CN109208737B - Construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation - Google Patents

Construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation Download PDF

Info

Publication number
CN109208737B
CN109208737B CN201811180792.XA CN201811180792A CN109208737B CN 109208737 B CN109208737 B CN 109208737B CN 201811180792 A CN201811180792 A CN 201811180792A CN 109208737 B CN109208737 B CN 109208737B
Authority
CN
China
Prior art keywords
well
plugging
new pipe
pipe
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811180792.XA
Other languages
Chinese (zh)
Other versions
CN109208737A (en
Inventor
曹祝华
聂承庆
李应姣
徐伟
张幸举
王宏斌
邱拥军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Urban Rail Engineering Co Ltd
Original Assignee
China Railway 11th Bureau Group Urban Rail Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 11th Bureau Group Urban Rail Engineering Co Ltd filed Critical China Railway 11th Bureau Group Urban Rail Engineering Co Ltd
Priority to CN201811180792.XA priority Critical patent/CN109208737B/en
Publication of CN109208737A publication Critical patent/CN109208737A/en
Application granted granted Critical
Publication of CN109208737B publication Critical patent/CN109208737B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F7/00Other installations or implements for operating sewer systems, e.g. for preventing or indicating stoppage; Emptying cesspools
    • E03F7/02Shut-off devices

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)

Abstract

The invention provides a construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation. The construction method specifically comprises the steps of firstly constructing a new pipe receiving well beside an existing working well adjacent to an original sewage pipeline, and sinking the wall of the existing working well to enable the new pipe receiving well to be communicated with the existing working well; then, temporary plugging flashboard is adopted in the existing working well to temporarily plug the original sewage pipe, the temporary plugging flashboard comprises a grid steel frame and a steel baffle, after the temporary plugging flashboard is installed, a diver descends into the well to plug the original sewage pipe at the downstream part of the temporary plugging flashboard by using masonry strip stones, and after the plugging is completed, underwater concrete is poured between the temporary gate valve and the plug. According to the invention, the temporary flashboard is adopted for temporary plugging, so that the impact force of water flow can be reduced, the impact force of water flow on divers and plugging walls is reduced, the operation risk is reduced, the plugging construction quality is improved, and the construction risk in the subway deep foundation pit excavation process is reduced.

Description

Construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation
Technical Field
The invention relates to a construction method for plugging a sewage pipeline by constructing a new pipe receiving well outside an existing sewage working well, plugging the new pipe receiving well with an original pipe working well, and then arranging a temporary flashboard in the original pipe working well to create a safe environment for a diver to work underwater.
Background
Along with the rapid development of urban subways, large sewage pipelines often exist in the subway construction process to cross station foundation pits, the most critical steps in the transfer and modification process are connection and plugging construction, and many projects have water leakage accidents in the later foundation pit excavation process because the original pipelines are not plugged in place. The plugging construction must be performed by divers, however, for large sewage pipelines, because the impact force of water flow is large, the large sewage pipelines do not have the condition of diving at all, so how to ensure the plugging quality of the original pipelines after the large sewage pipelines are changed becomes the primary problem. Taking subway stations in certain city as an example, a sewage pipeline with the diameter of 2400mm exists in the range of a station foundation pit and spans across the foundation pit, the pipeline is a main water inlet pipeline leading to a sewage treatment plant and is responsible for the collection and conveying tasks of sewage at the periphery of 209 square kilometers, the inner diameter of the pipeline is 2400mm, the outer diameter of the pipeline is 2880mm, the pipeline is originally constructed by adopting a pipe jacking method, the pipeline is permanently transferred and wound to the outer side of the foundation pit, the connection and the plugging construction are carried out through a current working well, the daily average flow of the pipeline is about 40 ten thousand m < 3 >/day, the water flow impact force is larger, the current working well does not have diving operation conditions, and effective measures are needed to be taken before plugging to relieve the water flow impact force, so that a diver can safely operate underwater.
Disclosure of Invention
According to the method, the new pipeline and the original pipeline can be well connected, the original pipeline can be plugged, the connection and plugging construction in the process of the transition are completed, the plugging difficult problem of the large sewage pipeline can be well solved, the plugging construction quality is guaranteed, and the construction risk is avoided for later subway construction.
The technical scheme provided by the invention is as follows: the construction method for connecting a new pipe and plugging an original pipe in the transition of a large sewage pipeline is characterized by comprising the following specific steps:
(1) Constructing a new pipe connecting hole communicated with a new pipe adjacent to the existing working well of the original sewage pipe, and sinking a wall of the existing working well to enable the new pipe connecting hole to be communicated with the existing working well after the new pipe is constructed;
(2) The temporary plugging flashboard comprises a grid steel frame and a steel baffle, the lower parts of the grid steel frame and the steel baffle are cut into arc shapes which are the same as the radian of a pipeline, the grid steel frame is vertically inserted into a launder of the existing working well, then the support piece is used for reinforcing and tightly supporting the launder, and then the steel baffle is inserted into the upstream surface for plugging;
(3) After the temporary plugging flashboard is installed, a diver goes into the well to plug the original sewage pipeline at the downstream part of the temporary plugging flashboard by using masonry strip stones;
(4) And after the plug reaches the strength, plugging a gap between the steel grid steel frame and the well wall by adopting a filler, and pouring underwater concrete between the temporary gate valve and the plug after plugging is completed.
The invention further adopts the technical scheme that: the construction steps of the new pipe receiving well in the step (1) are as follows:
a. constructing a new pipe receiving well by adopting an open cut reverse construction method, wherein the new pipe receiving well is a hexagonal reverse well or a quadrilateral square well, the excavation length is 9-11 m, the excavation width is 5.5-7 m, the well wall thickness is 0.5-1 m, and the well depth is the same as the depth of the existing working well; the outer ring of the construction new pipe receiving well is reinforced by adopting double rows of high-pressure jet grouting piles with the diameter of 800mm and the interval of 600mm, the bottom is reinforced by adopting high-pressure jet grouting piles to fill a hall, and the reinforcing depth is at least 2m below the bottom plate;
b. reserving a new pipe and old pipe connection hole when constructing a new pipe receiving well, and reserving a hole door ring beam construction position at the connection hole;
c. after the construction of the new pipe receiving well structure is completed, the existing working well wall at the connection opening of the new pipe and the old pipe is removed in a layering way by adopting a water drill coring way, the thickness of each time of removing is not more than 20cm, a wall body with 20cm is reserved, and after the water drill removing is completed, the well, a launder and a hole ring beam are manufactured in the new pipe receiving well along the launder direction;
d. after the construction of the well, the launder and the opening ring beam is completed, closing the flashboard in the newly built pipeline, starting to inject water into the newly built receiving well, ensuring that the water level is equal to the water level in the original sewage well, and then arranging the diver to use the pneumatic pick to chisel the last remaining 20cm wall of the old well and bricking the launder under water.
The invention further adopts the technical scheme that: the grid steel frame in the step (2) is a steel bar grid bracket which is formed by welding channel steel and has the same shape as that of the steel baffle plate, a plurality of supporting pieces are arranged at the rear side of the grid steel frame, the shape of the upper parts of the grid steel frame and the steel baffle plate is matched with that of the inner cavity of the existing working well, and after the grid steel frame and the steel baffle plate are installed, the edge of the grid steel frame is contacted with the inner wall of the existing working well; the arc-shaped part of the grid steel frame is downwards arranged on one side close to the water outlet of the existing working well, the arc-shaped part of the grid steel frame is fixed on the well wall of the existing working well through a plurality of supporting pieces on the rear side of the arc-shaped part, sliding grooves are respectively welded on two sides of the upstream surface of the grid steel frame, and two sides of the steel baffle are inserted from the upper part of the sliding grooves and fixedly clamped with the grid steel frame through the sliding grooves.
The invention has the preferable technical scheme that: the grid steel frame in the step (2) is formed by welding 40#a channel steel, the supporting piece is H20 section steel, and the steel baffle plate is a thick steel plate with the thickness of 20 mm; and (3) the filling material in the step (3) is cotton wool or a sand bag.
The invention has the preferable technical scheme that: when the wall of the last 20cm of the new pipe and old pipe connecting hole is chiseled, the outline outer ring of the reserved hole is first densely arranged and cored, the radial width is 500mm, the depth is 500mm, the reserved 200mm is reserved, a cast-in-place pipe is constructed after the completion, a water stop adhesive tape is applied between the cast-in-place pipe and the wall of the old well, a grouting pipe is pre-buried, and the grouting is used for preventing sewage leakage; after the cast-in-situ pipe construction is completed, water is injected into the new pipe receiving well, the water level is ensured to be the same as that in the existing working well, and then the diver dives to perform the residual well wall chiseling.
The invention has the preferable technical scheme that: and c, the wall thickness of the well constructed in the step (c) is 0.5m, the clear width is 4m, and the construction is carried out by adopting a sequential construction method.
The invention has the beneficial effects that:
(1) According to the invention, a new pipe receiving well is dug near the original sewage pipeline working well and is communicated with the new pipe, and then the new pipe receiving well is communicated with the working well, so that the original pipe and the new pipe can be quickly and safely connected, and the connection construction effect of the new pipe can be ensured;
(2) The invention firstly connects the original pipe and the new pipe through a new pipe receiving well, introduces the water in the original pipe into the new pipe, reduces the water flow in the original pipe, and is convenient for the later construction;
(3) When the original pipe is plugged, the temporary flashboard is adopted for temporary plugging, so that the impact force of water flow can be reduced, the impact force of water flow on divers and a plugging wall is reduced, the operation risk is reduced, the plugging construction quality is improved, and the construction risk in the process of excavating a deep foundation pit of a subway is further reduced;
(4) The temporary flashboard adopts a mode of combining the grid steel frame and the steel baffle, the lower part of the temporary flashboard is provided with an arc shape which is the same as the radian of a runner of a working well, the temporary flashboard can be accurately inserted into the runner to carry out temporary plugging, and the two parts are separately installed, the grid steel frame is firstly installed, the impact force of flowing water is reduced, the problem that the flashboard is inclined under the impact action of water flow in the installation process is solved, the steel frame can be ensured to be installed at a proper position, and then the steel baffle is further installed to carry out closure plugging;
(5) In the plugging process, the position where the temporary gate is in contact with the launder or the pipe wall is filled with the cotton wool, so that the water seepage quantity can be reduced, and a relatively calm water flow working environment is provided for plugging operation.
Drawings
FIGS. 1 to 4 are flowcharts of construction for transferring a new pipe to original sewage in the invention;
FIGS. 5 and 6 are flowcharts of the original sewer pipe plugging construction of the present invention;
FIG. 7 is a cross-sectional view of FIG. 5;
FIG. 8 is a top view of FIG. 6;
FIG. 9 is a schematic front view of a temporary shutoff gate;
FIG. 10 is a schematic side view of a temporary shutoff gate;
fig. 11 is a schematic view of a structure of a grid steel frame in a temporary plugging shutter.
In the figure: 1-grid steel frame, 2-steel baffle plates, 3-supporting parts, 4-original sewage pipes, 5-existing working wells, 6-cotton wadding filling materials, 7-sliding grooves, 8-new pipe receiving wells, 9-new pipe replacement, 10-bricking plugs, 11-drilling holes, 12-lifting lugs, 13-elder Guan connecting hole lines and 14-well-in-well.
Detailed Description
The invention will be further described with reference to the drawings and examples. The concrete structure of the temporary plugging flashboard in the embodiment of the invention is shown in fig. 9 and 10, and comprises a grid steel frame 1 and a steel baffle plate 2, wherein the steel baffle plate 2 adopts a thick steel plate with the thickness of 20mm, and the lower part of the steel baffle plate 2 is cut into an arc shape with the radian identical to that of the lower part of an original sewage pipe 4; the grid steel frame 1 is a steel grid support which is formed by welding channel steel and has the same shape as that of the steel baffle plate 2, a plurality of supporting pieces 3 are arranged on the rear side of the grid steel frame 1, the grid steel frame 1 adopts 40# a channel steel, and the supporting pieces 3 adopt H20 steel. The spacing between two adjacent transverse and longitudinal groove steels in the grid steel frame 1 is 500mm. The upper parts of the grid steel frame 1 and the steel baffle plate 2 are matched with the inner cavity of the existing working well 5 in shape, and after the grid steel frame is installed, the edges of the grid steel frame and the steel baffle plate are contacted with the inner wall of the existing working well 5. As shown in fig. 11, a chute 7 for fixing the steel baffle plate 2 is welded to each of the two sides of the upstream surface of the grid steel frame 1.
The invention is further described by combining implementation, the embodiment takes the change of a sewage pipeline of a certain subway station as an example, a sewage pipeline with DN2400 at the position of the subway station traverses a foundation pit, and the original pipeline is constructed by adopting a pipe jacking method; the top plate of the subway station has a height of 82.928m and a burial depth of about 4m, the current state D2400 sewage pipe has a height of 78.36m and a burial depth of about 8.6m at the pipe bottom of the crossing part with the subway station; the current situation D2400 sewage pipe collides with the project subway station in elevation, needs to be changed, and is provided with a new pipe according to a planned change route, the new pipe is laid and changed, the joint of the new pipe and the old pipe is changed, and the old pipe is blocked by adopting the method for construction, the concrete steps are as follows:
(1) The new pipe receiving well is constructed beside the existing working well adjacent to the original sewage pipeline, and the concrete construction steps are as follows:
a. as shown in fig. 1, the new pipe receiving well is constructed by adopting an open-cut reverse construction method, the new pipe receiving well is a hexagonal reverse well or a quadrilateral square well, the new pipe receiving well is specifically selected according to the shape of the existing working well, the excavation length of the new pipe receiving well is 9-11 m, the excavation width of the new pipe receiving well is 5.5-7 m, the thickness of a well wall is 0.5-1 m, and the well depth of the new pipe receiving well is the same as the depth of the existing working well; the outer ring of the construction new pipe receiving well is reinforced by adopting double rows of high-pressure jet grouting piles with the diameter of 800mm and the interval of 600mm, the bottom is reinforced by adopting high-pressure jet grouting piles to fill a hall, and the reinforcing depth is at least 2m below the bottom plate; the new pipe is communicated with the new pipe;
b. reserving a new pipe and old pipe connection hole when constructing a new pipe receiving well, and reserving a hole door ring beam construction position at the connection hole;
c. as shown in fig. 2, the existing working well walls at the connection openings of the new pipe and the old pipe are chiseled in a layered manner by adopting a water drill coring mode, the chiseling thickness is not more than 20cm each time, the phenomenon of water leakage is observed in the side wall chiseling process, and finally the wall body is reserved for 20cm (containing single-row steel bars); then as shown in figure 3, a well-in well is constructed in the new pipe receiving well along the direction of the launder, the wall thickness is 0.5m, the clear width is 4m, the well-in well is constructed by adopting a forward construction method, after the construction of the well-in well is finished, the launder and the portal ring beam are started to be constructed, after the ring beam construction is finished, firstly, the outline outer ring of the portal is reserved, the core is densely arranged, the radial width is 500mm, the depth is 500mm, the diameter is reserved for 200mm, a cast-in-place pipe is constructed after the construction is finished, a water stop adhesive tape is constructed between the cast-in-place pipe and the wall of the old well, and a grouting pipe is pre-buried, so that grouting can prevent sewage leakage;
d. after the construction of the well, the launder and the opening ring beam in the well is completed, closing a flashboard in the newly built pipeline, starting to fill water into the newly built receiving well, ensuring that the water level is equal to the water level in the original sewage well, and then arranging a diver to use a pneumatic pick to chisel the last left 20cm wall of the old well and lay the launder under water;
(2) The temporary plugging flashboard is adopted in the existing working well to temporarily plug the original sewage pipe, the temporary plugging flashboard comprises a grid steel frame and a steel baffle plate, the lower parts of the grid steel frame and the steel baffle plate are cut into arc shapes which are the same as the radian of a pipeline, as shown in fig. 5 and 7, the grid steel frame is vertically inserted into a launder of the existing working well, is reinforced and tightly pressed on the wall of the working well through a support piece 3 at the rear side, then the steel baffle plate 2 is inserted into a chute on the upstream surface of the grid steel frame 1 and is fixed, and after the steel baffle plate 2 is installed, in order to reduce the seepage amount, a relatively calm water flow working environment is provided for plugging operation; in order to avoid water seepage, cotton wool or sand bag filling materials can be filled at the joint of the grid steel frame 1 and the steel baffle plate 2 and the pipeline to be plugged;
(3) After the temporary plugging flashboard is installed, a diver goes into the well to plug the original sewage pipeline at the downstream part of the temporary plugging flashboard by using masonry strip stones;
(4) And after the plug reaches the strength, plugging gaps between the steel grid steel frame and the well wall by adopting a filler, pouring underwater concrete between the temporary gate valve and the plug after plugging is completed, wherein schematic diagrams after plugging are shown in fig. 6 and 8.
The embodiment reduces the underwater operation as much as possible, shortens the construction period compared with the original design, ensures the connection quality, adopts a temporary flashboard to temporarily block when the original pipe is blocked, reduces the impact force of water flow on divers and blocking walls, reduces the operation risk and improves the blocking construction quality.

Claims (4)

1. A construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation is characterized by comprising the following specific steps:
(1) Constructing a new pipe connecting hole communicated with a new pipe adjacent to the existing working well of the original sewage pipe, and sinking a wall of the existing working well to enable the new pipe connecting hole to be communicated with the existing working well after the new pipe is constructed;
the construction steps of the new pipe receiving well are as follows:
a. constructing a new pipe receiving well by adopting an open cut reverse construction method, wherein the new pipe receiving well is a hexagonal reverse well or a quadrilateral square well, the excavation length is 9-11 m, the excavation width is 5.5-7 m, the well wall thickness is 0.5-1 m, and the well depth is the same as the depth of the existing working well; the outer ring of the construction new pipe receiving well is reinforced by adopting double rows of high-pressure jet grouting piles with the diameter of 800mm and the interval of 600mm, the bottom is reinforced by adopting high-pressure jet grouting piles to fill a hall, and the reinforcing depth is at least 2m below the bottom plate;
b. reserving a new pipe and old pipe connection hole when constructing a new pipe receiving well, and reserving a hole door ring beam construction position at the connection hole;
c. after the construction of the new pipe receiving well structure is completed, the existing working well wall at the connection hole of the new pipe and the old pipe is removed in a layered way by adopting a water drill coring mode, the thickness of each time of removing is not more than 20cm, a wall body with 20cm is reserved, and then a well in the well, a launder and a hole ring beam are applied in the new pipe receiving well along the launder direction;
d. after the construction of the well, the launder and the opening ring beam in the well is completed, closing a flashboard in the newly built pipeline, starting to fill water into the newly built receiving well, ensuring that the water level is equal to the water level in the original sewage well, and then arranging a diver to use a pneumatic pick to chisel the last left 20cm wall of the old well and lay the launder under water;
(2) Temporary plugging flashboard is adopted in the existing working well to temporarily plug the original sewage pipe, the temporary plugging flashboard comprises a grid steel frame and a steel baffle, the lower parts of the grid steel frame and the steel baffle are cut into arc shapes which are the same as the radian of a pipeline, the grid steel frame is vertically inserted into a launder of the existing working well, then the supporting piece is used for reinforcing and tightly supporting the existing working well in place, and then the steel baffle is inserted into the upstream surface for plugging; the grid steel frame is a steel bar grid bracket which is formed by welding channel steel and has the same shape as the steel baffle plate, a plurality of supporting pieces are arranged at the rear side of the grid steel frame, the shape of the upper parts of the grid steel frame and the steel baffle plate is matched with that of the inner cavity of the existing working well, and after the grid steel frame and the steel baffle plate are installed, the edge of the grid steel frame is contacted with the inner wall of the existing working well; the arc-shaped part of the grid steel frame is downwards arranged at one side close to the water outlet of the existing working well, the arc-shaped part is fixed on the well wall of the existing working well through a plurality of supporting pieces at the rear side of the arc-shaped part, sliding grooves are respectively welded at the two sides of the upstream surface of the grid steel frame, and the two sides of the steel baffle are inserted from the upper part of the sliding grooves and fixedly clamped with the grid steel frame through the sliding grooves;
(3) After the temporary plugging flashboard is installed, a diver goes into the well to plug the original sewage pipeline at the downstream part of the temporary plugging flashboard by using masonry strip stones;
(4) And after the plug reaches the strength, plugging a gap between the steel grid steel frame and the well wall by adopting a filler, and pouring underwater concrete between the temporary gate valve and the plug after plugging is completed.
2. The construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation according to claim 1, wherein the construction method is characterized in that: the grid steel frame in the step (2) is formed by welding 40#a channel steel, the supporting piece is H20 section steel, and the steel baffle plate is a thick steel plate with the thickness of 20 mm; and (3) the filling material in the step (3) is cotton wool or a sand bag.
3. The construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation according to claim 1, wherein the construction method is characterized in that: when the wall of the last 20cm of the new pipe and old pipe connecting hole is chiseled, the outline outer ring of the reserved hole is first cored in a close-packed way, the wall of the well is designed to be 700mm, the wall of the well is taken out to be 500mm, the wall of the well is reserved to be 200mm, a door ring beam is constructed after the completion, a water stop adhesive tape is applied between a cast-in-situ pipe and the wall of the old well, a grouting pipe is pre-buried, and grouting is performed to prevent sewage leakage; after the construction of the portal gird beam is completed, water is injected into the new pipe receiving well, the water level is ensured to be the same as that in the existing working well, and then the diver dives to perform the residual well wall chiseling.
4. The construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation according to claim 1, wherein the construction method is characterized in that: and c, constructing the well in the step c, wherein the wall thickness of the well is 0.5m, the clear width is 4m, and constructing by adopting a sequential construction method.
CN201811180792.XA 2018-10-09 2018-10-09 Construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation Active CN109208737B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811180792.XA CN109208737B (en) 2018-10-09 2018-10-09 Construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811180792.XA CN109208737B (en) 2018-10-09 2018-10-09 Construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation

Publications (2)

Publication Number Publication Date
CN109208737A CN109208737A (en) 2019-01-15
CN109208737B true CN109208737B (en) 2024-02-06

Family

ID=64979523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811180792.XA Active CN109208737B (en) 2018-10-09 2018-10-09 Construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation

Country Status (1)

Country Link
CN (1) CN109208737B (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736416B (en) * 2019-01-24 2020-07-03 安徽省公路桥梁工程有限公司 New and old sewage pipeline deep well point connecting structure and construction method
CN109763556A (en) * 2019-01-29 2019-05-17 广东隆建工程有限公司 The construction method that a kind of bilge well and sewage network change its course
CN110080369B (en) * 2019-05-20 2020-08-11 中国二十冶集团有限公司 Cross sewage drainage pipeline construction method without interrupting sewage drainage
CN110965487B (en) * 2019-12-20 2023-12-08 广西建工集团第五建筑工程有限责任公司 Down-pass passage high-flow reverse-suction siphon sewage pipe and encapsulation treatment construction method
CN111236387B (en) * 2020-01-17 2021-05-25 中铁十二局集团有限公司 Construction method for connecting newly-built sewage pipe with existing sewage pipe
CN111456091B (en) * 2020-04-16 2021-04-13 上海市浦东新区建设(集团)有限公司 Pressure sewage pipe diversion method
CN112112249B (en) * 2020-09-15 2022-03-11 北京建工土木工程有限公司 Rapid construction method for non-stop water touch connection of newly-built sewage pipeline and main pipeline
CN112112246A (en) * 2020-09-22 2020-12-22 齐力建设集团有限公司 Temporary gate plate for large-scale sewage pipeline connection construction and construction method thereof
CN112282029B (en) * 2020-11-05 2022-01-18 上海交通建设总承包有限公司 Connection construction method for urban high-water-level large-diameter reinforced concrete sewage pipeline
CN113279429B (en) * 2021-07-01 2023-04-25 葛洲坝集团生态环保有限公司 Underground diversion operation plugging structure and plugging method
CN113445609B (en) * 2021-07-13 2022-12-20 中国建筑第四工程局有限公司 Well chamber prefabricated by municipal rainwater and sewage and well chamber pipe orifice plugging construction method
CN113700115A (en) * 2021-09-06 2021-11-26 中铁四局集团路桥工程有限公司 Suspension protection construction method for municipal drainage closed conduit steel pipe transformation
CN114753471B (en) * 2022-04-19 2023-10-03 五矿二十三冶建设集团有限公司 New and old sewage pipeline water connection construction method suitable for rectangular sewage well
CN114908856A (en) * 2022-06-14 2022-08-16 中交(广州)建设有限公司 Auxiliary well structure for connecting newly-built pipeline with existing well chamber and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201003207Y (en) * 2006-08-16 2008-01-09 无锡市排水管理处 Sewer pipe plug device
JP2016014290A (en) * 2014-07-03 2016-01-28 オリエンタル白石株式会社 Temporary shutoff method of existing underwater structure
CN107859145A (en) * 2017-11-17 2018-03-30 广州市自来水工程公司 A kind of drainpipe is plugged into construction method under water
CN108118770A (en) * 2017-12-29 2018-06-05 厦门城联科技有限公司 A kind of subdrainage channel traffic system
CN108222220A (en) * 2018-01-31 2018-06-29 杭州市市政工程集团有限公司 The construction method of new and old sewage pipe connection in a kind of sewage pipe displacement transformation
CN209053200U (en) * 2018-10-09 2019-07-02 中铁十一局集团城市轨道工程有限公司 A kind of interim flashboard suitable for the construction of down-stream pipe plugging

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201003207Y (en) * 2006-08-16 2008-01-09 无锡市排水管理处 Sewer pipe plug device
JP2016014290A (en) * 2014-07-03 2016-01-28 オリエンタル白石株式会社 Temporary shutoff method of existing underwater structure
CN107859145A (en) * 2017-11-17 2018-03-30 广州市自来水工程公司 A kind of drainpipe is plugged into construction method under water
CN108118770A (en) * 2017-12-29 2018-06-05 厦门城联科技有限公司 A kind of subdrainage channel traffic system
CN108222220A (en) * 2018-01-31 2018-06-29 杭州市市政工程集团有限公司 The construction method of new and old sewage pipe connection in a kind of sewage pipe displacement transformation
CN209053200U (en) * 2018-10-09 2019-07-02 中铁十一局集团城市轨道工程有限公司 A kind of interim flashboard suitable for the construction of down-stream pipe plugging

Also Published As

Publication number Publication date
CN109208737A (en) 2019-01-15

Similar Documents

Publication Publication Date Title
CN109208737B (en) Construction method for new pipe connection and original pipe plugging in large sewage pipeline relocation
CN109778992B (en) Horse riding well device for pipeline construction and construction method thereof
CN106120801B (en) Pipeline crosses the construction method at foundation ditch in water-rich sand layer
CN113669073B (en) Construction method for controlling adjacent building deformation of water-rich sandy stratum by tunneling before station
CN110306449A (en) A kind of connection method of new box culvert and existing road box culvert
CN111236387B (en) Construction method for connecting newly-built sewage pipe with existing sewage pipe
CN111733827A (en) Station yard deep foundation pit protection construction method under adjacent high-speed rail complex environment silt geology
CN112412472B (en) Pipe-jacking working well wall reverse-acting system in soft soil area and construction method and application thereof
CN113152518A (en) Water-rich stratum foundation pit pile plate wall inter-pile gravel reverse-filtration seepage-proofing structure and construction method
CN211816279U (en) New and old ground is wall interface processing structure even
CN115450221A (en) Construction method for subway crossing river channel
CN116398165A (en) New tunnel penetrating through existing station at zero distance and construction method thereof
CN110486062A (en) A kind of method of mechanical tunneling multilayer multispan underground engineering in weak soil
CN217870532U (en) Backfill structure for pipeline construction
CN110565740B (en) Method for connecting open hole of submarine tunnel and riser
CN114232602A (en) Underground continuous pile construction process
CN112228121A (en) Be applicable to tunnel corrosive water matter slip casting water shutoff reinforced structure
CN113266362A (en) Top pipe cover excavation construction method for penetrating through existing dense anchor cable area
CN102720202A (en) Foundation pit supporting and protecting structure of underground continuous wall and construction method of structure
CN217630349U (en) Sewage new and old pipe network connection system based on reverse construction method pipe jacking well
CN218969976U (en) Pushing structure suitable for pushing method construction continuous wall
CN113585237B (en) Diaphragm wall joint and diaphragm wall construction method
CN114855766B (en) Construction method of revetment lattice type underground continuous wall structure
CN214784160U (en) Gravel reverse-filtering anti-seepage structure between piles of pile plate wall of foundation pit in water-rich stratum
CN113529693B (en) Construction method for penetrating pipeline through cutter-suction type corner amplitude diaphragm wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Cao Zhuhua

Inventor after: Nie Chengqing

Inventor after: Li Yingjiao

Inventor after: Xu Wei

Inventor after: Zhang Xingju

Inventor after: Wang Hongbin

Inventor after: Qiu Yongjun

Inventor before: Cao Zhuhua

Inventor before: Nie Chengqing

Inventor before: Xu Wei

Inventor before: Zhang Xingju

Inventor before: Li Yingjiao

Inventor before: Wang Hongbin

Inventor before: Qiu Yongjun

GR01 Patent grant
GR01 Patent grant