CN109286083A - A kind of three-core cable welded joint and its mounting process - Google Patents

A kind of three-core cable welded joint and its mounting process Download PDF

Info

Publication number
CN109286083A
CN109286083A CN201811142048.0A CN201811142048A CN109286083A CN 109286083 A CN109286083 A CN 109286083A CN 201811142048 A CN201811142048 A CN 201811142048A CN 109286083 A CN109286083 A CN 109286083A
Authority
CN
China
Prior art keywords
layer
wrapped
repair
outside
repair layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811142048.0A
Other languages
Chinese (zh)
Inventor
高品银
高海达
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yueqing Huasai Cable Accessories Co Ltd
Original Assignee
Yueqing Huasai Cable Accessories Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yueqing Huasai Cable Accessories Co Ltd filed Critical Yueqing Huasai Cable Accessories Co Ltd
Priority to CN201811142048.0A priority Critical patent/CN109286083A/en
Publication of CN109286083A publication Critical patent/CN109286083A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R4/00Electrically-conductive connections between two or more conductive members in direct contact, i.e. touching one another; Means for effecting or maintaining such contact; Electrically-conductive connections having two or more spaced connecting locations for conductors and using contact members penetrating insulation
    • H01R4/02Soldered or welded connections
    • H01R4/021Soldered or welded connections between two or more cables or wires
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R4/00Electrically-conductive connections between two or more conductive members in direct contact, i.e. touching one another; Means for effecting or maintaining such contact; Electrically-conductive connections having two or more spaced connecting locations for conductors and using contact members penetrating insulation
    • H01R4/02Soldered or welded connections
    • H01R4/026Soldered or welded connections comprising means for eliminating an insulative layer prior to soldering or welding
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R4/00Electrically-conductive connections between two or more conductive members in direct contact, i.e. touching one another; Means for effecting or maintaining such contact; Electrically-conductive connections having two or more spaced connecting locations for conductors and using contact members penetrating insulation
    • H01R4/70Insulation of connections
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R4/00Electrically-conductive connections between two or more conductive members in direct contact, i.e. touching one another; Means for effecting or maintaining such contact; Electrically-conductive connections having two or more spaced connecting locations for conductors and using contact members penetrating insulation
    • H01R4/70Insulation of connections
    • H01R4/72Insulation of connections using a heat shrinking insulating sleeve
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R43/00Apparatus or processes specially adapted for manufacturing, assembling, maintaining, or repairing of line connectors or current collectors or for joining electric conductors
    • H01R43/02Apparatus or processes specially adapted for manufacturing, assembling, maintaining, or repairing of line connectors or current collectors or for joining electric conductors for soldered or welded connections
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/14Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for joining or terminating cables
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/16Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for repairing insulation or armouring of cables

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Cable Accessories (AREA)
  • Processing Of Terminals (AREA)

Abstract

The invention discloses a kind of three-core cable welded joints, it is related to power transmission technology field, the connector includes two cables interconnected and the interior repair layer group for repairing cable and coset of dispatching workers to do on-site repairs, every cable, which includes three, leads core and is coated on three external protection groups led on the outside of core, external protection group successively includes inner restrictive coating, armor, external sheath layer, coset of dispatching workers to do on-site repairs successively includes inner sheath repair layer, armouring repair layer, oversheath repair layer, oversheath repair layer is set as heat-shrinkable T bush, overlapped that both ends are arranged with cold shrink sleeve for external sheath layer and oversheath repair layer.The elastic contractile force of cold shrink sleeve is big, permanent elasticity cladding is able to carry out to the lap-joint at oversheath repair layer both ends, to form interference fit for a long time, effectively increase the relative stability between the both ends and external sheath layer of oversheath repair layer, and cold shrink sleeve can fit in securely the outside of external sheath layer, and then effectively improve the waterproof performance of cable after repair.

Description

A kind of three-core cable welded joint and its mounting process
Technical field
The present invention relates to power transmission technology fields, more particularly, to a kind of three-core cable welded joint and its erector Skill.
Background technique
Fusion formula cable connector is that a kind of utilization is locally heated to and is enough to melt or melt the ends of two sections of cable cores to complete It connects, forms the permanent splice of a continuous cable, be usually applied to the extension and reparation of cable.
In the prior art, the connecting of formula cable connector is fused the following steps are included: 1) peelling off the end of two sections of cables Surrounding layer;2) conductor of two sections of cables is packed into graphite jig, is integrated by the copper liquid fusion of melting;3) pass through polyethylene Insulating tape repairs the insulating layer of cable.
Wherein, during two conductors of exothermic weld, keep cable temperature excessively high without reliable cooling device, be easy Lead to cable plastics aging and influences service life.And it is easy between polyethylene insulation band there are gap to put to generate part Electricity influences the electric property of cable.
And three-core cable welded joint, after three groups being led core and being repaired one by one, it is also necessary to continue to repair lead it is outer on the outside of core Restrictive coating, in the prior art by using the contraction of heat-shrink tube to repair external sheath layer.But it leads core and easily sends out due to three groups Raw offset, at the same cable it is flexible under, the simple easy leak of lap-joint that will will lead to heat-shrink tube and cable using heat-shrink tube, into And its repairing effect is influenced, have much room for improvement.
Summary of the invention
In view of the deficiencies of the prior art, the present invention intends to provide a kind of three-core cable welded joint, have Good waterproof performance.
To achieve the above object, the present invention provides the following technical scheme that
A kind of three-core cable welded joint, interior repair layer group including two cables interconnected and for repairing cable and It dispatches workers to do on-site repairs coset, the every cable, which includes three, leads core and be coated on three external protection groups led on the outside of core, described Interior repair layer group and coset of dispatching workers to do on-site repairs, which are respectively used to repair, leads core and external protection group, and the external protection group successively includes interior shield Jacket layer, armor, external sheath layer, the coset of dispatching workers to do on-site repairs successively include for repairing the inner sheath repair layer of inner restrictive coating, using In armouring repair layer, the oversheath repair layer for repairing external sheath layer of repairing armor, the oversheath repair layer setting For heat-shrinkable T bush, overlapped that both ends are arranged with cold shrink sleeve for the external sheath layer and oversheath repair layer.
By using above-mentioned technical proposal, the elastic contractile force of cold shrink sleeve is big, to the overlap joint at oversheath repair layer both ends Place is able to carry out permanent elasticity cladding, to form interference fit for a long time, effectively increases the both ends of oversheath repair layer and outer Relative stability between restrictive coating, and cold shrink sleeve can fit in securely the outside of external sheath layer, and then effectively improve The waterproof performance of cable after repair.
The present invention is further arranged to: the core of leading successively includes conductor, interior semi-conductive layer, insulating layer, outer semiconducting layer And copper shield, the be connected outer sheath of part of two conductors is equipped with installation set, if the side wall of the installation set is through having Dry deflector hole.
By using above-mentioned technical proposal, by the way that the both ends of two conductors are inserted in installation set, so that it will not loose, into And it is aligned and ensure that the bonding strength of pad, for two conducting wires during exothermic weld, metal copper liquid is by two conductors Again interconnected meanwhile, it is capable to make conductor and installation set solid out of deflector hole flows between installation set and conductor hole Surely it is connected as one, increases the conductive area of conductor and reduce calorific value, enhance the mechanical strength of two conductor connections.This Outside, installation set can prevent from damaging conductor when polishing crator.
The present invention is further arranged to: the interior repair layer group successively includes interior semiconductive repair layer, insulation repair layer, outer Semiconductive repair layer, copper shield repair layer, the interior semiconductive repair layer, insulation repair layer, outer semiconductive repair layer, copper shield Repair layer, which is all made of wrapped mode and wraps up and repair, leads core.
By using above-mentioned technical proposal, corresponding layer in core will be led by wrapped mode and repaired, there is fitting The features such as degree is high, fastness is strong, and by wrapped mode, without being inserted in excessive corresponding reparation set before welding two conductors Pipe, mode of operation are more simple and effective.
The present invention is further arranged to: the interior semiconductive repair layer is formed by semiconductive polyethylene is wrapped, described outer Semiconductive repair layer is formed by semiconductive self-adhesive tape is wrapped.
By using above-mentioned technical proposal, under conditions of meeting reparation material, semiconductive self-adhesive tape has self-adhesion function, It is fixed without fixture or special process, it is easy to operate.
The present invention is further arranged to: the insulation repair layer is formed using insulation pyrocondensation belt is wrapped, and the insulation is repaired Layer can voluntarily be shunk by heating to eliminate interfacial gap and fuse with interior semiconductive repair layer, insulating layer and to form one.
By using above-mentioned technical proposal, insulation pyrocondensation belt first can be voluntarily shunk during heating to eliminate between interface Gap, and then air is discharged, and by wrapped mode, since overlap joint interface is more, be conducive to that more air are discharged, and then avoid Later period cable is punctured due to air remains by electric current;Isolating shrinkable when temperature reaches the fusing point of insulation pyrocondensation belt, after tightening Band can further filling interface gap, and fuse to form one with interior semiconductive repair layer, insulating layer, and the insulation after melting Pyrocondensation belt compared to it is wrapped when it is more smooth, be more advantageous to the reparation of subsequent outer semiconducting layer.
The present invention is further arranged to: the armouring repair layer and copper shield repair layer are all made of respective metal silk braid over braid It is wrapped to form.
By using above-mentioned technical proposal, is brought using corresponding metal wire knitted and repair copper shield and armor, no Only there is good repairing effect, and the structure of metal wire knitted band is highly convenient for winding.
Another object of the present invention is to provide a kind of mounting process of three-core cable welded joint, comprising the following steps:
Step 1, cable handling: by two sections of cables respectively according to external sheath layer, armor, inner restrictive coating, copper shield, outside partly lead Electric layer, insulating layer, interior semi-conductive layer are the longitudinal exploitation cable of sequence, and clear by the interior semi-conductive layer clast between conductor copper wire is clipped in Reason is clean, takes out the filler led between core and external protection group;
Step 2, preset accessory: 1-2 root heat-shrinkable T bush, 2-3 root cold shrink sleeve are inserted in the end of any one section of cable and is slided To external sheath layer;
Step 3, it connects conductor: being aligned conductor by cable three-phase phase-sequence requirement, by two respective conductors insertion installation sets, pass through The mode of exothermic weld is integrally formed corresponding two conductors with installation set fusion, by the cooling device being mounted on conductor So that cable is cooling;
Step 4, be surface-treated: when conductor temperature is cooled to 40-50 DEG C, cut on the outside of installation set extra copper material and by conductor and Installation set surface polishes smooth, according to the connection and surface treatment for similarly completing other two groups of conductors;
Step 5, interface processing: cone shape is cut into the end after insulating layer is exploited, and conical surface is polished smooth, It cuts out chamfering and polishes smooth in end after outer semiconducting layer is exploited;
Step 6, washes of absolute alcohol installation set, conductor, interior semi-conductive layer and insulating layer table first semi-conductive layer in restoring: are used Face, by semiconductive polyethylene tense after out of one wrapped to another interior semi-conductive layer in the outside of semi-conductive layer outside;
Step 7, insulating layer is restored: from the outer of wrapped to another insulating layer in the outside of an insulating layer after insulation pyrocondensation belt is tensed Band-like electric heater is wrapped up in side on the outside of insulation pyrocondensation belt, so that insulation pyrocondensation belt and semiconductive polyethylene, insulating layer fuse It is integrated, is polishing to after cooling smooth;
Step 8, restore outer semiconducting layer: with washes of absolute alcohol insulation repair layer surface, by semiconductive self-adhesive tape tense after On the outside of an outer semiconducting layer on the outside of wrapped to another outer semiconducting layer, semiconductive self-adhesive tape extensibility during wrapped For 180-220%;
Step 9, copper shield is restored: after proof copper-wire braided mesh belt is tensed, wrapped to another copper shield on the outside of a copper shield Layer outside, then proof copper-wire braided mesh belt is fixed on the outside of corresponding copper shield by two constant force springs;
Step 10, it restores filler: leading core for three and close up, the filler under exploitation is placed at former filler, or use glue The bod enters to make at former filler three to lead core as a cylindrical body;
Step 11, inner restrictive coating is restored: from inner restrictive coating outside and wrapped to another inner sheath after water-proof self-adhesion band is tensed Layer outside, winding layer number are reciprocal two layers;
Step 12, it restores armor: armor being polished bright, after stainless steel wire woven mesh belt is tensed on the outside of an armor On the outside of wrapped to another armor, then corresponding armour is fixed at the both ends of stainless steel wire woven mesh belt by two constant force springs It fills on the outside of layer;
Step 13, it restores external sheath layer: two external sheath layer distances and the surface of corresponding armor intersection 90-120mm is beaten Polish it is whole, in the wrapped 1-2 weeks water-proof seal adhesive tape of the burnishing part of two external sheath layers, the pyrocondensation being inserted on external sheath layer in advance Casing moves into the central location of connector, and the both ends of heat-shrinkable T bush are overlapped on respectively on corresponding external sheath layer, water-proof seal adhesive tape It is capped in the both ends of heat-shrinkable T bush, heat-shrinkable T bush is subjected to heat shrink, cold shrink sleeve is moved into heat-shrinkable T bush and outer shield The lap-joint of jacket layer simultaneously extracts internal plastic support out, so that cold shrink sleeve shrinks and packs tightly in heat-shrinkable T bush and external sheath layer On.
By using above-mentioned technical proposal, by the way that the both ends of two conductors are inserted in installation set, so that it will not loose, into And it is aligned and ensure that the bonding strength of pad, for two conducting wires during exothermic weld, metal copper liquid is by two conductors Again interconnected meanwhile, it is capable to make conductor and installation set solid out of deflector hole flows between installation set and conductor hole Surely it is connected as one, increases the conductive area of conductor and reduce calorific value, enhance the mechanical strength of two conductor connections.This Outside, installation set can prevent from damaging conductor when polishing crator.
End after insulating layer is exploited is cut into cone shape and is polished smooth, be more advantageous to eliminate insulation pyrocondensation belt with Overlap joint gap between insulating layer, the end after outer semiconducting layer is exploited are cut out chamfering and are polished smooth, be more advantageous to and disappear Except the overlap joint gap between semiconductive self-adhesive tape and outer semiconducting layer.
Dehydrated alcohol mainly plays cleaning action, simultaneously because semiconductive self-adhesive tape be carried out by way of stickup it is wrapped, By washes of absolute alcohol, it adheres to carrier, is conducive to improve firm pasting degree.In addition, semiconductive self-adhesive tape has good bullet Property, extensibility is that 180-220% can further effectively improve semiconductive self-adhesive tape on insulation repair layer during wrapped Firmness.
By restoring filler, enables to three to lead core as a cylindrical body, dispatch workers to do on-site repairs so as to be conducive to eliminate Coset and the interfacial gap between core is led, and then improves the relative stability for leading core between coset of dispatching workers to do on-site repairs.
Due to for ease of operation, needing first to lead stud for three and open during leading core for reparation three, therefore inciting somebody to action Three are led after core closes up, and can be generated outside distracted stress, by first back and forth winding water-proof self-adhesion band two layers, be realized pre- solid It is fixed, then further packed tightly by stainless steel wire braid over braid and lead core to overcome stress.
It can be improved the degree of interference fit between cold shrink sleeve and external sheath layer by water-proof seal adhesive tape, and then improve shrinkage The leakproofness at casing both ends avoids leak to improve waterproof performance.Meanwhile even certain relaxation occurs for cold shrink sleeve, Water-proof seal adhesive tape can continue to prevent leak as second defence line.
The present invention is further arranged to: in step 1, external sheath layer strips 400-800mm, and armor exposed length retains 30-60mm, inner restrictive coating exposed length retain 20-50mm, and copper shield exposed length retains 200-600mm, outer semiconducting layer Exposed length retains 15-30mm, and insulating layer exposed length retains 50-80mm, and it is 5-10mm that interior semi-conductive layer, which retains length,;In step In rapid 5, cone height is 20-50mm.
It by using above-mentioned technical proposal, reasonably strips length and retains length, can be convenient for welding two conductors While, it is also convenient for the wrapped of each repair layer.
The present invention is further arranged to: step 7, restoring insulating layer: from the outer of an insulating layer after insulation pyrocondensation belt is tensed The outside of side wrapped to another insulating layer repeatedly, until its wrapped outer diameter terminate when being greater than outer semiconducting layer 4-5mm it is wrapped;
The elasticity that wrapped one layer of extensibility is 180-220% on the outside of insulation pyrocondensation belt tightens band, and the both ends that elasticity tightens band pass through High temperature-resistanadhesive adhesive tape is fixed, and is tightened band outside in elasticity and is wrapped up aluminium thermal sheet, wraps up band-like electric heater on the outside of aluminium thermal sheet;
It is tightened in elasticity and is inserted into thermocouple between band and band-like electric heater, and cooling dress is installed at band-like electric heater both ends It sets;
Setting heating temperature is 145-185 DEG C of heating 60-120min, so that insulation pyrocondensation belt and semiconductive polyethylene, insulation Layer fusion is integrated, and is removed cooling device, band-like electric heater, thermocouple, aluminium thermal sheet and elasticity after cooling and is tightened Insulation repair layer is polishing to smooth by band.
By using above-mentioned technical proposal, band is tightened by wrapped on the outside of insulation pyrocondensation belt, stretches 180- tightening band Air can further be discharged under squeezing action after 220% in insulation pyrocondensation belt melting process to eliminate interfacial gap, and molten More consolidation after being integrated has stronger structural strength and structural stability.And it is enabled to using band-like electric heater Insulation pyrocondensation belt thermally equivalent, so that the insulation pyrocondensation belt after melting has more good surface smoothness after the cooling period.
The present invention is further arranged to: semiconductive polyethylene, insulation pyrocondensation belt, semiconductive self-adhesive tape, proof copper-wire braided net It is wrapped that band, water-proof self-adhesion band, stainless steel wire woven mesh belt are all made of half lap scarf joint formula, i.e., is partially overlapped in during wrapped wrapped On interface, another part is overlapped on itself.
It is wrapped by this plate bridging type by using above-mentioned technical proposal, there is higher structural stability after wrapped, To improve the structural strength and stability of cable after reparation.
In conclusion the invention has the following advantages:
1. the elastic contractile force of cold shrink sleeve is big, permanent elasticity cladding is able to carry out to the lap-joint at oversheath repair layer both ends, To form interference fit for a long time, the relative stability between the both ends and external sheath layer of oversheath repair layer is effectively increased, And cold shrink sleeve can fit in securely the outside of external sheath layer, and then effectively improve the waterproof performance of cable after repair;
2. insulation pyrocondensation belt first can be voluntarily shunk during heating to eliminate interfacial gap, and then is discharged air, and by around The mode of packet since overlap joint interface is more is conducive to that more air are discharged, and then avoids later period cable electric because of air residual Stream breakdown;When temperature reaches the fusing point of insulation pyrocondensation belt, insulation pyrocondensation belt after tightening can further filling interface gap, And fuse to form one with interior semiconductive repair layer, insulating layer, and the insulation pyrocondensation belt after melting compared to it is wrapped when it is more flat It is whole, it is more advantageous to the reparation of subsequent outer semiconducting layer;
3. band is tightened by wrapped on the outside of insulation pyrocondensation belt, it can in the case where tightening with the squeezing action after stretching 180-220% Air is discharged further in insulation pyrocondensation belt melting process to eliminate interfacial gap, and fusion be integrated after more consolidation, tool There are stronger structural strength and structural stability.And insulation pyrocondensation belt thermally equivalent is enabled to using band-like electric heater, make Insulation pyrocondensation belt after must melting has more good surface smoothness after the cooling period.
Detailed description of the invention
Fig. 1 is the partial sectional view of embodiment;
Fig. 2 is the structural schematic diagram after the exploitation of embodiment unit cable;
Fig. 3 is a-quadrant enlarged drawing in Fig. 1;
Fig. 4 is B area enlarged drawing in Fig. 1.
Description of symbols: 1, core is led;11, conductor;12, interior semi-conductive layer;13, insulating layer;14, outer semiconducting layer;15, Copper shield;2, external protection group;21, inner restrictive coating;22, armor;23, external sheath layer;3, interior repair layer group;31, interior half Conductive repair layer;32, insulate repair layer;33, outer semiconductive repair layer;34, copper shield repair layer;4, it dispatches workers to do on-site repairs coset;41, interior Sheath repair layer;42, armouring repair layer;43, oversheath repair layer;5, installation set;6, constant force spring;7, cold shrink sleeve.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
It referring to Fig.1, is that (specification is that tri- core of 3kV-35kV is crosslinked poly- second to a kind of three-core cable welded joint disclosed by the invention Alkene cable), the interior repair layer group 3 including two cables interconnected and for repairing cable and coset 4 of dispatching workers to do on-site repairs.Every Cable, which includes three, leads core 1 and is coated on three external protection groups 2 for leading 1 outside of core, interior repair layer group 3 and outer repair layer Group 4, which is respectively used to repair, leads core 1 and external protection group 2.
Referring to Fig. 2, Fig. 3, every lead core 1 from the inside to the outside successively include conductor 11, it is interior semi-conductive layer 12, insulating layer 13, outer Semi-conductive layer 14 and copper shield 15, interior repair layer group 3 successively include for repairing half in interior semi-conductive layer 12 from the inside to the outside Conductive repair layer 31, the insulation repair layer 32 for repairing insulating layer 13 are repaired for repairing the outer semiconductive of outer semiconducting layer 14 Cladding 33, the copper shield repair layer 34 for repairing copper shield 15.Wherein, interior semiconductive repair layer 31 is by semiconductive polyethylene It is formed with wrapped, outer semiconductive repair layer 33 is formed by semiconductive self-adhesive tape is wrapped.
Insulation repair layer 32 is formed using insulation pyrocondensation belt is wrapped, and the insulation repair layer 32 can voluntarily be received by heating Contracting is to eliminate interfacial gap and and interior semiconductive repair layer 31, the fusion formation one of insulating layer 13.
Wherein, the be connected outer sheath of part of two conductors 11 is equipped with installation set 5, and the side wall of the installation set 5 is through having Several deflector holes, two conductors 11 are repaired by way of exothermic weld.
Referring to Fig.1, Fig. 4, external protection group 2 successively include inner restrictive coating 21, armor 22, external sheath layer from the inside to the outside 23, coset of dispatching workers to do on-site repairs 4 successively includes for repairing the inner sheath repair layer 41 of inner restrictive coating 21, for repairing armouring from the inside to the outside Armouring repair layer 42, the oversheath repair layer 43 for repairing external sheath layer 23 of layer 22.Oversheath repair layer 43 is set as heat Heat-Shrinkable Tubings, overlapped that both ends are arranged with cold shrink sleeve 7 for external sheath layer 23 and oversheath repair layer 43.Oversheath repair layer 43 is set It is set to heat-shrinkable T bush, overlapped that both ends are arranged with cold shrink sleeve 7 for external sheath layer 23 and oversheath repair layer 43.
Wherein, armouring repair layer 42 and copper shield repair layer 34 are all made of that respective metal silk braid over braid is wrapped to be formed.
The mounting process of the three-core cable welded joint the following steps are included:
Step 1, cable handling: by two sections of cables respectively according to external sheath layer 23, armor 22, inner restrictive coating 21, copper shield 15, outer semiconducting layer 14, insulating layer 13, interior semi-conductive layer 12 are the longitudinal exploitation cable of sequence, and will be clipped between 11 copper wire of conductor 12 clast of interior semi-conductive layer clean out, take out and lead filler between core 1 and external protection group 2;Wherein, external sheath layer 23 is shelled Except 400-800mm, 22 exposed length of armor retains 30-60mm, and 21 exposed length of inner restrictive coating retains 20-50mm, copper shield 15 exposed length of layer retain 200-600mm, and 14 exposed length of outer semiconducting layer retains 15-30mm, and 13 exposed length of insulating layer is protected 50-80mm is stayed, it is 5-10mm that interior semi-conductive layer 12, which retains length,;
Step 2, preset accessory: 1-2 root heat-shrinkable T bush, 2-3 root cold shrink sleeve 7 are inserted in the end of any one section of cable and is slided To external sheath layer 23;
Step 3, it connects conductor 11: being aligned conductor 11 by cable three-phase phase-sequence requirement, two respective conductors 11 are inserted into installation set 5 It is interior, it fuses corresponding two conductors 11 with installation set 5 and is integrally formed, by being mounted on conductor 11 On cooling device make cable cooling;
Step 4, be surface-treated: when 11 temperature of conductor is cooled to 40-50 DEG C, the extra copper material in 5 outside of cutting installation set will simultaneously be led Body 11 and 5 surface of installation set polish smooth, according to the connection and surface treatment for similarly completing other two groups of conductors 11;
Step 5, interface processing: cone shape is cut into the end after insulating layer 13 is exploited, and conical surface is first used 240# It is polished smooth again with 600# sand paper after sand paper polishing, the end after outer semiconducting layer 14 is exploited cuts out chamfering and with 600# sand Paper polishes smooth;
Step 6, restore in semi-conductive layer 12: first using washes of absolute alcohol installation set 5, conductor 11, interior semi-conductive layer 12 and absolutely 13 surface of edge layer, by semiconductive polyethylene tense after out of one wrapped to another interior semi-conductive layer 12 in the outside of semi-conductive layer 12 Outside;
Step 7, insulating layer 13 is restored: from wrapped to another insulation repeatedly of the outside of an insulating layer 13 after insulation pyrocondensation belt is tensed The outside of layer 13 terminates wrapped when until its wrapped outer diameter is greater than 14 4-5mm of outer semiconducting layer;
The elasticity that wrapped one layer of extensibility is 180-220% on the outside of insulation pyrocondensation belt tightens band, and the both ends that elasticity tightens band pass through High temperature-resistanadhesive adhesive tape is fixed, and is tightened band outside in elasticity and is wrapped up aluminium thermal sheet, band-like electric heating is wrapped up on the outside of aluminium thermal sheet Device;
It is tightened in elasticity and is inserted into thermocouple between band and band-like electric heater, and cooling dress is installed at band-like electric heater both ends It sets;
Setting heating temperature is 145-185 DEG C of heating 60-120min, so that insulation pyrocondensation belt and semiconductive polyethylene, insulation 13 fusion of layer is integrated, and removes cooling device, band-like electric heater, thermocouple, aluminium thermal sheet and elasticity contracting after cooling Insulation repair layer 32 is polishing to smooth by taut band;
Step 8, it restores outer semiconducting layer 14: with the surface of washes of absolute alcohol insulation repair layer 32, semiconductive self-adhesive tape being drawn Next 14 outside of outer semiconducting layer wrapped to another on the outside of an outer semiconducting layer 14, the semiconductive self-adhesive tape is around packet procedures Middle extensibility is 180-220%;
Step 9, copper shield 15 is restored: after proof copper-wire braided mesh belt is tensed, from 15 wrapped to another copper in outside of a copper shield 15 outside of shielded layer, then proof copper-wire braided mesh belt is fixed on corresponding 15 outside of copper shield by two constant force springs 6;
Step 10, it restores filler: leading core 1 for three and close up, the filler under exploitation is placed at former filler, or use glue The bod enters to make at former filler three to lead core 1 as a cylindrical body;
Step 11, inner restrictive coating 21 is restored: on the outside of an inner restrictive coating 21 and wrapped to another interior after water-proof self-adhesion band is tensed 21 outside of restrictive coating, winding layer number are reciprocal two layers;
Step 12, it restores armor 22: armor 22 is polished light, from an armor after stainless steel wire woven mesh belt is tensed Wrapped to another 22 outside of armor in 22 outsides, then fixed the both ends of stainless steel wire woven mesh belt by two constant force springs 6 In corresponding 22 outside of armor;
Step 13, external sheath layer 23 is restored: two 23 distances of external sheath layer with corresponding 22 intersection 90-120mm's of armor Surface polishes flat, and in the wrapped 1-2 weeks water-proof seal adhesive tape of the burnishing part of two external sheath layers 23, is inserted in external sheath layer preparatory Heat-shrinkable T bush on 23 moves into the central location of connector, and the both ends of heat-shrinkable T bush are overlapped on respectively on corresponding external sheath layer 23, Water-proof seal adhesive tape is capped in the both ends of heat-shrinkable T bush;
It is heated with ethane gas spray gun alignment heat-shrinkable T bush, makes its contraction from heat-shrinkable T bush center to two sides heating, by shrinkage Casing 7 moves to the lap-joint of heat-shrinkable T bush and external sheath layer 23 and extracts internal plastic support out, so that cold shrink sleeve 7 is shunk And it packs tightly on heat-shrinkable T bush and external sheath layer 23.
Wherein, semiconductive polyethylene, insulation pyrocondensation belt, semiconductive self-adhesive tape, proof copper-wire braided mesh belt, water-proof self-adhesion band, It is wrapped that stainless steel wire woven mesh belt is all made of half lap scarf joint formula, i.e., is partially overlapped on wrapped interface during wrapped, another portion Divide and is overlapped on itself.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to restrict the invention, all in design structure of the invention Within think of, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of three-core cable welded joint, the interior repair layer group including two cables interconnected and for repairing cable (3) and coset of dispatching workers to do on-site repairs (4), the every cable include three lead core (1) and be coated on three lead it is outer on the outside of core (1) Protective layer group (2), the interior repair layer group (3) and coset of dispatching workers to do on-site repairs (4), which are respectively used to repair, leads core (1) and external protection group (2), it is characterised in that: the external protection group (2) successively include inner restrictive coating (21), armor (22), external sheath layer (23), The coset of dispatching workers to do on-site repairs (4) successively includes for repairing the inner sheath repair layer (41) of inner restrictive coating (21), for repairing armouring Armouring repair layer (42), the oversheath repair layer (43) for repairing external sheath layer (23) of layer (22), the oversheath reparation Layer (43) is set as heat-shrinkable T bush, and overlapped, and both ends are arranged with shrinkage for the external sheath layer (23) and oversheath repair layer (43) Casing (7).
2. a kind of three-core cable welded joint according to claim 1, it is characterised in that: the core (1) of leading successively includes Conductor (11), interior semi-conductive layer (12), insulating layer (13), outer semiconducting layer (14) and copper shield (15), two conductors (11) outer sheath of part of being connected is equipped with installation set (5), and the side wall of the installation set (5) is through there is several deflector holes.
3. a kind of three-core cable welded joint according to claim 2, it is characterised in that: the interior repair layer group (3) according to It is secondary include interior semiconductive repair layer (31), insulation repair layer (32), outer semiconductive repair layer (33), copper shield repair layer (34), The interior semiconductive repair layer (31), insulation repair layer (32), outer semiconductive repair layer (33), copper shield repair layer (34) are adopted It is wrapped up and is repaired with wrapped mode and lead core (1).
4. a kind of three-core cable welded joint according to claim 3, it is characterised in that: the interior semiconductive repair layer (31) it is formed by semiconductive polyethylene is wrapped, the outer semiconductive repair layer (33) is formed by semiconductive self-adhesive tape is wrapped.
5. a kind of three-core cable welded joint according to claim 4, it is characterised in that: the insulation repair layer (32) is adopted Formed with insulation pyrocondensation belt is wrapped, the insulation repair layer (32) can by heating voluntarily shrink with eliminate interfacial gap and and Interior semiconductive repair layer (31), insulating layer (13) fusion form one.
6. a kind of three-core cable welded joint according to claim 2, it is characterised in that: the armouring repair layer (42) and Copper shield repair layer (34) is all made of that respective metal silk braid over braid is wrapped to be formed.
7. a kind of mounting process of three-core cable welded joint according to claim 1, it is characterised in that: including following step Suddenly,
Step 1, cable handling: by two sections of cables respectively according to external sheath layer (23), armor (22), inner restrictive coating (21), copper Shielded layer (15), outer semiconducting layer (14), insulating layer (13), interior semi-conductive layer (12) are the longitudinal exploitation cable of sequence, and will folder Interior semi-conductive layer (12) clast between conductor (11) copper wire is cleaned out, and filling out between core (1) and external protection group (2) is led in taking-up Fill object;
Step 2, preset accessory: 1-2 root heat-shrinkable T bush, 2-3 root cold shrink sleeve (7) are inserted in from the end of any one section of cable and is slided It moves on external sheath layer (23);
Step 3, conductor (11) are connected: is aligned conductor (11) by cable three-phase phase-sequence requirement, two respective conductors (11) is inserted into In installation set (5), fuses corresponding two conductors (11) with installation set (5) and be integrally formed, pass through Crossing the cooling device being mounted on conductor (11) makes cable cooling;
Step 4, be surface-treated: when conductor (11) temperature is cooled to 40-50 DEG C, the extra copper material in cutting installation set (5) outside is simultaneously Conductor (11) and installation set (5) surface are polished smooth, at the connection and surface for similarly completing other two groups of conductors (11) Reason;
Step 5, interface processing: cone shape is cut into the end after insulating layer (13) exploitation, and conical surface is polished It is smooth, chamfering is cut into out in the end after outer semiconducting layer (14) exploitation and is polished smooth;
Step 6, washes of absolute alcohol installation set (5), conductor (11), interior semi-conductive layer first semi-conductive layer (12) in restoring: are used (12) and insulating layer (13) surface the outside of semi-conductive layer (12) is wrapped to another out of one after, semiconductive polyethylene is tensed The outside of interior semi-conductive layer (12);
Step 7, insulating layer (13) are restored: from wrapped to another insulation in outside of an insulating layer (13) after insulation pyrocondensation belt is tensed The outside of layer (13), wraps up band-like electric heater on the outside of insulation pyrocondensation belt, so that insulation pyrocondensation belt and semiconductive polyethylene, Insulating layer (13) fusion is integrated, and is polishing to after cooling smooth;
Step 8, restore outer semiconducting layer (14): with washes of absolute alcohol insulation repair layer (32) surface, by semiconductive self-adhesion After band tension on the outside of an outer semiconducting layer (14) on the outside of wrapped to another outer semiconducting layer (14), the semiconductive self-adhesive tape exists Extensibility is 180-220% during wrapped;
Step 9, copper shield (15) are restored: wrapped to another from a copper shield (15) outside after proof copper-wire braided mesh belt is tensed On the outside of one copper shield (15), then proof copper-wire braided mesh belt is fixed on corresponding copper shield by two constant force springs (6) (15) outside;
Step 10, it restores filler: leading core (1) for three and close up, the filler under exploitation is placed at former filler, or use Clay, which is filled at former filler, makes three to lead core (1) as a cylindrical body;
Step 11, inner restrictive coating (21) are restored: on the outside of an inner restrictive coating (21) and wrapped to another after water-proof self-adhesion band is tensed On the outside of one inner restrictive coating (21), winding layer number is reciprocal two layers;
Step 12, armor (22) are restored: armor (22) is polished bright, from an armour after stainless steel wire woven mesh belt is tensed It fills on the outside of layer (22) on the outside of wrapped to another armor (22), then passes through two constant force springs (6) for stainless steel wire woven mesh belt Both ends be fixed on the outside of corresponding armor (22);
Step 13, external sheath layer (23) are restored: two external sheath layer (23) distances and corresponding armor (22) intersection 90- The surface of 120mm polishes flat, in the wrapped 1-2 weeks water-proof seal adhesive tape of the burnishing part of two external sheath layers (23), preparatory set Enter the central location that the heat-shrinkable T bush on external sheath layer (23) moves into connector, the both ends of heat-shrinkable T bush are overlapped on corresponding outer respectively On restrictive coating (23), water-proof seal adhesive tape is capped in the both ends of heat-shrinkable T bush, and heat-shrinkable T bush is carried out heat shrink, will be cold Heat-Shrinkable Tubings (7) move to the lap-joint of heat-shrinkable T bush and external sheath layer (23) and extract internal plastic support out, so that shrinkage set Pipe (7) shrinks and packs tightly on heat-shrinkable T bush and external sheath layer (23).
8. a kind of mounting process of three-core cable welded joint according to claim 7, it is characterised in that: in step 1, External sheath layer (23) strips 400-800mm, and armor (22) exposed length retains 30-60mm, inner restrictive coating (21) exposed length Retain 20-50mm, copper shield (15) exposed length retains 200-600mm, and outer semiconducting layer (14) exposed length retains 15- 30mm, insulating layer (13) exposed length retain 50-80mm, and it is 5-10mm that interior semi-conductive layer (12), which retains length,;In steps of 5, Cone height is 20-50mm.
9. a kind of mounting process of three-core cable welded joint according to claim 7, it is characterised in that: step 7, reduction Insulating layer (13): from the outer of the outside of an insulating layer (13) wrapped to another insulating layer (13) repeatedly after insulation pyrocondensation belt is tensed Side terminates wrapped when until its wrapped outer diameter is greater than outer semiconducting layer (14) 4-5mm;
The elasticity that wrapped one layer of extensibility is 180-220% on the outside of insulation pyrocondensation belt tightens band, and the both ends that elasticity tightens band pass through High temperature-resistanadhesive adhesive tape is fixed, and is tightened band outside in elasticity and is wrapped up aluminium thermal sheet, wraps up band-like electric heater on the outside of aluminium thermal sheet;
It is tightened in elasticity and is inserted into thermocouple between band and band-like electric heater, and cooling dress is installed at band-like electric heater both ends It sets;
Setting heating temperature is 145-185 DEG C of heating 60-120min, so that insulation pyrocondensation belt and semiconductive polyethylene, insulation Layer (13) fusion is integrated, and removes cooling device, band-like electric heater, thermocouple, aluminium thermal sheet and elasticity after cooling Band is tightened, insulation repair layer (32) is polishing to smooth.
10. a kind of mounting process of three-core cable welded joint, feature according to claim 7-9 any one exist In: semiconductive polyethylene, insulation pyrocondensation belt, semiconductive self-adhesive tape, proof copper-wire braided mesh belt, water-proof self-adhesion band, stainless steel wire are compiled It is wrapped that knitmesh band is all made of half lap scarf joint formula, i.e., be partially overlapped on wrapped interface during wrapped, another part be overlapped in from With.
CN201811142048.0A 2018-09-28 2018-09-28 A kind of three-core cable welded joint and its mounting process Pending CN109286083A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811142048.0A CN109286083A (en) 2018-09-28 2018-09-28 A kind of three-core cable welded joint and its mounting process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811142048.0A CN109286083A (en) 2018-09-28 2018-09-28 A kind of three-core cable welded joint and its mounting process

Publications (1)

Publication Number Publication Date
CN109286083A true CN109286083A (en) 2019-01-29

Family

ID=65182436

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811142048.0A Pending CN109286083A (en) 2018-09-28 2018-09-28 A kind of three-core cable welded joint and its mounting process

Country Status (1)

Country Link
CN (1) CN109286083A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110011232A (en) * 2019-03-28 2019-07-12 北京首都机场动力能源有限公司 A kind of interconnection method of 10kV three-core cable
CN110492397A (en) * 2019-09-12 2019-11-22 国网黑龙江省电力有限公司哈尔滨供电公司 A kind of multi-purpose Quick repairing device and its application method of insulating of electric power
CN110943310A (en) * 2019-12-17 2020-03-31 北京航星机器制造有限公司 Connecting terminal connecting structure and processing method thereof
CN111326865A (en) * 2020-03-03 2020-06-23 中海石油(中国)有限公司 Connector suitable for oil well is three-phase power round cable in pit
WO2020253085A1 (en) * 2019-06-19 2020-12-24 东部超导科技(苏州)有限公司 Connection method for ybco superconducting material-based superconducting cable
CN112421558A (en) * 2020-12-01 2021-02-26 深圳供电局有限公司 Power cable intermediate head protector
CN113937589A (en) * 2021-11-05 2022-01-14 华能安阳能源有限责任公司 Cable connection construction process
CN114050517A (en) * 2021-09-24 2022-02-15 宁波东方电缆股份有限公司 Manufacturing process of middle wrapping fusion type soft joint of three-core cable

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102904140A (en) * 2012-09-28 2013-01-30 北京星航机电设备厂 Cable shielding layer splicing method
CN106329268A (en) * 2016-08-17 2017-01-11 长园电力技术有限公司 Wrapping and molding manufacturing method for middle connector of cross-linked polyethylene insulated power cable
CN106451256A (en) * 2016-11-24 2017-02-22 深圳供电局有限公司 Improved art with cable joint thermal contraction installation
CN108233282A (en) * 2018-01-17 2018-06-29 长园电力技术有限公司 A kind of power cable scene welded-connecting type belting type straight coupling technique
CN108292021A (en) * 2015-06-03 2018-07-17 康宁光电通信有限责任公司 With the fiber optic cables for bonding core element

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102904140A (en) * 2012-09-28 2013-01-30 北京星航机电设备厂 Cable shielding layer splicing method
CN108292021A (en) * 2015-06-03 2018-07-17 康宁光电通信有限责任公司 With the fiber optic cables for bonding core element
CN106329268A (en) * 2016-08-17 2017-01-11 长园电力技术有限公司 Wrapping and molding manufacturing method for middle connector of cross-linked polyethylene insulated power cable
CN106451256A (en) * 2016-11-24 2017-02-22 深圳供电局有限公司 Improved art with cable joint thermal contraction installation
CN108233282A (en) * 2018-01-17 2018-06-29 长园电力技术有限公司 A kind of power cable scene welded-connecting type belting type straight coupling technique

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110011232A (en) * 2019-03-28 2019-07-12 北京首都机场动力能源有限公司 A kind of interconnection method of 10kV three-core cable
WO2020253085A1 (en) * 2019-06-19 2020-12-24 东部超导科技(苏州)有限公司 Connection method for ybco superconducting material-based superconducting cable
CN110492397A (en) * 2019-09-12 2019-11-22 国网黑龙江省电力有限公司哈尔滨供电公司 A kind of multi-purpose Quick repairing device and its application method of insulating of electric power
CN110943310A (en) * 2019-12-17 2020-03-31 北京航星机器制造有限公司 Connecting terminal connecting structure and processing method thereof
CN111326865A (en) * 2020-03-03 2020-06-23 中海石油(中国)有限公司 Connector suitable for oil well is three-phase power round cable in pit
CN111326865B (en) * 2020-03-03 2021-08-06 中海石油(中国)有限公司 Connector suitable for oil well is three-phase power round cable in pit
CN112421558A (en) * 2020-12-01 2021-02-26 深圳供电局有限公司 Power cable intermediate head protector
CN112421558B (en) * 2020-12-01 2022-06-21 深圳供电局有限公司 Power cable intermediate head protector
CN114050517A (en) * 2021-09-24 2022-02-15 宁波东方电缆股份有限公司 Manufacturing process of middle wrapping fusion type soft joint of three-core cable
CN113937589A (en) * 2021-11-05 2022-01-14 华能安阳能源有限责任公司 Cable connection construction process
CN113937589B (en) * 2021-11-05 2024-03-19 华能安阳能源有限责任公司 Cable connection construction process

Similar Documents

Publication Publication Date Title
CN109286083A (en) A kind of three-core cable welded joint and its mounting process
CN109616962A (en) A kind of hot melten type cable centre connection mounting process
CN107994517B (en) 10kV to 35kV cable craft fusing type straight coupling production method
CN100544146C (en) The device that is used to cover the method for elongate object and is used for covering said elongate object
CN106451313B (en) A kind of DC ultra-high-voltage crosslinked cable connecting hose and manufacture craft
CN113555840B (en) Manufacturing process of self-melting insulating tape wrapping intermediate joint
EP1966863B1 (en) Joining method and related junction for electric cables
CN203367959U (en) A cable intermediate connector
JPH026286B2 (en)
JPH0475604B2 (en)
CN207368584U (en) Crosslinking polyethylene-insulated cable insulation shields isolating joint
CN106329268A (en) Wrapping and molding manufacturing method for middle connector of cross-linked polyethylene insulated power cable
CN105552791A (en) Method for making 10KV heat-shrinkable three-core cross-linked polyethylene cable intermediate joint
CN106024133A (en) Crosslinked polyethylene welding type insulated cable joint and manufacturing and installation processes thereof
CN110350451A (en) Manufacturing method of high-voltage crosslinked polyethylene insulated cable molding type insulated joint
CN109216966A (en) A kind of recovery cable body structure jointing and its method
CN207705751U (en) A kind of cable intermediate joint
CN107123956A (en) A kind of intermediate joint of electric cable welding and renovation technique
JPH01152038A (en) Thermal recovery article
CN110310766B (en) Cable multilayer hot melt sealing joint and installation device
CN108134343A (en) A kind of emergency repair method of three-core cable
CN208190228U (en) A kind of crosslinked cable hot melting connector
CN214900135U (en) Intermediate joint of wrapped insulated cable
CN209375031U (en) A kind of hot melten type cable intermediate connection structure
CN208445262U (en) A kind of transition joint restoring the connection of cable body structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190129

RJ01 Rejection of invention patent application after publication