CN109268035A - For leaning on the real-time regulation system and method for segment deformation after controlling - Google Patents

For leaning on the real-time regulation system and method for segment deformation after controlling Download PDF

Info

Publication number
CN109268035A
CN109268035A CN201811004138.3A CN201811004138A CN109268035A CN 109268035 A CN109268035 A CN 109268035A CN 201811004138 A CN201811004138 A CN 201811004138A CN 109268035 A CN109268035 A CN 109268035A
Authority
CN
China
Prior art keywords
jurisdiction
section
real
leaning
deformation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811004138.3A
Other languages
Chinese (zh)
Other versions
CN109268035B (en
Inventor
寇晓勇
黄德中
陈培新
宿文德
钱晓华
邱龑
翟欣
翟一欣
范杰
王浩
李刚
顾嫣
李永
吴列成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI SHIELD CENTER CO Ltd
Shanghai Tunneling Shield Engineering Co Ltd
Shanghai Tunnel Engineering Co Ltd
Original Assignee
SHANGHAI SHIELD CENTER CO Ltd
Shanghai Tunneling Shield Engineering Co Ltd
Shanghai Tunnel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI SHIELD CENTER CO Ltd, Shanghai Tunneling Shield Engineering Co Ltd, Shanghai Tunnel Engineering Co Ltd filed Critical SHANGHAI SHIELD CENTER CO Ltd
Priority to CN201811004138.3A priority Critical patent/CN109268035B/en
Publication of CN109268035A publication Critical patent/CN109268035A/en
Application granted granted Critical
Publication of CN109268035B publication Critical patent/CN109268035B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs

Abstract

The present invention relates to a kind of for leaning on the real-time regulating method of segment deformation after controlling, section of jurisdiction after described by section of jurisdiction to bear the effect of push pipe jacking counter-force in main tunnel, the real-time regulating method includes the following steps: divider wall of constructing in the soil body at section of jurisdiction after described, and the divider wall and the rear outer surface for leaning on section of jurisdiction is made to be enclosed a seal chamber, the soil body of the rear outer surface by section of jurisdiction is surrounded by the seal chamber;And during the push-bench tunneling construction, the rear deflection for leaning on section of jurisdiction described in real-time detection, and the injection rate of the non-hardening capacity slurries injected into the seal chamber is dynamically adjusted according to the deflection, the rear deformation for leaning on section of jurisdiction is controlled to realize.The present invention realizes the effect of real-time monitoring, solve the problems, such as in the prior art the only deformation extent of passive monitoring section of jurisdiction and without counter-measure, it is thus also avoided that the generation of overrun condition is deformed, so as to avoid additional the problem of increasing duration and cost.

Description

For leaning on the real-time regulation system and method for segment deformation after controlling
Technical field
The present invention relates to Tunnel Engineering fields, refer in particular to a kind of for leaning on real-time regulation system and the side of segment deformation after controlling Method.
Background technique
With the fast development of Urban Underground Space Excavation, service channel is logical as the emergency for linking up two adjacent tunnels Road, construction demand greatly improve, and compared to traditional shallow mining method, mechanical equipment method tunnel connection channel is in construction safety Property, have biggish advantage in terms of completion time of project and cost.Tunnel connection channel push bench process is push-bench in molded main tunnel A kind of mechanical execution method of not preparatory strengthening stratum is tunneled in road after cutting concrete pipe sheet.Push-bench tunnels forward required Promote counter-force then finally by main tunnel structure and its outside soil body shared, push-bench per one tube coupling distance of jacking forward, Jacking jack will bounce back, the rear jack jacking again in place of new tube coupling, repeatedly, main tunnel structure and its outside soil body Frequent loading-unloading operating condition will be faced.For tunnel structure deformation main in control jack-in process, guarantee construction safety, before construction Tunnel structure main at service channel would generally be carried out reinforcing or pre-reinforcement is carried out to the outside soil body.
Existing way often rests on passively the Deformation control of main tunnel structure during push pipe jacking construction The degree of monitoring will not generally take additional control measure as long as deformation is no more than design requirement, and due to main tunnel structure and Under the effect of loading-unloading operating condition, the resilience of the two is not consistent the behind soil body, can make section of jurisdiction and the behind soil body It disengages, increases the load share ratio of section of jurisdiction, while " fatigue " effect of metalloid may also be generated, be unfavorable for tunnel structure Deformation control and stress safety.If main tunnel deformation is more than design objective in jack-in process, service channel shut-down will lead to, And multiple slip casting is carried out to the soil body after wall, duration and cost are added additional, mechanical equipment method tunnel connection channel is weakened Advantage.
Summary of the invention
It is an object of the invention to overcome the deficiencies of existing technologies, a kind of real-time adjusting for after controlling by deforming is provided System and method, solve not can solve in the prior art promote counter-force frequent plus unloading to tunnel duct piece deformation and stress not Benefit influences, and deformation additionally increase when transfiniting duration and cost the problem of.
Realizing the technical solution of above-mentioned purpose is:
The present invention provides a kind of for leaning on the real-time regulating method of segment deformation after controlling, and it is main tunnel that section of jurisdiction is leaned on after described The section of jurisdiction of push pipe jacking counter-force effect is born in road, the real-time regulating method includes the following steps:
Constructed after described in the soil body at section of jurisdiction divider wall, and make the divider wall and it is described after by the outer of section of jurisdiction Surface is enclosed a seal chamber, and the soil body of the rear outer surface by section of jurisdiction is surrounded by the seal chamber;And
During the push-bench tunneling construction, the rear deflection for leaning on section of jurisdiction described in real-time detection, and according to described Deflection dynamically adjusts the injection rate of the non-hardening capacity slurries injected into the seal chamber, leans on after control is described to realize The deformation of section of jurisdiction.
The present invention provides a kind of methods adjusted in real time to lean on segment deformation after controlling, lean on the corresponding soil in section of jurisdiction prior to rear Divider wall is constructed in body with formed one with lean on the corresponding seal chamber in section of jurisdiction afterwards, thus adjusted according to the rear deflection by section of jurisdiction to The injection rate of the non-hardening capacity slurries of injection leans on the deformation of section of jurisdiction after controlling in seal chamber, realizes the effect of real-time monitoring, more It has mended in the prior art, the rear deficiency prevented in advance by section of jurisdiction Deformation control weight with subsequent disposition, light mid-event control, after realizing It is dynamically controlled in the thing of segment deformation.Solve in the prior art only the deformation extent of passive monitoring section of jurisdiction and without counter-measure The problem of, it is thus also avoided that the generation of overrun condition is deformed, so as to avoid additional the problem of increasing duration and cost.
The present invention be used for control after by segment deformation real-time regulating method further improvement lies in that, construction divider wall, Include:
Grouting Pipe is set from the reserved injected hole on the section of jurisdiction in the main tunnel, the Grouting Pipe is enabled to pass through corresponding section of jurisdiction And it squeezes into the soil body on the outside of corresponding section of jurisdiction;
Inject hardening capacity slurries into the soil body by the Grouting Pipe to form the divider wall.
The present invention be used for control after by segment deformation real-time regulating method further improvement lies in that, construction divider wall When, by with it is described after the divider wall that connect by section of jurisdiction be set to it is described after lean on the edge of section of jurisdiction, and rear lean on that section of jurisdiction is vertical to be connected with described It connects.
The present invention be used for control after lean on segment deformation real-time regulating method further improvement lies in that, in the push-bench Before tunneling construction, further includes:
Mud injection pipe is set from the reserved injected hole of the rear tube on piece, the mud injection pipe is enabled to squeeze into described In seal chamber;
Two-way slush pump is connected in the end being located in the main tunnel on the mud injection pipe, by described two-way Slush pump non-hardening capacity slurries can be injected into the seal chamber with increase it is described after lean on the pressure of section of jurisdiction outer surface, can also be from The non-hardening capacity slurries injected are extracted in the seal chamber to reduce the rear pressure for leaning on section of jurisdiction outer surface, to realize The injection rate of the dynamic non-hardening capacity slurries of adjustment and it is described after lean on the pressure of section of jurisdiction outer surface.
The present invention be used for control after lean on segment deformation real-time regulating method further improvement lies in that, described in real-time detection The deflection of section of jurisdiction is leaned on afterwards, comprising:
Inner surface installation one after described by section of jurisdiction passes through the sensing for detecting the sensor of section of jurisdiction convergent deformation The deflection of section of jurisdiction is leaned on after described in device real-time detection.
The present invention also provides a kind of for leaning on the real-time regulation system of segment deformation after controlling, and leans on based on section of jurisdiction after described The section of jurisdiction of push pipe jacking counter-force effect is born in tunnel, the real-time regulation system includes:
Set on the rear intracorporal divider wall of soil at section of jurisdiction, the divider wall is enclosed with the rear outer surface by section of jurisdiction It closes and forms a seal chamber, the soil body of the rear outer surface by section of jurisdiction is surrounded by the seal chamber;
It is installed on the detection unit of the rear tube on piece, for the rear deflection for leaning on section of jurisdiction described in real-time detection;And
The slip casting unit being all connected with the seal chamber and the detection unit, for dynamically being adjusted according to the deflection The injection rate of the whole non-hardening capacity slurries injected into the seal chamber controls the rear deformation for leaning on section of jurisdiction to realize.
The present invention be used for control after by segment deformation real-time regulation system further improvement lies in that, with it is described afterwards tube The divider wall of piece connection be set to it is described after by section of jurisdiction edge and with it is described after connect by section of jurisdiction is vertical.
The present invention be used for control after lean on segment deformation real-time regulation system further improvement lies in that, the slip casting unit Mud injection pipe that reserved injected hole including the tube on piece after described is squeezed into the seal chamber is connect with the Grouting Pipe Two-way slush pump and control module with the two-way slush pump control connection;
The control module is connect with the detection unit, and the control module can be double according to the deformation amount controlling It is described afterwards by the pressure of section of jurisdiction outer surface to increase to inject non-hardening capacity slurries into the seal chamber to slush pump, can also root The non-hardening capacity slurries injected are extracted out of described seal chamber according to two-way slush pump described in the deformation amount controlling to reduce The pressure of section of jurisdiction outer surface is leaned on after stating, to lean on the deformation of section of jurisdiction after realizing dynamic adjustment.
The present invention be used for control after lean on segment deformation real-time regulation system further improvement lies in that, the slip casting unit It further include the pressure sensor being installed on the mud injection pipe, the pressure sensor is connect with the control module, is used The pressure initiation reference pressure data of section of jurisdiction outer surface are leaned on after described in real-time detection, and by reference pressure data detected It is sent to the control module.
The present invention be used for control after lean on segment deformation real-time regulation system further improvement lies in that, the detection unit Sensor including being installed on the rear inner surface for leaning on section of jurisdiction and for detecting section of jurisdiction convergent deformation, passes through the sensor The deflection of section of jurisdiction is leaned on after described in real-time detection.
Detailed description of the invention
Fig. 1 is main tunnel, service channel in real-time regulation system and method for the present invention for leaning on segment deformation after controlling And the longitudinal sectional view of divider wall.
Fig. 2 is main tunnel, service channel in real-time regulation system and method for the present invention for leaning on segment deformation after controlling And the transverse sectional view of divider wall.
Fig. 3 is the flow chart of real-time regulating method of the present invention for leaning on segment deformation after controlling.
Specific embodiment
The present invention will be further explained below with reference to the attached drawings and specific examples.
Refering to fig. 1, the present invention provides a kind of for leaning on the real-time regulation system and method for segment deformation, application after controlling At the section of jurisdiction for supporting push-bench when construction by pipeline jacking method tunnel connection channel, since the push-bench in construction by pipeline jacking method can be leaned on to after Section of jurisdiction frequently loads-unloads, and push-bench must impact the overburden potential that section of jurisdiction additionally applies to section of jurisdiction, reality of the invention When regulating system and method can be regulated and controled in real time, by section of jurisdiction appearance after being adjusted in real time according to the rear deflection by section of jurisdiction The active force in face is achieved the purpose that after control with leaning on the deformation of section of jurisdiction after reducing to the greatest extent by segment deformation.It is right with reference to the accompanying drawing The present invention leans on the real-time regulation system of segment deformation and method to be illustrated after being used to control.
Refering to fig. 1, it is shown that the present invention be used for control after lean on segment deformation real-time regulation system and method in main tunnel, The longitudinal sectional view of service channel and divider wall.Below with reference to Fig. 1, to the present invention for leaning on the real-time of segment deformation after controlling Regulating system and method are illustrated.
As shown in Figure 1, the real-time regulation system for after control by segment deformation of the invention leans on section of jurisdiction 111 after being applied to Locate, the rear section of jurisdiction for leaning on section of jurisdiction 111 as support push-bench 31 on main tunnel 11, i.e., bears push pipe jacking counter-force work in main tunnel 11 Section of jurisdiction, push-bench 31 is used for the tunneling construction service channel 12 between two main tunnels 11, on the section of jurisdiction in main tunnel 11 The machinable part 112 of setting at the position of corresponding service channel 12 to be onstructed, the jacking jack of push-bench 31 pass through one Rear back frame with connect afterwards by section of jurisdiction 111, by the advance of jacking jack pushing tow push-bench 31, cut machinable part 112 and Tunneling construction service channel 12, when jacking and the retraction of jacking jack, the rear soil body meeting by section of jurisdiction 111 and its outside By loading-unloading operating condition.Main tunnel 11 and service channel 12 to be formed are placed in underground, i.e., are embedded in the soil body 10, It is non-reinforced structure in the soil body of main tunnel 11 and 12 periphery of service channel to be formed, the soil body is to main tunnel 11 and to be formed The outer surface of service channel 12 can apply certain Water And Earth Pressures, which acts on the appearance of the section of jurisdiction in main tunnel 11 Face, thus the rear main stress at the section of jurisdiction 111 include Water And Earth Pressures outside tunnel, push-bench driving generated reaction force and The restraining force of adjacent section of jurisdiction, when this it is rear by the discontinuity equalization of section of jurisdiction 111 when, easily deform.The present invention proposes to adjust in real time Section system leans on frequent loading-unloading operating condition of the section of jurisdiction 111 during 31 tunneling construction of push-bench after being directed to, after controlling Deformation by section of jurisdiction 111.
The real-time regulation system includes divider wall 21, detection unit and slip casting unit, as shown in connection with fig. 2, divider wall 21 After being set in the soil body 10 at section of jurisdiction 111, divider wall 21 and the rear outer surface by section of jurisdiction 111 are enclosed a seal chamber 22, The soil body 10 of the outer surface of section of jurisdiction 111 is leaned on after surrounding by the seal chamber 22.Detection unit is leaned on section of jurisdiction 111 after being mounted on, It, can also for leaning on the horizontal direction displacement of section of jurisdiction 111 after leaning on the deflection of section of jurisdiction 111, the deflection that can be after real-time detection To lean on the convergent deformation amount of section of jurisdiction 111 after being, the deformation of section of jurisdiction 111 is leaned on after can detecting in real time by detection unit.Note Slurry unit is connect with seal chamber 22 and detection unit, and slip casting unit obtains the rear deflection by section of jurisdiction 111 of detection unit detection, And the injection rate of the non-hardening capacity slurries injected into seal chamber 22 is dynamically adjusted according to deflection, to be leaned on after realizing control The deformation of section of jurisdiction 111.Slip casting unit is connect with seal chamber 22, for injecting non-hardening capacity slurries into seal chamber 22, is injected Non- hardening capacity slurries limited by the sealing of divider wall 21, and be filled in seal chamber 22, and non-hardening capacity slurries are flowing Property slurries, will not solidify, the outer surface to rear by section of jurisdiction 111 applies the soil body in the non-hardening capacity slurries and seal chamber 22 together Active force, thus slip casting unit is realized after dynamically adjusting by the injection rate of the non-hardening capacity slurries of dynamic adjustment injection Active force by the outer surface of section of jurisdiction 111 deforms after having achieved the effect that control by section of jurisdiction 111.
Preferably, bentonite slurry can be used in non-hardening capacity slurries, it can also be using a gram mud effect.
As a better embodiment of the invention, as depicted in figs. 1 and 2, with the rear divider wall 21 being connect by section of jurisdiction 111 After being set to by section of jurisdiction 11 edge and connect with rear by section of jurisdiction 111 is vertical.To which divider wall 21 is enclosed with rear by section of jurisdiction 111 Seal chamber 22 can be completely corresponding to after lean on section of jurisdiction 111 outer surface so that injection seal chamber 22 in non-hardening capacity slurries It can directly generate and correspond to (generated reaction force effect when 31 jacking of push-bench of counter-force active region after acting on section of jurisdiction 111 Range) active force, namely after acting on the entire outer surface of section of jurisdiction 111.
Rear part namely counter-force effect by section of jurisdiction 111 to correspond to push-bench 31 on the section of jurisdiction in main tunnel 11 of the invention Section of jurisdiction 111 is leaned on after being in section of jurisdiction part at area.When constructing divider wall 21, can construct four along the rear surrounding by section of jurisdiction 111 Side wall of the sequentially connected divider wall 21 as seal chamber 22 is then constructed on seal chamber 22 and facing by section of jurisdiction 111 afterwards Divider wall 21, the divider wall 21 and remaining four divider wall 21 are tightly connected, to be enclosed together with rear by section of jurisdiction 111 Seal chamber 22, and seal chamber 22 leans on the outer surface of section of jurisdiction 111 corresponding with rear, so that the non-hardening capacity slurry in injection seal chamber 22 Liquid can be generated directly act on after lean on 111 outer surface of section of jurisdiction active force.
Further, reserved injected hole is equipped on the section of jurisdiction in main tunnel 11, the present invention reserves injected hole using this and applies Work divider wall 21.Grouting Pipe is squeezed into according to reserved injected hole of the boundary of works area of divider wall 21 on section of jurisdiction, by the note of Grouting Pipe Slurry mouth is extend at the design position of divider wall 21, and then the pressure injection hardening capacity slurries into Grouting Pipe, and the hardening capacity slurries are solidifying The divider wall 21 with some strength and water proof is formd after Gu in the soil body 10, divider wall 21 is continuous wall body structure, The outside of section of jurisdiction 111 is leaned on after being located in, and is connect with the rear edge seal by section of jurisdiction 111, so as to form seal chamber 22.
Preferably, cement slurry can be used in hardening capacity slurries, cement mortar can also be used.
As another better embodiment of the invention, as shown in Figure 1, slip casting unit includes leaning on section of jurisdiction 111 from rear Mud injection pipe 23 that reserved injected hole is squeezed into seal chamber 22, the two-way slush pump being connect with the mud injection pipe 23 and with The control module of the two-way slush pump control connection;Two-way slush pump therein can be to 22 internal pressure injection slurry of seal chamber, can also be from Slurries are extracted in seal chamber 22.Control module is connect with detection unit, which can be according to detection unit real-time detection Deflection carrys out the operation of the two-way slush pump of real-time control, and two-way slush pump can control to inject non-hardening capacity slurries into seal chamber 22 With increase after lean on 111 outer surface of section of jurisdiction pressure, also can control two-way slush pump extracted out of seal chamber 22 injected it is non- Hardening capacity slurries with after reducing by section of jurisdiction 111 outer surface pressure, dynamically adjust non-hardening capacity slurries to realize Injection rate.
Deflection after detection unit detects by section of jurisdiction 111 is to deform outward, namely lean on section of jurisdiction 111 afterwards The stress of inner surface be greater than the stress of outer surface, at this time control module control two-way slush pump injected into seal chamber 22 it is non-can Rigid slurries, to lean on the pressure of the outer surface of section of jurisdiction 111 after increase, thus by the deformation of section of jurisdiction and tunnel after reducing.It is non-can be hard The injection rate of property slurries can gradually increase, referring concurrently to the deflection of real-time detection, until the deflection goes to zero or tends to connect When by the range of, the injection of non-hardening capacity slurries can be stopped.The change of section of jurisdiction 111 is leaned on after detection unit detects Shape amount is to deform inwardly, namely the stress by the outer surface of section of jurisdiction 111 is greater than the stress of inner surface, at this time control module control afterwards It makes two-way slush pump and extracts non-hardening capacity slurries from seal chamber 22, to lean on the pressure of the outer surface of section of jurisdiction 111 after reduction, thus By the deformation of section of jurisdiction and tunnel after reduction.During extracting non-hardening capacity slurries, referring concurrently to the deflection of real-time detection, When going to zero or tend in acceptable range to the deflection, the extraction of non-hardening capacity slurries can be stopped.The present invention realizes It is dynamic to adjust control, it can timely and effectively control the deformation of tunnel and section of jurisdiction.
Preferably, the mud injection pipe 23 in every endless tube on piece connects an individual two-way slush pump, using individually setting The two-way slush pump set controls the grouting amount of the mud injection pipe 23 of the section of jurisdiction of corresponding ring.The slip casting of every endless tube piece can be corresponded in this way Amount is individually controlled, and realizes the accuracy controlling of deformation.
Further, pressure sensing is connected in turn at the inner surface of section of jurisdiction 111 close to rear on mud injection pipe 23 Device and valve, pressure sensor for detecting pressure, detected by pressure be after suffered by outer surface by section of jurisdiction 111 Pressure, the pressure sensor are connect with the control module of slip casting unit, are provided reference data for the control of control module, are controlled mould Block can refer to pressure detected by pressure sensor when dynamically adjusting the injection rate of non-hardening capacity slurries, i.e., after lean on section of jurisdiction The pressure of 111 outer surfaces.Be provided with pressure limit within the control module, when pressure sensor detection pressure value be greater than etc. When the pressure limit, control module stops the injection of non-hardening capacity slurries and warning note site operation personnel are handled, So as to improve operation safety, avoids the amount of the non-hardening capacity slurries in indentation sealing chamber 22 excessive, and made to rear by section of jurisdiction At destruction.
As another better embodiment of the invention, detection unit include after being mounted on by section of jurisdiction 111 inner surface and For detecting the sensor of section of jurisdiction convergent deformation, by the deflection for leaning on section of jurisdiction 111 after the sensor real-time detection.The sensor It is connect with the control module of slip casting unit, the information of real-time detection is sent to control module.
The control module can be the control computer being arranged in main tunnel 11, and control computer is restrained according to section of jurisdiction to be become The data feedback of pressure sensor at shape sensor and mud injection pipe 23, the unlatching and closure of real-time control slush pump are adjusted Whole 22 mud injection rate of seal chamber leans on the stress condition of section of jurisdiction outer surface after adjustment, guarantee push-bench jacking stage tunnel structure The stabilization of deformation.
As another better embodiment of the invention, mud is provided at section of jurisdiction 111 close to rear in main tunnel 11 Storage bin, the Slurry Storage case are connect with two-way slush pump, and for storing non-hardening capacity slurries, two-way slush pump is by Slurry Storage Non- hardening capacity slurries in case are collected out and in pressure injections to seal chamber 22, and two-way slush pump can also can by non-in seal chamber 22 Rigid slurries are extracted out and are sent in Slurry Storage case and stored.
The principle of real-time regulation system of the invention is illustrated below: the original that tunnel structure deformation is cut with seam bolt Because being the imbalance of the surfaces externally and internally stress of section of jurisdiction.It is rear to receive the effect of jacking counter-force by section of jurisdiction in push-bench work progress, it should The main stress by section of jurisdiction includes the restraining force of jacking counter-force, tunnel outer Water And Earth Pressures and the section of jurisdiction that is connected, the pact of connected section of jurisdiction afterwards Beam force is for the pressure difference inside and outside balance tunnel.In counter-force loading-unloading, real-time regulation system dynamic adjustment sealing of the invention Chamber mud injection rate, adjustment outside Water And Earth Pressures tend to balance each other with jacking counter-force in tunnel, reduce connected section of jurisdiction constraint to the greatest extent Power and tunnel deformation.
After the completion of construction by pipeline jacking method, using the non-hardening capacity slurries in hardening capacity slurries replacement seal chamber 22, so that close Envelope chamber 22 is considered as the ruggedized construction with some strength and waterproof, then blocks the reserved injected hole of section of jurisdiction, removes related facility.
Real-time regulation system of the invention can adjust in real time counter-force and make use in Mechanical Method service channel jack-in process The active force of tunnel outer surface effectively controls counter-force and unloading is added to act on lower tunnel structure internal force, slows down " fatigue " effect, reduce tunnel Road malformation;After avoiding tunnel deformation from transfiniting, service channel is stopped work, and secondary grouting bring duration and cost increase on the outside of section of jurisdiction Add.
It is illustrated below to provided by the present invention for the real-time regulating method after control by segment deformation.
The present invention provides a kind of for leaning on the real-time regulating method of segment deformation after controlling, and is afterwards on main tunnel by section of jurisdiction The section of jurisdiction of push-bench is supported, real-time regulating method includes the following steps:
As shown in figure 3, executing step S101, a sealing is enclosed by section of jurisdiction in divider wall of constructing in the soil body, and with rear Chamber;Referring to figs. 1 and 2, in divider wall 21 of constructing in the rear soil body 10 by section of jurisdiction 111, and make divider wall 21 with after It is enclosed a seal chamber 22 by the outer surface of section of jurisdiction 111, the soil of the outer surface of section of jurisdiction 111 is leaned on after surrounding by seal chamber 22 Body;Then step S102 is executed;
It executes step S102, in push-bench construction, is dynamically adjusted in real time to close according to the rear deflection by section of jurisdiction of detection The injection rate of the non-hardening capacity slurries of intracavitary injection is sealed to lean on the deformation of section of jurisdiction after controlling.In the process of 31 tunneling construction of push-bench In, the deflection of section of jurisdiction 111 is leaned on after real-time detection, and inject into seal chamber 22 non-is dynamically adjusted according to deflection can be hard Property slurries injection rate, thus realize control after lean on section of jurisdiction 111 deformation.
Real-time regulating method of the invention main tunnel when being used for using service channel 12 between the main tunnel 11 of construction by pipeline jacking method The Deformation control of the section of jurisdiction (rear to lean on section of jurisdiction 111) supported on 11 sections of jurisdiction as push-bench 31, push-bench 31 pass through rear back frame and master Corresponding section of jurisdiction connection on tunnel 11, the rear back frame can apply counter-force to the section of jurisdiction of connection during 31 jacking of push-bench, Section of jurisdiction 111 is leaned on after being in the section of jurisdiction of the counter-force active region.Adjusting method of the invention is applied in the rear outside soil body 10 by section of jurisdiction The corresponding divider wall of work is enclosed a seal chamber using divider wall and the rear outer surface by section of jurisdiction, then by control to In seal chamber the injection rate of the non-hardening capacity slurries of injection come after adjusting by section of jurisdiction outer surface pressure, thus tube after controllable The deformation of piece.Solve the problems, such as in the prior art only the deformation extent of passive monitoring section of jurisdiction and without counter-measure, it is thus also avoided that The generation of overrun condition is deformed, so as to avoid additional the problem of increasing duration and cost.
As a better embodiment of the invention, the step of construction divider wall in the real-time regulating method, includes:
As depicted in figs. 1 and 2, Grouting Pipe is set from the reserved injected hole on the section of jurisdiction in main tunnel 11, Grouting Pipe is enabled to pass through Corresponding section of jurisdiction and squeeze into the soil body 10 on the outside of corresponding section of jurisdiction;Preferably, Grouting Pipe sets position according to divider wall Setting range determine;
Inject hardening capacity slurries into the soil body 10 by Grouting Pipe to form divider wall 21.Being formed by divider wall is tool There are certain intensity, waterproof and continuous wall.
Preferably, cement slurry can be used in hardening capacity slurries, cement mortar can also be used.
Further, when constructing divider wall 21, by section of jurisdiction after being set to the rear divider wall 21 being connect by section of jurisdiction 111 111 edge, and connect with rear by section of jurisdiction 111 is vertical.To divider wall 21 and the rear seal chamber 22 being enclosed by section of jurisdiction 111 The outer surface that section of jurisdiction 111 is leaned on after capable of being completely corresponding to enables the non-hardening capacity slurries in injection seal chamber 22 directly to produce Life corresponds to the effect of counter-force active region (range that generated reaction force acts on when 31 jacking of push-bench) on section of jurisdiction 111 after acting on Power, namely leaned on the entire outer surface of section of jurisdiction 111 after acting on.
As another better embodiment of the invention, before 31 tunneling construction of push-bench, further includes:
Mud injection pipe 23 is set from the rear reserved injected hole on section of jurisdiction 111, mud injection pipe 23 is enabled to squeeze into sealing In chamber 22;
Two-way slush pump is connected in the end being located in main tunnel 11 on mud injection pipe 23, it can by two-way slush pump Inject non-hardening capacity slurries into seal chamber 22 to lean on the pressure of 111 outer surface of section of jurisdiction after increasing, it can also be out of seal chamber 22 The non-hardening capacity slurries that are injected are extracted to lean on the pressure of 111 outer surface of section of jurisdiction after reducing, to realize dynamic adjustment The injection rate of non-hardening capacity slurries.
When the after deflection by section of jurisdiction 111 detected is outward to deform, namely the rear inner surface for leaning on section of jurisdiction 111 Stress be greater than outer surface stress, two-way slush pump injects non-hardening capacity slurries into seal chamber 22 at this time, with increase after lean on The pressure of the outer surface of section of jurisdiction 111, thus by the deformation of section of jurisdiction and tunnel after reducing.The injection rate of non-hardening capacity slurries can be gradually Increase, referring concurrently to the deflection of real-time detection, until can stop when the deflection is gone to zero or tended in acceptable range The injection of non-hardening capacity slurries.When the after deflection by section of jurisdiction 111 detected is inwardly to deform, namely lean on section of jurisdiction afterwards The stress of 111 outer surface is greater than the stress of inner surface, and two-way slush pump extracts non-hardening capacity slurries from seal chamber 22 at this time, To lean on the pressure of the outer surface of section of jurisdiction 111 after reduction, thus by the deformation of section of jurisdiction and tunnel after reducing.Extracting non-hardening capacity slurry During liquid, referring concurrently to the deflection of real-time detection, until when the deflection is gone to zero or tended in acceptable range, it can Stop the extraction of non-hardening capacity slurries.The present invention realizes dynamic adjust and controls, and can timely and effectively control tunnel and pipe The deformation of piece.
Preferably, the mud injection pipe 23 in every endless tube on piece connects an individual two-way slush pump, using individually setting The two-way slush pump set controls the grouting amount of the mud injection pipe 23 of the section of jurisdiction of corresponding ring.The slip casting of every endless tube piece can be corresponded in this way Amount is individually controlled, and realizes the accuracy controlling of deformation.
As another better embodiment of the invention, the deflection of section of jurisdiction is leaned on after real-time detection, comprising:
In the rear inner surface installation one by section of jurisdiction 111 for detecting the sensor of section of jurisdiction convergent deformation, pass through sensor reality When detection after lean on section of jurisdiction deflection.
Further, it is one control computer of two-way slush pump control connection, by control computer and is used to detect section of jurisdiction The sensor of convergent deformation connects, and the deflection of section of jurisdiction is leaned on after real-time reception, and control computer is sensed according to section of jurisdiction convergent deformation The data feedback of device, the unlatching and closure of real-time control slush pump adjust 22 mud injection rate of seal chamber, after adjustment outside section of jurisdiction The stress condition on surface guarantees the stabilization of push-bench jacking stage tunnel structure deformation.
Further, pressure sensing is connected in turn at the inner surface of section of jurisdiction 111 close to rear on mud injection pipe 23 Device and valve, pressure sensor for detecting pressure, detected by pressure be after suffered by outer surface by section of jurisdiction 111 Pressure, the pressure sensor are connect with control computer, provide reference data to control the control of computer, control computer exists Dynamic can refer to pressure detected by pressure sensor when adjusting the injection rate of non-hardening capacity slurries, i.e., after outside section of jurisdiction 111 Pressure at surface.It is provided with pressure limit within the control module, is somebody's turn to do when the pressure value of pressure sensor detection is more than or equal to When pressure limit, control module stops the injection of non-hardening capacity slurries and warning note site operation personnel are handled, thus It can be improved operation safety, avoid the amount of the non-hardening capacity slurries in indentation sealing chamber 22 excessive, and caused brokenly to rear by section of jurisdiction It is bad.
As another better embodiment of the invention, mud is provided at section of jurisdiction 111 close to rear in main tunnel 11 Storage bin, the Slurry Storage case are connect with two-way slush pump, and for storing non-hardening capacity slurries, two-way slush pump is by Slurry Storage Non- hardening capacity slurries in case are collected out and in pressure injections to seal chamber 22, and two-way slush pump can also can by non-in seal chamber 22 Rigid slurries are extracted out and are sent in Slurry Storage case and stored.
After the completion of construction by pipeline jacking method, using the non-hardening capacity slurries in hardening capacity slurries replacement seal chamber 22, so that close Envelope chamber 22 is considered as the ruggedized construction with some strength and waterproof, then blocks the reserved injected hole of section of jurisdiction, removes related facility.
The present invention has been described in detail with reference to the accompanying drawings, those skilled in the art can be according to upper It states and bright many variations example is made to the present invention.Thus, certain details in embodiment should not constitute limitation of the invention, this Invention will be using the range that the appended claims define as protection scope of the present invention.

Claims (10)

1. a kind of for leaning on the real-time regulating method of segment deformation after controlling, it is that push pipe top is born in main tunnel that section of jurisdiction is leaned on after described The section of jurisdiction acted on into counter-force, which is characterized in that the real-time regulating method includes the following steps:
In divider wall of constructing in the rear soil body by section of jurisdiction, and make the divider wall and the rear outer surface for leaning on section of jurisdiction It is enclosed a seal chamber, the soil body of the rear outer surface by section of jurisdiction is surrounded by the seal chamber;And
During the push-bench tunneling construction, the rear deflection for leaning on section of jurisdiction described in real-time detection, and according to the deformation Amount dynamically adjusts the injection rate of the non-hardening capacity slurries injected into the seal chamber, leans on section of jurisdiction after control is described to realize Deformation.
2. as described in claim 1 for leaning on the real-time regulating method of segment deformation after controlling, which is characterized in that construction isolation Wall, comprising:
Grouting Pipe is set from the reserved injected hole on the section of jurisdiction in the main tunnel, the Grouting Pipe is enabled to pass through corresponding section of jurisdiction and beat Enter to the soil body on the outside of corresponding section of jurisdiction;
Inject hardening capacity slurries into the soil body by the Grouting Pipe to form the divider wall.
3. as claimed in claim 1 or 2 for leaning on the real-time regulating method of segment deformation after controlling, which is characterized in that construction When divider wall, by with it is described after the divider wall that connect by section of jurisdiction be set to it is described after lean on the edge of section of jurisdiction, and with it is described rear by section of jurisdiction Vertical connection.
4. as described in claim 1 for leaning on the real-time regulating method of segment deformation after controlling, which is characterized in that on the top Before pipe machine tunneling construction, further includes:
Mud injection pipe is set from the reserved injected hole of the rear tube on piece, the mud injection pipe is enabled to squeeze into the sealing It is intracavitary;
Two-way slush pump is connected in the end being located in the main tunnel on the mud injection pipe, passes through the two-way mud Pump non-hardening capacity slurries can be injected into the seal chamber with increase it is described after lean on the pressure of section of jurisdiction outer surface, can also be from described The non-hardening capacity slurries injected are extracted in seal chamber to reduce the rear pressure for leaning on section of jurisdiction outer surface, to realize dynamic The injection rate of the non-hardening capacity slurries of adjustment of state and the rear pressure for leaning on section of jurisdiction outer surface.
5. as described in claim 1 for leaning on the real-time regulating method of segment deformation after controlling, which is characterized in that real-time detection The deflection of section of jurisdiction is leaned on after described, comprising:
Inner surface installation one after described by section of jurisdiction is real by the sensor for detecting the sensor of section of jurisdiction convergent deformation When detect it is described after lean on section of jurisdiction deflection.
6. a kind of for leaning on the real-time regulation system of segment deformation after controlling, it is that push pipe top is born in main tunnel that section of jurisdiction is leaned on after described The section of jurisdiction acted on into counter-force, which is characterized in that the real-time regulation system includes:
Set on the rear intracorporal divider wall of soil at section of jurisdiction, the divider wall and the rear outer surface for leaning on section of jurisdiction enclose shape At a seal chamber, the soil body of the rear outer surface by section of jurisdiction is surrounded by the seal chamber;
It is installed on the detection unit of the rear tube on piece, for the rear deflection for leaning on section of jurisdiction described in real-time detection;And
The slip casting unit being all connected with the seal chamber and the detection unit, for according to the deflection dynamically adjust to The injection rate of the non-hardening capacity slurries injected in the seal chamber controls the rear deformation for leaning on section of jurisdiction to realize.
7. as claimed in claim 6 for leaning on the real-time regulation system of segment deformation after controlling, which is characterized in that after described By section of jurisdiction connection the divider wall be set to it is described after by section of jurisdiction edge and with it is described after connect by section of jurisdiction is vertical.
8. as claimed in claim 6 for leaning on the real-time regulation system of segment deformation after controlling, which is characterized in that the slip casting Unit includes mud injection pipe and the Grouting Pipe squeezed into the seal chamber from the reserved injected hole of the rear tube on piece The two-way slush pump of connection and the control module connected with the two-way slush pump control;
The control module is connect with the detection unit, the control module two-way mud according to the deformation amount controlling It is described afterwards by the pressure of section of jurisdiction outer surface to increase that stock pump injects non-hardening capacity slurries into the seal chamber, can also be according to institute State two-way slush pump described in deformation amount controlling the non-hardening capacity slurries that are injected are extracted out of described seal chamber with reduce it is described after By the pressure of section of jurisdiction outer surface, to lean on the deformation of section of jurisdiction after realizing dynamic adjustment.
9. as claimed in claim 8 for leaning on the real-time regulation system of segment deformation after controlling, which is characterized in that the slip casting Unit further includes the pressure sensor being installed on the mud injection pipe, and the pressure sensor and the control module connect It connects, for the rear pressure initiation reference pressure data for leaning on section of jurisdiction outer surface described in real-time detection, and by detected with reference to pressure Force data is sent to the control module.
10. as claimed in claim 6 for leaning on the real-time regulation system of segment deformation after controlling, which is characterized in that the inspection Surveying unit includes being installed on the rear inner surface for leaning on section of jurisdiction and the sensor for detecting section of jurisdiction convergent deformation, by described The deflection of section of jurisdiction is leaned on after described in sensor real-time detection.
CN201811004138.3A 2018-08-30 2018-08-30 Real-time adjusting system and method for controlling deformation of back-rest duct piece Active CN109268035B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811004138.3A CN109268035B (en) 2018-08-30 2018-08-30 Real-time adjusting system and method for controlling deformation of back-rest duct piece

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811004138.3A CN109268035B (en) 2018-08-30 2018-08-30 Real-time adjusting system and method for controlling deformation of back-rest duct piece

Publications (2)

Publication Number Publication Date
CN109268035A true CN109268035A (en) 2019-01-25
CN109268035B CN109268035B (en) 2020-05-05

Family

ID=65154955

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811004138.3A Active CN109268035B (en) 2018-08-30 2018-08-30 Real-time adjusting system and method for controlling deformation of back-rest duct piece

Country Status (1)

Country Link
CN (1) CN109268035B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605923A (en) * 2021-09-18 2021-11-05 中铁第六勘察设计院集团有限公司 Subway laminated line interval tunnel connection channel structure and construction method
CN114878277A (en) * 2022-05-27 2022-08-09 中铁隧道局集团有限公司 Adjustable-density duct piece component and using method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005163382A (en) * 2003-12-03 2005-06-23 Railway Technical Res Inst Tunnel back side hollow filling method
JP2006219914A (en) * 2005-02-10 2006-08-24 Ohbayashi Corp Method of forming communicating section of juxtaposed shield tunnels
CN1916362A (en) * 2006-09-04 2007-02-21 上海隧道工程股份有限公司 Construction method for tunnel contact passage in shield section of underground railway
CN102434174A (en) * 2011-12-30 2012-05-02 中铁一局集团有限公司 Bentonite grouting method for construction of shield tunnel
CN103306684A (en) * 2012-03-08 2013-09-18 中铁隧道集团有限公司 Process for grouting on back of shield segment
CN104265326A (en) * 2014-08-06 2015-01-07 上海隧道工程有限公司 Method for controlling soil deformation in large rectangular pipe jacking
CN106948833A (en) * 2017-04-05 2017-07-14 宁波大学 Pin-connected panel service channel structure and its construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005163382A (en) * 2003-12-03 2005-06-23 Railway Technical Res Inst Tunnel back side hollow filling method
JP2006219914A (en) * 2005-02-10 2006-08-24 Ohbayashi Corp Method of forming communicating section of juxtaposed shield tunnels
CN1916362A (en) * 2006-09-04 2007-02-21 上海隧道工程股份有限公司 Construction method for tunnel contact passage in shield section of underground railway
CN102434174A (en) * 2011-12-30 2012-05-02 中铁一局集团有限公司 Bentonite grouting method for construction of shield tunnel
CN103306684A (en) * 2012-03-08 2013-09-18 中铁隧道集团有限公司 Process for grouting on back of shield segment
CN104265326A (en) * 2014-08-06 2015-01-07 上海隧道工程有限公司 Method for controlling soil deformation in large rectangular pipe jacking
CN106948833A (en) * 2017-04-05 2017-07-14 宁波大学 Pin-connected panel service channel structure and its construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605923A (en) * 2021-09-18 2021-11-05 中铁第六勘察设计院集团有限公司 Subway laminated line interval tunnel connection channel structure and construction method
CN113605923B (en) * 2021-09-18 2023-11-21 中铁第六勘察设计院集团有限公司 Subway line overlapping section tunnel connection channel structure and construction method
CN114878277A (en) * 2022-05-27 2022-08-09 中铁隧道局集团有限公司 Adjustable-density duct piece component and using method thereof

Also Published As

Publication number Publication date
CN109268035B (en) 2020-05-05

Similar Documents

Publication Publication Date Title
CN102278130B (en) Process method for reinforcing and grouting of high-pressure water-rich solution cavity of tunnel
CN104533467B (en) A kind of high artesian, the method for protecting support in fault disruption zone tunnel
CN102777189B (en) A kind of ultra-long tube curtain non-relay jacking construction device and method
CN106401645B (en) A kind of deep high stress tunnel pressure relief support control method for coordinating based on drilling release
CN103527219A (en) Tunnel supporting structure used for large deformation stratum and construction method of tunnel supporting structure
CN203515604U (en) Tunnel Support structure for schist layer in deformation
CN105370290A (en) Rectifying and reinforcing method of shield tunnels
CN108035742B (en) Active and passive harmonious support method for extremely soft coal seam roadway
CN110110489A (en) A kind of lithostratigraphy shield tunnel pressure from surrounding rock calculation method
CN113638398A (en) Active dynamic control method for stress of bag type grouting soil body
AU2020100838A4 (en) A kind of stress adjustment system for side walls of foundation pit in deep and unstable strata
CN104763436A (en) Method and device for receiving pipe jacking machine under condition of high water pressure complicated geological conditions
CN104047613A (en) Method for anchoring coal mine tunnel bottom plate
CN112832802B (en) Large-bottom plate supporting structure and method for asymmetric pressure
CN109268035A (en) For leaning on the real-time regulation system and method for segment deformation after controlling
CN110344784A (en) A kind of gushing water controlling device of the nearly horizontal orientation drilling of mine
Chang et al. Deformation and failure characteristics and control technology of roadway surrounding rock in deep coal mines
CN202970719U (en) Relay chamber-free jacking construction device for ultra-long pipe roof
Wang et al. Newly developed pressure adaptable concrete lining for high pressure hydraulic tunnels
CN104989419A (en) Tunnel early-stage support clearance-intrusion processing method and construction ancillary equipment of tunnel early-stage support clearance-intrusion processing method
CN109944236A (en) Root pile actively follows track delamination pour slurry system and construction method
CN206801564U (en) The hydraulic pressure support structure at existing station is worn under a kind of large span running tunnel super close distance
CN104074195B (en) A kind of method controlling the outer surface subsidence of foundation ditch by horizontal grouting
CN113790308A (en) Volume intelligent regulation and control air bag pile capable of reducing influence of back soil in pipe jacking construction and regulation and control method
CN110258580B (en) Construction method of foundation pit enclosure structure serving as permanent underground structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant