CN109339835A - A kind of anchoring system and underground engineering construction method - Google Patents

A kind of anchoring system and underground engineering construction method Download PDF

Info

Publication number
CN109339835A
CN109339835A CN201811326790.7A CN201811326790A CN109339835A CN 109339835 A CN109339835 A CN 109339835A CN 201811326790 A CN201811326790 A CN 201811326790A CN 109339835 A CN109339835 A CN 109339835A
Authority
CN
China
Prior art keywords
anchoring system
anchorage
backing plate
aperture
porous backing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811326790.7A
Other languages
Chinese (zh)
Inventor
汪波
郭新新
王勇
项小珍
徐建强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Fengqiang Engineering Design Consulting Research Institute Co Ltd
HANGZHOU DODRIVE ENGINEERING MATERIALS Ltd
Southwest Jiaotong University
Original Assignee
Hangzhou Fengqiang Engineering Design Consulting Research Institute Co Ltd
HANGZHOU DODRIVE ENGINEERING MATERIALS Ltd
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Fengqiang Engineering Design Consulting Research Institute Co Ltd, HANGZHOU DODRIVE ENGINEERING MATERIALS Ltd, Southwest Jiaotong University filed Critical Hangzhou Fengqiang Engineering Design Consulting Research Institute Co Ltd
Priority to CN201811326790.7A priority Critical patent/CN109339835A/en
Publication of CN109339835A publication Critical patent/CN109339835A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0093Accessories

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to underground chamber construction supporting fields, and in particular to a kind of anchoring system and underground engineering construction method.The underground construction method uses a kind of anchoring system, the anchoring system includes the first anchoring system for instant supporting, with the second anchoring system for later period strengthening supporting, first anchoring system includes the first anchorage and porous backing plate, and the second anchoring system includes the second anchorage added on the basis of the first anchoring system;Adjacent porous backing plate is locally overlapping, and the first anchorage and the second anchorage respectively correspond the aperture on porous backing plate and be staggered, and the first anchorage protrudes into the length of rock mass less than the second anchorage.Anchoring system of the invention is suitable for the first branch the case where performing limited space during partial excavation, does not allow vulnerable, and anchoring system connecting is good, and supporting power is incremented by gradually;Excavated surface, preliminary bracing face and the later period branch mask of construction method promote in proper order, can guarantee place safety, shorten digging time, accelerate construction progress.

Description

A kind of anchoring system and underground engineering construction method
Technical field
The present invention relates to underground chamber construction supporting fields, apply in particular to a kind of anchoring system and underground engineering Work method.
Background technique
Under the conditions of high-ground stress and weak broken wall rock, after underground chamber excavates, surrouding rock deformation is fast and deflection is big, if Anchor pole or cable bolting are used immediately, are easily influenced the failure for leading to anchoring system, and anchor pole or cable bolting by large deformation Construction time is long, it is difficult to which instant supporting country rock influences to continue to excavate, construction speed is slow.
Summary of the invention
The present invention is intended to provide a kind of anchoring system, for solving high-ground stress and weak surrounding rock condition in the prior art Under, anchoring system is easy failure, and long the time required to supporting, excavation off time is long, the slow problem of construction speed.
Another object of the present invention is to provide a kind of underground engineering construction methods to be guaranteed using above-mentioned anchoring system Under the conditions of high-ground stress and weak surrounding rock, guarantee construction site safety, shorten the off time of excavated section, quickening construct into Degree.
The embodiment of the present invention is achieved in that
The embodiment of the present invention provides a kind of anchoring system comprising for the first anchoring system of instant supporting, and is used for Second anchoring system of later period strengthening supporting, first anchoring system include the first anchorage and porous backing plate, second anchor Solid system includes the second anchorage added on the basis of the first anchoring system;
The adjacent porous backing plate is locally overlapping, and first anchorage and second anchorage respectively correspond described porous It aperture on backing plate and is staggered, the length that first anchorage protrudes into rock mass is less than second anchorage.
This anchoring system includes the first anchoring system and the second anchoring system, is beaten immediately in section country rock after section excavation Enter the first anchorage, and be set between the first anchorage and rock mass using porous backing plate, using overlapping porous backing plate by multiple As soon as anchorage integrates, squeezes into a small amount of anchorage and form the stronger system of anchoring ability, and the first anchoring body is being set Certain prestressing force can be applied to the first anchorage when being and accelerate the speed and branch of instant supporting to promote the bearing capacity of country rock Intensity is protected, to protect construction site safe, shortens the off time of excavation, conveniently continues section excavation, accelerate construction Progress;
Strengthening supporting is carried out after the release of rock mass internal pressure, rock mass deformation are stablized, then to country rock, by the second anchorage from corresponding Rock mass is squeezed into second aperture, and the length of the second anchorage is greater than the length of the first anchorage, and the second anchorage further gos deep into rock stratum, with the One anchoring system integrates the second anchoring system to be formed and take into account deep layer anchoring and shallow-layer anchoring, to having released internal pressure The country rock strengthening supporting to tend towards stability plays the role of firm rock mass, the deformation of prevention and treatment later period.
The present invention combines single anchorage by backing plate and forms connection by the first anchoring system of setting and the second anchoring system Dynamic anchor system, under the conditions of solving high-ground stress in the prior art and weak surrounding rock, anchoring system is easy failure, and supporting is taken Between it is long, excavate off time it is long, the slow problem of construction speed.
In an embodiment of the present invention, further, described in order to properly increase the anchor force of the first anchoring system The apertures in alignment of porous backing plate overlap position.
In an embodiment of the present invention, further, the porous backing plate close to rock mass one side setting it is fluted, It is correspondingly arranged on raised line on one side away from rock mass, the raised line at the overlapping position of the adjacent porous backing plate is matched with the groove It closes, to limit the adjacent porous backing plate Relative sliding.
In an embodiment of the present invention, further, the porous backing plate is in bar shaped, and the aperture includes that interval is set The first aperture and the second aperture set, first anchorage are correspondingly arranged in first aperture, and the second anchorage correspondence is set The length that second aperture, first aperture and second aperture are placed in along the porous backing plate is arranged in a word interval Column.
In an embodiment of the present invention, further, first aperture than second aperture quantity more than one A, first aperture is located at the both ends of the porous backing plate of bar shaped, and the end of the adjacent porous backing plate overlaps and institute State the first apertures in alignment.
In an embodiment of the present invention, further, first anchorage includes pressure-relieving achor bar, second anchorage Including anchor cable.
In an embodiment of the present invention, further, first anchorage, second anchorage and the porous pad It is separately provided for preventing the pad hoop of sliding between plate, first anchorage and second anchorage are equipped with for accommodating The annular groove of pad hoop is stated, the pad hoop is split ring, and ears and monaural, the monaural is circumferentially respectively set in opening position both sides It can slide to change the diameter that the pad is bound round along the ears.
In an embodiment of the present invention, further, the porous backing plate includes L shape, the L-shaped porous backing plate It is closed with palisades, the rock topstick of section, aperture is respectively set in the turning point both sides of the L-shaped backing plate.
In an embodiment of the present invention, further, first anchoring system further includes being set to rock mass and institute The first concrete layer between porous backing plate is stated, second anchoring system further includes being fixed on first anchorage and described Steel mesh between two anchorages, the reinforcing bar net surface are provided with the second concrete layer, and second concrete layer is mixed for fiber Solidifying soil.
A kind of underground engineering construction method comprising excavate excavated surface, the initial stage branch that direction successively promotes in proper order in edge Mask and later period branch mask, the section that the excavated surface excavates out use the above-mentioned instant supporting of the first anchoring system, to The second above-mentioned anchoring system strengthening supporting is used after section adjoining rock stability.
The excavation work that underground engineering construction method provided by the invention is successively promoted by setting along excavation direction in proper order Face, preliminary bracing face and later period branch mask come guarantee construction site safety, shorten excavate off time.Have first by setting The preliminary bracing face of anchoring system and later period branch mask with the second anchoring system, the first anchoring system carry out after excavation Instant supporting guarantees under the security situation of construction site, shortens and excavates off time, continues excavated section, and the second anchoring system exists Reinforcing, control efficiency, excavated surface, preliminary bracing face and later period branch mask, these three working face edges are played after adjoining rock stability It excavates direction to promote in proper order, can guarantee construction site safety under the conditions of high-ground stress and weak surrounding rock, shorten excavated section Off time, accelerate construction progress.
The beneficial effect comprise that
The case where anchoring system provided by the invention performs limited space suitable for the first branch during partial excavation, makes Single anchorage is combined by backing plate and forms linkage anchor system, under the conditions of solving high-ground stress in the prior art and weak surrounding rock, Anchoring system is easy failure, long the time required to supporting, and excavation off time is long, the slow problem of construction speed.
Underground engineering construction method provided by the invention, by be arranged have the first anchoring system preliminary bracing face and Later period branch mask with the second anchoring system, the first anchoring system carry out instant supporting after excavation, guarantee construction site peace In full situation, shorten and excavate off time, continue excavated section, the second anchoring system plays reinforcing, prevention and treatment after adjoining rock stability Effect, excavated surface, preliminary bracing face and later period branch mask, these three working faces promote in proper order along direction is excavated, increase gradually Add supporting power, anchoring system connecting is good, can guarantee construction site safety under the conditions of high-ground stress and weak surrounding rock, shorten It the off time of excavated section, accelerates construction progress.
Detailed description of the invention
In order to illustrate the technical solution of the embodiments of the present invention more clearly, below will be to needed in the embodiment attached Figure is briefly described, it should be understood that the following drawings illustrates only certain embodiments of the present invention, therefore is not construed as pair The restriction of range for those of ordinary skill in the art without creative efforts, can also be according to this A little attached drawings obtain other relevant attached drawings.
Fig. 1 is the structural schematic diagram in construction working face provided in an embodiment of the present invention.
Fig. 2 is the structural schematic diagram of anchoring system provided in an embodiment of the present invention;
Fig. 3 is the layout drawing of porous backing plate provided in an embodiment of the present invention;
Fig. 4 is the A-A sectional view of porous backing plate in Fig. 3;
Fig. 5 is a kind of mounting means schematic diagram of porous backing plate provided in an embodiment of the present invention;
Fig. 6 is another mounting means schematic diagram of porous backing plate provided in an embodiment of the present invention;
Fig. 7 is the another mounting means schematic diagram of porous backing plate provided in an embodiment of the present invention;
Fig. 8 is the structural schematic diagram of pad hoop provided in an embodiment of the present invention;
Fig. 9 is the B-B sectional view that hoop is padded in Fig. 8;
Icon: 1- excavated surface;The first concrete layer of 2-;The porous backing plate of 3-;The first anchorage of 4-;The second anchorage of 5-;6- Second concrete layer;7- pad hoop;71- ears;72- monaural;The preliminary bracing face 8-;9- later period branch mask.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.The present invention being usually described and illustrated herein in the accompanying drawings is implemented The component of example can be arranged and be designed with a variety of different configurations.
Therefore, the detailed description of the embodiment of the present invention provided in the accompanying drawings is not intended to limit below claimed The scope of the present invention, but be merely representative of selected embodiment of the invention.Based on the embodiments of the present invention, this field is common Technical staff's every other embodiment obtained without making creative work belongs to the model that the present invention protects It encloses.
It should also be noted that similar label and letter indicate similar terms in following attached drawing, therefore, once a certain Xiang Yi It is defined in a attached drawing, does not then need that it is further defined and explained in subsequent attached drawing.
In the description of the present invention, it should be noted that if occur term " center ", "upper", "lower", "left", "right", The orientation or positional relationship of the instructions such as "vertical", "horizontal", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, Either the invention product using when the orientation or positional relationship usually put, be merely for convenience of the description present invention and simplification retouched It states, rather than the device or element of indication or suggestion meaning must have a particular orientation, be constructed and operated in a specific orientation, Therefore it is not considered as limiting the invention.If only being used in addition, occurring term " first ", " second " etc. in description of the invention It is described in distinguishing, is not understood to indicate or imply relative importance.
If being not offered as requiring component absolute in addition, occurring the terms such as term "horizontal", "vertical" in description of the invention Horizontal or pendency, but can be slightly tilted.If "horizontal" only refers to that its direction is more horizontal with respect to for "vertical", not It is to indicate that the structure is had to fully horizontally, but can be slightly tilted.
In the description of the present invention, it is also necessary to which explanation is unless specifically defined or limited otherwise, if there is term " setting ", " installation ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, be also possible to detachably connect It connects, or is integrally connected;It can be mechanical connection, be also possible to be electrically connected;It can be directly connected, intermediate matchmaker can also be passed through Jie is indirectly connected, and can be the connection inside two elements.It for the ordinary skill in the art, can be with concrete condition Understand the concrete meaning of above-mentioned term in the present invention.
Embodiment
A kind of underground engineering construction method under the conditions of guaranteeing high-ground stress and weak surrounding rock, guarantees construction site safety, contracting It the off time of short excavated section, accelerates construction progress.
Above-mentioned underground engineering construction method includes excavation, preliminary bracing, later period supporting three process, and three process is sequential It carries out, please refers to shown in attached drawing 1, excavated surface 1, preliminary bracing face 8 and later period branch mask 9 are simultaneously in the construction process simultaneously In the presence of, and promoted in proper order along direction is excavated.
After section excavation goes out, the first anchoring system is set in Rock Mass immediately and is anchored immediately, preliminary bracing is formed Face 8;After Stress relieving of surrounding rocks, the first anchoring system is reinforced, forms later period branch mask 9.Three working faces can carry out simultaneously Construction operation, the first anchoring system is there are the surplus for allowing surrouding rock deformation, so that anchoring system is not easy damage inactivation, second Anchoring system reinforces anchor force, is conducive to that Rock Mass is made to remain steady in a long-term.
Attached drawing 2 is please referred to, the first anchoring system includes the first anchorage 4 and porous backing plate 3.
Attached drawing 2 is please referred to, the second anchoring system includes the second anchorage 5 added on the basis of the first anchoring system.
It please refers to shown in attached drawing 2,5 length of the second anchorage is less than the first anchorage 4, and 4 installation speed of the first anchorage is faster.
It please refers to shown in attached drawing 1 and attached drawing 5, is provided with the first aperture and the second aperture on porous backing plate 3, wherein first opens Hole is corresponding with the first anchorage 4, and the second aperture is corresponding with the second anchorage 5, the first aperture and the setting of the second aperture interval.
It should be noted that the difference of the first aperture and the second aperture is only that the area of its corresponding anchorage in the present invention Not, it can be adjusted according to required initial stage anchor force.It please refers to shown in attached drawing 5, there are three apertures for the porous tool of backing plate 3, if needing The initial stage anchor force wanted is larger, then the aperture at porous 3 both ends of backing plate is as the first aperture;If desired initial stage anchor force is smaller, Then both ends with the porous backing plate 3 of the first aperture and middle part there is the backing plate transpostion interval of the first aperture to be arranged;If desired into one Reduction initial stage anchor force is walked, then the first aperture of each porous backing plate 3 is respectively positioned on middle part.
After section excavation, the first concrete layer 2 first please be sprayed on Rock Mass surface, temporarily shown in Shenfu Fig. 1 and attached drawing 2 And firm rock mass.
Then, anchor hole is drilled through on rock mass, and the floating ash in anchor hole is cleaned out using high pressure blower, is then arranged first Anchoring system carries out instant supporting.
Referring to shown in attached drawing 5, porous backing plate 3 is installed on rock mass surface, adjacent 3 part of porous backing plate is overlapping.
For the ease of installation, the orderly support system of framework, further, the porous backing plate 3 be in bar shaped, described first Aperture and second aperture are arranged along the length of the porous backing plate 3 in a word interval.
Further, in order to keep the first anchoring system more firm, quantity of first aperture than second aperture More one, first aperture is located at the both ends of the porous backing plate 3 of bar shaped.
Referring to shown in attached drawing 1, attached drawing 2 and attached drawing 5, the first anchorage 4 is squeezed into the corresponding anchor hole of the first aperture and is fixed, this reality It applies the first anchorage 4 in example and uses anchor pole, in order to further function as the effect for preventing the first anchoring system from failing, first anchor Tool 4 uses pressure-relieving achor bar.
The first above-mentioned anchoring system is arranged immediately after section excavation, using porous backing plate 3 be set to the first anchorage 4 with Between rock mass, multiple first anchorages 4 are integrated using overlapping porous backing plate 3, a small amount of anchorage is squeezed into and just forms anchor Gu the stronger system of ability, and certain prestressing force can be applied to the first anchorage 4 when the first anchoring system is arranged, to be promoted The bearing capacity of country rock, accelerates the speed and supporting intensity of instant supporting, to protect construction site safe, shortens between excavation The gap time, conveniently continue section excavation, accelerates construction progress.
Then, after the release of rock mass internal pressure, rock mass deformation are stablized, then the second anchor is added on the basis of the first anchoring system Tool 5.It please refers to shown in attached drawing 5, there are three apertures for the porous tool of backing plate 3 in the present embodiment, wherein the first aperture is located at both ends, second Aperture is located at centre, and porous backing plate 3 becomes one the first anchorage 4, the second anchorage 5, to carry out strengthening supporting to country rock.
Second anchorage 5 is squeezed into the corresponding anchor hole of the second aperture to fix.Attached drawing 2 is please referred to, the length of the second anchorage 5 is greater than First anchorage 4, the second anchorage 5 further go deep into rock mass, integrated with the first anchoring system to be formed take into account deep layer anchoring and Second anchoring system of shallow-layer anchoring plays firm rock mass, anti-to the country rock strengthening supporting for having released internal pressure and tending towards stability Control the effect of later period deformation.The second anchorage 5 in the present embodiment uses anchor cable.
In order to further protect rock mass, long-term firm, prevention and treatment deformation effect is played, is please referred to shown in attached drawing 2, first Steel mesh is fixedly installed between anchorage 4 and the second anchorage 5, steel mesh can be welded on the first anchorage 4 and the second anchorage 5, be led to Steel mesh connection is crossed, the globality of the second anchoring system is reinforced, and anchoring, supporting power are promoted.
In order to preferably protect rock mass and support system, the second concrete layer 6 is sprayed in reinforcing bar net surface.In order to reinforce propping up Watch box system tension, bending strength, the second concrete layer 6 use fiber concrete, and the toughness of fiber concrete body is strong, can be effective Rock mass external crack is inhibited to carry out, in the case where concrete layer band crack works, durability is more preferable.
In order to enhance tension, the bending strength of support system the first concrete layer 2 and the second concrete layer 6, in fixed steel Before muscle net, first the sticking carbon fiber item on the first concrete layer 2, is then arranged steel mesh, the second concrete layer 6 of injection again.
Please referring to attached drawing 1, attached drawing 2, shown in attached drawing 3, multiple end to end arrangements of the porous backing plates 3 are in strip group, Multiple bar shaped groups are sequentially arranged along section excavation direction, form the skeleton of support palisades and rock top.Further, above-mentioned carbon fiber It ties up item and porous 3 bar shaped group of backing plate forms reticular structure, to further enhance the globality of the second anchoring system, improve supporting Ability.
In order to suitably enhance the anchor force of the first anchoring system, the apertures in alignment at the overlapping position of porous backing plate 3, i.e., as attached Shown in Fig. 6, porous 3 overlapping length of backing plate increases, and the first apertures in alignment of two porous backing plates 3 squeezes into the first anchorage 4, Satisfaction allow compressive strain surplus while, reinforce initial stage anchor force.
In rock mass weak part, the overlapping length of porous backing plate 3 can increase to reinforce initial stage anchor force or porous pad Plate 3 can also reinforce initial stage anchor force using multiple while overlapping forms.Please refer to attached drawing 7, it is thin in rock mass in the present embodiment Weak position is overlapping using three porous backing plates 3, and the first anchorage 4 is squeezed into first and opened by the first apertures in alignment of three porous backing plates 3 The corresponding anchor hole in hole is fixed.
For rock top and palisades delivery position, porous backing plate 3 is set as L shape, the L-shaped porous backing plate 3 and section Palisades, rock topstick close, and the first aperture is respectively set in the turning point both sides of the L-shaped backing plate, thus to palisades and two, rock top Face carries out initial stage anchoring respectively.
In order to further increase the attachment force of porous backing plate 3, prevents porous backing plate 3 from sliding, enhance the bending resistance of porous backing plate 3 Roll over effect, please refer to shown in attached drawing 4, the one side of porous backing plate 3 close to the rock mass be arranged it is fluted, faced away from the one of rock mass It should be provided with raised line, the raised line and the groove at the overlapping position of the adjacent porous backing plate 3 cooperate, to limit adjacent 3 Relative sliding of porous backing plate causes to be staggered.
In order to further increase porous 3 antiskid ability of backing plate, preferably anchor, the groove and the raised line separate phase Adjacent aperture, and around the aperture.
Further, in order to keep anchorage installation more secured, first anchorage 4, second anchorage 5 with it is described porous It is separately provided for preventing the pad hoop 7 of sliding between backing plate 3, first anchorage 4 and second anchorage 5, which are equipped with, to be used for Accommodate the annular groove of the pad hoop 7.
Attached drawing 8 and attached drawing 9 are please referred to, the pad hoop 7 is split ring, and ears 71 are circumferentially respectively set in opening position both sides With monaural 72, the monaural 72 can slide to change the diameter of the pad hoop 7 along the ears 71.
Underground engineering construction method provided by the invention and anchoring system have the initial stage of the first anchoring system by being arranged Branch mask 8 and later period branch mask 9 with the second anchoring system, the first anchoring system carry out instant supporting after excavation, guarantee Under the security situation of construction site, shorten and excavate off time, continue excavated section, the second anchoring system plays after adjoining rock stability It reinforces, control efficiency, excavated surface 1, preliminary bracing face 8 and later period branch mask 9, direction is excavated in proper order in these three working faces edge It promotes, under the conditions of solving high-ground stress in the prior art and weak surrounding rock, anchoring system is easy failure, and place is dangerous, supporting Required time is long, and excavation off time is long, the slow problem of construction speed.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of anchoring system, it is characterised in that: reinforce branch including the first anchoring system for instant supporting, and for the later period Second anchoring system of shield, first anchoring system include the first anchorage and porous backing plate, and second anchoring system includes The second anchorage added on the basis of the first anchoring system;
The adjacent porous backing plate is locally overlapping, and first anchorage and second anchorage respectively correspond the porous backing plate On aperture and be staggered, first anchorage protrude into rock mass length be less than second anchorage.
2. a kind of anchoring system according to claim 1, it is characterised in that: the aperture pair of the porous backing plate overlap position Together.
3. a kind of anchoring system according to claim 1, it is characterised in that: the porous backing plate is set on one side close to rock mass It is equipped with groove, is correspondingly arranged on raised line, the raised line at the overlapping position of the adjacent porous backing plate and institute on one side away from rock mass Groove cooperation is stated, to limit the adjacent porous backing plate Relative sliding.
4. a kind of anchoring system according to claim 1, it is characterised in that: the porous backing plate is in bar shaped, the aperture Including spaced first aperture and the second aperture, first anchorage is correspondingly arranged in first aperture, and described second Anchorage be correspondingly arranged in second aperture, first aperture and second aperture along the porous backing plate length in one Word interval arrangement.
5. a kind of anchoring system according to claim 4, it is characterised in that: first aperture is than second aperture Quantity is one more, and first aperture is located at the both ends of the porous backing plate of bar shaped, the end of the adjacent porous backing plate Overlapping and described first apertures in alignment.
6. a kind of anchoring system according to claim 1, it is characterised in that: first anchorage includes pressure-relieving achor bar, institute Stating the second anchorage includes anchor cable.
7. a kind of anchoring system according to claim 1, it is characterised in that: first anchorage, second anchorage with It is separately provided for preventing the pad hoop of sliding between the porous backing plate, first anchorage and second anchorage are equipped with For accommodating the annular groove of the pad hoop, the pad hoop is split ring, and ears and list are circumferentially respectively set in opening position both sides Ear, the monaural can slide to change the diameter of the pad hoop along the ears.
8. a kind of anchoring system according to claim 1, it is characterised in that: the porous backing plate includes L shape, L-shaped institute Palisades, the conjunction of rock topstick of porous backing plate and section are stated, aperture is respectively set in the turning point both sides of the L-shaped backing plate.
9. a kind of anchoring system according to claim 1, it is characterised in that: first anchoring system further includes being set to The first concrete layer between rock mass and the porous backing plate, second anchoring system further include being fixed on first anchorage Steel mesh between second anchorage, the reinforcing bar net surface are provided with the second concrete layer, second concrete layer For fiber concrete.
10. a kind of underground engineering construction method, it is characterised in that: including the excavation work successively promoted in proper order along excavation direction Face, preliminary bracing face and later period branch mask, the section that the excavated surface excavates out use claim 1-9 any one institute The instant supporting of the first anchoring system stated uses the second anchor described in any one of claim 1-9 after section adjoining rock stability Solid system strengthening supporting.
CN201811326790.7A 2018-11-08 2018-11-08 A kind of anchoring system and underground engineering construction method Pending CN109339835A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811326790.7A CN109339835A (en) 2018-11-08 2018-11-08 A kind of anchoring system and underground engineering construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811326790.7A CN109339835A (en) 2018-11-08 2018-11-08 A kind of anchoring system and underground engineering construction method

Publications (1)

Publication Number Publication Date
CN109339835A true CN109339835A (en) 2019-02-15

Family

ID=65314220

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811326790.7A Pending CN109339835A (en) 2018-11-08 2018-11-08 A kind of anchoring system and underground engineering construction method

Country Status (1)

Country Link
CN (1) CN109339835A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012769A (en) * 2019-06-01 2020-12-01 中铁十四局集团第二工程有限公司 Semi-rigid and semi-flexible anti-impact tunnel surrounding rock supporting structure under seismic belt and construction method thereof

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102226407A (en) * 2011-05-23 2011-10-26 中铁二院工程集团有限责任公司 Four-line large-span tunnel cable-arch combined primary support structure
CN202323709U (en) * 2011-09-21 2012-07-11 江苏大学 Composite type anchor group for FRP (fiber reinforce plastic) ribs
CN202390751U (en) * 2011-12-16 2012-08-22 中国水电顾问集团贵阳勘测设计研究院 Round steel bar anchor rod structure for cableway
CN102937030A (en) * 2012-11-26 2013-02-20 山东大学 Bolting-grouting integrated support method for zonal disintegration of deep roadway surrounding rock
CN103075165A (en) * 2013-01-10 2013-05-01 中国矿业大学(北京) Composite supporting method of vertical beam of coal road
CN103939110A (en) * 2014-05-07 2014-07-23 中铁第一勘察设计院集团有限公司 Strengthening system for slight cracking of existing tunnel arch portion lining
CN203795298U (en) * 2014-01-20 2014-08-27 安阳市公路管理局 Clamping plate type external prestress steel cable anchoring device
CN106368721A (en) * 2016-12-02 2017-02-01 西南交通大学 Anti-rockburst supporting method in tunnel and anti-rockburst supporting system in tunnel
CN107190757A (en) * 2017-07-27 2017-09-22 河北建科唐秦建筑科技有限公司 The construction method and support system of recyclable system of deep foundation pit support can be assembled
CN107218069A (en) * 2017-07-18 2017-09-29 陕西陕煤黄陵矿业有限公司 A kind of back suspension device and method for protecting support
CN108194100A (en) * 2017-12-21 2018-06-22 山东科技大学 A kind of accurate three-dimensional prestress strengthening method of crack coal and rock
CN209339136U (en) * 2018-11-08 2019-09-03 杭州图强工程材料有限公司 A kind of anchoring system

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102226407A (en) * 2011-05-23 2011-10-26 中铁二院工程集团有限责任公司 Four-line large-span tunnel cable-arch combined primary support structure
CN202323709U (en) * 2011-09-21 2012-07-11 江苏大学 Composite type anchor group for FRP (fiber reinforce plastic) ribs
CN202390751U (en) * 2011-12-16 2012-08-22 中国水电顾问集团贵阳勘测设计研究院 Round steel bar anchor rod structure for cableway
CN102937030A (en) * 2012-11-26 2013-02-20 山东大学 Bolting-grouting integrated support method for zonal disintegration of deep roadway surrounding rock
CN103075165A (en) * 2013-01-10 2013-05-01 中国矿业大学(北京) Composite supporting method of vertical beam of coal road
CN203795298U (en) * 2014-01-20 2014-08-27 安阳市公路管理局 Clamping plate type external prestress steel cable anchoring device
CN103939110A (en) * 2014-05-07 2014-07-23 中铁第一勘察设计院集团有限公司 Strengthening system for slight cracking of existing tunnel arch portion lining
CN106368721A (en) * 2016-12-02 2017-02-01 西南交通大学 Anti-rockburst supporting method in tunnel and anti-rockburst supporting system in tunnel
CN107218069A (en) * 2017-07-18 2017-09-29 陕西陕煤黄陵矿业有限公司 A kind of back suspension device and method for protecting support
CN107190757A (en) * 2017-07-27 2017-09-22 河北建科唐秦建筑科技有限公司 The construction method and support system of recyclable system of deep foundation pit support can be assembled
CN108194100A (en) * 2017-12-21 2018-06-22 山东科技大学 A kind of accurate three-dimensional prestress strengthening method of crack coal and rock
CN209339136U (en) * 2018-11-08 2019-09-03 杭州图强工程材料有限公司 A kind of anchoring system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012769A (en) * 2019-06-01 2020-12-01 中铁十四局集团第二工程有限公司 Semi-rigid and semi-flexible anti-impact tunnel surrounding rock supporting structure under seismic belt and construction method thereof

Similar Documents

Publication Publication Date Title
KR100740200B1 (en) Tunnelling method using pre-support concept and an adjustable apparatus thereof
CN107605489B (en) Three line Large span tunnel inclined shafts are into positive cavity construction method
CN107288653A (en) A kind of the benching tunnelling method excavation supporting structure of weak surrounding rock large cross-section tunnel double -side approach three and construction method
CN108166506A (en) A kind of foundation pit supporting construction
KR100855098B1 (en) Strut structure as temporary system using a vertical truss at the end and the method thereof
KR101353882B1 (en) Method of reinforcement and construction of pillar of neighboring tunnel
CN103510540B (en) Mortar flag stone retaining wall reinforcement construction method and structure thereof
US20150086278A1 (en) Systems and methods to reinforce excavation walls
CN210459228U (en) Building foundation pit supporting device
CN110629671A (en) Suspension bridge anchorage and construction method thereof
KR101001107B1 (en) Double pipe connection type enlarged steel pipe pile head reinforcement
CN207111103U (en) A kind of benching tunnelling method excavation supporting structure of weak surrounding rock large cross-section tunnel double -side approach three
CN108119164A (en) A kind of prefabricated assembled composite supporting construction
CN109339835A (en) A kind of anchoring system and underground engineering construction method
CN108035360B (en) A method of for pattern foundation pit supporting structure
CN104452775B (en) Pre-loaded support struts and construction method for foundation ditch
JP3793955B2 (en) Multiple support construction method
CN209339136U (en) A kind of anchoring system
CN204753603U (en) Supporting construction is deepened again to deep basal pit
CN107034905A (en) Control the combination retaining structure and its construction method of biased deformation
JPH0718669A (en) Earth retaining wall with underground continuous wall
CN106640117A (en) Underground cavern top arc structure, underground cavern and construction method of underground cavern
CN208441868U (en) A kind of liner structure of tunnel rock burst hole section
JPH03202599A (en) Reinforced structure of twin tunnels
CN103031841A (en) Post-tensioned prestressing rectangular hollow foundation pit support pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination