CN109295984A CN201811054506.5A CN201811054506A CN109295984A CN 109295984 A CN109295984 A CN 109295984A CN 201811054506 A CN201811054506 A CN 201811054506A CN 109295984 A CN109295984 A CN 109295984A
Authority
CN
China
Prior art keywords
lattice column
positioning
meet
enough
need
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811054506.5A
Other languages
Chinese (zh)
Inventor
童伟猛
商栏柱
李文旭
张植伟
侯永宾
闫晓冉
甘增岐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN201811054506.5A priority Critical patent/CN109295984A/en
Publication of CN109295984A publication Critical patent/CN109295984A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses lattice column positioning and verticality that one kind can be used in turn, rotate the device and construction method of angle control, the device includes that can have enough to meet the need a section lattice column, connecting screw and former engineering lattice column, the lower end for having enough to meet the need section lattice column is welded with spreading angle steel, side is welded with top angle cleat and upper nut, the upper end of the original engineering lattice column is welded with lower part angle cleat and lower nuts, the upper end of the connecting screw passes through top angle cleat, and it is locked with upper nut, lower end passes through lower part angle cleat, and it is locked with lower nuts, realize the connection that can have enough to meet the need section lattice column and former engineering lattice column, can have enough to meet the need when section lattice column rotates can drive former engineering lattice column to realize synchronization lifting and rotation.The present invention can have enough to meet the need the positioning and rotation angle of section lattice column by adjusting more than ground, realize to the positioning of former engineering lattice column, verticality and the control for rotating angle.

Description

The device and construction method of a kind of positioning of lattice column and verticality, rotation angle control
Technical field
The invention belongs to Construction Techniques for Deep Foundation Pit fields, and in particular to a kind of positioning of lattice column and verticality, rotation angle The device and construction method of control.
Background technique
With the development of Application in Underground Space technology, deep-foundation pit engineering is more and more.Currently, deep foundation pit support form mostly with Lattice column adds based on horizontal support structure form.Lattice column generally uses in crane lifting to stake holes, lifting and concreting In the process, the positioning of lattice column, verticality and rotation angle are not easy to guarantee, and are not easy to adjust after lifting, and the positioning of lattice column is hung down Straight degree and rotation angle control are always the difficult point of Construction control.It is easily horizontally-supported to the later period if above problem control is bad Structure construction impacts, and especially in reverse construction project, lattice column will generally be used as later period formal structure column, such as lattice Column positioning, verticality and rotation angle control are bad, may conflict with later period formal structure column reinforcing bar, or even prominent structural column In addition, cause structural column that can not construct.
Summary of the invention
In order to overcome lattice column positioning in deep-foundation pit engineering in the prior art, verticality and rotation angle not easy to control, lead The technological deficiency for causing deep foundation pit construction difficulty, the present invention provides a kind of positioning of lattice column and verticality, rotation angle to control Device and construction method are lengthened former engineering lattice column to more than ground using that can have enough to meet the need section lattice column, by adjusting on ground The above positioning for lengthening lattice column and rotation angle, and then reach positioning, verticality and the rotation angle for controlling former engineering lattice column The purpose of degree.
The present invention is achieved through the following technical solutions above-mentioned purpose, a kind of lattice column positioning and verticality, rotation angle The device and construction method of control, including a section lattice column, top angle cleat, upper nut, connecting screw, spreading angle can be had enough to meet the need Steel, former engineering lattice column, lower part angle cleat, lower nuts, positioning and plumbing frame, jack, bracket, positioning screw, positioning steel Muscle ring and stake holes, the lower end for having enough to meet the need section lattice column are welded with spreading angle steel, and side is welded with top angle cleat and upper Portion's nut, the upper end of former engineering lattice column are welded with lower part angle cleat and lower nuts, and the upper end of connecting screw passes through top Angle cleat, and locked with upper nut, lower end passes through lower part angle cleat, and is locked with lower nuts, and realizing can have enough to meet the need The connection of section lattice column and former engineering lattice column, can have enough to meet the need can drive former engineering lattice column to realize synchronous rise when section lattice column rotates Drop and rotation.
The device of a kind of above-mentioned lattice column positioning and verticality, rotation angle control, the positioning screw is welded on can Section lattice column upper end is had enough to meet the need, is distributed along front, rear, left and right four direction, is both placed on positioning and plumbing frame, passes through positioning screw Positioning adjusting can be carried out to former engineering lattice column top and rotates the control of angle.
The device of a kind of above-mentioned lattice column positioning and verticality, rotation angle control, positioning and plumbing frame lower end is set It is equipped with jack, is adjusted for flatness, the verticality to former engineering lattice column, jack lower end is placed with bracket, makees For bearing member;
The device of a kind of above-mentioned lattice column positioning and verticality, rotation angle control, the spacer bar ring are welded on former work Journey lattice column lower part is transferred to stake holes, is controlled the positioning of former engineering lattice column lower part.
In general, through the invention it is contemplated above technical scheme is compared with the prior art, can achieve following has Beneficial effect:
1, present invention utilization can have enough to meet the need section lattice column and lengthen former engineering lattice column to more than ground, and in former engineering lattice column Spacer bar ring is arranged in lower part, controls the positioning of lattice column lower part, and top utilization can have enough to meet the need section lattice column for former engineering lattice More than structure column spreading to ground, the positioning and rotation angle of lattice column are lengthened more than ground by adjusting, and then reaches control Positioning, verticality and the purpose for rotating angle of former engineering lattice column;
2, section lattice column of the present invention that has enough to meet the need can separately be had enough to meet the need after the completion of construction operation by rotating connecting screw The connection relationship of section lattice column and former engineering lattice column, will can have enough to meet the need section lattice column together with the top angle cleat welded above, Upper nut and spreading angle steel are hung out from foundation pit, can have enough to meet the need reuse, have been saved deep foundation pit construction operating cost, have been improved Construction efficiency.
Detailed description of the invention
Specific embodiments of the present invention are further described in detail with reference to the accompanying drawing, in which:
Fig. 1 is a kind of lattice column positioning of the present invention and verticality, the overall structure diagram for rotating the device that angle controls;
Fig. 2 is the cross section view of the position 1-1 in Fig. 1;
Fig. 3 is the cross section view of the position 2-2 in Fig. 1;
Fig. 4 is the cross section view of the position 3-3 in Fig. 1;
Fig. 5 is the structural schematic diagram of positioning and plumbing frame of the present invention;
Fig. 6 is the schematic diagram of the present invention for having enough to meet the need section lattice column and former engineering lattice column releasing connection relationship;
In figure: 1- can have enough to meet the need a section lattice column, the top 2- angle cleat, 3- upper nut, 4- connecting screw, 5- spreading angle steel, 6- Former engineering lattice column, the lower part 7- angle cleat, 8- lower nuts, 9- positioning and plumbing frame, 10- jack, 11- bracket, 12- positioning Screw rod, 13- spacer bar ring, 14- stake holes.
Specific embodiment
As shown in Figure 1, for a kind of lattice column positioning of the present invention and the device and construction method of verticality, rotation angle control Overall structure diagram, including section lattice column 1, top angle cleat 2, upper nut 3, connecting screw 4, spreading angle can be had enough to meet the need Steel 5, former engineering lattice column 6, lower part angle cleat 7, lower nuts 8, positioning and plumbing frame 9, jack 10, bracket 11, positioning spiral shell Bar 12, spacer bar ring 13 and stake holes 14, the lower end for having enough to meet the need section lattice column 1 are welded with spreading angle steel 5, and side is welded with Top angle cleat 2 and upper nut 3, the upper end of former engineering lattice column 6 are welded with lower part angle cleat 7 and lower nuts 8, even The upper end for connecing screw rod 4 passes through top angle cleat 2, and is locked with upper nut 3, and lower end passes through lower part angle cleat 7, and under use Portion's nut 8 is locked, and the connection that can have enough to meet the need section lattice column 1 and former engineering lattice column 6 is realized, when can have enough to meet the need the rotation of section lattice column 1 Former engineering lattice column 6 can be driven to realize synchronization lifting and rotation.
As shown in Fig. 2, positioning screw 12, which is welded on, can have enough to meet the need on section lattice column 1 for the cross section view of the position 1-1 in Fig. 1 End is distributed along front, rear, left and right four direction, and positioning screw 12 is both placed on positioning and plumbing frame 9, can by positioning screw 12 To carry out positioning adjusting to former 1 top of engineering lattice column and rotate the control of angle.
As shown in figure 3, spreading angle steel 5, which is welded on, can have enough to meet the need 1 lower end of section lattice column for the cross section view of the position 2-2 in Fig. 1 Four square positions, nested structure is formed with former engineering lattice column 6, so that section lattice column 1 and former engineering lattice column 6 can be had enough to meet the need Angle is identical when connection, realizes the synchronous rotary that can have enough to meet the need section lattice column 1 and former engineering lattice column 6.
As shown in figure 4, for the cross section view of the position 3-3 in Fig. 1, the spacer bar ring 13 is welded on former engineering lattice column 1 lower part is transferred to stake holes 14, is controlled the positioning of former 6 lower part of engineering lattice column.
As shown in figure 5, being the structural schematic diagram of positioning and plumbing frame 9 of the present invention, 9 lower end of positioning and plumbing frame is provided with thousand Jin top 10, for can have enough to meet the need the flatness of section lattice column 1, verticality is adjusted, and then realize to former engineering lattice column 6 Verticality is adjusted, and 10 lower end of jack is placed with bracket 11, as bearing member.
It is positioned in decentralization process and verticality, rotation angle in the use of the present invention, completing lattice column by following steps The control of degree, while realizing being used in turn for the device:
Step 1: progress pile foundation boring, borehole cleaning, descending reinforcing cage and concrete pouring construction first;
Step 2: after the completion of concreting, by bracket 11, jack 10 and vertical adjustment frame 9 are in place and level, and then lift lattice Column;
Step 3: after the spacer bar ring 13 of 6 lower weld of decentralization process Central Plains engineering lattice column is contacted with steel reinforcement cage, completion pair The lower part of former engineering lattice column 6 positions;
Step 4: after the former decentralization to ground elevation of engineering lattice column 6, section lattice column 1 can be had enough to meet the need and passed through with former engineering lattice column 6 Connecting screw 4 is attached, and is guaranteed former engineering lattice column 6 using spreading angle steel 5 and can be had enough to meet the need the angle phase of section lattice column 1 Together, original engineering lattice column 6 can synchronous rotary when can have enough to meet the need the rotation of section lattice column 1;
Step 5: after the former decentralization to designed elevation of engineering lattice column 6, by adjusting positioning screw 12, adjusting can have enough to meet the need a section lattice The positioning and rotation angle of column 1, and then control the positioning and rotation angle at former 6 top of engineering lattice column;
Step 6: by adjusting the jack 10 installed on bracket 11, the verticality that can have enough to meet the need section lattice column 1 is adjusted, and then control It is vertical with ground level to make 6 entire depth directions of former engineering lattice column;
Step 7: after positioning, verticality and rotation angular adjustment meet the requirements, section lattice column 1 and positioning and plumbing frame 9 can be had enough to meet the need Fixation can have enough to meet the need section lattice column 1 by the rotation releasing of connecting screw 4 after pile concrete solidifies and reaches some strength With the connection relationship of former engineering lattice column 6, section lattice column 1 will can be had enough to meet the need together with top angle cleat 2, the top spiral shell welded thereon Mother 3 and spreading angle steel 5 are hung out from foundation pit, can have enough to meet the need reuse, as shown in fig. 6, having enough to meet the need a section lattice to be of the present invention Structure column 1 and former engineering lattice column 6 release the schematic diagram of connection.
As it will be easily appreciated by one skilled in the art that the foregoing is merely illustrative of the preferred embodiments of the present invention, it is not used to The limitation present invention, any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should all include Within protection scope of the present invention.

Claims (2)

1. the device of lattice column positioning and verticality, rotation angle control that one kind can be used in turn, including a section lattice can be had enough to meet the need Column (1), top angle cleat (2), upper nut (3), connecting screw (4), spreading angle steel (5), former engineering lattice column (6), under Portion's angle cleat (7), lower nuts (8), positioning and plumbing frame (9), jack (10), bracket (11), positioning screw (12) and fixed Position reinforced steel bar ring (13), it is characterised in that:
The lower end for having enough to meet the need a section lattice column (1) is welded with spreading angle steel (5), side be welded with top angle cleat (2) and The upper end of upper nut (3), the original engineering lattice column (6) is welded with lower part angle cleat (7) and lower nuts (8);
The upper end of the connecting screw (4) passes through top angle cleat (2), and is locked with upper nut (3), and lower end passes through lower part Angle cleat (7), and locked with lower nuts (8), realize the company that can have enough to meet the need a section lattice column (1) and former engineering lattice column (6) It connects, former engineering lattice column (6) can be driven to realize synchronization lifting and rotation when can have enough to meet the need a section lattice column (1) rotation;
The positioning screw (12), which is welded on, can have enough to meet the need a section lattice column (1) upper end, be distributed along front, rear, left and right four direction, Be placed on positioning and plumbing frame (9), by positioning screw (12) former engineering lattice column (6) top can be carried out positioning adjusting and Rotate the control of angle;
Positioning and plumbing frame (9) lower end is provided with jack (10), is used to the flatness of former engineering lattice column (6), vertical Degree is adjusted, and jack (10) lower end is placed with bracket (11), as bearing member;
The spacer bar ring (13) is welded on former engineering lattice column (6) lower part, and decentralization is interior to stake holes (14), to former engineering lattice The positioning of column (6) lower part is controlled.
2. the construction method of lattice column positioning and verticality, rotation angle control that one kind can be used in turn, it is characterised in that: logical Cross following steps realize lattice column position in decentralization process and verticality, rotation angle control:
S1: progress pile foundation boring, borehole cleaning, descending reinforcing cage and concrete pouring construction first;
S2: after the completion of concreting, immediately by bracket (11), jack (10) and vertical adjustment frame (9) are in place and level, then hang Fill lattice column;
S3: after the spacer bar ring (13) of decentralization process Central Plains engineering lattice column (6) lower weld is contacted with steel reinforcement cage, completion pair The lower part of former engineering lattice column (6) positions;
S4: after former engineering lattice column (6) decentralization to ground elevation, a section lattice column (1) can be had enough to meet the need and former engineering lattice column (6) is logical It crosses connecting screw (4) to be attached, and guarantees former engineering lattice column (6) using spreading angle steel (5) and a section lattice column (1) can be had enough to meet the need Angle it is identical, can have enough to meet the need a section lattice column (1) rotation when original engineering lattice column (6) can synchronous rotary;
S5: after former engineering lattice column (6) decentralization to designed elevation, by adjusting positioning screw (12), adjusting can have enough to meet the need a section lattice The positioning and rotation angle of column (1), and then control the positioning at the top of former engineering lattice column (6) and rotation angle;
S6: by adjusting the jack (10) installed on bracket (11), adjusting can have enough to meet the need the verticality of a section lattice column (1), in turn It is vertical with ground level to control former engineering lattice column (6) entire depth direction;
S7: after the positioning of former engineering lattice column (6), verticality and rotation angular adjustment meet the requirements, a section lattice can be had enough to meet the need Column (1) and positioning and plumbing frame (9) fixation, after pile concrete solidifies and reaches some strength, by rotating connecting screw (4) contact can have enough to meet the need the connection relationship of a section lattice column (1) and former engineering lattice column (6), can have enough to meet the need a section lattice column (1), top Angle cleat (2), upper nut (3) and spreading angle steel (5) are hung out from foundation pit, i.e., reusable.
CN201811054506.5A 2018-09-11 2018-09-11 The device and construction method of a kind of positioning of lattice column and verticality, rotation angle control Pending CN109295984A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811054506.5A CN109295984A (en) 2018-09-11 2018-09-11 The device and construction method of a kind of positioning of lattice column and verticality, rotation angle control

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811054506.5A CN109295984A (en) 2018-09-11 2018-09-11 The device and construction method of a kind of positioning of lattice column and verticality, rotation angle control

Publications (1)

Publication Number Publication Date
CN109295984A true CN109295984A (en) 2019-02-01

Family

ID=65166468

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811054506.5A Pending CN109295984A (en) 2018-09-11 2018-09-11 The device and construction method of a kind of positioning of lattice column and verticality, rotation angle control

Country Status (1)

Country Link
CN (1) CN109295984A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101413264A (en) * 2008-11-20 2009-04-22 上海建工(集团)总公司 Lattice column triaxial automatic wireless real time hanging system and method
CN102493554A (en) * 2011-12-13 2012-06-13 北京城建中南土木工程集团有限公司 Abutting joint device of steel lattice column, and construction method of same
CN205296873U (en) * 2015-11-27 2016-06-08 武汉市汉阳市政建设集团公司 Real -time correction lattice column hang down straightness's device and lattice column installation mechanism
CN106759350A (en) * 2017-01-11 2017-05-31 北京建工土木工程有限公司 A kind of Extra-Deep Foundation Pit vertical lattice column positioning steering control system and application method
CN206625584U (en) * 2017-04-07 2017-11-10 中铁八局集团昆明铁路建设有限公司 It is located at the lattice column accurate positioning device of existing below ground for designing capital

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101413264A (en) * 2008-11-20 2009-04-22 上海建工(集团)总公司 Lattice column triaxial automatic wireless real time hanging system and method
CN102493554A (en) * 2011-12-13 2012-06-13 北京城建中南土木工程集团有限公司 Abutting joint device of steel lattice column, and construction method of same
CN205296873U (en) * 2015-11-27 2016-06-08 武汉市汉阳市政建设集团公司 Real -time correction lattice column hang down straightness's device and lattice column installation mechanism
CN106759350A (en) * 2017-01-11 2017-05-31 北京建工土木工程有限公司 A kind of Extra-Deep Foundation Pit vertical lattice column positioning steering control system and application method
CN206625584U (en) * 2017-04-07 2017-11-10 中铁八局集团昆明铁路建设有限公司 It is located at the lattice column accurate positioning device of existing below ground for designing capital

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
吴念祖: "《虹桥综合交通枢纽地下工程技术》", 28 February 2010, 上海科学技术出版社 *
陈克济: "《地铁工程施工技术》", 30 June 2014, 中国铁道出版社 *

Similar Documents

Publication Publication Date Title
WO2019128155A1 (en) Open caisson construction structure and method
CN104264902B (en) Structure for connecting concrete filled steel tubular column with pile foundation
CN103938616A (en) Underground diaphragm wall steel bar cage structure and construction method thereof
CN202466845U (en) Middle-layer node connecting structure for steel tube concrete column and steel reinforced concrete beam
CN103225301B (en) Root key pushing device suitable for root type tubular pile foundation
CN110016938A (en) A kind of contrary sequence method foundation pit rectangle lattice column positioning and plumbing device
CN203546728U (en) Improved installation fixing device of top-down steel pipe column
CN106958244A (en) The installation and locating method of ultra-deep and large diameter steel pipe column
CN103510541A (en) Device and method for installing steel pipe column to interior of lifting frame hole
CN109183812A (en) The construction method of combined type deep foundation pit supporting structure
CN109629555A (en) Improve the positioning device of empty stake interpolation steel pipe column and the method for pile integrated construction
CN202866304U (en) Reverse-building-method steel pipe column bottom locating device
CN206987509U (en) Supply line's electric pole plants lever apparatus
CN109972847A (en) A kind of positioning of structural column, plumbing device
CN205024719U (en) Pile foundation and integrated reverse construction vertical braces system of underground continuous wall
CN109295984A (en) The device and construction method of a kind of positioning of lattice column and verticality, rotation angle control
CN203821248U (en) Steel pipe arch main arch assembling supporting system
CN108951654A (en) Different cutting depth basement construction method for supporting
JP5189946B2 (en) Pile hole drilling method
CN207567784U (en) Deep basal pit combined type supporting
CN103981810A (en) Steel tube arch main arch splicing and supporting system
CN208563347U (en) Soft Soil Area elevator pit supporting construction
CN2893124Y (en) Derrick support device
CN208501666U (en) A kind of positioning device improving empty stake interpolation steel pipe column
CN105888076B (en) A kind of construction method in corridor waterborne

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190201