CN109284868A - A kind of petroleum production engineering scheme generation method and device - Google Patents

A kind of petroleum production engineering scheme generation method and device Download PDF

Info

Publication number
CN109284868A
CN109284868A CN201811093544.1A CN201811093544A CN109284868A CN 109284868 A CN109284868 A CN 109284868A CN 201811093544 A CN201811093544 A CN 201811093544A CN 109284868 A CN109284868 A CN 109284868A
Authority
CN
China
Prior art keywords
module
data
design
engineering
oil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811093544.1A
Other languages
Chinese (zh)
Inventor
杜敬国
王臣君
李开俊
张卓旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China University of Science and Technology
Original Assignee
North China University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China University of Science and Technology filed Critical North China University of Science and Technology
Priority to CN201811093544.1A priority Critical patent/CN109284868A/en
Publication of CN109284868A publication Critical patent/CN109284868A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/02Agriculture; Fishing; Mining

Abstract

The invention discloses a kind of petroleum production engineering schemes generation devices of oil field development technical field, including data platform module, second data analysis module, data download module, first Data Analysis Services module, multiple groups oil recovery subscheme generation module, first data acquisition module, number transmission module, database, final oil recovery schemes generation module, third Data Analysis Services module, second data acquisition module, petroleum production engineering schemes generation module and internet end, by modules match and, design complete scheme, the shared of data is realized by several transmission modules and internet end, internal staff can be thought apparatus main body supplement by internet end and improve data, so that conceptual design is more in line with actual needs, so that the design compilation work of the petroleum production engineering scheme of this programme is more orderly, more rationally, it is more efficient.

Description

A kind of petroleum production engineering scheme generation method and device
Technical field
The invention discloses a kind of petroleum production engineering scheme generation method and devices, specially oil field development technical field.
Background technique
Oil field development is a huge and complicated system engineering, before oil field puts into formal exploitation, it is necessary to establishment oil Overall construction scheme is developed in field, as oilfield economic, the directive document of Efficient Development.Petroleum production engineering scheme is overall plan The core that important component and scheme are implemented.
Currently, the petroleum production engineering mode of each oil field even constituent parts establishment is different, between the establishment of each subscheme Without adequately realizing the shared and data transmitting of data, the level of authorized personnel is also irregular, affects to a certain extent How the compiling level of scheme makes the design compilation of petroleum production engineering scheme work more orderly, more reasonable, more efficient as each oil field The major issue faced, for this purpose, we have proposed a kind of petroleum production engineering scheme generation methods and device to come into operation, on solving State problem.
Summary of the invention
The purpose of the present invention is to provide a kind of petroleum production engineering scheme generation method and devices, to solve above-mentioned background technique The problem of middle proposition.
To achieve the above object, the invention provides the following technical scheme: a kind of petroleum production engineering schemes generation device, including number According to console module, the second data analysis module, data download module, the first Data Analysis Services module, multiple groups oil recovery subscheme Generation module, the first data acquisition module, number transmission module, database, final oil recovery schemes generation module, the analysis of third data Processing module, the second data acquisition module, petroleum production engineering schemes generation module and internet end;
The output end and data download module of the data platform module are electrically connected, the output of the data download module End is electrically connected with the first Data Analysis Services module, the output end and multiple groups oil recovery subscheme of first Data Analysis Services Generation module is electrically connected, and the output end of the multiple groups oil recovery subscheme generation module electrically connects with the first data acquisition module It connects, the output end of first data acquisition module and the second Data Analysis Services module are electrically connected, second data point The output end and oil recovery schemes generation module for analysing module are electrically connected, the output end of the oil recovery schemes generation module and the second number It is electrically connected according to acquisition module, output end and the third Data Analysis Services module of second data acquisition module electrically connect It connects, the output end of the third Data Analysis Services module and final oil recovery schemes generation module are electrically connected, under the data Carry the defeated of module, multiple groups oil recovery subscheme generation module, petroleum production engineering schemes generation module and final oil recovery schemes generation module Outlet is electrically connected with database, first data acquisition module, the second data acquisition module, number transmission module, first Data Analysis Services module, the second Data Analysis Services module, third Data Analysis Services module and electrically two-way with database Connection, the data transmission module are electrically bi-directionally connected with internet end;
The downloading content of the data download module includes oil field geologic basic data module, reservoir engineering basic data mould Block, petroleum production engineering basic data module and domestic and international associated oil field processing scheme basic data module;
In the multiple groups subscheme design module, petroleum production engineering schemes generation module and final oil recovery schemes generation module Forgiving has conceptual design module, data computation module, graphic plotting module, macroeconomy evaluation module and instrument and equipment selection mould Block;
The conceptual design module includes drilling engineering design module, petroleum production engineering design module and ground surface works design mould Block;
Petroleum production engineering design module includes that Water Injection Engineering design module, oil production method selecting module, process matched therewith are set It counts module and oil field dynamic research monitor system designs module.
Preferably, the oil field geologic basic data module includes Geologic Structure Feature, STRATIGRAPHIC DIVISION and lithologic character, storage Layer feature, Oil Reservoir Types and oil, gas and water distribution, the reservoir engineering basic data module includes the composition and property of reservoir fluid Matter, reservoir pressure and temperature, reservoir rock seepage flow characteristics, formation testing and pilot production achievement and well test data explanation results, Oil Reservoir Types And prediction result, the oil of driving method, oil field development series of strata and development scheme and well net deployment, oil well productivity distribution and its variation Field development index predication, the petroleum production engineering basic data module include system protection oil reservoir, reservoir sensitivity, crustal stress situation And application.
Preferably, the design content of the drilling engineering design module includes meeting safety, economic and scientific principle;Oil reservoir The requirement of engineering and petroleum production engineering, drilling well basic condition and analysis, formation pore pressure, formation fracture pressure and formation collapse Pressure prediction, drilling well refractory gold ores and relevant art countermeasure, well type and drilling mode select, well structure design, drilling equipment It is required that well control requires, drilling technology requirement, drilling fluid conceptual design, reservoir protection requirement, completion requirements and well cementation scheme are set Meter completes the design of production pipe sleeve, gun perforation process conceptual design and operation measure, healthy and safe environmental management, drilling period prediction And drilling engineering investment estimation;For special oil field development, drilling engineering conceptual design should embody its specific aim;Oilfield adjustment bores Well full scale constructed wetland project design, since the production in oil field changes the strata pressure of original production layer, Oilfield adjustment spudder Journey conceptual design should also propose special supplement for the feature after production layer, that is, reservoir property variation in addition to the above Content and requirement.
Preferably, the Water Injection Engineering design module includes reservoir sensitivity to the impact analysis of water filling and the technology that should be taken Measure, water injection well bottom pressure and well head pressure design, water injection string design, water injection well throw metaideophone and management design, described to adopt Oily mode selecting module includes principle, foundation and the requirement of artificial lifting way selection, and oil well produces capability forecasting and analysis and lifting side The overall merit of formula, the process matched therewith design module include de-plugging process design, the design of oil-water well sand-preventing process, anti-ceroplastic Design, oilwell water shutoff process planning, antiscale and anticorrosion process design etc., the oil field dynamic research supervision design module includes oil The preliminary budget of field dynamic monitoring collectivity Scheme Design, the matched instrument and equipment of selection and oil field dynamic research monitoring expense.
Preferably, the ground surface works design module includes mating plant stand design and team foundation design.
Preferably, the economic benefit after the macroeconomy evaluation module includes the assessment of oil recovery program budget and puts into production Assessment.
Preferably, when in use, by basic data needed for data platform downloading, by the first Data Analysis Services mould Block processing, then by multiple groups oil recovery subscheme generation module produce oil recovery scheme, staff by related multiple groups oil recovery subscheme into Row is tested one by one, records data and problem during multiple subschemes progress are tested one by one, data and problem are passed through data Transmission module is transferred to the first data acquisition module, by the second Data Analysis Services resume module, passes through petroleum production engineering scheme Generation module production decision compares and selects suitable one group of petroleum production engineering scheme, then this scheme is tested, according to test feelings Condition come adjust and improve this scheme and determine final scheme, in the process, the information material of modules is deposited into database In, database, by data transmission to internet end, carries out information sharing by data transmission module, this internet end is insider Member is dedicated, and internal staff can also carry out data supplement and perfect as needed, so that scheme is more in line with actual demand, so that this The design compilation work of the petroleum production engineering scheme of scheme is more orderly, more reasonable, more efficient.
Compared with prior art, the beneficial effects of the present invention are: this programme is recovered the oil by the step of scheme working system Full scale constructed wetland project design assists the completion for completing oil recovery scheme equipped with device compatible with scheme working system, according to oil field development Integral deployment and programming principle and requirement, are analyzed, preparation package in the data downloaded by data download module, During this, data information, there are also the data of the production of scheme to be stored in database for the processing and analysis of data, passes through data It transmits defeated module and transfers data to internet end progress data sharing, this internet end is that internal staff is dedicated, passes through interconnection End is netted, staff can supplement data needed for writing petroleum production engineering scheme and perfect, so that scheme is more in line with reality Border demand.
Detailed description of the invention
Fig. 1 is present system block diagram.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Referring to Fig. 1, the present invention provides a kind of technical solution: a kind of petroleum production engineering schemes generation device, including data are flat Platform module, the second data analysis module, data download module, the first Data Analysis Services module, multiple groups oil recovery subscheme generate Module, the first data acquisition module, number transmission module, database, final oil recovery schemes generation module, third Data Analysis Services Module, the second data acquisition module, petroleum production engineering schemes generation module and internet end;
The output end and data download module of the data platform module are electrically connected, the output of the data download module End is electrically connected with the first Data Analysis Services module, the output end and multiple groups oil recovery subscheme of first Data Analysis Services Generation module is electrically connected, and the output end of the multiple groups oil recovery subscheme generation module electrically connects with the first data acquisition module It connects, the output end of first data acquisition module and the second Data Analysis Services module are electrically connected, second data point The output end and oil recovery schemes generation module for analysing module are electrically connected, the output end of the oil recovery schemes generation module and the second number It is electrically connected according to acquisition module, output end and the third Data Analysis Services module of second data acquisition module electrically connect It connects, the output end of the third Data Analysis Services module and final oil recovery schemes generation module are electrically connected, under the data Carry the defeated of module, multiple groups oil recovery subscheme generation module, petroleum production engineering schemes generation module and final oil recovery schemes generation module Outlet is electrically connected with database, first data acquisition module, the second data acquisition module, number transmission module, first Data Analysis Services module, the second Data Analysis Services module, third Data Analysis Services module and electrically two-way with database Connection, the data transmission module are electrically bi-directionally connected with internet end;
The downloading content of the data download module includes oil field geologic basic data module, reservoir engineering basic data mould Block, petroleum production engineering basic data module and domestic and international associated oil field processing scheme basic data module;
In the multiple groups subscheme design module, petroleum production engineering schemes generation module and final oil recovery schemes generation module Forgiving has conceptual design module, data computation module, graphic plotting module, macroeconomy evaluation module and instrument and equipment selection mould Block;
The conceptual design module includes drilling engineering design module, petroleum production engineering design module and ground surface works design mould Block;
Petroleum production engineering design module includes that Water Injection Engineering design module, oil production method selecting module, process matched therewith are set It counts module and oil field dynamic research monitor system designs module.
Wherein, the oil field geologic basic data module includes Geologic Structure Feature, STRATIGRAPHIC DIVISION and lithologic character, reservoir Feature, Oil Reservoir Types and oil, gas and water distribution, the reservoir engineering basic data module include reservoir fluid composition and property, Reservoir pressure and temperature, reservoir rock seepage flow characteristics, formation testing and pilot production achievement and well test data explanation results, Oil Reservoir Types and drive Flowing mode, oil field development series of strata and development scheme and well net deployment, oil well productivity distribution and its prediction result of variation, oil field are opened Mark of bristling with anger predicts that the petroleum production engineering basic data module includes system protection oil reservoir, reservoir sensitivity, crustal stress situation and answers With the design content of the drilling engineering design module includes meeting safety, economic and scientific principle;Reservoir engineering and oil recovery work The requirement of journey, drilling well basic condition and analysis, formation pore pressure, formation fracture pressure and formation collapsed pressure prediction are bored Well refractory gold ores and relevant art countermeasure, well type and drilling mode select, well structure design, and drilling equipment requirement, well control is wanted It asks, drilling technology requirement, drilling fluid conceptual design, reservoir protection requirement, completion requirements and well cementation conceptual design complete production Pipe sleeve design, gun perforation process conceptual design and operation measure, healthy and safe environmental management, drilling period prediction and drilling engineering are thrown Provide budgetary estimate;For special oil field development, drilling engineering conceptual design should embody its specific aim;Oilfield adjustment drilling engineering scheme is set Meter, since the production in oil field changes the strata pressure of original production layer, Oilfield adjustment drilling engineering conceptual design is removed Except above content, also special supplemental content and requirement, institute should be proposed for the feature after production layer, that is, reservoir property variation Stating Water Injection Engineering design module includes that reservoir sensitivity presses the impact analysis of water filling and the technical measures that should be taken, water injection well shaft bottom Power and well head pressure design, water injection string design, water injection well throws metaideophone and management design, the oil production method selecting module include Principle, foundation and the requirement of artificial lifting way selection, oil well produces the overall merit of capability forecasting and analysis and artificial lifting way, described to match Set technological design module includes de-plugging process design, the design of oil-water well sand-preventing process, wax control technological design, oilwell water shutoff technique side Case design, antiscale and anticorrosion process design etc., the oil field dynamic research supervision design module include oil field dynamic research monitoring overall plan It designs, matched instrument and equipment and oil field dynamic research is selected to monitor the preliminary budget of expense, the ground surface works design module packet Mating plant stand design and team foundation design are included, the macroeconomy evaluation module includes the assessment of oil recovery program budget and investment life The assessment of economic benefit in postpartum.
When in use, by basic data needed for data platform downloading, by the first Data Analysis Services resume module, Oil recovery scheme is produced by multiple groups oil recovery subscheme generation module again, staff is tried related multiple groups oil recovery subscheme one by one It tests, records the data and problem during multiple subschemes progress are tested one by one, data and problem are passed through into data transmission module It is transferred to the first data acquisition module, by the second Data Analysis Services resume module, passes through petroleum production engineering schemes generation module Generation scheme compares and selects suitable one group of petroleum production engineering scheme, then this scheme is tested, and is adjusted according to test situation It improves this scheme and determines final scheme, in the process, the information material of modules is deposited into database, database By data transmission module by data transmission to internet end, information sharing is carried out, this internet end is that internal staff is dedicated, interior Portion personnel can also carry out data supplement and perfect as needed, so that scheme is more in line with actual demand, so that this programme is adopted The design compilation work of oily engineering proposal is more orderly, more reasonable, more efficient.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (7)

1. a kind of petroleum production engineering schemes generation device, it is characterised in that: including data platform module, the second data analysis module, Data download module, the first Data Analysis Services module, multiple groups oil recovery subscheme generation module, the first data acquisition module, number Transmission module, final oil recovery schemes generation module, third Data Analysis Services module, the second data acquisition module, is adopted database Oily engineering proposal generation module and internet end;
The output end of the data platform module and data download module are electrically connected, the output end of the data download module with First Data Analysis Services module is electrically connected, and the output end and multiple groups oil recovery subscheme of first Data Analysis Services generate Module is electrically connected, and the output end of the multiple groups oil recovery subscheme generation module and the first data acquisition module are electrically connected, institute The output end and the second Data Analysis Services module for stating the first data acquisition module are electrically connected, second data analysis module Output end and oil recovery schemes generation module be electrically connected, the output end of the oil recovery schemes generation module and the second data acquisition Module is electrically connected, and the output end and third Data Analysis Services module of second data acquisition module are electrically connected, described The output end of third Data Analysis Services module and final oil recovery schemes generation module are electrically connected, the data download module, The output end of multiple groups oil recovery subscheme generation module, petroleum production engineering schemes generation module and final oil recovery schemes generation module with Database is electrically connected, first data acquisition module, the second data acquisition module, number transmission module, the analysis of the first data It processing module, the second Data Analysis Services module, third Data Analysis Services module and is electrically bi-directionally connected with database, it is described Data transmission module is electrically bi-directionally connected with internet end;
The downloading content of the data download module include oil field geologic basic data module, reservoir engineering basic data module, Petroleum production engineering basic data module and domestic and international associated oil field processing scheme basic data module;
In the multiple groups oil recovery subscheme generation module, petroleum production engineering schemes generation module and final oil recovery schemes generation module Forgiving has conceptual design module, data computation module, graphic plotting module, macroeconomy evaluation module and instrument and equipment selection mould Block;
The conceptual design module includes drilling engineering design module, petroleum production engineering design module and ground surface works design module;
The petroleum production engineering design module includes Water Injection Engineering design module, oil production method selecting module, process matched therewith design mould Block and oil field dynamic research monitor system design module.
2. a kind of petroleum production engineering schemes generation device according to claim 1, it is characterised in that: the oil field geologic basis Profiling module include Geologic Structure Feature, STRATIGRAPHIC DIVISION and lithologic character, reservoir characteristic, Oil Reservoir Types and oil, gas and water distribution, The reservoir engineering basic data module includes the composition and property, reservoir pressure and temperature, reservoir rock seepage flow of reservoir fluid Feature, formation testing and pilot production achievement and well test data explanation results, Oil Reservoir Types and driving method, oil field development series of strata and exploitation side Formula and well net deployment, the prediction result of oil well productivity distribution and its variation, oilfield development indexes prediction, the petroleum production engineering basis Profiling module includes system protection oil reservoir, reservoir sensitivity, crustal stress situation and application.
3. a kind of petroleum production engineering schemes generation device according to claim 1, it is characterised in that: the drilling engineering design The design content of module includes meeting safety, economic and scientific principle;The requirement of reservoir engineering and petroleum production engineering, drilling well is basic Situation and analysis, formation pore pressure, formation fracture pressure and formation collapsed pressure prediction, drilling well refractory gold ores and relevant art Countermeasure, well type and drilling mode select, well structure design, drilling equipment requirement, well control requirement, drilling technology requirement, drilling well Liquid conceptual design, reservoir protection requirement, completion requirements and well cementation conceptual design complete the design of production pipe sleeve, gun perforation process side Case design and operation measure, healthy and safe environmental management, drilling period prediction and drilling engineering investment estimation;For special oil field Exploitation, drilling engineering conceptual design should embody its specific aim;Oilfield adjustment drilling engineering conceptual design, since the production in oil field makes The strata pressure of original production layer is changed, and Oilfield adjustment drilling engineering conceptual design also answers needle in addition to the above To the feature after production layer, that is, reservoir property variation, special supplemental content and requirement are proposed.
4. a kind of petroleum production engineering schemes generation device according to claim 1, it is characterised in that: the Water Injection Engineering design Module includes that reservoir sensitivity sets the impact analysis of water filling and the technical measures that should be taken, water injection well bottom pressure and well head pressure Meter, water injection string design, water injection well throws metaideophone and management design, the oil production method selecting module include what artificial lifting way selected Principle, foundation and requirement, oil well produce the overall merit of capability forecasting and analysis and artificial lifting way, and the process matched therewith designs module Including de-plugging process design, the design of oil-water well sand-preventing process, wax control technological design, oilwell water shutoff process planning, antiscale and Anticorrosion process design etc., oil field dynamic research supervision design module include that oil field dynamic research monitoring collectivity Scheme Design, selection are mating Instrument and equipment and oil field dynamic research monitoring expense preliminary budget.
5. a kind of petroleum production engineering schemes generation apparatus system according to claim 1, it is characterised in that: the ground surface works Design module includes mating plant stand design and team foundation design.
6. a kind of petroleum production engineering schemes generation apparatus system according to claim 1, it is characterised in that: the macroeconomy Evaluation module includes the assessment of economic benefit after oil recovery program budget is assessed and put into production.
7. a kind of petroleum production engineering scheme generation method, it is characterised in that: when in use, pass through basis needed for data platform downloading Data generates oil recovery scheme, work by the first Data Analysis Services resume module, then by multiple groups oil recovery subscheme generation module Personnel are tested related multiple groups oil recovery subscheme one by one, record multiple subschemes carry out data during testing one by one and Data and problem are transferred to the first data acquisition module by data transmission module, by the second Data Analysis Services by problem Resume module generates scheme by petroleum production engineering schemes generation module, compares suitable one group of petroleum production engineering scheme of selecting, then will This scheme is tested, this scheme is adjusted and improved according to test situation and determines final scheme, in the process, modules Information material be deposited into database, database by data transmission module by data transmission to internet end, carry out letter Breath is shared, this internet end is that internal staff is dedicated, and internal staff can also carry out data supplement and perfect as needed, so that side Case is more in line with actual demand, so that the design compilation work of the petroleum production engineering scheme of this programme is more orderly, more reasonable, higher Effect.
CN201811093544.1A 2018-09-19 2018-09-19 A kind of petroleum production engineering scheme generation method and device Pending CN109284868A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811093544.1A CN109284868A (en) 2018-09-19 2018-09-19 A kind of petroleum production engineering scheme generation method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811093544.1A CN109284868A (en) 2018-09-19 2018-09-19 A kind of petroleum production engineering scheme generation method and device

Publications (1)

Publication Number Publication Date
CN109284868A true CN109284868A (en) 2019-01-29

Family

ID=65180853

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811093544.1A Pending CN109284868A (en) 2018-09-19 2018-09-19 A kind of petroleum production engineering scheme generation method and device

Country Status (1)

Country Link
CN (1) CN109284868A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109767348A (en) * 2019-03-29 2019-05-17 中国石油化工股份有限公司 A kind of oil field super-pressure nitrogen injection equipment matching process
CN112288202A (en) * 2019-07-25 2021-01-29 中国石油天然气股份有限公司 Oil extraction process measure data analysis method and device
CN112819247A (en) * 2021-02-25 2021-05-18 中国石油大学(北京) Prediction analysis system and prediction method for oilfield development index
CN112883473A (en) * 2021-02-25 2021-06-01 中国石油天然气集团有限公司 Drilling engineering design generation device and method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2582817A2 (en) * 2010-04-27 2013-04-24 Kiverdi, Inc. Use of oxyhydrogen microorganisms for non-photosynthetic carbon capture and conversion of inorganic and/or c1 carbon sources into useful organic compounds
CN104314547A (en) * 2014-08-18 2015-01-28 北京运嘉普泰石油天然气技术发展有限公司 HAFD segmented optimization method and system
CN106021571A (en) * 2016-06-01 2016-10-12 中国石油大学(北京) Method and device for generating oil production engineering scheme

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2582817A2 (en) * 2010-04-27 2013-04-24 Kiverdi, Inc. Use of oxyhydrogen microorganisms for non-photosynthetic carbon capture and conversion of inorganic and/or c1 carbon sources into useful organic compounds
CN104314547A (en) * 2014-08-18 2015-01-28 北京运嘉普泰石油天然气技术发展有限公司 HAFD segmented optimization method and system
CN106021571A (en) * 2016-06-01 2016-10-12 中国石油大学(北京) Method and device for generating oil production engineering scheme

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
《中华人民共和国石油天然气行业标准 采油工程方案设计编写规范》: "《中华人民共和国石油天然气行业标准 采油工程方案设计编写规范》", 1 December 2012 *
冯立等: "采油工程方案设计编制平台系统研制与应用", 《中国石油和化工》 *
檀朝东等: "基于协同设计的采油工程方案编制平台研究", 《中国石油和化工》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109767348A (en) * 2019-03-29 2019-05-17 中国石油化工股份有限公司 A kind of oil field super-pressure nitrogen injection equipment matching process
CN112288202A (en) * 2019-07-25 2021-01-29 中国石油天然气股份有限公司 Oil extraction process measure data analysis method and device
CN112819247A (en) * 2021-02-25 2021-05-18 中国石油大学(北京) Prediction analysis system and prediction method for oilfield development index
CN112883473A (en) * 2021-02-25 2021-06-01 中国石油天然气集团有限公司 Drilling engineering design generation device and method
CN112819247B (en) * 2021-02-25 2024-01-19 中国石油大学(北京) Prediction analysis system and prediction method for oilfield development index
CN112883473B (en) * 2021-02-25 2024-04-12 中国石油天然气集团有限公司 Drilling engineering design generating device and method

Similar Documents

Publication Publication Date Title
CN109284868A (en) A kind of petroleum production engineering scheme generation method and device
CN104747180B (en) A kind of fracture-pore reservoir for waterflooding extraction analyzes method and application thereof
CN104040376B (en) System and method for performing stimulation work
CN103032057B (en) Steam-driven three-dimensional physical simulation system for thick oil horizontal well
CN104453794A (en) Simulation experiment system for whole process of natural gas hydrate exploitation and simulation method
NO344317B1 (en) System and method for performing simulations for operation of oil fields
CN106522934A (en) Physical simulation experimental device and method for development of complex fractured oil reservoir horizontal well
CN107018672A (en) Energy industry operational feature and/or optimization
CN107013193A (en) One kind simulation underground mixed phase hot fluid oil production experimental device
CN112836349A (en) Injection-production joint debugging intelligent decision method and system based on shaft parameters
CN104541263A (en) Methods and systems for gas lift rate management
CN108301813A (en) The multilayer sandstone oil reservoir modification scenario method of scattered sand body development
NO342368B1 (en) System and method for performing oil field simulation operations
CN107130952B (en) A kind of three-level composite petroleum method for increasing
CN102373918B (en) Oil well batch production simulation experimental facility for low-permeability reservoir
CN105631137A (en) Leaching range monitoring method in in-situ leaching uranium mining process
Suarez-Rivera et al. Quantifying the induced stresses during stacked, multi-stage, multi-well completions, to define stimulation sequencing and optimize pad productivity
CN104863568B (en) Injection well zonal testing and allocating technology
CN107237601B (en) A kind of shale gas batch production wellbore construction method
CN103510945A (en) Multifunctional downhole intelligent actuator under control of superlong wave and pressure wave encoding
CN107239898A (en) A kind of deep southern regional evaluating production capacity method of Ulmaceae
CN102102504B (en) Pressure transfer eccentric water distribution blanking plug
CN102486089A (en) Isoline-based three-dimensional geologic structure map remodeling system
CN202325491U (en) Batch production simulating experimental facility of oil well with low-permeability reservoir
CN107023280A (en) A kind of visual experimental apparatus of simulation underground mixed phase hot fluid oil recovery mechanism

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190129