CN109236260A CN201811376431.2A CN201811376431A CN109236260A CN 109236260 A CN109236260 A CN 109236260A CN 201811376431 A CN201811376431 A CN 201811376431A CN 109236260 A CN109236260 A CN 109236260A
Authority
CN
China
Prior art keywords
tube
outer tube
liquid outlet
inner tube
liquid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811376431.2A
Other languages
Chinese (zh)
Other versions
CN109236260B (en
Inventor
冯强
杨晓勇
周后俊
郭鸣
王治华
李世恒
吕双
张华�
李伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
CNPC Bohai Drilling Engineering Co Ltd
Original Assignee
CNPC Bohai Drilling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNPC Bohai Drilling Engineering Co Ltd filed Critical CNPC Bohai Drilling Engineering Co Ltd
Priority to CN201811376431.2A priority Critical patent/CN109236260B/en
Publication of CN109236260A publication Critical patent/CN109236260A/en
Application granted granted Critical
Publication of CN109236260B publication Critical patent/CN109236260B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/25Methods for stimulating production
    • E21B43/26Methods for stimulating production by forming crevices or fractures
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B34/00Valve arrangements for boreholes or wells
    • E21B34/02Valve arrangements for boreholes or wells in well heads
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geophysics (AREA)
  • Jet Pumps And Other Pumps (AREA)
  • Structures Of Non-Positive Displacement Pumps (AREA)

Abstract

The present invention relates to a kind of hydro-jet fracturing technology imitative experimental appliances, including inner tube, outer tube, screw pump, upper flume and lower flume, inner pipe portion is nested in outer tube, the top side wall of inner tube is equipped with inlet, inlet is connected to upper flume by inlet tube, inner tube end side wall is equipped with liquid outlet, and outer tube top, bottom sidewall are respectively equipped with liquid outlet, lower liquid outlet, and upper liquid outlet, lower liquid outlet are connected to upper flume, lower flume by upper outlet tube, lower outlet tube respectively;Inlet tube pipeline is equipped with first pressure gauge, screw pump, and upper outlet tube pipeline is equipped with second pressure gauge, and lower outlet tube pipeline is equipped with first throttle valve and third pressure gauge;It is horizontal in lower flume to be equipped with partition, it is equipped with hydraulic pump at the top of lower flume, partition can move down under hydraulic pumping action along groove sidewall is lauched.The present invention can meet to different borehole sizes, string size, operational discharge capacity, liquid resistance-reducing yield, tool shut off ability, shaft bottom confining pressure environment injection pressure break processing simulation.

Description

A kind of hydro-jet fracturing technology imitative experimental appliance and application method
Technical field
The invention belongs to oil-gas reservoir completion technique field more particularly to a kind of hydro-jet fracturing technology imitative experimental appliances And application method.
Background technique
Hydraulic jetting fracturing technology can effectively employ reservoir reserves especially suitable for Thin oil sandwich fracturing reform, for Xin Jing and old well all have good adaptability, in recent years in the market success application such as Su Lige, Ji Dong, Hainan, fracturing effect It is substantially better than other separate stratum fracfturing modes.But will appear in application process deep-well it is low replace, circulating pressure is excessively high in perforating process Even superpressure, lead to the problems such as constructional difficulties, can not intuitive qualitative analysis, need to build experimental system for simulating.
Therefore, these problems are based on, a kind of hydro-jet fracturing technology imitative experimental appliance and application method are provided, can be expired Foot shuts off the injection of ability, shaft bottom confining pressure environment to different borehole sizes, string size, operational discharge capacity, liquid resistance-reducing yield, tool Fracturing technology simulation, facilitates the similar problem occurred in qualitative analysis site operation, has important practical significance.
Summary of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide one kind can meet to different borehole sizes, tubing string Size, operational discharge capacity, liquid resistance-reducing yield, tool shut off ability, shaft bottom confining pressure environment injection pressure break processing simulation, it is fixed to facilitate Property analysis site operation in the hydro-jet fracturing technology imitative experimental appliance and application method of the similar problem that occur.
The present invention solves its technical problem and adopts the following technical solutions to achieve:
A kind of hydro-jet fracturing technology imitative experimental appliance, including inner tube, outer tube, screw pump, upper flume and lower flume, Said inner tube part is nested in the outer tube, and the top side wall of said inner tube is equipped with inlet, and the inlet passes through feed liquor Pipe is connected to the upper flume, and said inner tube end side wall is equipped with liquid outlet, and the outer tube top, bottom sidewall are respectively equipped with Upper liquid outlet, lower liquid outlet, the upper liquid outlet, lower liquid outlet respectively by upper outlet tube, lower outlet tube be connected to upper flume, Lower flume;
The inlet tube pipeline is equipped with first pressure gauge, screw pump, and the upper outlet tube pipeline is equipped with second pressure Table, the lower outlet tube pipeline are equipped with first throttle valve and third pressure gauge;The screw pump absorbs water entrance out of upper flume Inner tube, liquid enters outer tube through the liquid outlet of inner tube and is discharged to upper flume by outer tube and upper outlet tube, to constitute cyclic system System;
It is horizontal in the lower flume to be equipped with partition, hydraulic pump is equipped at the top of the lower flume, the partition is made in hydraulic pump It can be moved down along groove sidewall is lauched under.
Further, the screw pump is equipped with frequency converter.
Further, the liquid outlet is equipped with second throttle.
The application method of hydro-jet fracturing technology imitative experimental appliance:
(1) processing simulation that different wellbores, string size combine
Screw pump is opened absorb water out of upper flume into inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and Upper outlet tube is discharged to upper flume, to constitute the circulatory system, the first throttle valve under outer tube on subordinate's outlet tube is in and is closed Closed state, by record first pressure gauge, second pressure gauge, the registration of third pressure gauge come investigate inner tube inlet pressure, Pressure on outer tube top under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;In being adjusted by replacement inner tube or appearance Bore, inner tube outside diameter, outer tube diameter, inner tube length, outer tube length dimension carry out different groups of experiments, to realize to difference The processing simulation of wellbore, string size portfolio ratio;
(3) to the processing simulation of different operational discharge capacities
Screw pump is opened absorb water out of upper flume into inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and Upper outlet tube is discharged to upper flume, to constitute the circulatory system, the throttle valve under outer tube on subordinate's outlet tube is in and closes shape State investigates pressure, the outer tube of inner tube inlet by record first pressure gauge, second pressure gauge, the registration of third pressure gauge Pressure on top under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;Pass through turning for frequency converter adjusting screw rod pump frequency conversion motor Number, and then realize the experiment of different liquids discharge capacity, to realize the processing simulation to different operational discharge capacities;
(3) processing simulation of liquid resistance-reducing yield
Screw pump is opened absorb water out of upper flume into inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and Upper outlet tube is discharged to upper flume, to constitute the circulatory system, the throttle valve under outer tube on subordinate's outlet tube is in and closes shape State investigates pressure, the outer tube of inner tube inlet by record first pressure gauge, second pressure gauge, the registration of third pressure gauge Pressure on top under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;By the way that inhomogeneity is added in the liquid into upper flume Type friction reducer, so as to adjust the liquid resistance-reducing yield in the circulatory system, to realize different resistance-reducing yields to the processing simulation of pipeline frictional resistance;
(4) shut off the processing simulation of ability to tool
Screw pump is opened absorb water out of upper flume into inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and Upper outlet tube is discharged to upper flume, to constitute the circulatory system, the throttle valve under outer tube on subordinate's outlet tube is in and closes shape State investigates pressure, the outer tube of inner tube inlet by record first pressure gauge, second pressure gauge, the registration of third pressure gauge Pressure on top under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;The second throttling on liquid outlet by controlling inner tube The aperture of valve realizes influence of the simulation tool throttling capacity to pipeline frictional resistance;
(5) processing simulation of shaft bottom confining pressure environment
Screw pump is opened absorb water out of upper flume into inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and Upper outlet tube is discharged to upper flume, to constitute the circulatory system, the throttle valve under outer tube on subordinate's outlet tube is in open shape State investigates pressure, the outer tube of inner tube inlet by record first pressure gauge, second pressure gauge, the registration of third pressure gauge Pressure on top under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;By hydraulic pump to the above space of partition in lower flume It suppresses, pressurizes to be lauched groove sidewall by partition edge and move downward to liquid, to realize different shaft bottoms in site operation Processing simulation under confining pressure environment.
The advantages and positive effects of the present invention are:
Hydro-jet fracturing technology imitative experimental appliance provided by the invention can meet to different borehole sizes, tubing string ruler Very little, operational discharge capacity, liquid resistance-reducing yield, tool shut off ability, shaft bottom confining pressure environment injection pressure break processing simulation, facilitate qualitative The similar problem occurred in analysis site operation.
Detailed description of the invention
Technical solution of the present invention is described in further detail below with reference to drawings and examples, but should Know, these attached drawings are designed for task of explanation, therefore not as the restriction of the scope of the invention.In addition, except non-specifically It points out, these attached drawings are meant only to conceptually illustrate structure construction described herein, without to be drawn to scale.
Fig. 1 is the structural schematic diagram of hydro-jet fracturing technology imitative experimental appliance provided in an embodiment of the present invention;
In figure:
1, inner tube 2, outer tube 3, liquid outlet
4, first pressure gauge 5, screw pump 6, frequency converter
7, inlet tube 8, second pressure gauge 9, upper outlet tube
10, third pressure gauge 11, first throttle valve 12, lower outlet tube
13, upper flume 14, hydraulic pump 15, partition
16, lower flume 17, inlet 18, upper liquid outlet
19, lower liquid outlet 20, second throttle
Specific embodiment
Firstly, it is necessary to which explanation, illustrates specific structure of the invention, feature and excellent for by way of example below Point etc., however what all descriptions were intended merely to be illustrated, and should not be construed as to present invention formation any restrictions.This Outside, any single technical characteristic for being described by or implying in each embodiment mentioned by this paper, still can be in these technologies spy Continue any combination between sign (or its equivalent) or delete, to obtain the sheet that may do not referred to directly herein More other embodiments of invention.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular Also it is intended to include plural form, in addition, term " includes " and " having " and their any deformation, it is intended that covering is not arranged His includes, for example, the process, method, system, product or equipment for containing a series of steps or units are not necessarily limited to clearly Those of list step or unit, but may include be not clearly listed or for these process, methods, product or equipment Intrinsic other step or units.
In the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, or be somebody's turn to do Invention product using when the orientation or positional relationship usually put, be merely for convenience of description of the present invention and simplification of the description, without It is that the device of indication or suggestion meaning or element must have a particular orientation, be constructed and operated in a specific orientation, therefore not It can be interpreted as limitation of the present invention.In addition, term " first ", " second ", " third " etc. are only used for distinguishing description, and cannot manage Solution is indication or suggestion relative importance.
It should be noted that in the absence of conflict, the features in the embodiments and the embodiments of the present application can phase Mutually combination.
The present invention just is illustrated in conjunction with Fig. 1 below.
Embodiment 1
Fig. 1 is the structural schematic diagram of hydro-jet fracturing technology imitative experimental appliance provided in an embodiment of the present invention;Such as Fig. 1 It is shown, a kind of hydro-jet fracturing technology imitative experimental appliance provided in this embodiment, including inner tube 1, outer tube 2, screw pump 5, Upper flume 13 and lower flume 16,1 part of said inner tube are nested in the outer tube 2, and the top side wall of said inner tube 1 is equipped with feed liquor Mouth 17, the inlet 17 are connected to the upper flume 13 by inlet tube 7, and 1 end side wall of said inner tube is equipped with liquid outlet 3,2 top of outer tube, bottom sidewall are respectively equipped with liquid outlet 18, lower liquid outlet 19, the upper liquid outlet 18, lower liquid outlet 19 are connected to upper flume 13, lower flume 16 by upper outlet tube 9, lower outlet tube 12 respectively;
7 pipeline of inlet tube is equipped with first pressure gauge 4, screw pump 5, and upper 9 pipeline of outlet tube is equipped with second Pressure gauge 8, lower 12 pipeline of outlet tube are equipped with first throttle valve 11 and third pressure gauge 10;The screw pump 5 is from Shang Shui Water suction enters inner tube 1 in slot 13, and liquid enters outer tube 2 through the liquid outlet 3 of inner tube 1 and is discharged to by outer tube 2 and upper outlet tube 9 Sink 13, to constitute the circulatory system;
It is horizontal in the lower flume 16 to be equipped with partition 15, hydraulic pump 14, the partition 15 are equipped at the top of the lower flume 16 It can be moved down along 16 side wall of lower flume under the effect of hydraulic pump 14.
For further, can also consider in the present embodiment: the screw pump 5 is equipped with frequency converter 6, to pass through Frequency converter realizes the revolving speed of screw pump motor, to realize the circulation of different liquids flow.
For further, can also consider in the present embodiment: the liquid outlet 3 is equipped with second throttle 20, leads to The aperture of control second throttle is crossed to realize the adjustment of liquid outlet outlet opening size.
Embodiment 2
The method for carrying out processing simulation by the hydro-jet fracturing technology imitative experimental appliance in embodiment 1:
(1) processing simulation that different wellbores, string size combine
Screw pump is opened absorb water out of upper flume into inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and Upper outlet tube is discharged to upper flume, to constitute the circulatory system, the first throttle valve under outer tube on subordinate's outlet tube is in and is closed Closed state, by record first pressure gauge, second pressure gauge, the registration of third pressure gauge come investigate inner tube inlet pressure, Pressure on outer tube top under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;In being adjusted by replacement inner tube or appearance Bore, inner tube outside diameter, outer tube diameter, inner tube length, outer tube length dimension carry out different groups of experiments, to realize to difference The processing simulation of wellbore, string size portfolio ratio;
(4) to the processing simulation of different operational discharge capacities
Screw pump is opened absorb water out of upper flume into inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and Upper outlet tube is discharged to upper flume, to constitute the circulatory system, the throttle valve under outer tube on subordinate's outlet tube is in and closes shape State investigates pressure, the outer tube of inner tube inlet by record first pressure gauge, second pressure gauge, the registration of third pressure gauge Pressure on top under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;Pass through turning for frequency converter adjusting screw rod pump frequency conversion motor Number, and then realize the experiment of different liquids discharge capacity, to realize the processing simulation to different operational discharge capacities;
(3) processing simulation of liquid resistance-reducing yield
Screw pump is opened absorb water out of upper flume into inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and Upper outlet tube is discharged to upper flume, to constitute the circulatory system, the throttle valve under outer tube on subordinate's outlet tube is in and closes shape State investigates pressure, the outer tube of inner tube inlet by record first pressure gauge, second pressure gauge, the registration of third pressure gauge Pressure on top under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;By the way that inhomogeneity is added in the liquid into upper flume Type friction reducer, so as to adjust the liquid resistance-reducing yield in the circulatory system, to realize different resistance-reducing yields to the processing simulation of pipeline frictional resistance;
(4) shut off the processing simulation of ability to tool
Screw pump is opened absorb water out of upper flume into inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and Upper outlet tube is discharged to upper flume, to constitute the circulatory system, the throttle valve under outer tube on subordinate's outlet tube is in and closes shape State investigates pressure, the outer tube of inner tube inlet by record first pressure gauge, second pressure gauge, the registration of third pressure gauge Pressure on top under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;The second throttling on liquid outlet by controlling inner tube The aperture of valve realizes influence of the simulation tool throttling capacity to pipeline frictional resistance;
(5) processing simulation of shaft bottom confining pressure environment
Screw pump is opened absorb water out of upper flume into inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and Upper outlet tube is discharged to upper flume, to constitute the circulatory system, the throttle valve under outer tube on subordinate's outlet tube is in open shape State investigates pressure, the outer tube of inner tube inlet by record first pressure gauge, second pressure gauge, the registration of third pressure gauge Pressure on top under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;By hydraulic pump to the above space of partition in lower flume It suppresses, pressurizes to be lauched groove sidewall by partition edge and move downward to liquid, to realize different shaft bottoms in site operation Processing simulation under confining pressure environment.
In conclusion can meet the present invention can provide a kind of hydro-jet fracturing technology imitative experimental appliance to different wells Eye size, string size, operational discharge capacity, liquid resistance-reducing yield, tool shut off ability, shaft bottom confining pressure environment injection fracturing technology mould It is quasi-, facilitate the similar problem occurred in qualitative analysis site operation.
Above embodiments describe the invention in detail, but content is only the preferred embodiment of the present invention, no It can be believed to be used to limit the scope of the invention.Any changes and modifications in accordance with the scope of the present application, It should still fall within the scope of the patent of the present invention.

Claims (4)

1. a kind of hydro-jet fracturing technology imitative experimental appliance, it is characterised in that: including inner tube, outer tube, screw pump, upper flume And lower flume, said inner tube part are nested in the outer tube, the top side wall of said inner tube is equipped with inlet, the inlet It is connected to the upper flume by inlet tube, said inner tube end side wall is equipped with liquid outlet, the outer tube top, bottom sidewall It is respectively equipped with liquid outlet, lower liquid outlet, the upper liquid outlet, lower liquid outlet are connected by upper outlet tube, lower outlet tube respectively To upper flume, lower flume;
The inlet tube pipeline is equipped with first pressure gauge, screw pump, and the upper outlet tube pipeline is equipped with second pressure gauge, institute Lower outlet tube pipeline is stated equipped with first throttle valve and third pressure gauge;The screw pump absorbs water out of upper flume enters inner tube, Liquid enters outer tube through the liquid outlet of inner tube and is discharged to upper flume by outer tube and upper outlet tube, to constitute the circulatory system;
It is horizontal in the lower flume to be equipped with partition, it is equipped with hydraulic pump at the top of the lower flume, the partition is under hydraulic pumping action It can be moved down along groove sidewall is lauched.
2. a kind of hydro-jet fracturing technology imitative experimental appliance according to claim 1, it is characterised in that: the screw rod Pump is equipped with frequency converter.
3. a kind of hydro-jet fracturing technology imitative experimental appliance according to claim 1, it is characterised in that: the liquid out Mouth is equipped with second throttle.
4. the application method of the described in any item hydro-jet fracturing technology imitative experimental appliances of claim 1-3, feature exist In:
(1) processing simulation that different wellbores, string size combine
Open screw pump and absorb water out of upper flume and enter inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and it is upper out Liquid pipe is discharged to upper flume, to constitute the circulatory system, the first throttle valve under outer tube on subordinate's outlet tube is in and closes shape State investigates pressure, the outer tube of inner tube inlet by record first pressure gauge, second pressure gauge, the registration of third pressure gauge Pressure on top under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;It is adjusted in inner tube by replacement inner tube or appearance Diameter, inner tube outside diameter, outer tube diameter, inner tube length, outer tube length dimension carry out different groups of experiments, to realize to different wells The processing simulation of eye, string size portfolio ratio;
(2) to the processing simulation of different operational discharge capacities
Open screw pump and absorb water out of upper flume and enter inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and it is upper out Liquid pipe is discharged to upper flume, to constitute the circulatory system, the throttle valve under outer tube on subordinate's outlet tube is in close state, and leads to Overwriting first pressure gauge, second pressure gauge, the registration of third pressure gauge investigate the pressure of inner tube inlet, on outer tube top Pressure under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;By the revolution of frequency converter adjusting screw rod pump frequency conversion motor, in turn The experiment of different liquids discharge capacity is realized, to realize the processing simulation to different operational discharge capacities;
(3) processing simulation of liquid resistance-reducing yield
Open screw pump and absorb water out of upper flume and enter inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and it is upper out Liquid pipe is discharged to upper flume, to constitute the circulatory system, the throttle valve under outer tube on subordinate's outlet tube is in close state, and leads to Overwriting first pressure gauge, second pressure gauge, the registration of third pressure gauge investigate the pressure of inner tube inlet, on outer tube top Pressure under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;By the way that different type drop resistance is added in the liquid into upper flume Agent, so as to adjust the liquid resistance-reducing yield in the circulatory system, to realize different resistance-reducing yields to the processing simulation of pipeline frictional resistance;
(4) shut off the processing simulation of ability to tool
Open screw pump and absorb water out of upper flume and enter inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and it is upper out Liquid pipe is discharged to upper flume, to constitute the circulatory system, the throttle valve under outer tube on subordinate's outlet tube is in close state, and leads to Overwriting first pressure gauge, second pressure gauge, the registration of third pressure gauge investigate the pressure of inner tube inlet, on outer tube top Pressure under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;Pass through opening for the second throttle on the liquid outlet of control inner tube Degree is to realize influence of the simulation tool throttling capacity to pipeline frictional resistance;
(5) processing simulation of shaft bottom confining pressure environment
Open screw pump and absorb water out of upper flume and enter inner tube, liquid through the liquid outlet of inner tube enter outer tube and by outer tube and it is upper out Liquid pipe is discharged to upper flume, so that the circulatory system is constituted, the throttle valve under outer tube on subordinate's outlet tube is in the open state, lead to Overwriting first pressure gauge, second pressure gauge, the registration of third pressure gauge investigate the pressure of inner tube inlet, on outer tube top Pressure under the pressure of liquid outlet, outer tube at subordinate's liquid outlet;The above space of partition in lower flume is suppressed by hydraulic pump, from And pressurizeed to liquid by partition along being lauched groove sidewall and move downward, to realize different shaft bottoms confining pressure environment in site operation Under processing simulation.
CN201811376431.2A 2018-11-19 2018-11-19 Hydraulic jet fracturing process simulation experiment device and using method Active CN109236260B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811376431.2A CN109236260B (en) 2018-11-19 2018-11-19 Hydraulic jet fracturing process simulation experiment device and using method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811376431.2A CN109236260B (en) 2018-11-19 2018-11-19 Hydraulic jet fracturing process simulation experiment device and using method

Publications (2)

Publication Number Publication Date
CN109236260A true CN109236260A (en) 2019-01-18
CN109236260B CN109236260B (en) 2020-11-03

Family

ID=65075940

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811376431.2A Active CN109236260B (en) 2018-11-19 2018-11-19 Hydraulic jet fracturing process simulation experiment device and using method

Country Status (1)

Country Link
CN (1) CN109236260B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6055874A (en) * 1999-02-02 2000-05-02 Halliburton Energy Services, Inc. Apparatus and method for simulating well bore conditions
CN202031564U (en) * 2010-12-30 2011-11-09 河南理工大学 Coal petrographic drilling hydraulic fracture experimental apparatus
CN203702138U (en) * 2014-02-27 2014-07-09 中国石油大学(北京) Experiment device of extrusion pressure of well opening after well closing of waxy oil well
CN104297128A (en) * 2014-10-28 2015-01-21 河南工程学院 Triaxial stress seepage experiment device under high pressure water and subpressure loading condition
CN206627513U (en) * 2017-04-07 2017-11-10 西南石油大学 A kind of experimental provision simulated natural gas hydrate stratum and shaked out on annular space influence
CN107882508A (en) * 2017-11-08 2018-04-06 中国石油大学(华东) Alternating temperature drilling simulation experimental facilities

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6055874A (en) * 1999-02-02 2000-05-02 Halliburton Energy Services, Inc. Apparatus and method for simulating well bore conditions
CN202031564U (en) * 2010-12-30 2011-11-09 河南理工大学 Coal petrographic drilling hydraulic fracture experimental apparatus
CN203702138U (en) * 2014-02-27 2014-07-09 中国石油大学(北京) Experiment device of extrusion pressure of well opening after well closing of waxy oil well
CN104297128A (en) * 2014-10-28 2015-01-21 河南工程学院 Triaxial stress seepage experiment device under high pressure water and subpressure loading condition
CN206627513U (en) * 2017-04-07 2017-11-10 西南石油大学 A kind of experimental provision simulated natural gas hydrate stratum and shaked out on annular space influence
CN107882508A (en) * 2017-11-08 2018-04-06 中国石油大学(华东) Alternating temperature drilling simulation experimental facilities

Also Published As

Publication number Publication date
CN109236260B (en) 2020-11-03

Similar Documents

Publication Publication Date Title
US5211242A (en) Apparatus and method for unloading production-inhibiting liquid from a well
CN103089206B (en) The system and method for improving the fluid-withdrawal rate of gas well
CN206917640U (en) The steady oil system of offshore oilfield horizontal well automatic control water
US20220098955A1 (en) Method for filling oil-gas well of fractured oil-gas reservoir with isolation particles to reduce water and increase oil production
US20120125625A1 (en) System and method for intermittent gas lift
US8978753B2 (en) Cyclonic strainer
CN104153982B (en) Method and device for acquiring characteristic curve of underground system of rod-pumped well
CN108071365B (en) Coal bed gas production, drainage and water injection integrated tubular column
AU2010300497B2 (en) Producing gas and liquid from below a permanent packer in a hydrocarbon well
CN201963286U (en) Oil production pipe for reducing water content of central pipe of horizontal well
CN109236260A (en) A kind of hydro-jet fracturing technology imitative experimental appliance and application method
CN104879097A (en) Gas well production string provided with double parallel pipes
Quintero et al. Dynamics of Multiphase Flow Regimes in Toe-Up and Toe-Down Horizontal Wells
CN107687413A (en) Up injection sucker rod pump same well production-injection device
RU49573U1 (en) PUMPING UNIT FOR SIMULTANEOUS SEPARATE OPERATION OF TWO LAYERS IN A WELL (OPTIONS)
Croce et al. Intermittent Gas Lift for Liquid Loaded Horizontal Wells in Tight Gas Shale Reservoirs
RU166990U1 (en) DEVICE FOR SIMULTANEOUSLY SEPARATE OPERATION OF TWO LAYERS IN A WELL
CN206158937U (en) Pipe type thick oil pump
CN2491622Y (en) Double acting pump for well oil water separation and refilling
CN201225129Y (en) Oil gas well selective well completion switch tool
RU2773895C1 (en) Installation for sampling gas from the annulus of an oil well
RU106677U1 (en) BODY PUMPING PLANT FOR OIL PRODUCTION AND WATER INJECTION
CN114922595B (en) Oil extraction method and oil extraction system thereof
CN205778792U (en) A kind of casing-head gas well array hydromining trachea post
CN205477549U (en) Nearly well spacing well group single tube does not have pole hydraulic pressure pilot production device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210715

Address after: 300457 Tianjin Binhai New Area Development Zone Second Avenue 83, China Petroleum Tianjin building Bohai Drilling Engineering Co., Ltd.

Patentee after: CNPC Bohai Drilling Engineering Co.,Ltd.

Patentee after: CHINA NATIONAL PETROLEUM Corp.

Address before: 300457 Tianjin Binhai New Area Development Zone Second Avenue 83, China Petroleum Tianjin building Bohai Drilling Engineering Co., Ltd.

Patentee before: CNPC Bohai Drilling Engineering Co.,Ltd.

TR01 Transfer of patent right