CN109335941A - A kind of friction winding in mine owner shaft device rapid installation process - Google Patents

A kind of friction winding in mine owner shaft device rapid installation process Download PDF

Info

Publication number
CN109335941A
CN109335941A CN201811158245.1A CN201811158245A CN109335941A CN 109335941 A CN109335941 A CN 109335941A CN 201811158245 A CN201811158245 A CN 201811158245A CN 109335941 A CN109335941 A CN 109335941A
Authority
CN
China
Prior art keywords
basis
shaft device
main shaft
parallels
center line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811158245.1A
Other languages
Chinese (zh)
Other versions
CN109335941B (en
Inventor
刘善仁
李祥迎
王娟
丁洋
房振友
王金良
马磊
李莎
张田田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co Ltd Of New Building Engineering Group Of Shandong China
Original Assignee
Co Ltd Of New Building Engineering Group Of Shandong China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Ltd Of New Building Engineering Group Of Shandong China filed Critical Co Ltd Of New Building Engineering Group Of Shandong China
Priority to CN201811158245.1A priority Critical patent/CN109335941B/en
Publication of CN109335941A publication Critical patent/CN109335941A/en
Application granted granted Critical
Publication of CN109335941B publication Critical patent/CN109335941B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B15/00Main component parts of mining-hoist winding devices
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Abstract

The present invention relates to friction winding in mine machine mounting technique field, specially a kind of friction winding in mine owner shaft device rapid installation process is comprised the following steps that: verification basis, unwrapping wire;Basis is levelling, places parallels;Main shaft device installation.Mounting process of the present invention, optimizes installation elevator process, main shaft and pillow seat are integrally carried out installation centering, saved the construction time, labour and crane cost are saved, it is most important that the valuable time won of going into operation for mine.

Description

A kind of friction winding in mine owner shaft device rapid installation process
Technical field
The present invention relates to friction winding in mine machine mounting technique field, specially a kind of friction winding in mine owner axis dress Set rapid installation process.
Background technique
Multi-rope friction hoisting machine is that a kind of big machinery transport applied to deep vertical, shallow vertical and inclined shaft hoisting is set It is standby, with high security, thin, the leading wheel diameter of wirerope diameter is small, weight of equipment is light, little power consumption, it is cheap the advantages that. Wirerope is taken on the capstan (friction pulley) for being placed on elevator, and both ends hang hoisting container or one end hangs balance weight (hammer), operating When, the frictional force between the friction lining and wirerope of borrower's guide wheel drives wirerope to complete the lifting of container.Multi-rope friction type The main component of elevator has main shaft, capstan, base bearing, grooving device, retarder, depth indicator, brake apparatus and leads To wheel etc..
The general procedure of main shaft of hoister device installation is first installation axle pillow in the prior art, pillow seat mounting and adjusting After the completion, then main shaft roller is installed, then just completes installation using multiple integrated regulation and debugging process.This erector The shortcomings that sequence has complex procedures, and the construction time is long, expends more labour, and delay mine is gone into operation.
Summary of the invention
In order to solve the above technical problems, the present invention provides a kind of friction winding in mine owner shaft device rapid installation process, It can save the construction time, save labour and crane cost, win valuable time for mine operation.
To achieve the above object, the present invention adopts the following technical scheme:
A kind of friction winding in mine owner shaft device rapid installation process, which is characterized in that comprise the following steps that:
(1) verification basis, unwrapping wire;
(2) basis is levelling, places parallels;
(3) main shaft device is installed.
Preferably, main shaft and pillow seat are integrally carried out installation centering in the step 3.
Preferably, the step 1 specifically comprises the processes of:
(1) verification basis: after the completion of civil construction, according to Design Requirement Drawing, checking basis, key dimension, After absolute altitude, basic hole, underlying strength reach requirement, lower step process can be just carried out;
(2) unwrapping wire: after basis verification is qualified, fixed promotion center line and absolute altitude are handed over according to construction unit, uses theodolite Center line, absolute altitude will be promoted to be respectively led into winding houses on pre-set pay off rack, made according to the requirement of design drawing Elevator promotes center line and relief.
Preferably, the step 2 specifically comprises the processes of:
(1) basis is levelling: according to spindle centerline, center line and layout design size is promoted, the base center of equipment On the basis of line is guided to the line of ink marker, the relative position of plant bottom case is then made according to design size, recycles level actual measurement each Foundation elevation makes a record, and is then ground to basis;
(2) it places parallels: after the completion of the grinding of basis, measuring the foundation elevation of each ram pack position, determine to pad pad The height of iron, then puts parallels by design, and parallels is made to contact uniform and stable, new and old knot when in order to back-grouting with basis Conjunction face is stronger.
Preferably, the step 3 specifically comprises the processes of: it is using crane that main shaft device is whole after parallels Leveling and centering It is placed on the basic plane for having arranged wedge-shaped parallels, repeated measurement and Leveling and centering reach main shaft pedestal levelness and absolute altitude To after design and quality criteria requirements, by all fastening adjustment of all bolts, until the longitudinal center line of main shaft device, promotion Center line and absolute altitude reach installation quality standard, and last bolt fastening is completed, i.e. one-piece rotor shaft device is installed.
Preferably, the specific method is as follows for the main shaft device centering: according to the big line of cross given, being promoted Hang down 3 line pendants on 0.5 millimeter of the steel wire that machine computer room pay off rack east-west direction is hung, and falls centering roller lock using three lines Disk lengthwise position determines centre of the drum's line position;In 0.5 millimeter of the steel wire that elevator computer room pay off rack North and South direction is hung On hang 2 lines pendant, be overlapped the midpoint at main shaft both ends with the big line of line pendant, determine the axial position of main shaft, then Axial direction and vertical equity measurement are carried out by level and frame level.
Beneficial effect
Friction winding in mine owner shaft device rapid installation process of the present invention optimizes installation elevator process, will Main shaft and pillow seat integrally carry out installation centering, have saved the construction time, save labour and crane cost, it is most important that It goes into operation the valuable time won for mine.Its implementation has the advantages that
1, working procedure is more reasonably optimized, the hoist installation engineering to accelerate later has established good base Plinth.
2, production time is shortened for mine, construction quality and efficiency are greatly enhanced.
3, the construction period is shortened, labour and machine-team expense has been saved, has saved the cost of project management department.
4, because site operation is cross-operation, influence time indirectly has been saved for other units in charge of construction.
Main shaft of hoister installation procedure of the present invention by optimization saves labour and alleviates labor intensity, most It is important to assure that the duration shifts to an earlier date.Save the cost is for example: project management department saves labour cost: 8 * 3 days=7200 yuan of 300 yuan of people *, 80 tons of One-Shift Costs save 4500*1 days=4500 yuan, have fulfiled main shaft device installation ahead of schedule.This technique is suitable for mine vertical Hoist installation, construction efficiency improve, and the duration shortens, and have accomplished effective cost control and have saved.
Specific embodiment
Below with reference to embodiment, technical solution of the present invention is further elaborated with.
Embodiment 1
The integral installation technique of friction type winder main shaft device, specifically includes the following steps:
According to on-site actual situations, preparation before being constructed in advance: verification basis, processing and fabricating pay off rack, throwing Point unwrapping wire.Specific mount scheme:
1. making the relative position of plant bottom case, then benefit according to spindle centerline, promotion center line and layout design size Each foundation elevation is surveyed with level, makes a record, then basis is ground, measure each ram pack position Foundation elevation.
2. after parallels Leveling and centering, main shaft device being integrally placed on using crane and has arranged the basis of wedge-shaped parallels and puts down On face, according to the big line of cross given, the axial direction for determining main shaft, Zong Xiangwei are fallen using the line on elevator computer room pay off rack It sets, then axial direction and vertical equity measurement, repeated measurement and Leveling and centering, last bolt is carried out by level and frame level Fastening is completed to be that one-piece rotor shaft device is installed.
Embodiment 2
The permanent III multi-rope friction hoisting machine main shaft device of gold mine main shaft console mode JKMD3.25 × 4Z in Yantai City Mouping District hundred Integral installation, device therefor material specification is as shown in table 1:
1. device therefor material specification of table
Mounting process specifically includes the following steps:
1, verification basis, unwrapping wire
After the completion of civil construction, relevant unit is organized to carry out an acceptance inspection by construction unit.According to Design Requirement Drawing, to base Plinth is checked, and whether observation key dimension, absolute altitude, basic hole meet design requirement, and whether underlying strength reaches requirement, full Foot can just carry out lower step process after requiring.
After acceptance(check), fixed promotion center line and absolute altitude are handed over according to construction unit, will promote center using theodolite Line, absolute altitude are respectively led into winding houses on pre-set pay off rack, are made elevator according to the requirement of design drawing and are promoted Center line and relief.
2, basis is levelling, places parallels
According to spindle centerline, center line and layout design size are promoted, the base center line line of ink marker of respective equipment On the basis of guiding to, the relative position of plant bottom case is then made according to design size, recycles each basis mark of level actual measurement Height makes a record, and is then ground to basis, after the completion of the grinding of basis, measures the basis mark of each ram pack position Height determines the height of padded parallels, then puts parallels by design, contacts parallels with basis uniform and stable, in order to two New and old faying face is stronger when secondary grouting.
3, main shaft device is installed
After parallels Leveling and centering, main shaft device is integrally placed on to the basic plane for having arranged wedge-shaped parallels using crane On, according to the big line of cross given, hang down 3 on 0.5 millimeter of the steel wire that elevator computer room pay off rack east-west direction is hung A line pendant determines centre of the drum's line position using three line pendant centering roller brake disc lengthwise positions, in elevator computer room unwrapping wire 2 line pendants are hung on 0.5 millimeter of the steel wire that frame North and South direction is hung, and the midpoint at main shaft both ends and line is made to fall big line respectively It is overlapped, determines the axial position of main shaft, then axial direction and vertical equity measurement are carried out by level and frame level, instead Repetition measurement amount and Leveling and centering are complete by all bolts after so that main shaft pedestal levelness and absolute altitude is reached design and quality criteria requirements Portion fastens side adjustment, until the longitudinal center line of main shaft device, promotion center line and absolute altitude reach installation quality standard, side is most Rear bolt fastening is completed to be that one-piece rotor shaft device is installed.
Main shaft of hoister installation procedure by optimization saves labour and alleviates labor intensity, it is most important that really Guarantor's duration shifts to an earlier date, and has accomplished effective cost control and has saved.Save the cost is for example: project management department saves labour cost: 8 people * 300 yuan * 3 days=7200 yuan, 80 tons of One-Shift Costs save 4500*1 days=4500 yuan, have fulfiled main shaft device installation ahead of schedule, by To mine side's favorable comment and affirmative.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, without departing from the technical principles of the invention, several improvements and modifications can also be made, these improve and become Type also should be regarded as protection scope of the present invention.

Claims (6)

1. a kind of friction winding in mine owner shaft device rapid installation process, which is characterized in that comprise the following steps that:
(1) verification basis, unwrapping wire;
(2) basis is levelling, places parallels;
(3) main shaft device is installed.
2. friction winding in mine owner shaft device rapid installation process according to claim 1, it is characterised in that: the step In rapid 3, main shaft and pillow seat are integrally subjected to installation centering.
3. friction winding in mine owner shaft device rapid installation process according to claim 1, it is characterised in that: the step Rapid 1 specifically comprises the processes of:
(1) verification basis: after the completion of civil construction, according to Design Requirement Drawing, basis is checked, key dimension, absolute altitude, After basic hole, underlying strength reach requirement, lower step process can be just carried out;
(2) unwrapping wire: after basis verification is qualified, fixed promotion center line and absolute altitude are handed over according to construction unit, will be mentioned using theodolite Liter center line, absolute altitude are respectively led into winding houses on pre-set pay off rack, make promotion according to the requirement of design drawing Machine promotes center line and relief.
4. friction winding in mine owner shaft device rapid installation process according to claim 1, it is characterised in that: the step Rapid 2 specifically comprises the processes of:
(1) basis is levelling: according to spindle centerline, promoting center line and layout design size, the base center line of equipment is used On the basis of the line of ink marker is guided to, the relative position of plant bottom case is then made according to design size, and level is recycled to survey each basis Absolute altitude makes a record, and is then ground to basis;
(2) it places parallels: after the completion of the grinding of basis, measuring the foundation elevation of each ram pack position, determine padded parallels Highly, parallels then is put by design, contacts parallels with basis uniform and stable, new and old faying face is more when in order to back-grouting Securely.
5. friction winding in mine owner shaft device rapid installation process according to claim 1, it is characterised in that: the step Rapid 3 specifically comprises the processes of: after parallels Leveling and centering, main shaft device is integrally placed on to the base for having arranged wedge-shaped parallels using crane In plinth plane, repeated measurement and Leveling and centering will after so that main shaft pedestal levelness and absolute altitude is reached design and quality criteria requirements All bolts all fastening adjustment, until the longitudinal center line of main shaft device, promotion center line and absolute altitude reach installation quality mark Standard, last bolt fastening are completed, i.e. one-piece rotor shaft device is installed.
6. friction winding in mine owner shaft device rapid installation process according to claim 5, it is characterised in that: the master The specific method is as follows for shaft device centering: according to the big line of cross given, hanging in elevator computer room pay off rack east-west direction 0.5 millimeter of steel wire on hang down 3 lines pendant, determine roller centerline using three lines pendant centering roller brake disc lengthwise positions Position;2 line pendants are hung on 0.5 millimeter of the steel wire that elevator computer room pay off rack North and South direction is hung, and make main shaft respectively The midpoint at both ends falls big line with line and is overlapped, and determines the axial position of main shaft, then carry out axis by level and frame level To and vertical equity measurement.
CN201811158245.1A 2018-09-30 2018-09-30 Rapid installation process for main shaft device of mine friction hoist Active CN109335941B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811158245.1A CN109335941B (en) 2018-09-30 2018-09-30 Rapid installation process for main shaft device of mine friction hoist

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811158245.1A CN109335941B (en) 2018-09-30 2018-09-30 Rapid installation process for main shaft device of mine friction hoist

Publications (2)

Publication Number Publication Date
CN109335941A true CN109335941A (en) 2019-02-15
CN109335941B CN109335941B (en) 2021-07-06

Family

ID=65307970

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811158245.1A Active CN109335941B (en) 2018-09-30 2018-09-30 Rapid installation process for main shaft device of mine friction hoist

Country Status (1)

Country Link
CN (1) CN109335941B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115303922A (en) * 2022-07-08 2022-11-08 中煤第三建设集团机电安装工程有限责任公司 Installation method of super-huge type mine hoist

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0881188A (en) * 1994-09-12 1996-03-26 Meidensha Corp Hoist
KR100497030B1 (en) * 2002-10-14 2005-06-28 반도종공 주식회사 Hoist having Drum Brake
KR20110098204A (en) * 2010-02-26 2011-09-01 한국고벨주식회사 Modularize hoist drive
CN103816983A (en) * 2014-02-24 2014-05-28 中建安装工程有限公司 Installation construction method of large coal pulverizer

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0881188A (en) * 1994-09-12 1996-03-26 Meidensha Corp Hoist
KR100497030B1 (en) * 2002-10-14 2005-06-28 반도종공 주식회사 Hoist having Drum Brake
KR20110098204A (en) * 2010-02-26 2011-09-01 한국고벨주식회사 Modularize hoist drive
CN103816983A (en) * 2014-02-24 2014-05-28 中建安装工程有限公司 Installation construction method of large coal pulverizer

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115303922A (en) * 2022-07-08 2022-11-08 中煤第三建设集团机电安装工程有限责任公司 Installation method of super-huge type mine hoist
CN115303922B (en) * 2022-07-08 2024-01-05 中煤第三建设集团机电安装工程有限责任公司 Installation method of oversized mine hoist

Also Published As

Publication number Publication date
CN109335941B (en) 2021-07-06

Similar Documents

Publication Publication Date Title
CN103816983B (en) A kind of construction method of installation of large-scale coal pulverizer
CN106865414B (en) A kind of combined hanging installation method of Con casting ladle revolving platform
CN102114553B (en) Method for mounting steel plate crop shear
CN109720976B (en) Mounting method of integral skid-mounted cold box in large-scale air separation project
CN101881021A (en) Hoisting method for deep water large-scale jacket construction on land
CN111636406B (en) Intelligent monitoring system for dynamic compaction machine
CN201196616Y (en) Dead-load pile-load type test apparatus for engineering pile
CN101397596A (en) Construction method for blast furnace bustle pipe integral installation
CN109335941A (en) A kind of friction winding in mine owner shaft device rapid installation process
CN101367116B (en) Mounting technique of vertical conticaster for smelting copper
CN105562438B (en) Vertical loop method for rapidly debugging
CN108910730A (en) The construction method of installation of large-scale horizontal derrick crane
CN203143872U (en) Mobile platform for elevator installation construction
CN103862251B (en) A kind of hanging method of the main equipment by restricted by three-dimensional space
CN1107394A (en) Central line measuring and correction technique for metal pipe rolled by piercing mill
CN102071780B (en) Method for manufacturing and mounting 120-meter long roof tile at high altitude
CN211057882U (en) Weight box for static load test of building foundation pile
CN206143824U (en) Pile foundation static test loading system
CN105773138B (en) O-shaped four-tipping car dumper mounting process
CN204662409U (en) A kind of static loading test equipment
CN202482772U (en) Collapse-proof stop block mounting system for railway bridge
CN102431912B (en) Method for assessing balance weight of tower crane
CN202023298U (en) Roof truss-sectioned roof girder structure capable of being hoisted by cross type tower crane
CN111502120A (en) Construction method for hoisting platform steel stand column
CN104149792A (en) Quick installation construction process of overhead person carrying device in coal mine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant