CN109311628A - Restore support system - Google Patents
Restore support system Download PDFInfo
- Publication number
- CN109311628A CN109311628A CN201680084657.8A CN201680084657A CN109311628A CN 109311628 A CN109311628 A CN 109311628A CN 201680084657 A CN201680084657 A CN 201680084657A CN 109311628 A CN109311628 A CN 109311628A
- Authority
- CN
- China
- Prior art keywords
- information
- time
- unit
- lift appliance
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B5/00—Applications of checking, fault-correcting, or safety devices in elevators
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B5/00—Applications of checking, fault-correcting, or safety devices in elevators
- B66B5/02—Applications of checking, fault-correcting, or safety devices in elevators responsive to abnormal operating conditions
Abstract
Restoring support system has lift appliance (1) and monitoring arrangement (2).Monitoring arrangement (2) has number calculation part (9), number information's acquisition unit (10), time calculation part (11) and transmission unit (12).Number calculation part (9) calculating can use the number per unit time that the lift appliance (1) that can restore automatically is taken refuge.Time calculation part (11) calculates the time it takes until the people stayed in building (5) takes refuge.Transmission unit (12) will be sent to service companies (7) by the information of time calculation part (11) calculated time.
Description
Technical field
The present invention relates to the systems being supported for the recovery to lift appliance.
Background technique
A kind of lift appliance is described in patent document 1.Lift appliance documented by patent document 1 occurs in earthquake
When, carry out controlled operation when the earthquake for making carriage rest in nearest floor.The sedan-chair when have passed through the stipulated time from earthquake generation
In the case that compartment does not rest in nearest floor yet, it is notified to central monitoring position.
Existing technical literature
Patent document
Patent document 1: Japanese Unexamined Patent Publication 2007-276924 bulletin
Summary of the invention
Problems to be solved by the invention
The service companies for carrying out the maintenance of lift appliance are generated when earthquake occurs by sending based on the sending of maintenance personnel
It draws.Plan is sent according to generated, sends maintenance personnel to the building for being provided with lift appliance.In the past according to maintenance personnel
Moving distance and the size etc. of building determine which building maintenance personnel is sent to.
Recent lift appliance some has in the function of restoring automatically after the earthquake.Therefore, according to previous such
When plan is sent in the generations such as the moving distance according to maintenance personnel, there are problems that efficiently resuming operation.
The present invention is precisely in order to solving the problems, such as described above and completing, it is intended that providing one kind can be to dimension
System is supported in the recovery that shield company provides the required information that resumes operation for efficiently carrying out lift appliance.
The means used to solve the problem
Recovery support system of the invention has the multiple elevator device for being set to building and can fill with multiple elevator
The monitoring arrangement that the service companies set are communicated.Each lift appliance in multiple elevator device is used for when earthquake occurs
Determine the point that can restore automatically inspection operating.Monitoring arrangement includes number computing unit, calculates in per unit after the earthquake
The number that can be taken refuge using the lift appliance that can restore automatically in multiple elevator device in time;Number information takes
Unit is obtained, is obtained in the information for staying number between floors after the earthquake;1st time calculating unit, according to by people
Information number computing unit calculated number and obtained by number information's acquisition unit is calculated until staying people between floors
The time it takes until taking refuge;And transmission unit, it will be sent by the information of the 1st time calculating unit calculated time
To service companies.
Recovery support system of the invention has the lift appliance for being set to building and can be with progress lift appliance
The monitoring arrangement that the service companies of maintenance are communicated.Can lift appliance be carried out when earthquake occurs for determining restore automatically
Point inspection operating.Monitoring arrangement includes number computing unit, if be able to carry out in lift appliance after the earthquake automatic extensive
Multiple, then the number computing unit calculates the number that can be taken refuge using lift appliance in per unit time;Number information takes
Unit is obtained, is obtained in the information for staying number between floors after the earthquake;Time calculating unit, according to by population number meter
The information calculating the calculated number of unit and being obtained by number information's acquisition unit, calculates until staying people between floors to take refuge
Until the time it takes;And transmission unit, maintenance will be sent to by the information of time calculating unit calculated time
Company.
Invention effect
In recovery support system of the invention, calculate until stay that people between floors spent until taking refuge when
Between, by the information of calculated time be sent to service companies.Recovery support system according to the present invention, can be public to maintenance
Department provides the required information that resumes operation for efficiently carrying out lift appliance.
Detailed description of the invention
Fig. 1 is the figure for showing the structural example of recovery support system of embodiments of the present invention 1.
Fig. 2 is the flow chart for showing the movement of lift appliance.
Fig. 3 is the flow chart for showing the movement of monitoring arrangement.
Fig. 4 is the flow chart for showing the movement of recovery system.
Fig. 5 is the figure for showing the hardware configuration of monitoring arrangement.
Specific embodiment
It is described with reference to the present invention.Repeat description suitably will be simplified or be omitted.In various figures, identical
Label indicates identical part or comparable part.
Embodiment 1
Fig. 1 is the figure for showing the structural example of recovery support system of embodiments of the present invention 1.Restoring support system has
Lift appliance 1, monitoring arrangement 2, access management system 3 and recovery system 4.
Fig. 1 shows the example that 4 lift appliances 1 are set to same building object 5.It is set to the lift appliance 1 of building 5
Number of units can be 3 hereinafter, being also possible to 5 or more.For example, it is also possible to which 1 lift appliance 1 is only arranged to building 5.
Lift appliance 1 has auto restore facility.In the example depicted in figure 1, complete set on the lift appliance 1 of building 5
Portion has auto restore facility.A part of lift appliance 1 for being also possible to only be provided at building 5 has auto restore facility.
Auto restore facility is to intervene the function that can restore automatically in Maintenance free personnel after the earthquake.For example, being set in building 5
There is seismic sensor 6.Lift appliance 1 starts to manage when earthquake when detecting the earthquake of a certain grade or more by seismic sensor 6
System operating.Controlled operation is the operating for making user from carriage descending stair when earthquake.In earthquake in controlled operation, carriage is stopped
Lean against nearest floor.When carriage rests in nearest floor, door is opened.When have passed through the stipulated time from door opening, Men Guan
It closes.Controlled operation terminates when earthquake as a result, and lift appliance 1 stops.
When lift appliance 1 have passed through the stipulated time controlled operation terminates when from earthquake, starting point inspection operating.Point inspection fortune
Turn to be the operating for determining to restore automatically.For example, obtaining various data in inspection operating.By acquired data with
The a reference value or reference range of the data are compared.It can be restored automatically according to the judgement of above-mentioned comparison result.
In addition, if carriage rests in stop and without passenger's boarding in carriage, lift appliance 1 when earthquake occurs
Controlled operation begins to an inspection operating when can also be without earthquake.
If lift appliance 1 does not detect specific exception in inspection operating, it is judged to restore.Lift appliance
If 1 can restore, signal can be restored to the transmission of monitoring arrangement 2.Lift appliance 1 is restored and is started again at as a result,
Usually operating.Usually operating is the operating for making carriage respond registered call.
Lift appliance 1 is judged to restore when detecting specific exception in inspection operating.Lift appliance 1 is such as
Fruit cannot restore, then cannot restore signal to the transmission of monitoring arrangement 2.Point inspection operating stops as a result, and lift appliance 1 stops again.
3 pairs of disengaging buildings 5 of access management system are managed.Access management system 3 is for example with the knowledge held by people
The reader of the information of distinguishing label and reading identification label.Reader is set to wall for example adjacent with the entrance of building 5
On.The information for showing the position (place) of holder of identification label is stored in access management system 3.The information according to by
The information that reader is read out is updated regularly.Therefore, it is stored with and is currently located in building 5 in access management system 3
The information of people.
Access management system 3 can also be managed the room and floor etc. passed in and out in building 5.In such case
Under, the information for being currently located at the people in each room of building 5 or the people positioned at each floor are stored in access management system 3
Information.
Service companies 7 are responsible for being set to the maintenance of the lift appliance 1 of building 5.In the present embodiment, maintenance is shown
Company 7 is responsible for being set to the example of the maintenance of all lift appliances 1 of building 5.Several maintenance personnel are under the jurisdiction of service companies
7.Maintenance personnel is the professional technician about elevator.The maintenance of lift appliance 1 is the maintenance people by being under the jurisdiction of service companies 7
What member carried out.Service companies 7 can carry out two-way communication with monitoring arrangement 2.
The monitoring of monitoring arrangement 2 is set to the lift appliance 1 of building 5.Monitoring arrangement 2 is for example set on building 5.Monitoring arrangement
2 for example with restore signal receiving part 8, number calculation part 9, number information's acquisition unit 10, time calculation part 11, transmission unit 12,
Send plan receiving unit 13, time calculation part 14 and notification unit 15.
Restore signal receiving part 8 and receives information from lift appliance 1.What is sent from lift appliance 1 can restore signal and not
It can restore signal and be resumed the reception of signal receiving part 8.In addition, the multiple elevator device 1 for being set to building 5 can also be by group
Managing device carries out group management.In this case, restore signal receiving part 8 can from group management system receive can be extensive
Complex signal and signal cannot be restored.
Number calculation part 9 calculates the number that can be taken refuge using lift appliance 1 in per unit time.For example, number
Calculation part 9 carries out above-mentioned calculating according in the signal that recovery signal receiving part 8 receives after the earthquake.
Number information's acquisition unit 10 obtains the information for staying in the number of the people in building 5.For example, number information's acquisition unit
10 obtain above- mentioned information from access management system 3 after the earthquake.
Time calculation part 11 calculates the time it takes until the people stayed in building 5 takes refuge.For example, the time counts
Calculation portion 11 is according to above-mentioned to calculate by the calculated number of number calculation part 9 and the information acquired by number information's acquisition unit 10
Time.
Transmission unit 12 sends information to service companies 7.In the example shown in present embodiment, service companies 7 have extensive
Complex system 4.For example, transmission unit 12 will be sent to recovery system 4 by the information of the calculated time of time calculation part 11.
Recovery system 4 for example with send plan generating unit 16.The plan generation of generating unit 16 is sent to be under the jurisdiction of service companies 7
Maintenance personnel send plan.For example, plan generating unit 16 is sent to be generated according to the information of the time sent from transmission unit 12
Send plan.It is sending in the works, is being registered for each maintenance personnel to restore lift appliance and the building to be gone to
Sequence.By send plan generating unit 16 generate send plan to be sent to monitoring arrangement 2.
Plan receiving unit 13 is sent to receive information from service companies 7.In the example shown in present embodiment, plan is sent
Receiving unit 13 sends plan from the reception of recovery system 4.
Time calculation part 14 calculates the time it takes until being set to 1 full recovery of lift appliance of building 5.
Time calculation part 14 sends plan and calculates the above-mentioned time according to by send that plan receiving unit 13 receives.
Notification unit 15 to notify the information in relation to elevator from notifying device 17.Notifying device 17 is for example set on lift appliance 1.Example
Such as, notifying device 17 is made of the display or broadcaster for being set to stop etc..Notifying device 17 can not also be set to lift appliance
1.For example, notifying device 17 is also possible to the portable terminal for identifying that the holder of label is held.Notification unit 15 makes from notice
Device 17 was notified by the calculated time of time calculation part 14.
In the following, the movement for restoring support system is described in detail also referring to Fig. 2~Fig. 4.Fig. 2 is to show lift appliance
The flow chart of 1 movement.
Determine whether to have occurred earthquake (S101) in lift appliance 1.If earthquake does not occur, in lift appliance 1
Usually operated.When detecting earthquake by seismic sensor 6 when usually being operated, carriage stops (S102).Example
Such as, when earthquake has occurred in the movement in carriage, start controlled operation when earthquake.Controlled operation when by carrying out earthquake, sedan-chair
Compartment rests in nearest floor.
When controlled operation have passed through the stipulated time terminating when in lift appliance 1 from earthquake, starting point inspection operating
(S103).Various data are obtained in inspection operating.Acquired data by a reference value or reference range with the data into
Row compares.It can be restored automatically (S104) according to the judgement of above-mentioned comparison result.
If lift appliance 1 does not detect specific exception in inspection operating, be judged to restore (S104:
It is).If lift appliance 1 can restore, signal (S105) can be restored to the transmission of monitoring arrangement 2.Also, lift appliance 1
Automatically restored and start again at usually operating (S106).
Lift appliance 1 is judged to restore (S104: no) when detecting specific exception in inspection operating.Electricity
If ladder device 1 cannot restore, signal (S107) cannot be restored to the transmission of monitoring arrangement 2.Also, lift appliance 1 stop and
It is in standby, until maintenance personnel restore manually (S108).
Fig. 3 is the flow chart for showing the movement of monitoring arrangement 2.Determining whether it has received in monitoring arrangement 2 can restore
Signal cannot restore signal (S201).When earthquake occurs, signal can be restored or cannot be extensive from the transmission of lift appliance 1
Complex signal.In monitoring arrangement 2, signal can be restored and cannot restore signal (S201: yes) by restoring the reception of signal receiving part 8.
When restore signal receiving part 8 receive from all lift appliances 1 for being set to building 5 can restore signal or
Cannot extensive time multiplexed signal, number calculation part 9 calculate per unit time in can be kept away in building 5 using lift appliance 1
Difficult number (S202).For example, number calculation part 9, which calculates in per unit time, to be filled using the elevator for being set to building 5
Set the number that the lift appliance 1 that can restore automatically in 1 is taken refuge.It is also possible to restoring signal receiving part 8 from having
All lift appliances 1 of auto restore facility receive can restore signal or cannot extensive time multiplexed signal, number calculation part 9 into
The processing of row S202 and the processing of following S203.
For example, it is contemplated that the specified number of the carriage of lift appliance 1 is 5 minutes 8 people, carriage lowest levels in building 5
The round-trip example between top layer.Assuming that received from 2 lift appliances 1 in 4 lift appliances 1 can restore signal,
Signal cannot be restored by receiving from 2 lift appliances 1.In this case, number calculation part 9 obtain 3.2 according to the following formula (people/
Minute) calculated result.
8 (people) × 2 (platform)/5 (minute)=3.2 (people/minute) ... (1)
In addition, in the case where starting again at usually operating in the S106 of Fig. 2, without the point executed by maintenance personnel
Inspection.It is usually operated accordingly it is also possible to reduce car speed before by the point executed by maintenance personnel inspection.In this feelings
Under condition, number calculation part 9 for example can will be to the result obtained as formula (1) multiplied by value obtained by coefficient, when being calculated as per unit
Between number.Following formula is the example that coefficient is set as to 0.5.In addition, the value of coefficient is not limited to 0.5.
8 (people) × 2 (platform)/5 (minute) × 0.5=1.6 (people/minute) ... (2)
In addition, receiving in recovery signal receiving part 8 from all lift appliances 1 for being set to building 5 can restore to believe
Number or cannot extensive time multiplexed signal, number information's acquisition unit 10, which obtains, stays in number information (S203) in building 5.For example,
Number information's acquisition unit 10 obtains above- mentioned information from access management system 3.For example, the acquirement of number information's acquisition unit 10 stays in building
Proprietary number information in object 5.
Furthermore it is possible to consider the unfavorable lift appliance 1 of the people for being located at the floor below a certain floor and utilize stair etc. into
The case where row is taken refuge.In the case that room in 3 pairs of disengaging buildings 5 of access management system is managed, number information is taken
The number information of some people stayed in building 5 can also be obtained by obtaining portion 10.For example, number information's acquisition unit 10 can also be with
Obtain the number information of the people in the floor for staying in 5 layers of building 5 or more.
Then, time calculation part 11 calculates the time it takes (S204) until the people stayed in building 5 takes refuge.
Time calculation part 11 calculates the above-mentioned time according to number calculated in S202 and the number information obtained in S203.Example
Such as, considering that number calculation part 9 calculates number per unit time is 1.6 (people/minute), and number information's acquisition unit 10 achieves
The case where 100 people stay in the information in building 5.In this case, time calculation part 11 obtains 62.5 points according to the following formula
The calculated result of clock.
100 (people)/1.6 (people/minute)=62.5 (minute)
Transmission unit 12 will be sent to service companies 7 (S205) by the information of the calculated time of time calculation part 11.It sends
Portion 12 can also will send jointly to service companies 7 by the information of the calculated time of time calculation part 11 and other information.Example
Such as, transmission unit 12 can also be by the information for being judged as irreclaimable lift appliance 1, the exception detected in inspection operating
Information and the information of the number stayed in building 5 be sent to service companies 7.
Fig. 4 is the flow chart for showing the movement of recovery system 4.Determine whether to receive from monitoring arrangement 2 in recovery system 4
The information (S301) by the calculated time of time calculation part 11 is arrived.In addition, service companies 7 are not only responsible for being set to building
The maintenance of 5 lift appliance 1, and be responsible for being set to the maintenance of the lift appliance of other buildings.Therefore, occur in earthquake
When, recovery system 4 also receives the time it takes until completing to take refuge from the monitoring arrangement for being set to other buildings
Information.
Send what plan generating unit 16 generated maintenance personnel according to the information received from multiple monitoring arrangements to send meter
It draws (S302).By send plan generating unit 16 generate send the information of plan to be sent to monitoring arrangement 2 from recovery system 4
(S303)。
After having carried out the transmission of information in S205, determines whether to receive from recovery system 4 in monitoring arrangement 2 and send
Send the information (S206) of plan.When sending plan receiving unit 13 to receive the information for sending plan, time calculation part 14 is calculated
The time it takes (S207) until being set to 1 full recovery of lift appliance of building 5.Notification unit 15 makes from notice
Device 17 notifies the information (S208) by the calculated time of time calculation part 14.
In the example shown in present embodiment, calculate until the people that stays in building 5 using lift appliance 1 take refuge for
The information of calculated time is sent to service companies 7 by only the time it takes.Therefore, service companies 7 can be additionally contemplates that
Situation is taken refuge in building 5 to generate and send plan.Maintenance personnel can be carried out efficiently the elevator dress for being set to building 5
It sets 1 and is set to resuming operation for the lift appliance of other buildings.
In the example shown in present embodiment, plan is sent to calculate until restoring according to what is received from service companies 7
Until time, the information of calculated time is notified from notifying device 17.Therefore, the people in building 5 can learn electricity
When ladder device 1 restores.In addition, can know when take refuge without using the people that lift appliance 1 cannot take refuge.It can subtract
The mental burden of the light people in building 5.
In the example shown in present embodiment, the example for being equipped with multiple elevator device 1 to building 5 has been carried out specifically
It is bright.As described above, 1 lift appliance 1 can also only be arranged to building 5.In this case, if lift appliance 1 can
Automatic to restore, then number calculation part 9 calculates the number that can be taken refuge using lift appliance 1 in per unit time.
Each section shown in label 8-15 indicates the function that monitoring arrangement 2 has.Fig. 5 is the hardware for showing monitoring arrangement 2
The figure of structure.Monitoring arrangement 2 has the processing circuit for example including processor 18 and memory 19 as hardware resource.Monitoring
Device 2 realizes various functions by executing the program being stored in memory 19 by processor 18.
Processor 18 is also referred to as CPU (Central Processing Unit, central processing unit), central processing dress
It sets, processing unit, arithmetic unit, microprocessor, microcomputer or DSP.Memory 19 can use semiconductor memory, magnetic
Disk, floppy disk, CD, compact disk, mini-disk or DVD.The semiconductor memory that can be used include RAM, ROM, flash memory,
EPROM and EEPROM etc..
The some or all of various functions possessed by monitoring arrangement 2 can also be realized by hardware.As reality
The hardware of the function of existing monitoring arrangement 2, can also be using single circuit, compound circuit, programmed process device, multiple programming processing
Device, ASIC, FPGA or their combination.
In addition, plan generating unit 16 is sent to show the function that recovery system 4 has.The hardware configuration of recovery system 4 with
Example shown in fig. 5 is identical.Recovery system 4 has the processing electricity for example including processor and memory as hardware resource
Road.Recovery system 4 realizes above-mentioned various functions by executing program stored in memory by processor.It can also lead to
Hardware is crossed to realize some or all of function that recovery system 4 has.
Equally, the hardware configuration of the control system of lift appliance 1 is identical as example shown in fig. 5.The control of lift appliance 1
System has the processing circuit for example including processor and memory as hardware resource.The control system of lift appliance 1 is logical
It crosses and program stored in memory is executed by processor to realize above-mentioned various functions.Electricity can also be realized by hardware
Function possessed by the control system of ladder device 1 it is some or all.
Industrial availability
Recovery support system of the invention can be suitable for including the system with the lift appliance of auto restore facility.
Label declaration
1 lift appliance;2 monitoring arrangements;3 access management systems;4 recovery systems;5 buildings;6 seismic sensors;7 maintenances
Company;8 restore signal receiving part;9 number calculation parts;10 number information's acquisition units;(the 1st time calculated single 11 time calculation parts
Member);12 transmission units;13 send plan receiving unit;14 time calculation parts (the 2nd time calculating unit);15 notification units;16 send meter
Draw generating unit;17 notifying devices;18 processors;19 memories.
Claims (4)
1. a kind of recovery support system, wherein the recovery supports system to include
Multiple elevator device, they are set to building;And
Monitoring arrangement can be communicated with the service companies of the multiple elevator device,
Can each lift appliance in the multiple elevator device carry out the point inspection for determining restore automatically when earthquake occurs
Operating,
The monitoring arrangement includes
Number computing unit, calculating can be using the energy in the multiple elevator device in per unit time after the earthquake
The number that enough lift appliances restored automatically are taken refuge;
Number information's acquisition unit obtains the information in the number stayed in the building after the earthquake;
1st time calculating unit, basis are obtained by the calculated number of the number computing unit and by the number information
The information that unit obtains calculates the time it takes until the people stayed in the building takes refuge;And
Transmission unit will be sent to the service companies by the information of the 1st time calculating unit calculated time.
2. recovery support system according to claim 1, wherein
The recovery support system, which also has, sends plan generation unit, and it is public that this sends plan generation unit to be set to the maintenance
Department, the maintenance personnel for being under the jurisdiction of the service companies is generated according to the information of the time sent from the transmission unit sends meter
It draws.
3. recovery support system according to claim 1 or 2, wherein
The monitoring arrangement also includes
2nd time calculating unit is calculated according to the information for sending plan received from the service companies until described more
The time it takes until platform lift appliance full recovery;And
Notification unit to notify the information by the 2nd time calculating unit calculated time from notifying device.
4. a kind of recovery support system, wherein the recovery supports system to include
Lift appliance is set to building;And
Monitoring arrangement can be communicated with the service companies for the maintenance for carrying out the lift appliance,
Can the lift appliance carry out the point inspection operating for determining restore automatically when earthquake occurs,
The monitoring arrangement includes
Number computing unit, if can restore automatically in the lift appliance after the earthquake, the number computing unit meter
Calculate the number that can be taken refuge using the lift appliance in per unit time;
Number information's acquisition unit obtains the information in the number stayed in the building after the earthquake;
Time calculating unit, according to by the calculated number of the number computing unit and by number information's acquisition unit
The information of acquirement calculates the time it takes until the people stayed in the building takes refuge;And
Transmission unit will be sent to the service companies by the information of the time calculating unit calculated time.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PCT/JP2016/068417 WO2017221329A1 (en) | 2016-06-21 | 2016-06-21 | Recovery support system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109311628A true CN109311628A (en) | 2019-02-05 |
CN109311628B CN109311628B (en) | 2020-08-07 |
Family
ID=60784484
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201680084657.8A Active CN109311628B (en) | 2016-06-21 | 2016-06-21 | Recovery support system |
Country Status (3)
Country | Link |
---|---|
JP (1) | JP6288391B1 (en) |
CN (1) | CN109311628B (en) |
WO (1) | WO2017221329A1 (en) |
Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01256477A (en) * | 1988-04-05 | 1989-10-12 | Toshiba Corp | Controller for elevator |
JP2000335844A (en) * | 1999-05-27 | 2000-12-05 | Toshiba Corp | Elevator control system |
JP2002114463A (en) * | 2000-10-12 | 2002-04-16 | Hitachi Building Systems Co Ltd | Inspection operation execution method of elevator |
JP3375454B2 (en) * | 1995-05-01 | 2003-02-10 | 三菱電機ビルテクノサービス株式会社 | Elevator seismic control operation device |
JP2003146552A (en) * | 2001-11-14 | 2003-05-21 | Mitsubishi Electric Corp | Operation device of elevator |
JP2005104631A (en) * | 2003-09-29 | 2005-04-21 | Mitsubishi Electric Corp | Control device for elevator |
JP2007119228A (en) * | 2005-10-31 | 2007-05-17 | Toshiba Elevator Co Ltd | Elevator system and operation resuming method for elevator |
CN101016132A (en) * | 2006-02-07 | 2007-08-15 | 株式会社日立制作所 | Elevator control device |
JP2007210713A (en) * | 2006-02-07 | 2007-08-23 | Mitsubishi Electric Building Techno Service Co Ltd | Elevator control system |
CN101233065A (en) * | 2006-08-29 | 2008-07-30 | 三菱电机株式会社 | Method and device for controlling elevator |
JP2009023809A (en) * | 2007-07-20 | 2009-02-05 | Mitsubishi Electric Building Techno Service Co Ltd | Elevator control device and its repairing method |
CN101811635A (en) * | 2009-02-20 | 2010-08-25 | 三菱电机株式会社 | The rope swing detecting device of elevator and control method for operation automaticlly recovering after earthquake |
CN102123932A (en) * | 2009-10-19 | 2011-07-13 | 东芝电梯株式会社 | Rescue operation system for elevator |
CN202346532U (en) * | 2011-10-14 | 2012-07-25 | 东营市宏安电梯有限责任公司 | Elevator emergency management technology supporting system |
JP5118538B2 (en) * | 2008-04-07 | 2013-01-16 | 株式会社日立ビルシステム | Elevator wire rope strand breakage diagnosis system |
CN203164426U (en) * | 2012-11-27 | 2013-08-28 | 广州市寰宇电子科技有限公司 | Elevator detection alarm device |
CN104803248A (en) * | 2014-01-23 | 2015-07-29 | 东芝电梯株式会社 | Elevator control device |
EP3003945A1 (en) * | 2013-05-31 | 2016-04-13 | KONE Corporation | Elevator evacuation system |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4311632B2 (en) * | 2003-09-29 | 2009-08-12 | 三菱電機株式会社 | Elevator control device |
FI118332B (en) * | 2005-10-14 | 2007-10-15 | Kone Corp | Elevator system |
JP2007314263A (en) * | 2006-05-23 | 2007-12-06 | Mitsubishi Electric Corp | Evacuation situation simulating device |
EP2589560A4 (en) * | 2010-06-29 | 2017-11-29 | Mitsubishi Electric Corporation | Control device for elevator |
-
2016
- 2016-06-21 CN CN201680084657.8A patent/CN109311628B/en active Active
- 2016-06-21 WO PCT/JP2016/068417 patent/WO2017221329A1/en active Application Filing
- 2016-06-21 JP JP2017549832A patent/JP6288391B1/en active Active
Patent Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01256477A (en) * | 1988-04-05 | 1989-10-12 | Toshiba Corp | Controller for elevator |
JP3375454B2 (en) * | 1995-05-01 | 2003-02-10 | 三菱電機ビルテクノサービス株式会社 | Elevator seismic control operation device |
JP2000335844A (en) * | 1999-05-27 | 2000-12-05 | Toshiba Corp | Elevator control system |
JP2002114463A (en) * | 2000-10-12 | 2002-04-16 | Hitachi Building Systems Co Ltd | Inspection operation execution method of elevator |
JP2003146552A (en) * | 2001-11-14 | 2003-05-21 | Mitsubishi Electric Corp | Operation device of elevator |
JP2005104631A (en) * | 2003-09-29 | 2005-04-21 | Mitsubishi Electric Corp | Control device for elevator |
JP2007119228A (en) * | 2005-10-31 | 2007-05-17 | Toshiba Elevator Co Ltd | Elevator system and operation resuming method for elevator |
JP2007210713A (en) * | 2006-02-07 | 2007-08-23 | Mitsubishi Electric Building Techno Service Co Ltd | Elevator control system |
CN101016132A (en) * | 2006-02-07 | 2007-08-15 | 株式会社日立制作所 | Elevator control device |
CN101233065A (en) * | 2006-08-29 | 2008-07-30 | 三菱电机株式会社 | Method and device for controlling elevator |
JP2009023809A (en) * | 2007-07-20 | 2009-02-05 | Mitsubishi Electric Building Techno Service Co Ltd | Elevator control device and its repairing method |
JP5118538B2 (en) * | 2008-04-07 | 2013-01-16 | 株式会社日立ビルシステム | Elevator wire rope strand breakage diagnosis system |
CN101811635A (en) * | 2009-02-20 | 2010-08-25 | 三菱电机株式会社 | The rope swing detecting device of elevator and control method for operation automaticlly recovering after earthquake |
CN102123932A (en) * | 2009-10-19 | 2011-07-13 | 东芝电梯株式会社 | Rescue operation system for elevator |
CN202346532U (en) * | 2011-10-14 | 2012-07-25 | 东营市宏安电梯有限责任公司 | Elevator emergency management technology supporting system |
CN203164426U (en) * | 2012-11-27 | 2013-08-28 | 广州市寰宇电子科技有限公司 | Elevator detection alarm device |
EP3003945A1 (en) * | 2013-05-31 | 2016-04-13 | KONE Corporation | Elevator evacuation system |
CN104803248A (en) * | 2014-01-23 | 2015-07-29 | 东芝电梯株式会社 | Elevator control device |
Also Published As
Publication number | Publication date |
---|---|
CN109311628B (en) | 2020-08-07 |
WO2017221329A1 (en) | 2017-12-28 |
JP6288391B1 (en) | 2018-03-07 |
JPWO2017221329A1 (en) | 2018-07-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111099462B (en) | Intelligent robot elevator taking control method and system | |
CN111225866B (en) | Automatic call registration system and automatic call registration method | |
JP2017114670A (en) | Elevator group management control device and group management system as well as elevator system | |
WO2019087242A1 (en) | Elevator operation management system, and operation management method | |
CN110009786A (en) | Invite the method and device and system and storage medium of visitor and visitor's arriving reminding | |
JP2019081622A (en) | Vehicle allocation system of external system cooperation and method | |
CN110228738B (en) | Disaster information processing device and disaster information notification method | |
US20200223660A1 (en) | Remote monitoring system and a method for remotely monitoring an elevator system | |
JP2009298495A (en) | Information distribution system of elevator | |
CN110914875B (en) | Location-based behavior monitoring | |
JP2010006613A (en) | Traffic demand predicting device of elevator | |
US11087564B2 (en) | Person display control device, person display control system and person display control method | |
CN109311628A (en) | Restore support system | |
US20210155453A1 (en) | System and a method for detecting an out-of-operation state of an elevator system | |
JP5597522B2 (en) | Elevator control device and elevator operation system | |
JP6054628B2 (en) | Electric lock control device and electric lock control method | |
EP4136045A1 (en) | An access control system, an elevator system, and a method for controlling an access control system | |
CN115315400B (en) | Prediction system | |
CN110550513A (en) | Elevator dispatching method, system, storage medium and elevator system | |
US20240059525A1 (en) | Elevator control | |
JP7444475B2 (en) | information processing system | |
EP3279879A1 (en) | Activity amount calculation system, activity amount calculation device, activity amount calculation method, and computer-readable recording medium | |
WO2022148895A1 (en) | System, method and computer program for monitoring operating status of elevator | |
JP2016017850A (en) | Structure verification system and structure verification program | |
JP2021158444A (en) | Controller, apparatus control system, upload method, and program |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |