CN109282286A - A kind of pinpoint accuracy garbage burning boiler installation method - Google Patents
A kind of pinpoint accuracy garbage burning boiler installation method Download PDFInfo
- Publication number
- CN109282286A CN109282286A CN201811000458.1A CN201811000458A CN109282286A CN 109282286 A CN109282286 A CN 109282286A CN 201811000458 A CN201811000458 A CN 201811000458A CN 109282286 A CN109282286 A CN 109282286A
- Authority
- CN
- China
- Prior art keywords
- fire grate
- installation
- liner plate
- road
- burning boiler
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F23—COMBUSTION APPARATUS; COMBUSTION PROCESSES
- F23G—CREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
- F23G5/00—Incineration of waste; Incinerator constructions; Details, accessories or control therefor
- F23G5/006—General arrangement of incineration plant, e.g. flow sheets
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F23—COMBUSTION APPARATUS; COMBUSTION PROCESSES
- F23G—CREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
- F23G5/00—Incineration of waste; Incinerator constructions; Details, accessories or control therefor
- F23G5/44—Details; Accessories
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Gasification And Melting Of Waste (AREA)
Abstract
The purpose of the present invention is to provide a kind of pinpoint accuracy garbage burning boiler installation methods, for solving the technical issues of improving garbage burning boiler installation accuracy.A kind of pinpoint accuracy garbage burning boiler installation method, comprising the following steps: 1. fire grate steel bracket installation centering scribing line, 2. fire grate is installed, and ash bucket is 3. descended to install, and 4. pusher is installed, 5. feed hopper and chute installation, and 6. slag extractor is installed, and 7. incinerator sealing element is installed;Its main innovation point is incinerator arranging construction method.
Description
Technical field
The present invention relates to garbage burning boiler installation method technical field, specifically a kind of pinpoint accuracy waste incineration
Boiler erection method.
Background technique
In order to save installation procedure and time, waste industrialization incinerator mostly uses modularization assembling mode in the prior art.
But also secure its mounting means in this way, i.e. the erection sequence of equipment from bottom to top first installs equipment steel bracket, then according to
Secondary installation slag extractor, ash bucket under fire grate, fire grate system, pusher, boiler furnace.This kind of process can make device fabrication and installation inclined
Incineration furnace grate top is arrived in difference accumulation, and waste incineration and generating electricity surplus heat of power plant furnace heating surface is suspension type, and heating surface is installed tired
Product deviation is in lower furnace portion, the excessive sealing element installation difficulty increasing that will lead to fire grate and burner hearth of the cumulative departure of fire grate and heating surface
Greatly, or even its sealing effect is influenced.
Summary of the invention
The purpose of the present invention is to provide a kind of pinpoint accuracy garbage burning boiler installation methods, improve rubbish for solving
The technical issues of burning boiler installation accuracy.
The technical scheme adopted by the invention to solve the technical problem is that:
A kind of pinpoint accuracy garbage burning boiler installation method, comprising the following steps: 1. fire grate steel bracket installation centering is drawn
Line, 2. fire grate is installed, and ash bucket is 3. descended to install, and 4. pusher is installed, 5. feed hopper and chute installation, and 6. slag extractor is installed, and is 7. burnt
Burn the installation of furnace sealing element;
Wherein, incinerator arranging construction method:
Step 1: the installation of fire grate road
Using lifting device, fire grate road is lifted on the fire grate steel bracket for having been mounted to position, then adjusts fire grate road
Position of center line is connect with steel bracket in length and breadth;
Step 2: the installation of fire grate frame liner plate
Fire grate frame liner plate include side liner plate, intermediate liner plate and after keep off liner plate, side liner plate is mounted on fire grate respectively
Two side positions of road frame, intermediate liner plate are mounted on the middle position of fire grate road frame;It is installed in the middle position of fire grate frame
The shaft of rear baffle is mounted on axis supporting element by axis supporting element and hold-down bolt, and checks the angular position of rotation of rear baffle in
Heart position;Then, the limit band steel for limiting rear baffle is installed in the middle position of fire grate frame;Finally, checking each side
Whether the angular displacement of liner plate, intermediate liner plate and rear gear liner plate meets installation requirement;
Step 3: the transmission device of rear baffle is installed
According to fire grate center line install swing arm bearing block, swing arm be mounted on swing arm bearing block by shaft and with fire grate road
Motion bar connection;
Step 4: fire grate segment installation
Control number, which from top to bottom successively installs fire grate segment, can carry out lower row after upper grate furnace screening adjustment gap is qualified
The installation of fire grate segment;
Step 5: scraper plate installation
It is joined with bolts between continuous scraper plate, adjustment scraper plate leading portion is straight line.
Further, wherein 3. descend ash bucket face throw process can be installed with 4. pusher, 5. feed hopper and chute installation procedure
Adjustment.
Further, before fire grate road is lifted on fire grate steel bracket, check whether the locking device of fire grate drive rod is loose
It is dynamic;And check whether bolt hole center's size that fire grate road is connect with fire grate steel bracket is consistent.
Further, in fire grate frame liner plate installation steps, after side liner plate and intermediate liner plate are in place, pass through fastening bolt
It is docked with the screw hole on fire grate road frame, adjusts separately side liner plate and intermediate lining board clearance first, then tighten fastening spiral shell again
Bolt makes side liner plate and intermediate liner plate positioning.
Further, swing arm is connect after the installation is completed with the motion bar in fire grate road, and it is opposite to test swing arm by external impetus
The activity in fire grate road is without hindrance.
Further, before scraper plate installation, the motion bar in fire grate road is moved to a high position using external impetus;Scraper plate leading portion tune
It is whole motion bar to be moved on to low level, adjusts the height of elastic washer, and tightens bolt after straight line.
The effect provided in summary of the invention is only the effect of embodiment, rather than invents all whole effects, above-mentioned
A technical solution in technical solution have the following advantages that or the utility model has the advantages that
Garbage burning boiler installation accuracy can be improved by the refinement mounting means to fire grate in the present invention.
Specific embodiment
In order to clearly illustrate the technical characterstic of this programme, below by specific embodiment, present invention omits to public affairs
Component and technical description are known to avoid the present invention is unnecessarily limiting.
A kind of pinpoint accuracy garbage burning boiler installation method, includes the following steps, sequence are as follows: 1. fire grate steel bracket is installed
Centering scribing line, 2. fire grate is installed, and ash bucket is 3. descended to install, and 4. pusher is installed, 5. feed hopper and chute installation, and 6. slag extractor is pacified
Dress, 7. incinerator sealing element is installed.Wherein 3. descend ash bucket face throw process can with 4. and 5. adjust, garbage incinerator fire grate is installed
The installation of waste-heat oven can be carried out afterwards.
Burn fire grate detailed construction method:
Step 1: the installation of fire grate road
It checks whether the locking device of fire grate drive rod loosens, is locked if loosening;And check fire grate road and fire grate
Whether bolt hole center's size of steel bracket connection is consistent.After inspection, using lifting device, fire grate road is lifted on
On the fire grate steel bracket being installed in place, then adjusting fire grate road, position of center line is connect with steel bracket in length and breadth.
Step 2: the installation of fire grate frame liner plate
Fire grate frame liner plate include side liner plate, intermediate liner plate and after keep off liner plate, side liner plate is mounted on fire grate respectively
Two side positions of road frame, intermediate liner plate are mounted on the middle position of fire grate road frame.After side liner plate and intermediate liner plate are in place,
It is docked by fastening bolt with the screw hole on fire grate road frame.Side liner plate and intermediate lining board clearance are adjusted separately, is then twisted again
Tightly fixing bolt makes side liner plate and intermediate liner plate positioning.
In the middle position installation axle supporting element and hold-down bolt of fire grate frame, the shaft of rear baffle is mounted on axis support
Part, and check angular position of rotation and the center of rear baffle;Then, after the installation of the middle position of fire grate frame is for limiting
The limit band steel of baffle.Finally, check whether the angular displacement of each side liner plate, intermediate liner plate and rear gear liner plate meets the requirements,
If meeting the requirements, the transmission device of rear baffle is installed.
Step 3: the transmission device of rear baffle is installed
Swing arm bearing block is installed according to fire grate center line, (swing arm is respectively forward and backward swing arm, has in swing arm and is divided into admittedly for swing arm
Fixed end and movable end should be distinguished clear) swing arm bearing block is mounted on by shaft and is connect with the motion bar in fire grate road.Swing arm peace
It is without hindrance with respect to the activity in fire grate road by external impetus (such as suspender cucurbit is drawn) test swing arm after dress.
Step 4: fire grate segment installation
Control number, which from top to bottom successively installs fire grate segment, can carry out lower row after upper grate furnace screening adjustment gap is qualified
The installation of fire grate segment.
Step 5: scraper plate installation
Before scraper plate installation, the motion bar in fire grate road is moved to a high position using external impetus (such as suspender cucurbit is drawn);Peace
Scraper plate support and limit are filled, is joined with bolts between continuous scraper plate, adjustment scraper plate leading portion is straight line.It then, will be movable
Bar moves on to low level, by nut according to design, adjusts the height of elastic washer, and tightens and spell cap bolt.
Except for the technical features described in the specification, it all is technically known to those skilled in the art.
Above-mentioned specific embodiments of the present invention have been described, but it is not intended to limit the protection scope of the present invention,
On the basis of technical solution of the present invention, those skilled in the art do not need to pay for creative labor the various modifications that can be made
Or deformation is still within the scope of the present invention.
Claims (6)
1. a kind of pinpoint accuracy garbage burning boiler installation method, comprising the following steps: 1. fire grate steel bracket installation centering scribing line,
2. fire grate is installed, ash bucket is 3. descended to install, 4. pusher is installed, 5. feed hopper and chute installation, and 6. slag extractor is installed, 7. incinerator
Sealing element installation;It is characterized in that fire grate construction method of installation:
Step 1: the installation of fire grate road
Using lifting device, fire grate road is lifted on the fire grate steel bracket for having been mounted to position, then adjusts fire grate road in length and breadth
Position of center line is connect with steel bracket;
Step 2: the installation of fire grate frame liner plate
Fire grate frame liner plate include side liner plate, intermediate liner plate and after keep off liner plate, side liner plate is mounted on fire grate road frame respectively
Two side positions of frame, intermediate liner plate are mounted on the middle position of fire grate road frame;In the middle position installation axle branch of fire grate frame
The shaft of rear baffle is mounted on axis supporting element by support member and hold-down bolt, and checks the angular position of rotation and centre bit of rear baffle
It sets;Then, the limit band steel for limiting rear baffle is installed in the middle position of fire grate frame;Finally, check each side liner plate,
Whether the angular displacement of intermediate liner plate and rear gear liner plate meets installation requirement;
Step 3: the transmission device of rear baffle is installed
Swing arm bearing block is installed according to fire grate center line, swing arm is mounted on the work on swing arm bearing block and with fire grate road by shaft
Lever connection;
Step 4: fire grate segment installation
Control number, which from top to bottom successively installs fire grate segment, can carry out lower grate furnace row after upper grate furnace screening adjustment gap is qualified
The installation of piece;
Step 5: scraper plate installation
It is joined with bolts between continuous scraper plate, adjustment scraper plate leading portion is straight line.
2. a kind of pinpoint accuracy garbage burning boiler installation method according to claim 1, characterized in that wherein 3. lower grey
Bucket, which faces throwing process, to be adjusted with the installation of 4. pusher, 5. feed hopper and chute installation procedure.
3. a kind of pinpoint accuracy garbage burning boiler installation method according to claim 1, characterized in that hung in fire grate road
Before fire grate steel bracket, check whether the locking device of fire grate drive rod loosens;And check fire grate road and fire grate steel bracket
Whether bolt hole center's size of connection is consistent.
4. a kind of pinpoint accuracy garbage burning boiler installation method according to claim 1, characterized in that fire grate frame lining
In plate installation steps, after side liner plate and intermediate liner plate are in place, docked by fastening bolt with the screw hole on fire grate road frame, it is first
Side liner plate and intermediate lining board clearance are first adjusted separately, then tightens fastening bolt again, makes side liner plate and intermediate liner plate positioning.
5. a kind of pinpoint accuracy garbage burning boiler installation method according to claim 1, characterized in that swing arm and fire grate
It is without hindrance with respect to the activity in fire grate road that the motion bar connection in road tests swing arm after the installation is completed, by external impetus.
6. a kind of pinpoint accuracy garbage burning boiler installation method according to claim 1, characterized in that scraper plate installation
Before, the motion bar in fire grate road is moved to a high position using external impetus;After scraper plate leading portion is adjusted to straight line, motion bar is moved on to low
Position, adjusts the height of elastic washer, and tighten bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811000458.1A CN109282286B (en) | 2018-08-29 | 2018-08-29 | High-precision garbage incineration boiler installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811000458.1A CN109282286B (en) | 2018-08-29 | 2018-08-29 | High-precision garbage incineration boiler installation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109282286A true CN109282286A (en) | 2019-01-29 |
CN109282286B CN109282286B (en) | 2020-04-17 |
Family
ID=65184217
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811000458.1A Active CN109282286B (en) | 2018-08-29 | 2018-08-29 | High-precision garbage incineration boiler installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109282286B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110440272A (en) * | 2019-08-09 | 2019-11-12 | 湖南省工业设备安装有限公司 | A kind of incinerator installation method |
CN110864301A (en) * | 2019-11-21 | 2020-03-06 | 杭州新世纪能源环保工程股份有限公司 | Mounting method of two-section reciprocating type garbage incinerator base oblique beam |
CN111396881A (en) * | 2020-03-30 | 2020-07-10 | 济源霖林环保能源有限公司 | Construction and installation method of garbage incinerator |
CN111594841A (en) * | 2020-04-29 | 2020-08-28 | 中国电建集团河南工程有限公司 | Reverse-pushing mechanical grate garbage incinerator installation construction method |
CN111928218A (en) * | 2020-06-08 | 2020-11-13 | 五冶集团上海有限公司 | 500m2Sintering plant waste heat boiler installation construction method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1328758A1 (en) * | 2000-10-25 | 2003-07-23 | Von Roll Umwelttechnik AG | Grate-type trough serving as a part of a grate for an installation that thermally processes refuse |
RU2602709C2 (en) * | 2011-10-24 | 2016-11-20 | Диффенбахер Гмбх Машинен- Унд Анлагенбау | Grate consisting of fire bars for combustion and installation method of fire bars in grate and their removal therefrom |
KR20180085269A (en) * | 2017-01-18 | 2018-07-26 | 주식회사 진화메탈 | Side-wall fire grate for incineratior and installation structure thereof |
-
2018
- 2018-08-29 CN CN201811000458.1A patent/CN109282286B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1328758A1 (en) * | 2000-10-25 | 2003-07-23 | Von Roll Umwelttechnik AG | Grate-type trough serving as a part of a grate for an installation that thermally processes refuse |
RU2602709C2 (en) * | 2011-10-24 | 2016-11-20 | Диффенбахер Гмбх Машинен- Унд Анлагенбау | Grate consisting of fire bars for combustion and installation method of fire bars in grate and their removal therefrom |
KR20180085269A (en) * | 2017-01-18 | 2018-07-26 | 주식회사 진화메탈 | Side-wall fire grate for incineratior and installation structure thereof |
Non-Patent Citations (4)
Title |
---|
孙世平: "生活垃圾焚烧炉的安装技术", 《安装》 * |
武松: "新工艺环保项目垃圾焚烧锅炉安装", 《内燃机与配件》 * |
胡兆如: "往复炉排的安装", 《锅炉安装技术》 * |
黄鹤: "浅析850t/d 机械炉排本体安装方案", 《技术与应用》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110440272A (en) * | 2019-08-09 | 2019-11-12 | 湖南省工业设备安装有限公司 | A kind of incinerator installation method |
CN110864301A (en) * | 2019-11-21 | 2020-03-06 | 杭州新世纪能源环保工程股份有限公司 | Mounting method of two-section reciprocating type garbage incinerator base oblique beam |
CN110864301B (en) * | 2019-11-21 | 2021-07-30 | 杭州新世纪能源环保工程股份有限公司 | Mounting method of two-section reciprocating type garbage incinerator base oblique beam |
CN111396881A (en) * | 2020-03-30 | 2020-07-10 | 济源霖林环保能源有限公司 | Construction and installation method of garbage incinerator |
CN111396881B (en) * | 2020-03-30 | 2022-04-01 | 焦作市绿鑫城发有限公司 | Construction and installation method of garbage incinerator |
CN111594841A (en) * | 2020-04-29 | 2020-08-28 | 中国电建集团河南工程有限公司 | Reverse-pushing mechanical grate garbage incinerator installation construction method |
CN111594841B (en) * | 2020-04-29 | 2022-06-14 | 中国电建集团河南工程有限公司 | Reverse-pushing mechanical grate garbage incinerator installation construction method |
CN111928218A (en) * | 2020-06-08 | 2020-11-13 | 五冶集团上海有限公司 | 500m2Sintering plant waste heat boiler installation construction method |
Also Published As
Publication number | Publication date |
---|---|
CN109282286B (en) | 2020-04-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109282286A (en) | A kind of pinpoint accuracy garbage burning boiler installation method | |
CN110440272B (en) | Incinerator installation method | |
CN107062233A (en) | A kind of drive device of refuse incineration grate furnace | |
CN201785409U (en) | Deformation prevention device for installation of top ring | |
CN110094719A (en) | A kind of circle type coal burner installation method | |
CN215757151U (en) | Furnace column applied to heat recovery coke oven | |
CN202107662U (en) | Coke oven coke quenching car body device | |
CN106196075B (en) | A kind of waste incinerator garbage inlet furnace wall mounting structure | |
CN112664954B (en) | Thermal expansion compensation device of waste incinerator fire grate and installation method thereof | |
CN212057332U (en) | Chain grate capable of realizing partial coal gasification combustion | |
CN208074986U (en) | Large-scale incinerator for thermal decomposition rotary fire grate device | |
CN211332018U (en) | Burn burning furnace carriage location frock | |
CN208720255U (en) | A kind of side lifting construction system suitable for fluoroplastics flue gas heat-exchange unit | |
CN103849706A (en) | Segmental assembling method for steelmaking converter | |
CN207146400U (en) | A kind of drive device of garbage incinerator grates | |
CN2398522Y (en) | Whole body plenum and wind adjusting and blowing device for boiler | |
CN209978052U (en) | Large-scale burning furnace side wall expansion structure that burns | |
CN207569865U (en) | A kind of slagging mechanism of circulating fluidized bed boiler | |
CN207973710U (en) | Lower dreg discharging powder coal gasification furnace preventing clogging up device | |
CN211925765U (en) | Movable grate support beam | |
CN210374626U (en) | Device for adjusting material guide plate of charging machine | |
CN213416937U (en) | Novel refining furnace blanking pipe anti-blocking device | |
CN210388119U (en) | Tool for positioning steel structure stand column | |
CN111267043A (en) | Tool and method for adjusting center position of inclined manhole cover plate of nuclear power station | |
CN219841801U (en) | Adjustable material scattering box |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |