CN109323057A - A kind of turbocharging pipeline and preparation method thereof - Google Patents

A kind of turbocharging pipeline and preparation method thereof Download PDF

Info

Publication number
CN109323057A
CN109323057A CN201811230113.5A CN201811230113A CN109323057A CN 109323057 A CN109323057 A CN 109323057A CN 201811230113 A CN201811230113 A CN 201811230113A CN 109323057 A CN109323057 A CN 109323057A
Authority
CN
China
Prior art keywords
layer
enhancement layer
rubber
turbocharging
thickness
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811230113.5A
Other languages
Chinese (zh)
Inventor
张洪起
陈亮
薛俊芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Peng Ling Group Ltd By Share Ltd
Original Assignee
Tianjin Peng Ling Group Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Peng Ling Group Ltd By Share Ltd filed Critical Tianjin Peng Ling Group Ltd By Share Ltd
Priority to CN201811230113.5A priority Critical patent/CN109323057A/en
Publication of CN109323057A publication Critical patent/CN109323057A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L11/00Hoses, i.e. flexible pipes
    • F16L11/04Hoses, i.e. flexible pipes made of rubber or flexible plastics
    • F16L11/08Hoses, i.e. flexible pipes made of rubber or flexible plastics with reinforcements embedded in the wall
    • F16L11/085Hoses, i.e. flexible pipes made of rubber or flexible plastics with reinforcements embedded in the wall comprising one or more braided layers

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Laminated Bodies (AREA)
  • Rigid Pipes And Flexible Pipes (AREA)

Abstract

The invention discloses a kind of turbocharging pipelines and preparation method thereof; turbocharger tube routing is successively made of barrier layer, the first enhancement layer, adhesive layer, the second enhancement layer and protective layer from inside to outside; wherein; barrier layer is with a thickness of 1.5~2.5mm; first enhancement layer with a thickness of 0.1~0.2mm; thickness of adhibited layer is 0.8~1.5mm, the second enhancement layer with a thickness of 0.1~0.2mm, protective layer thickness is 1.5~2.5mm.Turbocharging pipeline prepared by the present invention improves the performances such as the outer diameter variation of product, burst pressure, impulse oscillation, finally improves the use function of product.

Description

A kind of turbocharging pipeline and preparation method thereof
Technical field
The present invention relates to automobile pipeline technical fields, and in particular to a kind of turbocharging pipeline and preparation method thereof.
Background technique
Currently, because turbocharging hose size is excessive, mainstream production technology is divided into two kinds at present in automobile pipeline system, One kind is manual canoe, and for another kind to squeeze out knitting, the whole world has extremely a small amount of braiding production technology;
Winding production technology can be assisted by a locking equipment by hand, but there is still a need for consume a large amount of costs of labor, production effect Low, and homogeneity of product is slightly worse, nonetheless but it is in aspect of performance greater advantage;Knitting is squeezed out using extrusion Production equipment, enhancement layer use knitting, high production efficiency, and material cost is saved, therefore extrusion is widely used in the industry at present Production technology, but relatively winding is poor by hand in terms of its properties of product.
As the environmental consciousness in global range is constantly promoted, motor vehicle emission requires constantly promoted, therefore small displacement Engine application amount is sharply increasing, small displacement turbocharged engine at work compressed air and amount of fuel in lesser cylinder It burns in body, therefore generates bigger high temperature and pressure exhaust gas, squeezing out knitting product to tradition is a kind of test.
Summary of the invention
The purpose of the present invention is to provide a kind of turbocharging pipeline and preparation method thereof, the present invention provides a kind of more efficient Rate, the preparation method of safer environmental protection and high performance turbocharging pipeline.
The present invention solves its technical problem and adopts the following technical solutions to realize.
The invention proposes a kind of turbocharging pipelines, from inside to outside successively by barrier layer, the first enhancement layer, adhesive layer, Second enhancement layer and protective layer composition, barrier layer with a thickness of 1.5~2.5mm, the first enhancement layer with a thickness of 0.1~0.2mm, glue Layer is connect with a thickness of 0.8~1.5mm, the second enhancement layer with a thickness of 0.1~0.2mm, protective layer thickness is 1.5~2.5mm.
The present invention also proposes a kind of preparation method of above-mentioned turbocharging pipeline, comprising the following steps:
Internal layer barrier layer is squeezed out on plug, is then woven in the outer surface of barrier layer to form the first enhancement layer, It is extruded into adhesive layer on the surface of the first enhancement layer, the second enhancement layer is formed in the surface weave of adhesive layer, finally second Outer protective layer is squeezed out on enhancement layer, obtains semifinished tube embryo;By the cooling after cure of semifinished tube embryo, then cleaning cutting, is obtained To turbocharging pipeline.
The beneficial effects of the present invention are:
The present invention provides a kind of turbocharging pipeline and preparation method thereof, turbocharging pipeline prepared by the present invention is promoted The performances such as the outer diameter variation of product, burst pressure, impulse oscillation, finally improve the use function of product.
Specific embodiment
It in order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below will be in the embodiment of the present invention Technical solution be clearly and completely described.The person that is not specified actual conditions in embodiment, according to normal conditions or manufacturer builds The condition of view carries out.Reagents or instruments used without specified manufacturer is the conventional production that can be obtained by commercially available purchase Product.
A kind of turbocharging pipeline provided in an embodiment of the present invention and preparation method thereof is specifically described below.
The embodiment of the present invention provides a kind of turbocharging pipeline, from inside to outside successively by barrier layer, the first enhancement layer, bonding Layer, the second enhancement layer and protective layer composition, barrier layer with a thickness of 1.5~2.5mm, the first enhancement layer with a thickness of 0.1~ 0.2mm, thickness of adhibited layer are 0.8~1.5mm, the second enhancement layer with a thickness of 0.1~0.2mm, protective layer thickness is 1.5~ 2.5mm。
The embodiment of the present invention provides a kind of turbocharging pipeline, the turbocharging pipeline, from inside to outside successively by barrier layer, First enhancement layer, adhesive layer, the second enhancement layer and protective layer composition, internal layer barrier layer is squeezed out first on plug, utilizes resin The advantages that barrier material barotolerance (high-barrier) and high chemical resistance, so that turbocharging pipeline of the present invention has well Barrier property and chemical resistance, then weave the first enhancement layer, recycle adhesive layer to be bonded, then weave the second enhancing Layer enhances the performances such as the outer diameter variation for improving product, burst pressure, impulse oscillation using above-mentioned double layer fibre structure, so After squeeze out protective layer, obtain the turbocharging pipeline of five-layer structure, the turbocharger tube of the five-layer structure in the embodiment of the present invention The structure on road is totally different from the structure of the turbocharging pipeline of existing three-decker, and existing three-decker is for internal layer and outside Layer between have braiding enhancement layer, due between internal layer and outer layer only have one layer of braiding layer, the mechanical strength of pipeline and Burst pressure is all poor, especially small displacement turbocharged engine at work compressed air and amount of fuel in lesser cylinder It burns in body, therefore generates bigger high temperature and pressure exhaust gas, above-mentioned three-decker is unable to satisfy requirement, and five in the present invention The properties of turbocharging pipeline can be remarkably reinforced in layer structure, finally improve the use function of product.
In some embodiments, barrier layer is selected from nitrile rubber NBR, neoprene CR, chlorinated polyethylene rubber CM, second Any one in alkene acrylic rubber AEM, acrylic rubber ACM or fluorubber FKM.
In some embodiments, the first enhancement layer is 830d selected from specification or the p-aramid fiber of 1100d, specification are Any one in the meta-aramid Nomex or aromatic series polyoxadiazoles fiber POD of 1320d.
In some embodiments, neoprene CR, chlorinated polyethylene rubber CM, ethylene-acrylate rubber AEM, propylene Any one in acid esters rubber ACM or silicon rubber VMQ.
In some embodiments, the second enhancement layer is 830d selected from specification or the p-aramid fiber of 1100d, specification are Any one in the meta-aramid Nomex of 1320d, the polyester line or aromatic series polyoxadiazoles fiber POD that specification is 1100d.
In some embodiments, protective layer is selected from neoprene CR, chlorinated polyethylene rubber CM, ethylene-acrylate rubber Any one in glue AEM, acrylic rubber ACM or silicon rubber VMQ.
As it can be seen that a kind of turbocharging pipeline is also provided in the embodiment of the present invention, the turbocharging pipeline, from the inside to the outside successively It is formed including barrier layer, the first enhancement layer, adhesive layer, the second enhancement layer and protective layer, is each in the embodiment of the present invention above Preferred material used in layer.By selecting above-mentioned material, using its good resistance to mild weather resistance, so that whirlpool of the present invention Taking turns pressure piping has good mechanical performance, while it is also possible that product can satisfy ultra-low penetration (high-barrier) performance It is required that so that turbocharging pipeline of the present invention can satisfy the use environment requirement of automobile dynamic system high temperature, high pressure.
The embodiment of the present invention also provides a kind of preparation method of above-mentioned turbocharging pipeline, comprising the following steps: in plug Upper extrusion internal layer barrier layer, is then woven in the outer surface of barrier layer to form the first enhancement layer, in the first enhancement layer Surface is extruded into adhesive layer, forms the second enhancement layer in the surface weave of adhesive layer, finally squeezes out on the second enhancement layer outer Layer protective layer, obtains semifinished tube embryo;By the cooling after cure of semifinished tube embryo, then cleaning cutting, obtains turbocharging pipeline.
Internal layer barrier layer is prepared by extrusion in the embodiment of the present invention, the first enhancement layer is then wound by knitting machine again, Extrusion bonding layer again winds the second enhancement layer by knitting machine, squeezes out outer protective layer.Pass through extruder first in the table of plug Face squeezes out barrier layer, then the first enhancement layer and the second enhancement layer are formed enhancement layer, adhesive layer on barrier layer by adhesive layer It can play by barrier layer and enhancement layer bonding, to improve the effect of turbocharging pipeline overall performance, at the same time it can also basis The different temperature resistant grade requirement of turbocharging pipeline, selects different bonding layer materials, enhances by using double layer fibre and promoted The performances such as the outer diameter variation of product, burst pressure, impulse oscillation, finally improve the use function of product, and the present invention is implemented Example structure squeezes out knitting production technology instead of tradition, and that breaks extrusion knitting production technology product uses bottleneck, to product Promotion is can be carried out.
In some embodiments, the extrusion temperature of barrier layer are as follows: 60 DEG C~80 DEG C, 60 DEG C are followed successively by from head to screw rod ~80 DEG C, 60 DEG C~80 DEG C, 50 DEG C~70 DEG C;The extrusion temperature of adhesive layer is followed successively by 60 DEG C~80 DEG C from head to screw rod, and 60 DEG C~80 DEG C, 60 DEG C~80 DEG C, 50 DEG C~70 DEG C;The extrusion temperature of protective layer are as follows: 60 DEG C~80 are followed successively by from head to screw rod DEG C, 60 DEG C~80 DEG C, 60 DEG C~80 DEG C, 50 DEG C~70 DEG C.
In some embodiments, vulcanize specifically: nitrile rubber NBR, neoprene CR or chlorinated polyethylene rubber CM, It is 160~180 DEG C in temperature, the time is that 15~30min is once vulcanized, ethylene-acrylate rubber AEM, acrylate rubber Glue ACM, silicon rubber VMQ or fluorubber FKM are 160~180 DEG C in curing temperature, and vulcanization time is that 15~30min is carried out once Vulcanization;It then is 160~180 DEG C in curing temperature, vulcanization time is that 2~4h carries out post-cure.
In some embodiments, the first enhancement layer or the second enhancement layer prepare it is specific as follows: it is fine using knitting Tieing up specification is from 8300~2000 points of Tekes, and knitting machine uses 18~32 needle types.
Feature and performance of the invention are described in further detail with reference to embodiments.
Embodiment 1
The turbocharging pipeline that 8 differences including serial number 1#~8# form altogether of embodiment 1.Following table 1 is serial number The structure composition of the turbocharging pipeline of 1#~8#, wherein P aramid fiber refers to that p-aramid fiber, Nomex are meta-aramid Nomex, POD Fiber is aromatic series polyoxadiazoles fiber POD.
1 structure composition of table
The structure of turbocharging pipeline in the embodiment of the present invention it can be seen from the above table 1 is five layers of pipeline structure, often One layer of rubber material that can choose different compositions.
Comparative example 1
The structure of turbocharging pipeline is NBR/CR material, material serial number 9#.
Embodiment 2
Test method:
Adhesive force: test test fiber interlayer is carried out according to 1 type ring type sample in GB/T14905~2009;
Outer diameter variation: it is tested according to the hydrostatic test method of GB/T5563~2006;
Burst pressure: the hydrostatic test method of GB/T5563~2006 test;
Impulse oscillation:
A. test(ing) medium: compressed air;
B. pulse: 0~2.3bar, pulse frequency: 0.5Hz
C. waveform: sine wave;
D, vibration frequency 0.7Hz, amplitude~29~+22mm
E. test number (TN): totally 25 ten thousand times (environment temperature: 1#, 2#, 3# are 100 DEG C, and 4#, 5# are 125 DEG C, and 6#, 7#, 8# are 155℃;Medium temperature 1#, 2#, 3# are 125 DEG C;4#, 5# are 185 DEG C, and 6#, 7# are 200 DEG C, 8#, 9# are 210 DEG C).
Following table 2 is the test result in the embodiment of the present invention 1 and comparative example 1:
2 test result of table
It is tested, is tied from adhesive force, outer diameter variation, burst pressure and impulse oscillation number it can be seen from the above table 2 Fruit shows: 1#~5# is bright in terms of adhesive force, outer diameter variation, burst pressure and impulse oscillation in the embodiment of the present invention 1 The aobvious corresponding experimental data higher than in comparative example 1, although 6#~8# of the embodiment of the present invention when temperature is 200 or more, 250,000 There is exception in subpulse vibration, however has already appeared crackle in comparative example 1.It can be seen that adhesive force, the outer diameter of present invention entirety Variation, burst pressure and impulse oscillation number are apparently higher than the corresponding performance in comparative example 1.
To sum up, the invention discloses a kind of turbocharging pipeline and preparation method thereof, which is routed from inside to outside Successively be made of barrier layer, the first enhancement layer, adhesive layer, the second enhancement layer and protective layer, barrier layer with a thickness of 1.5~2.5mm, First enhancement layer with a thickness of 0.1~0.2mm, thickness of adhibited layer is 0.8~1.5mm, the second enhancement layer with a thickness of 0.1~ 0.2mm, protective layer thickness are 1.5~2.5mm.The outer diameter that turbocharging pipeline prepared by the present invention improves product changes, is quick-fried The performances such as broken pressure, impulse oscillation, finally improve the use function of product.
The invention has the following advantages:
The present invention uses multiple rubber material, nitrile rubber NBR, neoprene CR, chlorinated polyethylene rubber CM, ethylene propylene Olefin(e) acid ester rubber AEM, acrylic rubber ACM or fluorubber FKM, silicon rubber VMQ, using production technology five-layer structure and a variety of Fiber is designed and verifies, and ensure that the production efficiency and good one of traditional extrusion knitting in terms of production technology In addition cause property enhances the performances such as the outer diameter variation for improving product, burst pressure, impulse oscillation using double layer fibre, finally mentions The use function of product is risen, structure of the embodiment of the present invention squeezes out knitting production technology instead of tradition, breaks extrusion knitting life Production. art product uses bottleneck, is promoted, while improving application range to properties of product, can also meet truck etc. more Harsh working environment carry out using.
Embodiments described above is a part of the embodiment of the present invention, instead of all the embodiments.Reality of the invention The detailed description for applying example is not intended to limit the range of claimed invention, but is merely representative of selected implementation of the invention Example.Based on the embodiments of the present invention, obtained by those of ordinary skill in the art without making creative efforts Every other embodiment, shall fall within the protection scope of the present invention.

Claims (10)

1. a kind of turbocharging pipeline, which is characterized in that from inside to outside successively by barrier layer, the first enhancement layer, adhesive layer, second Enhancement layer and protective layer composition, the barrier layer with a thickness of 1.5~2.5mm, first enhancement layer with a thickness of 0.1~ 0.2mm, the thickness of adhibited layer be 0.8~1.5mm, second enhancement layer with a thickness of 0.1~0.2mm, the protective layer With a thickness of 1.5~2.5mm.
2. turbocharging pipeline according to claim 1, which is characterized in that the barrier layer is selected from nitrile rubber NBR, chlorine Appoint in buna CR, chlorinated polyethylene rubber CM, ethylene-acrylate rubber AEM, acrylic rubber ACM or fluorubber FKM It anticipates one kind.
3. turbocharging pipeline according to claim 1, which is characterized in that it is 830d that first enhancement layer, which is selected from specification, Or the p-aramid fiber of 1100d, specification are any one in the meta-aramid Nomex or aromatic series polyoxadiazoles fiber POD of 1320d Kind.
4. turbocharging pipeline according to claim 1, which is characterized in that the adhesive layer is selected from neoprene CR, chlorine Change any one in polyethylene rubber CM, ethylene-acrylate rubber AEM, acrylic rubber ACM or silicon rubber VMQ.
5. turbocharging pipeline according to claim 1, which is characterized in that it is 830d that second enhancement layer, which is selected from specification, Or the p-aramid fiber of 1100d, specification be 1320d meta-aramid Nomex, specification be 1100d polyester line or fragrant adoption dislike Any one in diazole fiber POD.
6. turbocharging pipeline according to claim 1, which is characterized in that the protective layer is selected from neoprene CR, chlorine Change any one in polyethylene rubber CM, ethylene-acrylate rubber AEM, acrylic rubber ACM or silicon rubber VMQ.
7. a kind of preparation method of turbocharging pipelines described in any item according to claim 1~6, which is characterized in that including Following steps:
Internal layer barrier layer is squeezed out on plug, is then woven in the outer surface of the barrier layer to form the first enhancement layer, It is extruded into adhesive layer on the surface of first enhancement layer, forms the second enhancement layer in the surface weave of the adhesive layer, most Outer protective layer is squeezed out on second enhancement layer afterwards, obtains semifinished tube embryo;The semifinished tube embryo is cooled down into after cure, Then cleaning cutting, obtains turbocharging pipeline.
8. the preparation method of turbocharging pipeline according to claim 7, which is characterized in that the extrusion temperature of the barrier layer Degree are as follows: 60 DEG C~80 DEG C, 60 DEG C~80 DEG C, 60 DEG C~80 DEG C, 50 DEG C~70 DEG C are followed successively by from head to screw rod;The adhesive layer Extrusion temperature 60 DEG C~80 DEG C, 60 DEG C~80 DEG C, 60 DEG C~80 DEG C, 50 DEG C~70 DEG C are followed successively by from head to screw rod;It is described The extrusion temperature of protective layer are as follows: it is followed successively by 60 DEG C~80 DEG C from head to screw rod, 60 DEG C~80 DEG C, 60 DEG C~80 DEG C, 50 DEG C~ 70℃。
9. the preparation method of turbocharging pipeline according to claim 8, which is characterized in that the vulcanization specifically: institute Nitrile rubber NBR, the neoprene CR or the chlorinated polyethylene rubber CM are stated, is 160~180 DEG C in temperature, the time is 15~30min is once vulcanized, the ethylene-acrylate rubber AEM, the acrylic rubber ACM, silicon rubber VMQ or Fluorubber FKM is 160~180 DEG C in curing temperature, and vulcanization time is that 15~30min is once vulcanized;Then in vulcanization temperature Degree is 160~180 DEG C, and vulcanization time is that 2~4h carries out post-cure.
10. the preparation method of turbocharging pipeline according to claim 7, which is characterized in that first enhancement layer or Preparing for second enhancement layer is specific as follows: using knitting, fiber dimensious is from 8300~2000 points of Tekes, knitting Machine uses 18~32 needle types.
CN201811230113.5A 2018-10-22 2018-10-22 A kind of turbocharging pipeline and preparation method thereof Pending CN109323057A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811230113.5A CN109323057A (en) 2018-10-22 2018-10-22 A kind of turbocharging pipeline and preparation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811230113.5A CN109323057A (en) 2018-10-22 2018-10-22 A kind of turbocharging pipeline and preparation method thereof

Publications (1)

Publication Number Publication Date
CN109323057A true CN109323057A (en) 2019-02-12

Family

ID=65262658

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811230113.5A Pending CN109323057A (en) 2018-10-22 2018-10-22 A kind of turbocharging pipeline and preparation method thereof

Country Status (1)

Country Link
CN (1) CN109323057A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1396670A1 (en) * 2002-09-06 2004-03-10 ContiTech Schlauch GmbH Hose
CN2844614Y (en) * 2005-11-11 2006-12-06 天津市大港胶管有限公司 Turbine pressurized hose
CN203162376U (en) * 2013-03-12 2013-08-28 浙江铁马科技股份有限公司 Novel oil return tube for supercharger
CN206234501U (en) * 2016-05-23 2017-06-09 天津鹏翎胶管股份有限公司 A kind of rubber hose
CN107084285A (en) * 2017-04-10 2017-08-22 山东美晨科技股份有限公司 A kind of ethylene-acrylate rubber turbine pressurized hose and preparation method thereof
JP2018031397A (en) * 2016-08-23 2018-03-01 横浜ゴム株式会社 hose
CN107791548A (en) * 2017-10-20 2018-03-13 青岛三祥科技股份有限公司 Turbine pressurized hose

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1396670A1 (en) * 2002-09-06 2004-03-10 ContiTech Schlauch GmbH Hose
CN2844614Y (en) * 2005-11-11 2006-12-06 天津市大港胶管有限公司 Turbine pressurized hose
CN203162376U (en) * 2013-03-12 2013-08-28 浙江铁马科技股份有限公司 Novel oil return tube for supercharger
CN206234501U (en) * 2016-05-23 2017-06-09 天津鹏翎胶管股份有限公司 A kind of rubber hose
JP2018031397A (en) * 2016-08-23 2018-03-01 横浜ゴム株式会社 hose
CN107084285A (en) * 2017-04-10 2017-08-22 山东美晨科技股份有限公司 A kind of ethylene-acrylate rubber turbine pressurized hose and preparation method thereof
CN107791548A (en) * 2017-10-20 2018-03-13 青岛三祥科技股份有限公司 Turbine pressurized hose

Similar Documents

Publication Publication Date Title
KR960006174B1 (en) Hose for transport for refrigerant fluids and fuel oils
CN109648943B (en) Bionic composite material and preparation method thereof
CN102276953B (en) Acrylate rubber (ACM) and ethylene acrylate rubber (AEM) combined composition
CN108610526A (en) A kind of fuel rubber pipe and preparation method thereof
CN105626983A (en) AEM rubber turbo-charging hose and preparation method thereof
CN109323057A (en) A kind of turbocharging pipeline and preparation method thereof
CN104017259A (en) Cloth clamping concrete piston for high-pressure slurry pump and manufacturing method of piston
CN106930998A (en) A kind of enhanced lightweight hydraulic cylinder of carbon fibre composite
CN110466179A (en) A kind of preparation method of ant-scaling enhancing thermoplastic composite tube
CN107061883A (en) Low-penetration fuel hose and preparation method thereof and the fuel system comprising the fuel hose
CN208595322U (en) A kind of composite material enhancing flexible pipe with incubation and thermal insulation function
CN102734570A (en) Cooling hose for turbocharger of engine
CA3005824C (en) Hose inner layer formed of eco blended with nbr/pvc
CN110202845A (en) A kind of double braiding layer high-pressure anti-wear hoses
CN110608320A (en) Thin-wall high-temperature-resistant high-pressure-resistant intercooler corrugated pipe
CN205036986U (en) A dash stake hose assembly that is used for self -elevating drilling unit to dash transport high pressure sea water of stake system
CN105840926B (en) A kind of deep-sea oil gas engineering composite and flexible pipe and its manufacturing method
KR102266487B1 (en) Composition of rubber for a concreate docking hose and the concreate docking hose including the same
CN207848651U (en) A kind of extremely low contamination type fuel charger rubber tube
CN110529671B (en) Carbon silica gel high-pressure steel wire woven hose for oil well
CN204004861U (en) Mixed construction strengthens flexible pipe
KR101663766B1 (en) Rubber composite sheet having oriented chopped fiber, method for preparing the same, multilayer rubber composite article having cross-oriented chopped fiber, and method for preparing the same
CN105065803A (en) Pile-impacting flexible pipe assembly for transporting high-pressure seawater used for self-elevating drilling platform pile-impacting system and preparation method thereof
JP3146739B2 (en) Hose for automotive fuel piping
CN201636456U (en) Novel high-strength hose

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190212

RJ01 Rejection of invention patent application after publication