CN109293220A - Tie up brick structure and kiln pond - Google Patents
Tie up brick structure and kiln pond Download PDFInfo
- Publication number
- CN109293220A CN109293220A CN201811168035.0A CN201811168035A CN109293220A CN 109293220 A CN109293220 A CN 109293220A CN 201811168035 A CN201811168035 A CN 201811168035A CN 109293220 A CN109293220 A CN 109293220A
- Authority
- CN
- China
- Prior art keywords
- insulation sleeve
- brick
- support
- bolt
- screw rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- C—CHEMISTRY; METALLURGY
- C03—GLASS; MINERAL OR SLAG WOOL
- C03B—MANUFACTURE, SHAPING, OR SUPPLEMENTARY PROCESSES
- C03B5/00—Melting in furnaces; Furnaces so far as specially adapted for glass manufacture
- C03B5/16—Special features of the melting process; Auxiliary means specially adapted for glass-melting furnaces
-
- C—CHEMISTRY; METALLURGY
- C03—GLASS; MINERAL OR SLAG WOOL
- C03B—MANUFACTURE, SHAPING, OR SUPPLEMENTARY PROCESSES
- C03B5/00—Melting in furnaces; Furnaces so far as specially adapted for glass manufacture
- C03B5/02—Melting in furnaces; Furnaces so far as specially adapted for glass manufacture in electric furnaces, e.g. by dielectric heating
- C03B5/027—Melting in furnaces; Furnaces so far as specially adapted for glass manufacture in electric furnaces, e.g. by dielectric heating by passing an electric current between electrodes immersed in the glass bath, i.e. by direct resistance heating
- C03B5/03—Tank furnaces
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Materials Engineering (AREA)
- Organic Chemistry (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Furnace Housings, Linings, Walls, And Ceilings (AREA)
Abstract
The embodiment provides one kind to tie up brick structure and kiln pond, is related to TFT glassmaking art.It includes rack, supporting element, insulation sleeve, elastic component and support device that this, which ties up brick structure, supporting element is connect with rack, one end of insulation sleeve has opening, one end of supporting element is slidably protruded into insulation sleeve by opening, supporting element passes through elastic component and insulation sleeve elastic connection, insulation sleeve is connect far from one end of opening with support device, and support device, which is used to support, ties up brick.Kiln pond includes tying up brick structure, and there is this to tie up the repertoire of brick structure.
Description
Technical field
The present invention relates to TFT glassmaking arts, tie up brick structure and kiln pond in particular to one kind.
Background technique
In the manufacturing of TFT glass, the high-tech special glass such as high intensity, high rigidity ultra-thin glass plate is widely applied,
Being melted for up to 1600 DEG C of glass must be melted.And use tin oxide electrode heating that can reach on 1800 DEG C of fusing points.
Heap electrode made of tin oxide cell electrode is piled up.Kiln side is mounted on by the steel frame of special designing.It is right
Glass metal in pool wall carries out electrified regulation, and to guarantee heating amount, electrical power is higher, and voltage is larger.
Inventor has found under study for action, existing at least to have the disadvantage in that in the related technology
Electric current is possible to from pool wall and ties up outflow from brick structure.
Summary of the invention
The purpose of the present invention includes, for example, providing one kind ties up brick structure, improving the deficiencies in the prior art, capable of leading to
Cross a possibility that setting insulation sleeve reduces electric current outflow.
It is also an objective of the invention that, providing a kind of kiln pond, electric current outflow can be reduced by setting insulation sleeve
A possibility that.
The embodiment of the present invention this can be implemented so that
The embodiment provides one kind to tie up brick structure comprising rack, supporting element, insulation sleeve, elastic component and branch
Support arrangement, the supporting element are connect with the rack, and one end of the insulation sleeve has opening, and one end of the supporting element passes through
The opening slidably protrudes into the insulation sleeve, and the supporting element is connected by the elastic component and the insulation sleeve elasticity
It connects, the one end of the insulation sleeve far from the opening is connect with the support device, and the support device, which is used to support, ties up brick.
Optionally, the supporting element includes screw rod, the first bolt and the second bolt, and the rack is provided with perforating, institute
It states screw rod to be arranged in the perforating, first bolt and second bolt connect and distinguished with the screw flight
Positioned at the two sides of the rack, the screw rod is connect by first bolt and second bolt with the rack, described
One end of screw rod is slidably protruded into the insulation sleeve by the opening.
Optionally, the support device includes third bolt and support rod, and the third bolt and the insulation sleeve are separate
One end of the opening is fixedly connected, and the support rod includes integrally formed thread head and U-shaped support portion, the screw thread
End is located at the middle part of the support portion, and the thread head is connect with the third bolt thread, and the support portion has two
A support end, two support ends, which are used to support, described ties up brick.
Optionally, the support device further includes two supporting blocks, two supporting blocks respectively with two supports
End connection, the supporting block, which is used to support, described ties up brick.
Optionally, the support device further includes steel structure, and two supporting blocks are connect with the steel structure, the steel structure
Side far from the supporting block with the brick of tying up for being bonded.
Optionally, the material of the supporting element is stainless steel, and the material of the insulation sleeve is ceramics, the support device
Material is stainless steel.
Optionally, the elastic component is spring, and the spring is located in the insulation sleeve, and one end of the spring and institute
It states insulation sleeve connection or abuts, the other end of the spring connect or abuts with one end of the screw rod.
Optionally, the brick structure of tying up further includes insulated ring and collets, and the insulated ring is sheathed on the one of the screw rod
It holds and, the inner wall sliding contact of the insulated ring and the insulation sleeve relatively fixed with the screw rod, the collets is located at institute
It states in insulation sleeve, and the collets are located between one end and the spring of the screw rod.
Optionally, the elastic component is spring, second bolt relative to first bolt close to the insulation sleeve,
The spring is arranged the screw rod, and one end of the spring is abutted with second bolt, the other end of the spring and institute
It states insulation sleeve to abut close to one end of the opening, one end that the screw rod protrudes into the insulation sleeve is arranged with insulator, described
The inner wall sliding contact of insulator and the insulation sleeve.
The embodiments of the present invention also provide a kind of kiln ponds comprising mentioned above ties up brick structure, ties up with this
The repertoire of brick structure.
Compared with prior art, the embodiment of the present invention tie up brick structure and the beneficial effect in kiln pond includes, for example:
By the way that insulation sleeve is arranged, it can to insulate between pool wall and rack, reduce the probability that electric current outflow occurs, together
When, the setting of elastic component can to tie up brick and cling on pool wall, easy for assemble or unload.
Detailed description of the invention
In order to illustrate the technical solution of the embodiments of the present invention more clearly, below will be to needed in the embodiment attached
Figure is briefly described, it should be understood that the following drawings illustrates only certain embodiments of the present invention, therefore is not construed as pair
The restriction of range for those of ordinary skill in the art without creative efforts, can also be according to this
A little attached drawings obtain other relevant attached drawings.
Fig. 1 is the structural schematic diagram in kiln pond provided in this embodiment;
Fig. 2 be it is provided in this embodiment the first tie up the structural schematic diagram under the first visual angle of brick structure;
Fig. 3 be it is provided in this embodiment the first tie up the structural schematic diagram under the second visual angle of brick structure;
Fig. 4 is the second provided in this embodiment structural schematic diagram for tying up brick structure;
Fig. 5 is that provided in this embodiment the third ties up the structural schematic diagram of brick structure.
Icon: 100- kiln pond;10- pool wall;20- ties up brick structure;21- rack;22- supporting element;221- screw rod;222-
One bolt;The second bolt of 223-;23- insulation sleeve;24- spring;25- support device;251- third bolt;252- support rod;
2521- thread head;2522- support portion;The first support end of 2523-;The second support end of 2524-;The first supporting block of 253-;254-
Second supporting block;255- steel structure;26- insulated ring;27- collets;28- insulator;30- ties up brick.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention
In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is
A part of the embodiment of the present invention, instead of all the embodiments.The present invention being usually described and illustrated herein in the accompanying drawings is implemented
The component of example can be arranged and be designed with a variety of different configurations.
Therefore, the detailed description of the embodiment of the present invention provided in the accompanying drawings is not intended to limit below claimed
The scope of the present invention, but be merely representative of selected embodiment of the invention.Based on the embodiments of the present invention, this field is common
Technical staff's every other embodiment obtained without creative efforts belongs to the model that the present invention protects
It encloses.
It should also be noted that similar label and letter indicate similar terms in following attached drawing, therefore, once a certain Xiang Yi
It is defined in a attached drawing, does not then need that it is further defined and explained in subsequent attached drawing.
In the description of the present invention, it should be noted that if occur term " center ", "upper", "lower", "left", "right",
The orientation or positional relationship of the instructions such as "vertical", "horizontal", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings,
Either the invention product using when the orientation or positional relationship usually put, be merely for convenience of the description present invention and simplification retouched
It states, rather than the device or element of indication or suggestion meaning must have a particular orientation, be constructed and operated in a specific orientation,
Therefore it is not considered as limiting the invention.
In addition, being only used for distinguishing description if there is term " first ", " second ", " third " etc., and should not be understood as indicating
Or imply relative importance.
In addition, be not offered as requiring component abswolute level or pendency if there is term "horizontal", "vertical", " pendency " etc.,
But it can be slightly tilted.It is not to indicate the knot if "horizontal" only refers to that its direction is more horizontal with respect to for "vertical"
Structure is had to fully horizontally, but can be slightly tilted.
In the description of the present invention, it is also necessary to which explanation is unless specifically defined or limited otherwise, if there is term
" setting ", " installation ", " connected ", " connection " etc. shall be understood in a broad sense, for example, it may be being fixedly connected, be also possible to detachable
Connection, or be integrally connected;It can be mechanical connection, be also possible to be electrically connected;It can be directly connected, centre can also be passed through
Medium is indirectly connected, and can be the connection inside two elements.It for the ordinary skill in the art, can specific feelings
Condition understands the concrete meaning of above-mentioned term in the present invention.
It should be noted that in the absence of conflict, the feature in the embodiment of the present invention can be combined with each other.
Embodiment 1
Referring to FIG. 1, a kind of kiln pond 100 is present embodiments provided, and it is corresponding, it provides one kind and ties up brick structure 20.
Kiln pond 100 includes pool wall 10 and ties up brick structure 20.
Specifically, in conjunction with Fig. 2 and Fig. 3, this tie up brick structure 20 include rack 21, supporting element 22, insulation sleeve 23, elastic component and
Support device 25, supporting element 22 are connect with rack 21, and one end of insulation sleeve 23 has opening, and one end of supporting element 22 passes through opening
It slidably protrudes into insulation sleeve 23, supporting element 22 is by elastic component and 23 elastic connection of insulation sleeve, and insulation sleeve 23 is far from opening
One end connect with support device 25, support device 25, which is used to support, ties up brick 30.
Tying up brick 30 can be understood as needing the brick tied up, and the glass liquid level under high temperature fused state is in pool wall 10, in pool wall
The position of 10 corresponding liquid levels is generally always at erosion state, generally requires in this place and ties up brick 30, that is to say, that in pool wall
Brick 30 is tied up in 10 outside installation.Brick 30 is tied up generally according to certain shape, brick is tied up at the serious position of erosion of electrode, is prevented at this
Glass metal exudation, increases tank furnace service life.
In the present embodiment, rack 21 is the steel frame for being mounted on 10 outside of pool wall, is equipped with thereon for pool wall 10
Interior glass metal carries out the heap electrode of electrified regulation.Rack 21 can select I-steel, channel steel etc..In other embodiments, rack
21 are also possible to individual frame body, are mounted directly on the ground.
One end of supporting element 22 is slidably connected with insulation sleeve 23, and insulation sleeve 23 can play limit to the sliding of supporting element 22
Effect.
The setting of elastic component allows this to tie up brick 30 and produces relative to pool wall 10 so that tying up brick 30 with pool wall 10 is not to contact firmly
Raw lesser displacement, so as to extend tie up brick 30 and pool wall 10 service life.
When in use, by the way that insulation sleeve 23 is arranged, it can to insulate between pool wall 10 and rack 21, reduce and electric current occurs
The probability of outflow, meanwhile, the setting of elastic component can to tie up brick 30 and cling on pool wall 10, easy for assemble or unload.
In conjunction with Fig. 2 and Fig. 3, in the present embodiment, supporting element 22 includes screw rod 221, the first bolt 222 and the second bolt 223,
Rack 21 is provided with perforating, and screw rod 221 is arranged in perforating, the first bolt 222 and the second bolt 223 with screw rod 221
The two sides of rack 21 are threadedly coupled and are located at, screw rod 221 is connected by the first bolt 222 and the second bolt 223 with rack 21
It connects, one end of screw rod 221 is slidably protruded into insulation sleeve 23 by opening.
In general, needing to reserve installation space in rack 21, screw rod 221 passes through the first bolt 222 and the second bolt 223
It is fixed in rack 21.In other embodiments, threaded hole can also be opened in rack 21, screw rod 221 directly with 21 screw thread of rack
It connects relatively fixed to realize.
In the present embodiment, support device 25 includes third bolt 251 and support rod 252, third bolt 251 and insulation sleeve 23
One end far from opening is fixedly connected, and support rod 252 includes integrally formed thread head 2521 and U-shaped support portion 2522,
Thread head 2521 is located at the middle part of support portion 2522, and thread head 2521 is threadedly coupled with third bolt 251, support portion 2522
There are two support ends for tool, and two support ends, which are used to support, ties up brick 30.
Two support ends are respectively the first support end 2523 and the second support end 2524, the first support end 2523 and second
The setting of support end 2524 can make to tying up being more uniformly stressed for brick 30, meanwhile, pass through thread head 2521 and third spiral shell
Bolt 251 is threadedly engaged, and is easily installed and is dismantled.
Specifically, the insulation sleeve 23 is made of ceramics, it can be during molding, by insulation sleeve 23 and third bolt
251 moldings together, are also possible to leave mounting groove when insulation sleeve 23 forms, and third bolt 251 is caught in mounting groove by the later period,
Realization third bolt 251 is relatively fixed with insulation sleeve 23.
In conjunction with Fig. 3, in the present embodiment, support device 25 further includes two supporting blocks, two supporting blocks respectively with two branch
End connection is supportted, supporting block, which is used to support, ties up brick 30.
Two supporting blocks are respectively the first supporting block 253 and the second supporting block 254, and the connection of supporting block and support end can be with
Be it is integrally formed, be also possible to be threadedly engaged, by two supporting blocks, can increase and tie up the contact area of brick 30 so that
Tie up being more uniformly stressed for brick 30.
In the present embodiment, support device 25 further includes steel structure 255, and two supporting blocks are connect with steel structure 255, steel structure 255
Side far from supporting block is used for and ties up brick 30 and be bonded.
Steel structure 255 can be understood as the frame body of steel, or is welded by multiple steel bars, and one side and supporting block connect
It connects, the other side is bonded with brick 30 is tied up, and applies external force to it, will be tied up brick 30 and is firmly fixed on pool wall 10, can to tie up brick
30 are more uniformly stressed.
In the present embodiment, the material of supporting element 22 is stainless steel, and the material of insulation sleeve 23 is ceramics, the material of support device 25
Matter is stainless steel.
Specifically, screw rod 221, the first bolt 222, the second bolt 223, third bolt 251, support rod 252, first support
Block 253, the second supporting block 254 and steel structure 255 can be made of stainless steel.In general, insulation sleeve 23 is made of ceramics,
Insulation effect is preferable, of courses, and can also select the higher insulating materials of hardness in the prior art.
In the present embodiment, elastic component is spring 24, and spring 24 is located in insulation sleeve 23, and one end of spring 24 and insulation sleeve
23 connections abut, and the other end of spring 24 connect or abuts with one end of screw rod 221.
24 uniform force of spring, can make screw rod 221 and insulation sleeve 23 is elastic connection, meanwhile, insulation sleeve 23
The movement of screw rod 221 is limited, so that overall stability is stronger.
It should be noted that elastic component can also select the steel plate of elasticity in other embodiments, it is arranged after bending exhausted
In edge set 23, the elastic connection of screw rod 221 and insulation sleeve 23 equally can be realized.
Optionally, in conjunction with Fig. 4, tying up brick structure 20 further includes insulated ring 26 and collets 27, and insulated ring 26 is sheathed on screw rod
221 one end and, the inner wall sliding contact of insulated ring 26 and insulation sleeve 23 relatively fixed with screw rod 221, collets 27 are located at exhausted
In edge set 23, and collets 27 are located between one end and spring 24 of screw rod 221.
Collets 27 are arranged, and can make the not direct contact spring 24 of screw rod 221, the setting of insulated ring 26 can make
It obtains screw rod 221 and is also not directly contacted with insulation sleeve 23, can further promote insulation effect.
Optionally, in conjunction with Fig. 5, elastic component is spring 24, and the second bolt 223 is relative to the first bolt 222 close to insulation sleeve
23, spring 24 is arranged screw rod 221, and one end of spring 24 is abutted with the second bolt 223, the other end and insulation sleeve 23 of spring 24
It is abutted close to one end of opening, one end that screw rod 221 protrudes into insulation sleeve 23 is arranged with insulator 28, insulator 28 and insulation sleeve 23
Inner wall sliding contact.
The spring 24 is located at the outside of insulation sleeve 23, the elastic connection of screw rod 221 Yu insulation sleeve 23 equally may be implemented, together
When, it is arranged insulator 28 in the end of the screw rod 221, the insulation effect between insulation sleeve 23 and screw rod 221 can be further enhanced
Fruit.
Brick structure 20 is tied up according to one kind provided in this embodiment, the working principle for tying up brick structure 20 is:
By being slidably matched for screw rod 221 and insulation sleeve 23, and the two is elastic connection, can permit tie up brick 30 with
Lesser displacement is generated between pool wall 10, meanwhile, insulation sleeve 23 limits the movement of screw rod 221, ensure that whole steady
Qualitative, insulation sleeve 23, which is adopted, to be made from an insulative material, so that cannot pass through screw rod 221 via the electric current for tying up the outflow of brick 30 flow to rack
On 21.
One kind provided in this embodiment is tied up brick structure 20 and is had at least the following advantages:
Structure is simple, low cost;
It may be implemented to tie up the insulation of brick 30 Yu rack 21, it is possible to prevente effectively from electric current outflows.
In conclusion the present invention provides one kind to tie up brick structure 20, by the way that insulation sleeve 23 is arranged, 10 He of pool wall can be made
It insulate between rack 21, reduces the probability that electric current outflow occurs, meanwhile, the setting of elastic component can to tie up brick 30 and cling to
It is easy for assemble or unload on pool wall 10.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any
In the technical scope disclosed by the present invention, any changes or substitutions that can be easily thought of by those familiar with the art, all answers
It is included within the scope of the present invention.Therefore, protection scope of the present invention should be with the scope of protection of the claims
It is quasi-.
Claims (10)
1. one kind ties up brick structure, which is characterized in that including rack, supporting element, insulation sleeve, elastic component and support device, the branch
Support member is connect with the rack, and one end of the insulation sleeve has opening, and one end of the supporting element can be slided by the opening
Dynamic protrudes into the insulation sleeve, and the supporting element passes through the elastic component and the insulation sleeve elastic connection, the insulation sleeve
One end far from the opening is connect with the support device, and the support device, which is used to support, ties up brick.
2. according to claim 1 tie up brick structure, which is characterized in that the supporting element includes screw rod, the first bolt and
Two bolts, the rack are provided with perforating, and the screw rod is arranged in the perforating, first bolt and described second
Bolt connect with the screw flight and is located at the two sides of the rack, and the screw rod passes through first bolt and institute
It states the second bolt to connect with the rack, one end of the screw rod is slidably protruded into the insulation sleeve by the opening.
3. according to claim 2 tie up brick structure, which is characterized in that the support device includes third bolt and support
Bar, the third bolt are fixedly connected with the insulation sleeve far from one end of the opening, and the support rod includes being integrally formed
Thread head and U-shaped support portion, the thread head is located at the middle part of the support portion, the thread head and described the
The connection of three bolt threads, for support portion tool there are two support end, two support ends, which are used to support, described ties up brick.
4. according to claim 3 tie up brick structure, which is characterized in that the support device further includes two supporting blocks, and two
A supporting block is connect with two support ends respectively, and the supporting block, which is used to support, described ties up brick.
5. according to claim 4 tie up brick structure, which is characterized in that the support device further includes steel structure, described in two
Supporting block is connect with the steel structure, and the steel structure is used to be bonded with the brick of tying up far from the side of the supporting block.
6. according to claim 1-5 tie up brick structure, which is characterized in that the material of the supporting element is stainless
Steel, the material of the insulation sleeve are ceramics, and the material of the support device is stainless steel.
7. tying up brick structure according to claim 2-5 is described in any item, which is characterized in that the elastic component is spring, the bullet
Spring is located in the insulation sleeve, and one end of the spring connect or abuts with the insulation sleeve, the other end of the spring with
One end of the screw rod connects or abuts.
8. according to claim 7 tie up brick structure, which is characterized in that the brick structure of tying up further includes insulated ring and insulation
Block, the insulated ring are sheathed on one end of the screw rod and, the insulated ring and the insulation sleeve relatively fixed with the screw rod
Inner wall sliding contact, the collets are located in the insulation sleeve, and the collets are located at one end and the institute of the screw rod
It states between spring.
9. tying up brick structure according to claim 2-5 is described in any item, which is characterized in that the elastic component is spring, described the
For two bolts relative to first bolt close to the insulation sleeve, the spring is arranged the screw rod, and one end of the spring
It is abutted with second bolt, the other end of the spring is abutted with the insulation sleeve close to one end of the opening, the spiral shell
One end that bar protrudes into the insulation sleeve is arranged with insulator, the inner wall sliding contact of the insulator and the insulation sleeve.
10. a kind of kiln pond, which is characterized in that tie up brick structure including claim 1-9 is described in any item.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811168035.0A CN109293220A (en) | 2018-10-08 | 2018-10-08 | Tie up brick structure and kiln pond |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811168035.0A CN109293220A (en) | 2018-10-08 | 2018-10-08 | Tie up brick structure and kiln pond |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109293220A true CN109293220A (en) | 2019-02-01 |
Family
ID=65161879
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811168035.0A Pending CN109293220A (en) | 2018-10-08 | 2018-10-08 | Tie up brick structure and kiln pond |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109293220A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113390266A (en) * | 2021-04-02 | 2021-09-14 | 山东墨龙石油机械股份有限公司 | Cooling device for transition zone of smelting reduction furnace |
CN115353273A (en) * | 2022-08-15 | 2022-11-18 | 虹阳显示(咸阳)科技有限公司 | Electrode bottom brick-supporting device for liquid crystal substrate glass kiln and mounting method |
CN117088595A (en) * | 2023-08-18 | 2023-11-21 | 青岛融合光电科技有限公司 | Device for delaying damage of side wall bricks of electrode bricks of tank furnace and installation method of device |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6810068B2 (en) * | 2000-10-18 | 2004-10-26 | Saint-Gobain Isover | Electric glass melting furnace, with pivoting wall elements |
CN205635348U (en) * | 2016-05-04 | 2016-10-12 | 东旭科技集团有限公司 | A electric melting furnace for melting glass |
CN206089426U (en) * | 2016-10-09 | 2017-04-12 | 芜湖东旭光电科技有限公司 | Kiln pool wall supporting tool and bearing structure thereof |
CN206858416U (en) * | 2017-04-12 | 2018-01-09 | 彩虹集团新能源股份有限公司 | A kind of device reinforced for kiln tank block |
CN107892464A (en) * | 2017-11-24 | 2018-04-10 | 郑州旭飞光电科技有限公司 | Electrode block puopulsion equipment and electric smelting glass furnace |
-
2018
- 2018-10-08 CN CN201811168035.0A patent/CN109293220A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6810068B2 (en) * | 2000-10-18 | 2004-10-26 | Saint-Gobain Isover | Electric glass melting furnace, with pivoting wall elements |
CN205635348U (en) * | 2016-05-04 | 2016-10-12 | 东旭科技集团有限公司 | A electric melting furnace for melting glass |
CN206089426U (en) * | 2016-10-09 | 2017-04-12 | 芜湖东旭光电科技有限公司 | Kiln pool wall supporting tool and bearing structure thereof |
CN206858416U (en) * | 2017-04-12 | 2018-01-09 | 彩虹集团新能源股份有限公司 | A kind of device reinforced for kiln tank block |
CN107892464A (en) * | 2017-11-24 | 2018-04-10 | 郑州旭飞光电科技有限公司 | Electrode block puopulsion equipment and electric smelting glass furnace |
Non-Patent Citations (1)
Title |
---|
王学普: "浅谈浮法玻璃熔窑的池壁绑砖", 《2016年中国玻璃行业年会暨技术研讨会》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113390266A (en) * | 2021-04-02 | 2021-09-14 | 山东墨龙石油机械股份有限公司 | Cooling device for transition zone of smelting reduction furnace |
CN115353273A (en) * | 2022-08-15 | 2022-11-18 | 虹阳显示(咸阳)科技有限公司 | Electrode bottom brick-supporting device for liquid crystal substrate glass kiln and mounting method |
CN117088595A (en) * | 2023-08-18 | 2023-11-21 | 青岛融合光电科技有限公司 | Device for delaying damage of side wall bricks of electrode bricks of tank furnace and installation method of device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109293220A (en) | Tie up brick structure and kiln pond | |
CN102245519B (en) | Molten glass carrier facility element and glass production system | |
CN203360255U (en) | Novel Platinum channel adopting corrosion-resistant refractory bricks for production of glass substrates | |
CN204497154U (en) | A kind of relay pushing mechanism and relay | |
KR20170068447A (en) | Glass manufacturing device and glass manufacturing method | |
CN105529218B (en) | A kind of relay pushing mechanism and relay | |
CN101236845B (en) | A club contactor for high-voltage appliance | |
CN208284933U (en) | A kind of route mounting rack for architectural engineering | |
CN207368442U (en) | A kind of high-tension switch cabinet with arc-suppression function | |
US20160123667A1 (en) | Electric arc furnace | |
CN204857336U (en) | Outdoor clavate pillar porcelain insulator of 800kV | |
CN210506043U (en) | Insulating block device for fixing TFT liquid crystal glass kiln pool wall bricks | |
CN209016045U (en) | A kind of modified groove profile gate associated transistor | |
CN203447098U (en) | Vacuum electric heating container | |
CN207718957U (en) | A kind of composite insulator of corrosion resistance and good | |
CN2924725Y (en) | Insulated lifting platform | |
CN110015840A (en) | Shaping furnace | |
CN201765898U (en) | Novel dry type hollow shunt electric reactor | |
CN212082015U (en) | Open stove and lead electrical pillar | |
CN218959142U (en) | Super heater wiring fixed support seat for flexible glass production | |
CN203474618U (en) | Electrode water jacket fixing insulating support | |
CN203480944U (en) | 252kV arc extinguishing chamber porcelain bushing | |
CN102910799A (en) | Heating electrode and alkali-free boron-free aluminosilicate glass melting furnace with same | |
CN210945324U (en) | Multi-layer bottom-inserted electrode structure | |
CN208240555U (en) | Disconnecting switch ruggedized construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190201 |
|
RJ01 | Rejection of invention patent application after publication |