication mode system of selection of component, communication system and mobile terminal in a kind of application
CN205901430U (en) High reliability network deployment structure based on distributing type power supply system
CN108810072A (en) Internet of Things access point control method and device, information processing system
CN107682192A (en) A kind of method of county domain power supply station data communication
WO2006048867A1 (en) System for providing power over ethernet through a patch panel
CN109471961B (en) Loop display method and device for secondary system of intelligent substation
CN100442632C (en) Automatic module configuration in a telecommunications power system and battery configuration with a click
CN107370771A (en) A kind of power station centralized control system and method based on internet
CN106056304A (en) Flexible DC interconnection device address selection method and device
CN110472867A (en) Power distribution network Network adaptation assessment processing method and device
CN109547238A (en) A method of realizing automatic network-building in equipment management system
CN208564072U (en) Communications equipment room
CN103500384A (en) Comprehensive management system for power distribution and consumption side communication basic resources
CN207475113U (en) Electric power extra-high voltage station used in communication machine room " mesh " font two-layer wiring slot box
CN105183960B (en) The generation method and device of electric network wiring scheme
CN206224034U (en) Emergency communication case and emergency communication component

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant