CN109272420A - Electricity shares system and method - Google Patents

Electricity shares system and method Download PDF

Info

Publication number
CN109272420A
CN109272420A CN201811011414.9A CN201811011414A CN109272420A CN 109272420 A CN109272420 A CN 109272420A CN 201811011414 A CN201811011414 A CN 201811011414A CN 109272420 A CN109272420 A CN 109272420A
Authority
CN
China
Prior art keywords
intelligent
terminal
power information
electricity
subregion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811011414.9A
Other languages
Chinese (zh)
Inventor
徐泽军
钟洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Wind Communication Technologies Co Ltd
Original Assignee
Shanghai Wind Communication Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Wind Communication Technologies Co Ltd filed Critical Shanghai Wind Communication Technologies Co Ltd
Priority to CN201811011414.9A priority Critical patent/CN109272420A/en
Publication of CN109272420A publication Critical patent/CN109272420A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Mobile Radio Communication Systems (AREA)

Abstract

The present embodiments relate to the communications field, discloses a kind of electricity and share system and method.Wherein, electricity shares system and includes terminal and be applied to unit area, and the unit area includes at least two subregions, and each subregion is respectively provided with intelligent node;The intelligent node is used to count power information when itself being powered;The intelligent node is also used to the power information being sent to the terminal in the form of data packet;The terminal is used to count total power information of intelligent node described in each subregion respectively according to the data packet received.Compared with prior art, the present invention can enable the multiple users for sharing unit area according to total power information that intelligent node in respective subregion voluntarily counts to share the electricity charge.

Description

Electricity shares system and method
Technical field
The present embodiments relate to the communications field, in particular to electricity shares system and method.
Background technique
At present for resident, one electricity measuring instrument usually is installed to measure household electricity by unit each household of family Amount.Or for incorporated business, an electricity measuring instrument is installed to survey by each incorporated business usually as unit of incorporated business Measure the electricity consumption of incorporated business.With the raising of development level, rent is higher and higher, then occurs much sharing phenomenon, including Office shares or residential quarter is shared.
Summary of the invention
A kind of electricity of being designed to provide of embodiment of the present invention shares system and method, can make to share unit area Multiple users can share the electricity charge according to total power information that intelligent node in respective subregion voluntarily counts.
In order to solve the above technical problems, embodiments of the present invention, which provide a kind of electricity, shares system, the electricity point Booth system includes terminal and is applied to unit area, and the unit area includes at least two subregions, each subregion It is respectively provided with intelligent node;The intelligent node is used to count power information when itself being powered;The intelligent node be also used to by The power information is sent to the terminal in the form of data packet;The terminal is used for according to the data packet point received Total power information of intelligent node described in each subregion is not counted.
Embodiments of the present invention additionally provide a kind of electricity methodology, share system based on above-mentioned electricity;The electricity Amount methodology includes: power information when intelligent node counts itself energization;The intelligent node by the power information with The form of data packet is sent to the terminal;Wherein, the terminal is used to count every respectively according to the data packet received Total power information of intelligent node described in a subregion.
Embodiment of the present invention in terms of existing technologies, due to unit area include at least two subregions, each Subregion is respectively provided with intelligent node, and intelligent node counts power information when itself being powered and by power information with the shape of data packet Formula is sent to terminal.Terminal counts total power information of intelligent node in each subregion according to the data packet received respectively. Therefore, for including the unit area of at least two subregions, total power information in each subregion can be carried out Statistics, can always use telecommunications according to what intelligent node in respective subregion voluntarily counted convenient for sharing multiple users of unit area Breath is to share the electricity charge.
In addition, the intelligent node at least two in each subregion, and the intelligent node includes at least One intelligent socket and at least one intelligent power equipment;The intelligent power equipment accesses the intelligence by way of grafting It can socket;The intelligent socket is used to measure the intelligent power equipment when the intelligent power equipment accesses intelligent socket Power information;The intelligent socket is also used to the power information of measurement being sent to the terminal.In this way, The electricity of intelligent socket monitoring intelligent electrical equipment can directly be passed through, realized convenient for the subsequent data according to intelligent socket monitoring Analysis to electricity.
In addition, the intelligent socket is specifically used for the title of the intelligent power equipment and corresponding with the title The electricity consumption be sent to the terminal.In this way, it can analyze out the electricity consumption of each intelligent power equipment, just Power supply is adjusted flexibly in analysis result of the subsequent basis to power information.
In addition, the intelligent socket is also used to show the power information of measurement.In this way, so that user can The power information of current intelligent power equipment is intuitively observed with the power information shown by intelligent socket.
In addition, the intelligent node at least two in each subregion;Lead between each intelligent node It crosses bluetooth group and carries out information exchange;The intelligent node is also used to forward the electricity consumption of other intelligent nodes in the form of data packet Information is to the terminal.In this way, the networking mode of intelligent node in the flexible and changeable unit area of one kind is provided.
In addition, each subregion is respectively provided with display screen;The display screen is used to show the institute of each subregion State total power information.In this way, user is allowed intuitively to observe total electricity consumption of each subregion by display screen Information.
In addition, the power information is sent to the terminal especially by gateway by the intelligent node.Due to gateway The uniqueness of location, it is possible to the power information in each subregion is specifically counted according to the address of gateway, it can also be according to every Power information in sub-regions analyzes the duration of being specifically in of user in each subregion.
In addition, the unit area further includes public domain;The public domain setting intelligent socket and intelligent power are set It is standby, and the intelligent socket of the public domain and terminal binding;The intelligent socket is triggered by the terminal to set with power supply Standby conducting;The intelligent socket is used to measure the intelligent power when the intelligent power equipment accesses the intelligent socket The power information of equipment;The terminal is specifically used for: according to the power information of the data packet and measurement that receive Total power information of intelligent node described in each subregion is counted respectively.It can be according to the end mutually bound with intelligent socket End counts user in each subregion to the service condition of public domain intelligent node, and then counts in each subregion and use The electricity charge of public domain are shared convenient for user in each sub-regions in the electricity consumption of public domain in family.
Detailed description of the invention
One or more embodiments are illustrated by the picture in corresponding attached drawing, these exemplary theorys The bright restriction not constituted to embodiment, the element in attached drawing with same reference numbers label are expressed as similar element, remove Non- to have special statement, composition does not limit the figure in attached drawing.
Fig. 1 is the structural block diagram that first embodiment electricity shares system according to the present invention;
Fig. 2 is the structural block diagram that second embodiment electricity shares system according to the present invention;
Fig. 3 is the flow chart of third embodiment electricity methodology according to the present invention.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with attached drawing to the present invention Each embodiment be explained in detail.However, it will be understood by those skilled in the art that in each embodiment party of the present invention In formula, in order to make the reader understand this application better, many technical details are proposed.But even if without these technical details And various changes and modifications based on the following respective embodiments, the application technical solution claimed also may be implemented.
The first embodiment of the present invention is related to a kind of electricity to share system.As shown in Figure 1, the electricity shares system packet It includes terminal 11 and is applied to unit area 12.The unit area 12 includes at least two subregions 121, each subregion 121 are respectively provided with intelligent node 123.Wherein, intelligent node 123 can be intelligent socket or intelligent power equipment.Intelligent power is set It is standby can be, but not limited to for it is following any one or any combination thereof: intelligent TV set, intelligent electric rice cooker, intelligent lamp, intelligence are eventually Hold 11 (mobile phone, computers etc.) etc..The intelligent node 123 is used to count power information when itself being powered.The intelligent node 123 can be specifically used for power information when real-time statistics itself are powered.By this design method, family can be used and obtain in real time The electricity for taking intelligent node 123 currently used.Itself power information is counted when working by intelligent node 123, so that not needing The power information of additional monitoring intelligent node 123.Wherein, power information may include it is following any one or any combination thereof: Electricity consumption, current time, 123 title of intelligent node.The intelligent node 123 is also used to the power information with data packet Form is sent to the terminal 11.The terminal 11 is used to count each sub-district respectively according to the data packet received Total power information of intelligent node 123 described in domain 121.
The intelligent node 123 is specifically used for: the current/voltage generated when itself is powered and conduction time are acquired, and The power information is counted according to the current/voltage and the conduction time.By this design method, a kind of system is provided The specific implementation for counting power information, helps to ensure that feasibility of the invention.Specifically, can be in intelligent node 123 Inside be arranged electrical measurement unit, by electrical measurement unit measure itself be powered when power information.Electrical measurement unit It may include: acquisition module, timing module and processing module.The acquisition module and the timing module be electrically connected in The processing module.The acquisition module is used to acquire the current/voltage generated when the intelligent node 123 is powered.The meter When time for being powered for intelligent energy-saving described in real-time statistics of module.The processing module be used for according to the current/voltage with And the time counts electricity consumption.
In addition, the unit area 12 further includes public domain 122.Intelligent socket and intelligence is arranged in the public domain 122 Energy electrical equipment, and the intelligent socket of the public domain 122 and terminal 11 are bound.The intelligence is triggered by the terminal 11 Energy socket is connected with power supply unit.Specifically, terminal 11 can be communicated by bluetooth or network with intelligent socket, thus eventually End 11 can be connected by bluetooth or network-control intelligent socket with power supply unit.Specifically, the inside of each intelligent node 123 can Bluetooth mould group is arranged, to realize bluetooth group.For example, installing application program in terminal 11, end is associated with by application program End 11 and intelligent socket trigger intelligent socket by APP and are connected with power supply unit.The intelligent socket is set in the intelligent power When the standby access intelligent socket, the power information of the intelligent power equipment is measured.The terminal 11 is according to the institute received The power information for stating data packet and measurement counts the total of intelligent node 123 described in each subregion 121 respectively Power information.In this way, it can be counted in each subregion 121 and be used according to the terminal 11 mutually bound with intelligent socket Family counts in each subregion 121 user in public domain to the service condition of 122 intelligent node 123 of public domain 122 electricity consumption shares the electricity charge of public domain 122 convenient for user in each sub-regions 121.
Since unit area 12 includes at least two subregions 121, each subregion 121 is respectively provided with intelligent node 123, intelligence Energy node 123 counts power information when itself being powered and power information is sent to terminal 11 in the form of data packet.Terminal 11 count total power information of intelligent node 123 in each subregion 121 according to the data packet received respectively.Therefore, for For unit area 12 including at least two subregions 121, it can unite to total power information in each subregion 121 Meter, can voluntarily count total according to intelligent node 123 in respective subregion 121 convenient for sharing multiple users of unit area 12 Power information shares the electricity charge.
For example, for example unit area 12 can be a set of house or a set of office.It is a set of in unit area 12 When house, which may include public domain 122 and at least two subregions 121.Wherein, public domain 122 can be Any one or any combination thereof below: dining room, kitchen, toilet, parlor;Subregion 121 can be bedroom.Alternatively, in list When position region 12 is a set of office, which may include public domain 122 and at least two subregions 121.Wherein, Public domain 122 can for it is following any one or any combination thereof: meeting room, Tea Room, toilet;Subregion 121 can be with For Office Area.
It is illustrated so that unit area 12 is one set of house as an example: assuming that one set of house includes that a kitchen and two are sleeping Room.Two bedrooms are respectively bedroom A and bedroom B, and the terminal 11 that the user of bedroom A uses is first terminal, and the user of bedroom B makes Terminal 11 is second terminal, and the terminal 11 of landlord is third terminal.Terminal 11 and son can be stored in advance in present embodiment The related information in region 121.For example, the related information of first terminal Yu bedroom A is stored in advance, the pass of second terminal and bedroom B Join information.
Intelligent node 123 in kitchen can be intelligent socket, intelligent electric cooker etc..When the user for leasing bedroom A uses When the electric cooker of public domain 122 is cooked, triggering intelligent socket and power supply can be operable to the APP of first terminal Intelligent electric cooker is accessed intelligent socket, realizes rice-cooking function by equipment conducting.Since first terminal is associated with bedroom A, When power information is uploaded to the third terminal of landlord by intelligent socket, the user of bedroom A can analyze out by third terminal To the service condition and electricity consumption of the intelligent power equipment of public domain 122.It similarly be can analyze out and crouched by third terminal Service condition and electricity consumption of the user of room B to the intelligent power equipment of public domain 122.By this design, convenient for sleeping The user of room A and the user of bedroom B share the electricity charge of public domain 122.
Intelligent node 123 in bedroom can be intelligent socket, smart television etc..Intelligent socket, smart television can be with Power information when itself being powered is counted, and power information is sent to the third terminal of landlord.Or smart television access intelligence When socket, the power information of smart television is measured by intelligent socket, and power information is sent to the third terminal of landlord.Pass through Third terminal can analyze out service condition and electricity consumption of the user to intelligent node 123 in respective bedroom of bedroom A or bedroom B Amount.
Compared with prior art, present embodiment can enable the multiple users for sharing unit area 12 according to respective son Intelligent node 123 voluntarily counts in region 121 total power information shares the electricity charge.
Second embodiment of the present invention is related to a kind of electricity and shares system.Present embodiment and first embodiment are not Together, it is in place of the main distinction: (intelligent socket and/or the intelligent power of the intelligent node in subregion in the first embodiment Equipment) count itself be powered when power information, and in the present embodiment in subregion pass through intelligent socket statistics access The power information of the intelligent power equipment of intelligent socket.
Include terminal 11 and be applied to unit area 12 as shown in Fig. 2, the electricity shares system.The unit area 12 Including at least two subregions 121, each subregion 121 is respectively provided with intelligent node 123.Wherein, intelligent node 123 can be with For intelligent socket or intelligent power equipment.Intelligent power equipment can be, but not limited to for it is following any one or any combination thereof: Intelligent TV set, intelligent electric rice cooker, intelligent lamp, intelligent terminal 11 (mobile phone, computer etc.) etc..The intelligent node 123 is for uniting Count power information when itself being powered.The intelligent node 123 can be specifically used for using telecommunications when real-time statistics itself are powered Breath.By this design method, family can be used and obtain the currently used electricity of intelligent node 123 in real time.Pass through intelligent node Itself power information is counted when 123 work, so that not needing the power information of additional monitoring intelligent node 123.Wherein, telecommunications is used Breath may include it is following any one or any combination thereof: electricity consumption, current time, 123 title of intelligent node.The intelligence section Point 123 is also used to for the power information to be sent to the terminal 11 in the form of data packet.The terminal 11 is used for basis and connects The data packet received counts total power information of intelligent node 123 described in each subregion 121 respectively.
The intelligent node 123 is specifically used for: the current/voltage generated when itself is powered and conduction time are acquired, and The power information is counted according to the current/voltage and the conduction time.By this design method, a kind of system is provided The specific implementation for counting power information, helps to ensure that feasibility of the invention.Specifically, can be in intelligent node 123 Inside be arranged electrical measurement unit, by electrical measurement unit measure itself be powered when power information.Electrical measurement unit It may include: acquisition module, timing module and processing module.The acquisition module and the timing module be electrically connected in The processing module.The acquisition module is used to acquire the current/voltage generated when the intelligent node 123 is powered.The meter When time for being powered for intelligent energy-saving described in real-time statistics of module.The processing module be used for according to the current/voltage with And the time counts electricity consumption.
In addition, the intelligent node 123 at least two in each subregion 121, and the intelligent node 123 Including at least one intelligent socket 1231 and at least one intelligent power equipment 1232.The intelligent power equipment 1232 passes through The mode of grafting accesses the intelligent socket 1231.The intelligent socket 1231 is used to access in the intelligent power equipment 1232 When intelligent socket 1231, the power information of the intelligent power equipment 1232 is measured.The intelligent socket 1231 is also used to survey The power information of amount is sent to the terminal 11.In this way, intelligence directly can be monitored by intelligent socket 1231 The electricity of energy electrical equipment 1232 realizes the analysis to electricity convenient for the subsequent data monitored according to intelligent socket 1231.Wherein, The intelligent socket 1231 is specifically used for the title of the intelligent power equipment 1232 and institute corresponding with the title It states electricity consumption and is sent to the terminal 11.In this way, it can analyze out the electricity consumption of each intelligent power equipment 1232, Power supply is adjusted flexibly convenient for analysis result of the subsequent basis to power information.
In addition, the intelligent socket 1231 is also used to show the power information of measurement.In this way, so that with The power information that family can be shown by intelligent socket 1231 intuitively observes the power information of current intelligent power equipment 1232. Display screen can be set in each subregion 121;The display screen is used to show the described total of each subregion 121 Power information.In this way, allow what user intuitively observed each subregion 121 by display screen always to use telecommunications Breath.
The intelligent node 123 at least two in present embodiment, in each subregion 121;It is each described Information exchange is carried out by bluetooth group between intelligent node 123;The intelligent node 123 is also used to turn in the form of data packet The power informations of other intelligent nodes 123 is sent out to the terminal 11.In this way, a kind of flexible and changeable unit is provided The networking mode of intelligent node 123 in region 12.
In addition, the power information is sent to the terminal 11 especially by gateway 13 by the intelligent node 123.Due to The uniqueness of 13 address of gateway, it is possible to the power information in each subregion 121 is specifically counted according to the address of gateway 13, The duration of being specifically in of user in each subregion 121 can also be analyzed according to the power information in each subregion 121.
The unit area 12 further includes public domain 122.Intelligent socket 1231 and intelligence is arranged in the public domain 122 Electrical equipment 1232, and the intelligent socket 1231 of the public domain 122 and terminal 11 are bound.It is triggered by the terminal 11 The intelligent socket 1231 is connected with power supply unit.Specifically, terminal 11 can pass through bluetooth or network and intelligent socket 1231 It is communicated, so that terminal 11 can be connected by bluetooth or network-control intelligent socket 1231 with power supply unit.For example, terminal Application program is installed on 11, by application program come associated terminal 11 and intelligent socket 1231, intelligent socket is triggered by APP 1231 are connected with power supply unit.The intelligent socket 1231 accesses the intelligent socket 1231 in the intelligent power equipment 1232 When, measure the power information of the intelligent power equipment 1232.The terminal 11 is according to the data packet received and survey The power information of amount counts total power information of intelligent node 123 described in each subregion 121 respectively.Pass through this Kind of mode can count in each subregion 121 user to public area according to the terminal 11 bound with 1231 phase of intelligent socket The service condition of 122 intelligent node 123 of domain, and then user is counted in each subregion 121 in the electricity consumption of public domain 122 Amount, shares the electricity charge of public domain 122 convenient for user in each sub-regions 121.
Since unit area 12 includes at least two subregions 121, each subregion 121 is respectively provided with intelligent node 123, intelligence Energy node 123 counts power information when itself being powered and power information is sent to terminal 11 in the form of data packet.Terminal 11 count total power information of intelligent node 123 in each subregion 121 according to the data packet received respectively.Therefore, for For unit area 12 including at least two subregions 121, it can unite to total power information in each subregion 121 Meter, can voluntarily count total according to intelligent node 123 in respective subregion 121 convenient for sharing multiple users of unit area 12 Power information shares the electricity charge.
For example, for example unit area 12 can be a set of house or a set of office.It is a set of in unit area 12 When house, which may include public domain 122 and at least two subregions 121.Wherein, public domain 122 can be Any one or any combination thereof below: dining room, kitchen, toilet, parlor;Subregion 121 can be bedroom.Alternatively, in list When position region 12 is a set of office, which may include public domain 122 and at least two subregions 121.Wherein, Public domain 122 can for it is following any one or any combination thereof: meeting room, Tea Room, toilet;Subregion 121 can be with For Office Area.
It is illustrated so that unit area 12 is one set of house as an example: assuming that one set of house includes that a kitchen and two are sleeping Room.Two bedrooms are respectively bedroom A and bedroom B, and the terminal 11 that the user of bedroom A uses is first terminal, and the user of bedroom B makes Terminal 11 is second terminal, and the terminal 11 of landlord is third terminal.Terminal 11 and son can be stored in advance in present embodiment The related information in region 121.For example, the related information of first terminal Yu bedroom A is stored in advance, the pass of second terminal and bedroom B Join information.
Intelligent node 123 in kitchen can be intelligent socket 1231, intelligent electric cooker etc..As the user for leasing bedroom A When being cooked using the electric cooker of public domain 122, triggering intelligent socket can be operable to the APP of first terminal 1231 are connected with power supply unit, and intelligent electric cooker is accessed intelligent socket 1231, realizes rice-cooking function.Due to first terminal and crouch Room A is associated, therefore when power information is uploaded to the third terminal of landlord by intelligent socket 1231, can be with by third terminal The user of bedroom A is analyzed to the service condition and electricity consumption of the intelligent power equipment 1232 of public domain 122.Similarly pass through Third terminal can analyze out the user of bedroom B to the service condition and use of the intelligent power equipment 1232 of public domain 122 Electricity.By this design, the electricity charge of public domain 122 are shared convenient for the user of bedroom A and the user of bedroom B.
Intelligent node 123 in bedroom can be intelligent socket 1231, smart television etc..Intelligent socket 1231, intelligence electricity Depending on can count power information when itself being powered, and power information is sent to the third terminal of landlord.Or smart television When accessing intelligent socket 1231, the power information of smart television is measured by intelligent socket 1231, and power information is sent to room The third terminal in east.It can analyze out the user of bedroom A or bedroom B to intelligent node 123 in respective bedroom by third terminal Service condition and electricity consumption.
Compared with prior art, present embodiment can enable the multiple users for sharing unit area 12 according to respective son Intelligent node 123 voluntarily counts in region 121 total power information shares the electricity charge.
Third embodiment of the invention is related to a kind of electricity methodology, the electricity based on first or second embodiment point Booth system.The electricity shares system and includes terminal and be applied to unit area.The unit area includes at least two sub-districts Domain, each subregion are respectively provided with intelligent node.For example, for example unit area can be a set of house or a set of office Room.When unit area is one set of house, which may include public domain and at least two subregions.Wherein, public Region can for it is following any one or any combination thereof: dining room, kitchen, toilet, parlor;Subregion can be bedroom.Or Person, when unit area is a set of office, which may include public domain and at least two subregions.Wherein, Public domain can for it is following any one or any combination thereof: meeting room, Tea Room, toilet;Subregion can be office Area.
As shown in figure 3, the electricity methodology includes:
Step S31, intelligent node count power information when itself being powered.
Wherein, intelligent node can be intelligent socket or intelligent power equipment.Intelligent power equipment can be, but not limited to for Any one or any combination thereof below: intelligent TV set, intelligent electric rice cooker, intelligent lamp, intelligent terminal (mobile phone, computer etc.) Deng.When intelligent node is intelligent socket and intelligent power equipment, intelligent socket can measure the intelligence for accessing the intelligent socket The power information of electrical equipment, and the power information of measurement is sent to terminal.
Power information is sent to terminal by step S32, intelligent node in the form of data packet.
Step S33, terminal are used to count total use of intelligent node in each subregion respectively according to the data packet received Power information.
Since unit area includes at least two subregions, each subregion is respectively provided with intelligent node, intelligent node statistics Itself be powered when power information and power information is sent to terminal in the form of data packet.Terminal is according to the data received Packet counts total power information of intelligent node in each subregion respectively.Therefore, for the unit including at least two subregions For region, total power information in each subregion can be counted, convenient for sharing multiple user's energy of unit area It is enough that the electricity charge are shared according to total power information that intelligent node in respective subregion voluntarily counts.
Compared with prior art, present embodiment can enable the multiple users for sharing unit area according to respective sub-district Intelligent node voluntarily counts in domain total power information shares the electricity charge.
It is not difficult to find that present embodiment is embodiment of the method corresponding with first or second embodiment, this embodiment party Formula can work in coordination implementation with first or second embodiment.The relevant technical details mentioned in first or second embodiment exist In present embodiment still effectively, in order to reduce repetition, which is not described herein again.Correspondingly, the correlation mentioned in present embodiment Technical detail is also applicable in first or second embodiment.
It will be understood by those skilled in the art that the respective embodiments described above are to realize specific embodiments of the present invention, And in practical applications, can to it, various changes can be made in the form and details, without departing from the spirit and scope of the present invention.

Claims (10)

1. a kind of electricity shares system, which is characterized in that the electricity shares system and includes terminal and be applied to unit area, institute Stating unit area includes at least two subregions, and each subregion is respectively provided with intelligent node;
The intelligent node is used to count power information when itself being powered;
The intelligent node is also used to the power information being sent to the terminal in the form of data packet;
The terminal is used to count intelligent node described in each subregion respectively according to the data packet received Total power information.
2. electricity according to claim 1 shares system, which is characterized in that the intelligence section in each subregion Point at least two, and the intelligent node includes at least one intelligent socket and at least one intelligent power equipment;
The intelligent power equipment accesses the intelligent socket by way of grafting;
The intelligent socket is used to measure the use of the intelligent power equipment when the intelligent power equipment accesses intelligent socket Power information;
The intelligent socket is also used to the power information of measurement being sent to the terminal.
3. electricity according to claim 2 shares system, which is characterized in that the intelligent socket is specifically used for the intelligence The title of energy electrical equipment and the electricity consumption corresponding with the title are sent to the terminal.
4. electricity according to claim 2 shares system, which is characterized in that the intelligent socket is also used to show measurement The power information.
5. electricity according to claim 2 shares system, which is characterized in that the intelligence section in each subregion Point at least two;Information exchange is carried out by bluetooth group between each intelligent node;
The intelligent node is also used to forward the power information of other intelligent nodes to the terminal in the form of data packet.
6. electricity according to claim 1 shares system, which is characterized in that each subregion is respectively provided with display screen;
The display screen is used to show total power information of each subregion.
7. electricity as claimed in any of claims 1 to 6 shares system, which is characterized in that the intelligent node tool The power information is sent to the terminal by gateway by body.
8. electricity according to claim 1 shares system, which is characterized in that the unit area further includes public domain;
The public domain setting intelligent socket and intelligent power equipment, and the intelligent socket of the public domain and terminal are tied up It is fixed;
The intelligent socket is triggered by the terminal to be connected with power supply unit;
The intelligent socket is used to measure the intelligent power equipment when the intelligent power equipment accesses the intelligent socket Power information;
The terminal is specifically used for: counting each respectively according to the power information of the data packet and measurement that receive Total power information of intelligent node described in the subregion.
9. electricity according to claim 8 shares system, which is characterized in that the terminal and the subregion is stored in advance Related information.
10. a kind of electricity methodology, which is characterized in that shared based on electricity described in any one of claim 1 to 9 and be System;
The electricity methodology includes:
Intelligent node counts power information when itself being powered;
The power information is sent to the terminal by the intelligent node in the form of data packet;Wherein, the terminal is used for Count total power information of intelligent node described in each subregion respectively according to the data packet received.
CN201811011414.9A 2018-08-31 2018-08-31 Electricity shares system and method Pending CN109272420A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811011414.9A CN109272420A (en) 2018-08-31 2018-08-31 Electricity shares system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811011414.9A CN109272420A (en) 2018-08-31 2018-08-31 Electricity shares system and method

Publications (1)

Publication Number Publication Date
CN109272420A true CN109272420A (en) 2019-01-25

Family

ID=65155110

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811011414.9A Pending CN109272420A (en) 2018-08-31 2018-08-31 Electricity shares system and method

Country Status (1)

Country Link
CN (1) CN109272420A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111062711A (en) * 2019-12-31 2020-04-24 广东伟邦科技股份有限公司 Intelligent management system for shared electricity in area

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202261351U (en) * 2011-09-28 2012-05-30 海尔集团公司 Device used for monitoring electricity consumption information
CN202939450U (en) * 2012-11-22 2013-05-15 上海电器科学研究院 Household electricity quantity monitoring system
CN103474842A (en) * 2013-08-20 2013-12-25 青岛歌尔声学科技有限公司 Intelligent socket system
CN103823400A (en) * 2014-02-20 2014-05-28 上海新物科技有限公司 Socket monitoring system
CN104914757A (en) * 2015-04-23 2015-09-16 惠州Tcl移动通信有限公司 Intelligent socket, intelligent socket management system and intelligent socket management method based on Zigbee technology
CN105334816A (en) * 2015-09-24 2016-02-17 北京博锐尚格节能技术股份有限公司 Intelligent cloud socket system and methods for identifying electric equipment types and achieving data interaction
CN105976173A (en) * 2016-05-03 2016-09-28 华中科技大学 Electric quantity statistics device for dormitory
CN107359487A (en) * 2017-09-05 2017-11-17 兰州交通大学 Distributed remote control apparatus socket and management of power use method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202261351U (en) * 2011-09-28 2012-05-30 海尔集团公司 Device used for monitoring electricity consumption information
CN202939450U (en) * 2012-11-22 2013-05-15 上海电器科学研究院 Household electricity quantity monitoring system
CN103474842A (en) * 2013-08-20 2013-12-25 青岛歌尔声学科技有限公司 Intelligent socket system
CN103823400A (en) * 2014-02-20 2014-05-28 上海新物科技有限公司 Socket monitoring system
CN104914757A (en) * 2015-04-23 2015-09-16 惠州Tcl移动通信有限公司 Intelligent socket, intelligent socket management system and intelligent socket management method based on Zigbee technology
CN105334816A (en) * 2015-09-24 2016-02-17 北京博锐尚格节能技术股份有限公司 Intelligent cloud socket system and methods for identifying electric equipment types and achieving data interaction
CN105976173A (en) * 2016-05-03 2016-09-28 华中科技大学 Electric quantity statistics device for dormitory
CN107359487A (en) * 2017-09-05 2017-11-17 兰州交通大学 Distributed remote control apparatus socket and management of power use method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111062711A (en) * 2019-12-31 2020-04-24 广东伟邦科技股份有限公司 Intelligent management system for shared electricity in area

Similar Documents

Publication Publication Date Title
Han et al. Smart home energy management system including renewable energy based on ZigBee and PLC
Kusriyanto et al. Smart home using local area network (LAN) based arduino mega 2560
US8581743B2 (en) Method and system for automated power meter infrastructure
CN105354933B (en) Methods, devices and systems for the charging of multiple online air conditioners family
CN202261351U (en) Device used for monitoring electricity consumption information
Ju et al. An efficient home energy management system based on automatic meter reading
CN104898591A (en) Intelligent household appliance cooperation control method
CN103823400B (en) Socket monitoring system
CN101702690A (en) Method for carrying out human-computer interaction by embedded equipment through internet instant messaging system
CN108508755A (en) Smart home device configuration method and intelligent domestic system
CN108540973A (en) Data service handling method, device and system under roaming scence
CN104200547A (en) Internet-of-Things-based intelligent doorbell photographing and monitoring system and control method thereof
CN103336493A (en) An energy management system
AU2010257246A1 (en) Safety interlocks for electricity meter control relays
CN108833491A (en) The energy consumption statistical method and server of Internet of things system
CN109272420A (en) Electricity shares system and method
CN110045705A (en) Using the intelligent home furnishing control method of heterogeneous wireless network, apparatus and system
CN106656830A (en) Household energy router and control method thereof
CN107592360A (en) A kind of Internet of Things data polymerization and system based on mixed cloud
CN106058537A (en) Power socket system based on cloud service
CN116382111A (en) Equipment control method and device, storage medium and electronic device
JP2017108382A (en) House
CN109327504A (en) Electricity statistical system and electricity statistical method
CN104569577B (en) A kind of household electricity information acquisition system based on micro power radio communication agreement
CN107171443A (en) A kind of intelligent power shows system and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190125

WD01 Invention patent application deemed withdrawn after publication