CN109317981A - A kind of preparation facilities of the pedestal for Blade measuring - Google Patents

A kind of preparation facilities of the pedestal for Blade measuring Download PDF

Info

Publication number
CN109317981A
CN109317981A CN201811497580.4A CN201811497580A CN109317981A CN 109317981 A CN109317981 A CN 109317981A CN 201811497580 A CN201811497580 A CN 201811497580A CN 109317981 A CN109317981 A CN 109317981A
Authority
CN
China
Prior art keywords
blade
axis
pedestal
coordinate system
side elevation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811497580.4A
Other languages
Chinese (zh)
Other versions
CN109317981B (en
Inventor
黄文俊
刘青海
龙永胜
蒋志平
吴小燕
杨国旺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
AECC South Industry Co Ltd
Original Assignee
AECC South Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by AECC South Industry Co Ltd filed Critical AECC South Industry Co Ltd
Priority to CN201811497580.4A priority Critical patent/CN109317981B/en
Publication of CN109317981A publication Critical patent/CN109317981A/en
Application granted granted Critical
Publication of CN109317981B publication Critical patent/CN109317981B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P23/00Machines or arrangements of machines for performing specified combinations of different metal-working operations not covered by a single other subclass
    • B23P23/04Machines or arrangements of machines for performing specified combinations of different metal-working operations not covered by a single other subclass for both machining and other metal-working operations

Abstract

A kind of preparation facilities of the pedestal for Blade measuring comprising, casting equipment, cutting equipment and positioning templet.A kind of preparation facilities of pedestal for Blade measuring provided by the present invention standardizes pedestal by preparation, is substantially shorter the measurement duration of blade, while can reduce production cost and maintenance cost.

Description

A kind of preparation facilities of the pedestal for Blade measuring
Technical field
The present invention relates to aero-engine production technical field, in particular to a kind of turbine in Small Aeroengine In blade manufacturing process, it is used to prepare the device of the pedestal measured to blade part.
Background technique
In the manufacturing process of aero-engine, the mode that hot investment casting can be used in turbo blade carries out single blade part Casting and forming, then single blade part is assembled on listrium, assembling formed turbine entirety.
Fig. 1 a is a kind of stereochemical structure schematic illustration of Turbine Blade;Fig. 1 b is a kind of the vertical of second turbine blade Body principle schematic diagram;Fig. 1 c is a kind of stereochemical structure schematic illustration of free turbine blade;Fig. 2 a is to the one of Fig. 1 a Grade turbo blade carries out the schematic illustration of blade profile dimensional measurement;Fig. 2 b is to carry out listrium size to the Turbine Blade of Fig. 1 a The schematic illustration of measurement;Fig. 2 c is that the principle for carrying out the slot dimensional measurement of tenon tooth locking tab to the Turbine Blade of Fig. 1 a is shown It is intended to;In figure 2 c, it is shown that in measurement process, the facing structure schematic illustration and left view structural principle of measured material are illustrated Figure.
Referring to shown in Fig. 1 a-2c, in gas turbine manufacturing process, for every kind produced by hot investment casting process Individual turbo blade casting requires usually after 1 Foundry Production of turbo blade comes out to the blade profile size of blade 11, edge 131 size of locking plate slot at 13 top of size and tenon tooth of plate 12 measures, so that the single blade for judging that Foundry Production goes out is No is qualified product.
In existing measurement process, the measurement for blade profile size needs on special vice with a pair as shown in Figure 2 a Roller 2 (having corresponding dedicated roller 2, that is, the roller 2 of different-diameter for the different types of design of blade 1) is clamped Tenon tooth 13, elder generation's centering roller 2, for establishing coordinate system when Blade measuring, reuses special measuring tool and (does not regard in figure when measurement The blade profile size of blade 11 is measured out).
Measurement for 12 size of listrium needs to clamp whole tenon tooths 13 using special measurement tooling as shown in Figure 2 b, will Listrium 12 exposes, then the size of listrium 12 is measured with special measuring tool (not regarding out in figure).
Dimensional measurement for 13 locking tab slot 131 of tenon tooth need to use special measurement tooling to clamp tenon as shown in Figure 2 c Tooth 13 simultaneously exposes apical tooth position, and the locking plate slot 131 is not blocked, and reuses special measuring tool (not regarding out in figure) survey Measure 131 relative dimensions of locking plate slot.
Although the every kind of individual turbo blade 1 produced by hot investment casting process all accuracy with size obtain The cylindrical false boss 14 of guarantee, but in existing production technology, the false boss 14 is mainly used for follow-up machine and adds process Clamping and the purposes such as positioning, in existing measurement process, utilization physically is not carried out to the false boss 14 and (such as is pressed from both sides The purposes such as hold, position).
As shown in Figure 2 a, during existing Blade measuring, the foundation of the theoretical reference coordinate system of the blade 1 is usually adopted With following principle, (usually it is clamped in as shown in Figure 2 a described first with the roller 2 of the tenon tooth 13 of blade 1 described in held tight First pair of recessed portion of 13 apical tooth two sides of tenon tooth) establish datum plane, that is, according to the axis of theoretical two parallel rollers 2 Line establishes x-y plane, and the axis by the cylindrical false boss 14 of the blade 1 is z-axis, the friendship of z-axis and x-y plane Point is origin, and for x-axis by origin and parallel with the axis of roller 2, y-axis is vertical with x-axis.In the theoretical referring to seat of the blade 1 In mark system, z-axis is used to indicate positional relationship between the blade 11, the listrium 12 and the tenon tooth 13, usual situation its It is oriented to the direction that the blade 11 is directed toward by the tenon tooth 13, x-axis and y-axis are mainly for for indicating the tooth of the tenon tooth 13 Shape, therefore the direction of x-axis and y-axis can (such as the matching of the reference coordinate system in measurement process with measuring tool facilitates journey as needed Degree) it adjusts, that is to say, that the pointing direction of x-axis can be the direction that exhaust side is directed toward from blade leading edge, be also possible to On the contrary, the pointing direction of y-axis is also possible to opposite either from the direction of leaf basin side direction blade back side.
It is above-mentioned in measurement process during being measured using different measuring tools or for different types of blade Theoretical reference coordinate system can be translated according to the actual conditions of measuring tool, in other words, in order to which measuring instrument is convenient for reading, blade 1 theoretical reference coordinate system origin can mobile △ x, △ y, △ z on the direction of three reference axis respectively, so as to measurement The reference coordinate system of instrument is overlapped.Certainly, it will be appreciated by those skilled in the art that for the ease of measuring instrument operation, such as scheme Shown in 2b, 2c, the theoretical reference coordinate system of blade can also be rotated.
As previously mentioned, existing measurement process is to survey for the different turbo blades such as Fig. 1 a- Fig. 1 c Tenon tooth 13 is clamped using special measurement tooling when measuring the blade profile of the blade 11 (such as to be pressed from both sides on special vice with a pair of of roller 2 Firmly first pair of recessed portion of the apical tooth two sides of tenon tooth 13) expose blade profile, it is positioned with tenon tooth 13 to measure blade profile size;In measurement tenon When 13 locking tab 131 relative dimensions of slot of tooth, special measurement tooling is replaced, clamp most of tenon tooth 13 and will be revealed at the top of tenon tooth Out, to measure 131 relative dimensions of locking plate slot;When measuring 12 size of listrium, it may be desirable to according to the variation of measuring point Replacement covers special measurement tooling, clamps the exposing listrium 12 of tenon tooth 13 and is tested position, measures relative dimensions.
Above-mentioned existing measurement method, process very complicated, for example, clamping 2 clamping of roller using vice when measuring blade profile During, the horizontality of two rollers 2 can finally influence the precision for the blade profile data that measurement obtains, therefore operator It must the experienced efficiency that could ensure 2 process of clamping roller;And the special measurement for measuring listrium 12 and locking plate slot 131 Tooling clamps rear blade state if mounting groove gap is too big and is difficult to guarantee unanimously as shown in figs. 2 b and 2 c, can if gap is too small Blade is caused to be difficult to pack into, therefore mounting groove manufacture difficulty is big, precision is difficult to guarantee.And in order to avoid causing to damage to blade, Under normal conditions, the blade 1 can be less than for manufacturing the hardness of the material of special measurement tooling (especially installation groove location) The hardness of material therefore in use, also easily cause the abrasion of mounting groove, to cause change in size.
In measurement process, since each measuring point requires special tooling, cause to require each blade More set special toolings, so that production cost is high.In addition, tooling quantity also results in management difficulty more big, tooling Maintenance difficulties increase.And since all processes are all manual operationss, the clamping measurement process of each size is both needed to grasp Author has more skilled operation skill.
Existing measurement process operating efficiency is very low.For at least up to a hundred various blade essence castings of every batch of in actual production Part finished product, since every blade is both needed to measure, measurement process needs to expend the very long time, drags to can become One of an important factor for prolonging the entire production cycle.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of preparation facilities of pedestal for Blade measuring, to reduce or It avoids the problem that being formerly mentioned.
In order to solve the above technical problems, the invention proposes a kind of preparation facilities of pedestal for Blade measuring, it is described The locking plate slot size that pedestal is used at the top of blade profile size, the size of listrium and tenon tooth to the blade of turbo blade measures, The pedestal is the rectangular block around the tenon tooth formed of being cast by low-melting alloy, and the locking plate slot is not closed by low melting point Gold covers, and the turbo blade has a theoretical reference coordinate system, z-axis and the blade of the theoretical reference coordinate system The axis of false boss is overlapped, and the x-y plane of the theoretical reference coordinate system can be by capableing of apical tooth two sides to the tenon tooth Two standard rollers that first pair of recessed portion is clamped are established in two axis of clamp position, the friendship of z-axis and x-y plane Point is origin, and for x-axis by origin and parallel with the axis of the roller, y-axis is vertical with x-axis.The rectangular block includes that sequence connects The first side elevation, the second side elevation, third side elevation and the 4th side elevation connect, first side elevation and/or the third Side elevation is parallel with the x-axis of the theoretical reference coordinate system, second side elevation and/or the 4th side elevation and the reason Parallel by the y-axis of reference frame, the rectangular block further includes vertical with the z-axis of the theoretical reference coordinate system close to described The first level face of locking plate slot, the top surface of the rectangular block and the minimum range of the listrium in the z-axis direction are not less than 2mm. It includes casting equipment, cutting equipment and positioning templet, and the casting equipment includes casting pedestal, positioning templet and casting Chamber, the casting pedestal are connected with liftable first boom, and first boom has been rotatably connected the first work by bearing Skill boss fixes device, and the positioning templet is detachably connected with the casting pedestal, and the cutting equipment includes cutting base And cutting rack, the cutting base are connected with liftable second boom, second boom is provided with the second false boss Clamp device, the cutting rack has a liftable u-bracket, is equipped with heating wire in the u-bracket, described to cut Cut frame and the removable connection of the cutting base.
Preferably, first false boss fixes device and the second false boss clamp device is provided with and institute State the matched jack of false boss.
Preferably, the mold cavity is a T-type cavity, and the T-type face of the mold cavity is for forming first water The horizontal type face of plane.
Preferably, at least one side of the mold cavity is the inclined-plane being inclined outwardly.
Preferably, at least one side of the mold cavity is formed by dismountable flapper.
Preferably, second boom is equipped with bearing, the fixed device of second false boss by bearing with it is described Second boom is rotatably connected, and the positioning templet is detachably connected with the cutting base.
The preparation facilities of pedestal provided by the present invention for Blade measuring,
Detailed description of the invention
The following drawings are only intended to schematically illustrate and explain the present invention, not delimit the scope of the invention.Wherein,
Fig. 1 a is a kind of stereochemical structure schematic illustration of Turbine Blade;
Fig. 1 b is a kind of stereochemical structure schematic illustration of second turbine blade;
Fig. 1 c is a kind of stereochemical structure schematic illustration of free turbine blade;
Fig. 2 a is the schematic illustration that blade profile dimensional measurement is carried out to the Turbine Blade of Fig. 1 a;
Fig. 2 b is the schematic illustration that listrium dimensional measurement is carried out to the Turbine Blade of Fig. 1 a;
Fig. 2 c is the schematic illustration that the slot dimensional measurement of tenon tooth locking tab is carried out to the Turbine Blade of Fig. 1 a;
Fig. 3 a for a kind of pedestal for Blade measuring of a specific embodiment according to the present invention preparation facilities institute Manufactured pedestal carries out the schematic illustration of blade profile dimensional measurement for turbo blade;
Fig. 3 b is the schematic illustration that listrium dimensional measurement is carried out to the turbo blade of Fig. 3 a;
Fig. 3 c is the schematic illustration that the slot dimensional measurement of tenon tooth locking tab is carried out to the turbo blade of Fig. 3 a;
Fig. 4 a is a kind of broken section principle schematic diagram of the casting equipment of pedestal for being used to prepare Fig. 3 a;
Fig. 4 b is the overlooking state partial cross principle schematic diagram of the casting equipment of Fig. 4 a;
Fig. 5 is the broken section principle schematic diagram of the cutting equipment for the cutting drawing 4a rectangular block prepared.
Specific embodiment
For a clearer understanding of the technical characteristics, objects and effects of the present invention, this hair of Detailed description of the invention is now compareed Bright specific embodiment.Wherein, identical component uses identical label.
Fig. 1 a is a kind of stereochemical structure schematic illustration of Turbine Blade;Fig. 2 a is the Turbine Blade to Fig. 1 a Carry out the schematic illustration of blade profile dimensional measurement;Fig. 3 a is that one kind of a specific embodiment according to the present invention is surveyed for blade Pedestal made by the preparation facilities of the pedestal of amount carries out the schematic illustration of blade profile dimensional measurement for turbo blade;Fig. 3 b is The schematic illustration of listrium dimensional measurement is carried out to the turbo blade of Fig. 3 a;Fig. 3 c is to carry out tenon tooth top to the turbo blade of Fig. 3 a Schematic illustration Fig. 4 a of portion's locking plate slot dimensional measurement is a kind of preparation of pedestal for Blade measuring for being used to prepare Fig. 3 a The broken section principle schematic diagram of the equipment of device;Fig. 4 b is the overlooking state partial cross structural principle of the equipment of Fig. 4 a Schematic diagram;Fig. 5 is the broken section principle schematic diagram of the cutting equipment for the cutting drawing 4a rectangular block prepared.Referring to figure Shown in 1a, 2a, 3a-5, the present invention provides a kind of preparation facilities of pedestal for Blade measuring, the pedestal is used for whirlpool 131 size of locking plate slot at 13 top of the blade profile size of the blade 11 of impeller blade 1, the size of listrium 12 and tenon tooth measures, institute Stating pedestal is the rectangular block 3 around the tenon tooth 13 formed of being cast by low-melting alloy, and the locking plate slot 131 is not by eutectic Point alloy covers, and exposes the rectangular block 3, and the turbo blade 1 has a theoretical reference coordinate system, the theoretical reference The z-axis of coordinate system is overlapped with the axis of the false boss 14 of the blade 1, and the x-y plane of the theoretical reference coordinate system can be by It can be to two standard rollers 2 that first pair of recessed portion of the apical tooth two sides of the tenon tooth 13 is clamped the two of clamp position Root axis is established, and the intersection point of z-axis and x-y plane is origin, and x-axis passes through origin and, y-axis parallel with the axis of the roller 2 It is vertical with x-axis.The rectangular block 3 includes that the first side elevation being linked in sequence, the second side elevation, third side elevation and the 4th are edge-on Face, first side elevation and/or the third side elevation are parallel with the x-axis of the theoretical reference coordinate system, described second side Facade and/or the 4th side elevation are parallel with the y-axis of the theoretical reference coordinate system, the rectangular block 3 further include with it is described The vertical first level face 31 close to the locking plate slot 131 of the z-axis of theoretical reference coordinate system, the top surface of the rectangular block and institute The minimum range of listrium 12 in the z-axis direction is stated not less than 2mm.Comprising:
One casting equipment 4, the casting equipment 4 includes casting pedestal 41, positioning templet 42 and mold cavity 43, described Casting pedestal 41 is connected with liftable first boom 411, is equipped with bearing on first boom 411, can be revolved by bearing Turn to be connected with the fixed device 44 of the first false boss, the insertion of the false boss 14 of the blade 1 to be measured is mounted on institute It states in the fixed device 44 of the first false boss, then is locked the blade 1 in the fixed dress of first false boss by screw It sets in 44, is lifted on the blade 1 on first boom 411, by adjusting first boom 411 is locked in Vertical Square To position, the direction of the x, y, z axis of the theoretical reference coordinate system of the blade 1 can be thus fixed up, but The blade 1 (that is to say the theoretical reference coordinate system) can rotate on first boom 411.Then, by tested institute It states the corresponding positioning templet 42 of blade 1 to be mounted on the casting pedestal 41, in this manner it is possible to pass through the positioning templet 42 and the blade 1 the listrium 12 fitting, the fixed blade 1 it is angular so that all freedom of the blade 1 Degree is fixed.
The fixed device 44 of first false boss is provided with the jack that (clearance fit) is matched with the false boss 14, And fixing screws are connected in jack, thus can by the false boss 14 is inserted into the jack and tighten screw come Connection relationship between the fixed blade 1 and the fixed device of first false boss.By the false boss 14 of the blade 1 It is mounted on the fixed device 44 of first false boss, also allows for the theoretical reference coordinate system of the blade 1 in this way X, y, z direction is fixed, irremovable, but can rotate along bearing centre.For different types of turbo blade, can correspond to every The kind blade 1 manufactures a dedicated positioning templet 42, and as shown in Fig. 4 a, 4b, the positioning templet 42 can be by tight Gu screw is fixedly connected with the casting pedestal 41, by the auxiliary positioning of the positioning templet 42, can ensure and the work The blade 1 that skill boss clamp device 44 connects, which can be stablized, rests on the mold cavity 43, and can ensure the blade 1 The theoretical reference coordinate system is parallel with the coordinate system where the side wall of the mold cavity 43.Namely make the mold cavity 43 Side wall facing each other it is parallel with the x-axis of the theoretical reference coordinate system and y-axis respectively, when replacing the different types of leaf When piece 1, fastening screw only need to be unclamped, removing and replacing the corresponding positioning templet 42 can be realized to different types of described The positioning of blade 1.
In Fig. 4 a and Fig. 4 b, a global facility is shown in the mold cavity 43, but those skilled in the art should Understand, as a casting mold cavity, removes the rectangular block 3 after casting for convenience, the mold cavity 43 can be made at least One side is formed by dismountable flapper, it is of course also possible to be make at least one side of the mold cavity 43 to The inclined-plane of outer incline.
The mold cavity 43 can a T-type cavity as shown in Figure 4 a, in this way, the T-type face 431 of the mold cavity 43 As the horizontal type face for forming the first level face 31, since casting process can the fully wrapped around covering top of tenon tooth 13 The locking plate slot 131 in portion, therefore, the mold cavity 43 use T-type cavity, then can avoid the 431 molding institute of institute of T-type face First level face 31 is stated in subsequent extra low-melting alloy structure removal process, will not be destroyed, and can be used as reference plane Convenient for successor operation.
The side wall and adjacent side wall of the mold cavity 3 where the positioning templet 42 can be used as contoured sidewall, use In the x-axis and y-axis that ensure that at least two side walls of the rectangular block 3 can respectively with the theoretical reference coordinate system of the blade 1 In parallel.
Later, it can be poured low-melting alloy in the mold cavity 43, is stained with cold water brush in eutectic using hairbrush after casting It on point alloy, waits 5 seconds or so, to low-melting alloy cooled and solidified, unclamps the screw of the fixed device 44 of the false boss, when When at least one side of the mold cavity 43 is formed by dismountable flapper, the active catch of the mold cavity 43 is removed Plate lifts the boom 411, so that it may take out the blade 1 for being provided with the rectangular block 3.When the mold cavity 43 At least one side is the inclined-plane being inclined outwardly.It then can directly lift the boom 411, so that it may which taking-up has been provided with the square The blade 1 of shape block 3.
A cutting equipment 5 is provided again, and the cutting equipment 5 includes cutting base 51 and cutting rack 52, the cutting Pedestal 51 is connected with liftable second boom 511, and second boom 511 is provided with the second false boss clamp device 54, The insertion of the false boss 14 of the blade 1 to be measured is mounted in the fixed device 54 of second false boss, then is led to It crosses screw to lock the blade 1 in the fixed device 54 of second false boss, the blade 1 is made to be lifted on described second It, thus can be by the blade 1 by adjusting locking second boom 511 in the position of vertical direction on boom 511 The direction of the x, y, z axis of the theoretical reference coordinate system is fixed up, and the cutting rack 52 has a liftable U-shaped branch Frame 521 is equipped with heating wire 522 in the u-bracket 521, can reach 230 degrees Celsius after electric-heating-wire-heating, can thus lead to It crosses and moves the cutting rack 52 along the cutting base 51 to utilize the heating wire 522 to cut the packet of 13 bottom of tenon tooth The alloy component for covering the locking plate slot 131, by the height for adjusting the u-bracket 521, it can be ensured that the heating wire 522 The first level face 31 alloy component below is cut, to will not be impacted to the first level face 31. Namely it is adapted to the alloy cutting to different type blade.After cutting, the cladding locking plate slot of 13 bottom of tenon tooth 131 alloy component is fallen naturally, to also just complete the preparation to the rectangular block 3.
Shown in Figure 5, second boom 511 is also mountable bearing, the fixed device 54 of second false boss It is rotatably connected by bearing and second boom 511, in this way, being lifted on second boom 511 it in the blade 1 Afterwards, the direction of the x, y, z axis of the theoretical reference coordinate system of the blade 1 is fixed up, but the theoretical reference coordinate system It can still be rotated on second boom 511.Then, the tested corresponding positioning templet 42 of the blade 1 is mounted on On the cutting base 51, in this manner it is possible to by the fitting of the positioning templet 42 and the listrium 12 of the blade 1, The angular of the blade 1 is fixed, so that all freedom degrees of the blade 1 are fixed.To may make for same class Type blade, when cutting the running track of the cutting rack 52 it is identical, also can be by the way that phase be arranged on the cutting base 51 The guide rail answered simplifies the mobile control to the cutting rack 52.
The casting equipment 4 can share a pedestal with the cutting equipment 5, that is to say, that the casting pedestal 41 With the cutting base 51 all operationss can be completed in a station in this way on same bottom plate.
Since low-melting alloy has good hardness and strength, the present invention using low-melting alloy by being cast Mode, form the rectangular block 3 around the tenon tooth 13, low-melting alloy, can be to the tenon tooth after cooling and solidifying sizing 13 shrink, to form the firm double team to the tenon tooth 13 using the tooth form of the tenon tooth 13.
Due to first side elevation of the rectangular block 3 and/or the third side elevation and the theoretical reference coordinate The x-axis of system is parallel, and second side elevation and/or the 4th side elevation are parallel with the y-axis of the theoretical reference coordinate system, institute It is vertical with the z-axis of the theoretical reference coordinate system to state first level face 31, that is, the first level face 31 and the x-y are put down Face is parallel, therefore, by the limit of the outer surface to the rectangular block 3, can limit the reference frame of the blade 1, and The theoretical reference coordinate system of the blade 1 can be made parallel with the reference coordinate system of measuring instrument, easily so as to very square It will pass through and the blade 1 is determined using the similar fixture that can be limited at least three faces in each measuring phases Position is fixed, and the reference coordinate system that also can very easily adjust measuring instrument is overlapped with the theoretical reference coordinate system of the blade 1, Also it can simplify the measurement tooling of each measurement process and the structure of measuring tool.And promote measurement efficiency.
First side elevation and/or the third side elevation of the rectangular block 3 and second side elevation and/or 4th side elevation is mainly used for clamping position, can be by determining the false boss 14 in subsequent measurement process Therefore position only needs not lean on too close with the listrium 12, has a spacing to control the reference frame of the blade 1 From (such as minimum range is not less than 5mm, maximum distance is not more than 30mm, apart from excessive, be easy to cause 3 volume of rectangular block It is larger, waste the energy consumption of manufacturing process), therefore, when fixing the blade 1 to be measured before casting, it need to only keep described Listrium 12 and the side wall of the mold cavity 43 have certain distance, certainly, by the way that the positioning templet 42 is arranged, may make The coordinate system for the rectangular block 3 that blade 1 described in same type is cast is stablized, consequently facilitating subsequent massization standardization carries out Measurement.
The top surface and the minimum range of the listrium 12 in the z-axis direction that can control the rectangular block 3 are greater than 2mm, in this way It can ensure the space needs that the size to the listrium 12 measures.
The first level face 31 can be made to be greater than 1.5mm with the minimum range of the locking plate slot 131 in the z-axis direction.This Sample can reserve enough measurement spaces for the locking plate slot 131.
In practice, to 3 kinds of turbo blades of Mr. Yu's h type engine h, when due to using the device of the invention, device can be closed It and is a set of, it is only necessary to the pedestal preparation of different type blade can be realized with changing positioning templet.And the measurement work of measurement process The structure of dress and measuring tool is also greatly simplified, so that the time of replacement measuring tool is greatly decreased, compared with described in background technique Original process method, can shorten for about 50% or so time on the duration.Moreover, because reducing measurement tooling, drop significantly Low production cost, can usually reduce by 60% or so frock cost compared with former measurement method described in background technique.It was measuring Cheng Zhong can avoid using as being that plane as the side elevation and horizontal plane to the rectangular block 3 carries out positioning clamping High-precision loose piece positioning as stated in the background art, while reducing tooling manufacturing cost, also reduces tooling maintenance difficulties.
A kind of preparation facilities of pedestal for Blade measuring provided by the present invention standardizes pedestal by preparation, can The measurement duration of blade is greatly shortened, while can reduce production cost and maintenance cost.
It will be appreciated by those skilled in the art that although the present invention is described in the way of multiple embodiments, It is that not each embodiment only contains an independent technical solution.So narration is used for the purpose of for the sake of understanding in specification, The skilled in the art should refer to the specification as a whole is understood, and by technical solution involved in each embodiment Regard as and can be combined with each other into the modes of different embodiments to understand protection scope of the present invention.
The foregoing is merely the schematical specific embodiment of the present invention, the range being not intended to limit the invention.It is any Those skilled in the art, made equivalent variations, modification and combination under the premise of not departing from design and the principle of the present invention, It should belong to the scope of protection of the invention.

Claims (6)

1. a kind of preparation facilities of the pedestal for Blade measuring, the pedestal is used for the blade profile ruler to the blade of turbo blade Locking plate slot size at the top of very little, listrium size and tenon tooth measures, and the pedestal is cast by low-melting alloy to be formed Around the rectangular block of the tenon tooth, the locking plate slot is not covered by low-melting alloy, and the turbo blade has a theory The z-axis of reference frame, the theoretical reference coordinate system is overlapped with the axis of the false boss of the blade, the theoretical reference Two standards that the x-y plane of coordinate system can be clamped by first pair of recessed portion for capableing of apical tooth two sides to the tenon tooth are rolled Stick is established in two axis of clamp position, and the intersection point of z-axis and x-y plane is origin, x-axis by origin and with the roller Axis it is parallel, y-axis is vertical with x-axis.The rectangular block includes the first side elevation being linked in sequence, the second side elevation, third side The x-axis of facade and the 4th side elevation, first side elevation and/or the third side elevation and the theoretical reference coordinate system is flat Row, second side elevation and/or the 4th side elevation are parallel with the y-axis of the theoretical reference coordinate system, the rectangular block It further include the first level face close to the locking plate slot vertical with the z-axis of the theoretical reference coordinate system, the rectangular block Top surface and the minimum range of the listrium in the z-axis direction are not less than 2mm.It includes casting equipment, cutting equipment and positioning sample Plate, the casting equipment include that casting pedestal, positioning templet and mold cavity, the casting pedestal are connected with liftable first Boom, first boom have been rotatably connected the fixed device of the first false boss by bearing, the positioning templet with it is described Casting pedestal is detachably connected, and the cutting equipment includes cutting base and cutting rack, and the cutting base, which is connected with, to be risen Second boom of drop, second boom are provided with the second false boss clamp device, and the cutting rack has one can rise The u-bracket of drop is equipped with heating wire, the cutting rack and the removable connection of the cutting base in the u-bracket.
2. the apparatus according to claim 1, which is characterized in that the fixed device of first false boss and second work Skill boss clamp device is provided with and the matched jack of the false boss.
3. the apparatus according to claim 1, which is characterized in that the mold cavity is a T-type cavity, the mold cavity T-type face is the horizontal type face for forming the first level face.
4. the apparatus according to claim 1, which is characterized in that at least one side of the mold cavity is inclined outwardly Inclined-plane.
5. the apparatus according to claim 1, which is characterized in that at least one side of the mold cavity is by removably living Dynamic baffle is formed.
6. the apparatus according to claim 1, which is characterized in that second boom is equipped with bearing, second technique The fixed device of boss is rotatably connected by bearing and second boom, and the positioning templet and the cutting base are detachable Connection.
CN201811497580.4A 2018-12-07 2018-12-07 Preparation device for base used for blade measurement Active CN109317981B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811497580.4A CN109317981B (en) 2018-12-07 2018-12-07 Preparation device for base used for blade measurement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811497580.4A CN109317981B (en) 2018-12-07 2018-12-07 Preparation device for base used for blade measurement

Publications (2)

Publication Number Publication Date
CN109317981A true CN109317981A (en) 2019-02-12
CN109317981B CN109317981B (en) 2021-02-09

Family

ID=65257217

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811497580.4A Active CN109317981B (en) 2018-12-07 2018-12-07 Preparation device for base used for blade measurement

Country Status (1)

Country Link
CN (1) CN109317981B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202071133U (en) * 2010-12-31 2011-12-14 陈少纯 Arc cutting and pulp scraping multipurpose machine
CN203083481U (en) * 2013-03-21 2013-07-24 哈尔滨汽轮机厂有限责任公司 Six-point locating-based gas turbine blade clamp measuring tool
WO2015022369A1 (en) * 2013-08-13 2015-02-19 Hamuel Maschinenbau Gmbh & Co. Kg Processing machine and method for restoring a used turbine blade, a used impeller or a used blisk, and turbine blade, impeller or blisk
CN105436838A (en) * 2015-11-05 2016-03-30 西安航空动力股份有限公司 Machining method for turbine work blade
CN206912216U (en) * 2017-04-25 2018-01-23 内蒙古恒方科技有限公司 Lever cantilever air injection machine
CN206967636U (en) * 2017-06-21 2018-02-06 浙江中科恒泰新材料科技有限公司 A kind of PMI foamed materials cutting machine

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202071133U (en) * 2010-12-31 2011-12-14 陈少纯 Arc cutting and pulp scraping multipurpose machine
CN203083481U (en) * 2013-03-21 2013-07-24 哈尔滨汽轮机厂有限责任公司 Six-point locating-based gas turbine blade clamp measuring tool
WO2015022369A1 (en) * 2013-08-13 2015-02-19 Hamuel Maschinenbau Gmbh & Co. Kg Processing machine and method for restoring a used turbine blade, a used impeller or a used blisk, and turbine blade, impeller or blisk
CN105436838A (en) * 2015-11-05 2016-03-30 西安航空动力股份有限公司 Machining method for turbine work blade
CN206912216U (en) * 2017-04-25 2018-01-23 内蒙古恒方科技有限公司 Lever cantilever air injection machine
CN206967636U (en) * 2017-06-21 2018-02-06 浙江中科恒泰新材料科技有限公司 A kind of PMI foamed materials cutting machine

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
申秀丽: "《航空燃气涡轮发动机典型制造工艺》", 30 June 2016 *

Also Published As

Publication number Publication date
CN109317981B (en) 2021-02-09

Similar Documents

Publication Publication Date Title
CN1693014B (en) Method and apparatus for determining the location of core-generated features in an investment casting
CN109458901A (en) A kind of blade subsidiary pedestal manufacturing device
CN109317936A (en) A kind of Blade measuring pedestal preparation method
CN109483172A (en) A kind of turbo blade positioning pedestal manufacturing method
CN109317981A (en) A kind of preparation facilities of the pedestal for Blade measuring
CN109332652A (en) A kind of blade positioning base manufacturing device
CN109458900A (en) A kind of blade subsidiary pedestal manufacturing method
CN109465606A (en) A kind of preparation method of the pedestal for Blade measuring
CN109357599B (en) Integral machining measuring device and method for intermediary case wax mold
CN109434396A (en) A method of manufacture is used for the integrated base of Blade measuring
CN109405699A (en) A kind of Blade roughcast measuring block manufacturing device
CN109332654A (en) A kind of blade of aviation engine pedestal preparation facilities
CN109443146A (en) A kind of integrated base for Blade measuring
CN109317980A (en) A kind of Blade measuring pedestal preparation facilities
CN109332653A (en) A kind of blade positioning base manufacturing method
CN109373949A (en) A kind of turbo blade positioning pedestal manufacturing device
CN110303386B (en) Turbine blade pouring box alignment device and working method
CN109622923A (en) A kind of blade of aviation engine pedestal preparation method
CN109115112B (en) Scanning support and scanning method thereof
CN109465405A (en) A kind of Blade roughcast measuring block manufacturing method
CN114799383B (en) Method and device for trimming casting flange plate of single crystal turbine blade and single crystal turbine blade
CN109530626A (en) A kind of turbo blade pedestal preparation method
CN109397141A (en) A kind of turbo blade pedestal preparation facilities
CN112414330B (en) Gas device for measuring angle of small micropore of blade
CN112284306B (en) Liquid state method device for measuring angle of small micropore of blade

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant