CN109235834A - A kind of diamond dust anticracking plays the construction technology of ash - Google Patents

A kind of diamond dust anticracking plays the construction technology of ash Download PDF

Info

Publication number
CN109235834A
CN109235834A CN201811150690.3A CN201811150690A CN109235834A CN 109235834 A CN109235834 A CN 109235834A CN 201811150690 A CN201811150690 A CN 201811150690A CN 109235834 A CN109235834 A CN 109235834A
Authority
CN
China
Prior art keywords
diamond dust
ash
concrete
construction
mesh
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811150690.3A
Other languages
Chinese (zh)
Inventor
陈步云
谢明康
陈建光
纪丹
刘文解
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN201811150690.3A priority Critical patent/CN109235834A/en
Publication of CN109235834A publication Critical patent/CN109235834A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Curing Cements, Concrete, And Artificial Stone (AREA)

Abstract

The invention discloses the construction technologies that a kind of diamond dust anticracking plays ash, comprising the following steps: step 1: the setting of construction area lattice;Step 2: material, preparation of construction;Step 3: fixed steel bars net;Step 4: casting concrete compacting strikes off;Step 5: it sheds diamond dust, smear stranding;Step 6: it smoothes out;Step 5: curing sealing agent, grinding, maintenance are smeared.The present invention adds 6@of 6m × 6m single-layer bidirectional φ, 200 reinforced mesh in concrete floor layer, height terrace layer at the middle and upper levels, using the reduction temperature stress bring influence of storehouse method is jumped when construction, diamond dust divides the assimilation effect for dividing time floating to increase diamond dust all over dispensing, it is additionally arranged curing agent, ash has been prevented, refinement has been optimized to work progress, forming quality is good, it prevents the later period from largely reprocessing, saves social resources, development cost.

Description

A kind of diamond dust anticracking plays the construction technology of ash
Technical field
The present invention relates to technical field of buildings, and the construction technology of ash is played more particularly to a kind of diamond dust anticracking.
Background technique
The ground such as industrial premises, warehouse, supermarket, heavy-duty machinery factory, mechanical repair plant, parking lot, cargo laydown area, square at present Since its vehicles while passing is more, load capacity is big, big to its wear-resistant pressure-resistant demand, for wear-resistant pressure-resistant, reduces dust and is convenient for Cleaning etc. requires, and widely applies wear-resisting diamond dust terrace.
It is also substantially cement products to diamond dust terrace, it is the production that high-mark cement is mixed with the quartz sand of different stage Object, it has the feature of cement products certainly: Ca+, Mg+ of free state do not stop that the generation for causing dust is precipitated from pore;By Hydrate acts on the loss of last water, causes to produce many pores, has in turn resulted in not fine and close therefore its intensity, resistance to Grit all weakens significantly, is usually 3 to 5 millimeters due to the thickness of diamond dust, is very easy to fall off, if the time of blanking does not have It grasps.After this thickness degree is worn, cement below has just started ash, therefore the terrace usually after using 1 year, i.e., Make there is waxing to safeguard, also inevitably scratches and wear.
Existing construction technology be 1), cast-in-place concrete or rammed earth be affixed by 120mm thickness C30 concrete;2), plain-water slurry One time (inside mixing building adhesive);3) 5mm-7mm thickness metal wear resistant material, dedicated trowelling machine are spread in, 50mm thickness C30 abrasion-proof concrete, face Compacting smoothes out.The way is simple, simple plain concrete terrace be easy to produce during this large-area construction of basement by Temperature stress and the crack occurred, and while spreading diamond dust material, once dispenses and completes again that smearing effect is not good enough, and there are the terrace later periods The disadvantages of cracking, dust protection are ineffective, construction directiveness is not strong.
Summary of the invention
The object of the invention is that providing a kind of construction technology of diamond dust anticracking ash to solve the above-mentioned problems.
The present invention through the following technical solutions to achieve the above objectives:
A kind of diamond dust anticracking plays the construction technology of ash, comprising the following steps:
Step 1: will need construction area to carry out lattice, and dividing joint spacing is 6m × 6m, slit width 10mm, stitch deep screed-coat thickness A quarter, pillar quadrangle cut by quadrangle or diamond shape, and for cutting seam from column 300mm, every piece of dividing joint area is 36 ㎡ left It is right;
Step 2: beating 70mm thickness ash cake, and spacing 1.5m-2m makes " 7 " steel bar, makes 6m × 6m reinforced mesh, binding or weldering It connects securely, is being punched with a distance from dividing joint 150mm, hole depth 60mm, aperture 12mm, pitch of holes 1000mm;
Step 3: " 7 " the steel bar long side made is inserted in the hole, later by single-layer bidirectional 6m × 6m at preprocessing steel mesh Piece welding is bound securely on " 7 " steel bar short side, and in construction using storehouse method is jumped, with 6m × 6m for one piece, two sides use 5# channel steel formwork;
Step 4: answering vibration compacting when pouring C30 concrete, with brush cement slurry with concrete is laid with, and then with 2m long darby It is struck off according to ash cake, is then rolled back and forth, in length and breadth with roller;
Step 5: being struck off with aluminium alloy foot bar, guarantees that concrete pulp noodle are substantially smooth, slurry thickness is uniform, first time spreading Buddha's warrior attendant Increase material utilization amount at sand, Mo Bian and joint-cutting, corner is reinforced, and to be hardened dose after concrete surface absorption moisture is dimmed, starts Gasoline trowelling machine smears stranding and proposes slurry, is then struck off with foot bar, and second of the spreading of remaining diamond dust, direction and last time hang down later Directly, local spreading amount is adjusted according to the thickness degree of last time spreading in right amount, is finally reached that curing agent thickness degree is uniform, and curing agent is inhaled Water it is dimmed after starting gasoline trowelling machine smear rubbing and pressure slurry, be finally reached thickness uniformly, uniform color, surfacing;
Step 6: smoothing out, and after upper complete 2 hours, basal plane concrete has sufficient intensity, Surface hardened layer oxidant layer close to final set Basic aquation gelling, slurry consistency significantly increase, and start ram compression in gasoline trowelling machine and smear, direction smoothes out repeatedly in length and breadth;
Step 7: being polished after diamond dust abrasion-resistant concrete ground base cleaning using 300 mesh sand of terrazzo machine, roller coating sealing and curing Agent 1 time, roller coating curing sealing agent the 2nd time after surface drying is polished after surface drying with 500 mesh sand, then with -800 mesh resin abrasive disc of 500 mesh Grinding 2 times conserves curing sealing agent working face 24 hours.
Preferably, " 7 " steel bar, diameter 10mm, bond length 30mm, long side length are in the step 2 110mm。
Preferably, it is 6mm, bar spacing 200mm that 6m × 6m reinforced mesh, which uses bar diameter, in the step 2.
Preferably, first time spreading diamond dust amount is the 2/3 of total amount in the step 5.
Preferably, roller coating curing sealing agent dosage is not less than 0.3L/ ㎡ in the step 7.
Compared with the existing technology, advantages of the present invention is as follows:
The present invention adds 6@of 6m × 6m single-layer bidirectional φ, 200 reinforced mesh in concrete floor layer, highly in terrace layer on Layer is influenced using jumping storehouse method and reduce temperature stress bring when construction, and diamond dust point point increases diamond dust all over smoothing out all over dispensing Assimilation effect, be additionally arranged curing agent, prevented ash, refinement is optimized to work progress, forming quality is good, prevents the later period big Amount is reprocessed, and social resources, development cost are saved.
Specific embodiment
The present invention is further illustrated combined with specific embodiments below, but the invention is not limited to these to implement Example.
Embodiment 1
A kind of diamond dust anticracking plays the construction technology of ash, and its step are as follows:
Step 1: will need construction area to carry out lattice, and dividing joint spacing is 6m × 6m, slit width 10mm, stitch deep screed-coat thickness A quarter, pillar quadrangle cut by quadrangle or diamond shape, and for cutting seam from column 300mm, every piece of dividing joint area is 36 ㎡ left It is right;
Step 2: beating 70mm thickness ash cake, and spacing 1.5m makes " 7 " steel bar, diameter 10mm, bond length 30mm, long side Length is 110mm, makes 6m × 6m reinforced mesh, bar diameter 6mm, bar spacing 200mm, binding or firm welding, It is being punched with a distance from dividing joint 150mm, hole depth 60mm, aperture 12mm, pitch of holes 1000mm;
Step 3: " 7 " the steel bar long side made is inserted in the hole, later by single-layer bidirectional 6m × 6m at preprocessing steel mesh Piece welding is bound securely on " 7 " steel bar short side, and in construction using storehouse method is jumped, with 6m × 6m for one piece, two sides use 5# channel steel formwork;
Step 4: answering vibration compacting when pouring C30 concrete, with brush cement slurry with concrete is laid with, and then with 2m long darby It is struck off according to ash cake, is then rolled back and forth, in length and breadth with roller;
Step 5: being struck off with aluminium alloy foot bar, guarantees that concrete pulp noodle are substantially smooth, slurry thickness is uniform, first time spreading Buddha's warrior attendant Increase material utilization amount at 2/3, the Mo Bian and joint-cutting of sand total amount, corner is reinforced, and to be hardened dose absorbs moisture in concrete surface and become After dark, starting gasoline trowelling machine smears stranding and proposes slurry, is then struck off with foot bar, later by second of the spreading of remaining diamond dust, direction It is vertical with last time, local spreading amount is adjusted according to the thickness degree of last time spreading in right amount, it is uniform to be finally reached curing agent thickness degree, Curing agent water suction it is dimmed after starting gasoline trowelling machine smear rubbing and pressure slurry, be finally reached thickness uniformly, uniform color, surfacing;
Step 6: smoothing out, and after upper complete 2 hours, basal plane concrete has sufficient intensity, Surface hardened layer oxidant layer close to final set Basic aquation gelling, slurry consistency significantly increase, and start ram compression in gasoline trowelling machine and smear, direction smoothes out repeatedly in length and breadth;
Step 7: being polished after diamond dust abrasion-resistant concrete ground base cleaning using 300 mesh sand of terrazzo machine, roller coating sealing and curing Agent 1 time, curing sealing agent dosage is not less than 0.3L/ ㎡, roller coating curing sealing agent the 2nd time after surface drying, with 500 mesh sand after surface drying Polishing, then ground 2 times with 500 mesh resin abrasive discs, it conserves curing sealing agent working face 24 hours.
Embodiment 2
A kind of diamond dust anticracking plays the construction technology of ash, and its step are as follows:
Step 1: will need construction area to carry out lattice, and dividing joint spacing is 6m × 6m, slit width 10mm, stitch deep screed-coat thickness A quarter, pillar quadrangle cut by quadrangle or diamond shape, and for cutting seam from column 300mm, every piece of dividing joint area is 36 ㎡ left It is right;
Step 2: beating 70mm thickness ash cake, and spacing 2m makes " 7 " steel bar, diameter 10mm, bond length 30mm, long side length Degree is 110mm, makes 6m × 6m reinforced mesh, bar diameter 6mm, bar spacing 200mm, binding or firm welding, It is punched with a distance from dividing joint 150mm, hole depth 60mm, aperture 12mm, pitch of holes 1000mm;
Step 3: " 7 " the steel bar long side made is inserted in the hole, later by single-layer bidirectional 6m × 6m at preprocessing steel mesh Piece welding is bound securely on " 7 " steel bar short side, and in construction using storehouse method is jumped, with 6m × 6m for one piece, two sides use 5# channel steel formwork;
Step 4: answering vibration compacting when pouring C30 concrete, with brush cement slurry with concrete is laid with, and then with 2m long darby It is struck off according to ash cake, is then rolled back and forth, in length and breadth with roller;
Step 5: being struck off with aluminium alloy foot bar, guarantees that concrete pulp noodle are substantially smooth, slurry thickness is uniform, first time spreading Buddha's warrior attendant Increase material utilization amount at 2/3, the Mo Bian and joint-cutting of sand total amount, corner is reinforced, and to be hardened dose absorbs moisture in concrete surface and become After dark, starting gasoline trowelling machine smears stranding and proposes slurry, is then struck off with foot bar, later by second of the spreading of remaining diamond dust, direction It is vertical with last time, local spreading amount is adjusted according to the thickness degree of last time spreading in right amount, it is uniform to be finally reached curing agent thickness degree, Curing agent water suction it is dimmed after starting gasoline trowelling machine smear rubbing and pressure slurry, be finally reached thickness uniformly, uniform color, surfacing;
Step 6: smoothing out, and after upper complete 2 hours, basal plane concrete has sufficient intensity, Surface hardened layer oxidant layer close to final set Basic aquation gelling, slurry consistency significantly increase, and start ram compression in gasoline trowelling machine and smear, direction smoothes out repeatedly in length and breadth;
Step 7: being polished after diamond dust abrasion-resistant concrete ground base cleaning using 300 mesh sand of terrazzo machine, roller coating sealing and curing Agent 1 time, curing sealing agent dosage is not less than 0.3L/ ㎡, roller coating curing sealing agent the 2nd time after surface drying, with 500 mesh sand after surface drying Polishing, then ground 2 times with 800 mesh resin abrasive discs, it conserves curing sealing agent working face 24 hours.
Embodiment described above only expresses several embodiments of the invention, and the description thereof is more specific and detailed, but not Therefore energy is interpreted as the limitation of the invention patent range.It should be pointed out that for those of ordinary skill in the art, Without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to protection model of the invention It encloses.

Claims (5)

1. the construction technology that a kind of diamond dust anticracking plays ash, it is characterised in that: the following steps are included:
Step 1: will need construction area to carry out lattice, and dividing joint spacing is 6m × 6m, slit width 10mm, stitch deep screed-coat thickness A quarter, pillar quadrangle cut by quadrangle or diamond shape, and for cutting seam from column 300mm, every piece of dividing joint area is 36 ㎡ left It is right;
Step 2: beating 70mm thickness ash cake, and spacing 1.5m-2m makes " 7 " steel bar, makes 6m × 6m reinforced mesh, binding or weldering It connects securely, is being punched with a distance from dividing joint 150mm, hole depth 60mm, aperture 12mm, pitch of holes 1000mm;
Step 3: " 7 " the steel bar long side made is inserted in the hole, later by single-layer bidirectional 6m × 6m at preprocessing steel mesh Piece welding is bound securely on " 7 " steel bar short side, and in construction using storehouse method is jumped, with 6m × 6m for one piece, two sides use 5# channel steel formwork;
Step 4: answering vibration compacting when pouring C30 concrete, with brush cement slurry with concrete is laid with, and then with 2m long darby It is struck off according to ash cake, is then rolled back and forth, in length and breadth with roller;
Step 5: being struck off with aluminium alloy foot bar, guarantees that concrete pulp noodle are substantially smooth, slurry thickness is uniform, first time spreading Buddha's warrior attendant Increase material utilization amount at sand, Mo Bian and joint-cutting, corner is reinforced, and to be hardened dose after concrete surface absorption moisture is dimmed, starts Gasoline trowelling machine smears stranding and proposes slurry, is then struck off with foot bar, and second of the spreading of remaining diamond dust, direction and last time hang down later Directly, local spreading amount is adjusted according to the thickness degree of last time spreading in right amount, is finally reached that curing agent thickness degree is uniform, and curing agent is inhaled Water it is dimmed after starting gasoline trowelling machine smear rubbing and pressure slurry, be finally reached thickness uniformly, uniform color, surfacing;
Step 6: smoothing out, and after upper complete 2 hours, basal plane concrete has sufficient intensity, Surface hardened layer oxidant layer close to final set Basic aquation gelling, slurry consistency significantly increase, and start ram compression in gasoline trowelling machine and smear, direction smoothes out repeatedly in length and breadth;
Step 7: being polished after diamond dust abrasion-resistant concrete ground base cleaning using 300 mesh sand of terrazzo machine, roller coating sealing and curing Agent 1 time, roller coating curing sealing agent the 2nd time after surface drying is polished after surface drying with 500 mesh sand, then with -800 mesh resin abrasive disc of 500 mesh Grinding 2 times conserves curing sealing agent working face 24 hours.
2. the construction technology that a kind of diamond dust anticracking according to claim 1 plays ash, it is characterised in that: in the step 2 " 7 " steel bar, diameter 10mm, bond length 30mm, long side length 110mm.
3. the construction technology that a kind of diamond dust anticracking according to claim 1 plays ash, it is characterised in that: in the step 2 6m × 6m reinforced mesh is 6mm, bar spacing 200mm using bar diameter.
4. the construction technology that a kind of diamond dust anticracking according to claim 1 plays ash, it is characterised in that: in the step 5 First time spreading diamond dust amount is the 2/3 of total amount.
5. the construction technology that a kind of diamond dust anticracking according to claim 1 plays ash, it is characterised in that: in the step 7 Roller coating curing sealing agent dosage is not less than 0.3L/ ㎡.
CN201811150690.3A 2018-09-29 2018-09-29 A kind of diamond dust anticracking plays the construction technology of ash Pending CN109235834A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811150690.3A CN109235834A (en) 2018-09-29 2018-09-29 A kind of diamond dust anticracking plays the construction technology of ash

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811150690.3A CN109235834A (en) 2018-09-29 2018-09-29 A kind of diamond dust anticracking plays the construction technology of ash

Publications (1)

Publication Number Publication Date
CN109235834A true CN109235834A (en) 2019-01-18

Family

ID=65054167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811150690.3A Pending CN109235834A (en) 2018-09-29 2018-09-29 A kind of diamond dust anticracking plays the construction technology of ash

Country Status (1)

Country Link
CN (1) CN109235834A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110607894A (en) * 2019-08-12 2019-12-24 中国建筑第二工程局有限公司 Construction method for floor of constructional engineering
CN110952752A (en) * 2019-11-21 2020-04-03 浙江二十冶建设有限公司 Method for paving anti-cracking, anti-sanding and wear-resistant ground

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107060171A (en) * 2016-12-27 2017-08-18 上海森信建设工程有限公司 The super flat reinforced concrete flooring of large area and colored diamond dust surface layer one-step moulding method
CN108019031A (en) * 2017-12-12 2018-05-11 徐州恒奥立体车库有限公司 A kind of garage abrasion-proof terrace
CN108952080A (en) * 2018-08-29 2018-12-07 启东建筑集团有限公司 Concrete dense curing agent abrasion-proof terrace monolithic construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107060171A (en) * 2016-12-27 2017-08-18 上海森信建设工程有限公司 The super flat reinforced concrete flooring of large area and colored diamond dust surface layer one-step moulding method
CN108019031A (en) * 2017-12-12 2018-05-11 徐州恒奥立体车库有限公司 A kind of garage abrasion-proof terrace
CN108952080A (en) * 2018-08-29 2018-12-07 启东建筑集团有限公司 Concrete dense curing agent abrasion-proof terrace monolithic construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110607894A (en) * 2019-08-12 2019-12-24 中国建筑第二工程局有限公司 Construction method for floor of constructional engineering
CN110952752A (en) * 2019-11-21 2020-04-03 浙江二十冶建设有限公司 Method for paving anti-cracking, anti-sanding and wear-resistant ground

Similar Documents

Publication Publication Date Title
US20240011291A1 (en) Decorative concrete with uniform surface and method of forming the same
CN106836815A (en) Large area diamond dust floor structure plate and surface layer one-off construction method
CN105587102B (en) A kind of wet construction method to the wet type high abrasion terrace that paves
CN110905162A (en) Construction method of fiber-reinforced carborundum wear-resistant ground
US7591967B2 (en) Method for the aesthetic surface treatment of a monolithic concrete floor and product of the method
CN103114728B (en) Grid construction method of large area cement wear-resisting floor
CN108952080A (en) Concrete dense curing agent abrasion-proof terrace monolithic construction method
DE102008037518B3 (en) Terrazzo floor and manufacturing process
CN107143111A (en) A kind of construction method of abrasion-proof terrace
CN106401144A (en) Construction technology for addition type wear resisting concrete ground
CN110656753A (en) Concrete grindstone terrace
CN104929365B (en) Refuse of refuse burning generating plant discharging platform combined type surface construction technology
CN109797945A (en) Abrasion-proof concrete grinding stone construction method of ground
CN111608362A (en) Hollowing-proof and cracking-proof process for concrete terrace leveling layer
CN109235834A (en) A kind of diamond dust anticracking plays the construction technology of ash
CN102251455A (en) Vibration-free anti-slip lane and construction method thereof
CN110607894A (en) Construction method for floor of constructional engineering
CN107246123A (en) A kind of terrace composite coating and its preparation technology
CN107060271A (en) A kind of dust-proof hardened artiwear method for constructing terrace
CN102777015A (en) Integrally-cast steel rib millstone terrace and construction process thereof
CN105544935A (en) Cement terrace production method
CN207959466U (en) A kind of Waterstones ground drain structure
CN111946083B (en) Cement mortar surface layer of polypropylene packing belt net for reinforcing masonry structure and construction method
CN104452583A (en) Composite anti-skidding abrasion layer, and preparation method and application of composite anti-skidding abrasion layer
CN110835997A (en) One-step construction molding construction process for wear-resistant terrace and structural plate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190118