CN109205459A - A kind of suspender and production method of the plastering bucket for building a wall - Google Patents
A kind of suspender and production method of the plastering bucket for building a wall Download PDFInfo
- Publication number
- CN109205459A CN109205459A CN201710543978.6A CN201710543978A CN109205459A CN 109205459 A CN109205459 A CN 109205459A CN 201710543978 A CN201710543978 A CN 201710543978A CN 109205459 A CN109205459 A CN 109205459A
- Authority
- CN
- China
- Prior art keywords
- cross
- reinforcing bar
- suspender
- building
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/22—Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks
- B66C1/34—Crane hooks
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A kind of suspender of the plastering bucket for building a wall, including upright bar and double-layer cross frame, it is characterized by: the upright bar is diameter >=20mm, length >=957mm steel pipe (2), the double-layer cross frame (3) is the identical reinforcing bar cross brace of two structure and size sizes, wherein: lower layer's cross center and the bottom end of pole steel tube are welded and fixed, it is welded and fixed in the middle part of upper layer cross and upright bar, upright bar is vertical with reinforcing bar cross brace plane.The suspender and production method of plastering bucket for building a wall of the invention have hanger structure simple, easy to make, 2-8 plastering bucket can be once lifted according to actual needs, the advantages of greatly improving work efficiency, speed up the work and reduce engineering cost.
Description
Technical field
The present invention relates to a kind of suspenders of building wall construction site, specifically, being a kind of plastering for building a wall
The suspender and production method of bucket.
Background technique
In November, 2016, Yunnan Coca-Cola project management department civil engineering secondary structure, which is built, enters construction peak period, secondary structure
Building materials are using building block and stirring ash is added, and build a wall up to 12m.Construction personnel is constructed using scaffold building, high aerial
It needs building block brick and stirring ash to be transported on height scaffolding operating platform.Construction personnel is using electric block as haulagman
Tool also can not meet construction speed if construction efficiency if substantially reduces one barrel of plastering bucket, one barrel of transport equipped with mortar.
Therefore the means of transportation of known plastering bucket there are problems that it is above-mentioned various inconvenient and.
Summary of the invention
The purpose of the present invention is to propose a kind of suspender of quick, efficient plastering bucket for building a wall.
It is another object of the present invention to propose a kind of suspender production side of quick, efficient plastering bucket for building a wall
Method.
To achieve the above object, the technical solution of the invention is as follows:
A kind of suspender of the plastering bucket for building a wall, including upright bar and double-layer cross frame, it is characterised in that:
The upright bar is diameter >=20mm, length >=957mm steel pipe, is equipped with suspension hook on the top of steel pipe;
The double-layer cross frame is the identical reinforcing bar cross brace of two structure and size sizes, four branch of reinforcing bar cross brace
Pole length is equal, and the upper layer cross of double-layer cross frame and lower layer's cross are arranged in parallel, is spaced 400mm;Reinforcing bar cross
Each strut ends of bracket, which are equipped with, hooks seat, to hook plastering bucket lifting rope;
Wherein: lower layer's cross center and the bottom end of pole steel tube are welded and fixed, and are welded and fixed in the middle part of upper layer cross and upright bar,
Upright bar is vertical with reinforcing bar cross brace plane.
The suspender of plastering bucket for building a wall of the invention can also be further achieved by the following technical measures.
It is previously described for the suspender of plastering bucket built a wall, wherein the suspension hook is diameter 50mm annulus.
It is previously described for the suspender of plastering bucket built a wall, wherein four piece branch of the cross by diameter 12mm, long 400mm
Bar is formed by welding.
It is previously described for the suspender of plastering bucket built a wall, wherein the seat that hooks is that the reinforcing bar that two parallel intervals are arranged is short
Bar, reinforcing bar quarter butt are perpendicularly fixed at strut ends, and two reinforcing bar quarter butts constitute hooking end open upwards.
A kind of suspender production method of the plastering bucket for building a wall, it is characterised in that the following steps are included:
A, upright bar and suspension hook production: a diameter 20mm, long 957mm steel pipe is taken to make upright bar, steel pipe upper end is welded and fixed always
Diameter is that 50mm annulus makees suspension hook, and annulus is that 20mm round steel makes with diameter;
B, reinforcing bar cross brace makes: taking two diameters is 12mm, long 800mm reinforcing bar, it is made to be mutually perpendicular to weld with respective midpoint
It connects fixation and lower layer's cross is made;Lower layer's cross center is welded and fixed with steel pipe lower end, and steel pipe is vertical with cross plane;
Upper layer cross is made with same method, is welded and fixed in the middle part of upper layer cross center and steel pipe, makes upper layer cross and lower layer
The spacing of cross is 400mm;
C, the reinforcing bar quarter butt of two parallel intervals setting is respectively welded in eight strut ends of double-layer cross frame, and reinforcing bar quarter butt is vertical
Strut ends are fixed on, two reinforcing bar quarter butts constitute hook seat open upwards, to hook plastering bucket lifting rope.
The suspender production method of the plastering bucket for building a wall of the invention can also be using technical measures below come into one
Step is realized.
Method above-mentioned, wherein the reinforcing bar quarter butt is diameter 8mm, long 50mm reinforcing bar.
After adopting the above technical scheme, the suspender and production method of the plastering bucket for building a wall of the invention are with following excellent
Point:
1, hanger structure is simple, easy to make;
2,2-8 plastering bucket can be once lifted according to actual needs, greatly improved work efficiency;
3, it speeds up the work, reduces engineering cost.
Detailed description of the invention
Fig. 1 is the hanger structure schematic diagram of the plastering bucket of the embodiment of the present invention.
In figure: 1 suspension hook, 2 steel pipes, 3 crosses, 4 hook seat.
Specific embodiment
With reference to embodiments and its attached drawing further explains the present invention.
Embodiment 1
The suspender of plastering bucket for building a wall of the invention, including upright bar and double-layer cross frame.
Referring now to the hanger structure schematic diagram for the plastering bucket that Fig. 1, Fig. 1 are the embodiment of the present invention.As shown, described vertical
Bar is diameter 20mm, length 957mm steel pipe 2, is equipped with suspension hook 1 on the top of steel pipe, the suspension hook is diameter 50mm annulus.
The double-layer cross frame 3 be the identical reinforcing bar cross brace of two structure and size sizes, the four of reinforcing bar cross brace
Strut lengths are equal, and the upper layer cross of double-layer cross frame and lower layer's cross are arranged in parallel, are spaced 400mm;Reinforcing bar
Each strut ends of cross brace, which are equipped with, hooks seat 4, to hook plastering bucket lifting rope;The cross is by diameter 12mm, length
Four struts of 400mm are formed by welding.Described to hook the reinforcing bar quarter butt that seat is the setting of two parallel intervals, reinforcing bar quarter butt is vertically solid
Due to strut ends, two reinforcing bar quarter butts constitute hooking end open upwards.
Lower layer's cross center and the bottom end of pole steel tube are welded and fixed, and are welded and fixed in the middle part of upper layer cross and upright bar,
Upright bar is vertical with reinforcing bar cross brace plane.
Embodiment 2
The suspender production method of plastering bucket for building a wall of the invention, comprising the following steps:
A, upright bar and suspension hook production: a diameter 20mm, long 957mm steel pipe 2 is taken to make upright bar, steel pipe upper end is welded and fixed always
Diameter is that 50mm annulus makees suspension hook 1, and annulus is that 20mm round steel makes with diameter;
B, reinforcing bar cross brace makes: taking two diameters is 12mm, long 800mm reinforcing bar, it is made to be mutually perpendicular to weld with respective midpoint
It connects fixation and lower layer's cross is made;Lower layer's cross center is welded and fixed with 2 lower end of steel pipe, and steel pipe and cross plane are hung down
Directly;Upper layer cross is made with same method, is welded and fixed in the middle part of upper layer cross center and steel pipe 2, make upper layer cross with
The spacing of lower layer's cross is 400mm;
C, the reinforcing bar quarter butt of two parallel intervals setting is respectively welded in eight strut ends of double-layer cross frame 3, and reinforcing bar quarter butt hangs down
Strut ends are directly fixed on, two reinforcing bar quarter butts constitute hook seat 4 open upwards, to hook plastering bucket lifting rope.The steel
Muscle quarter butt is diameter 8mm, long 50mm reinforcing bar.
The suspender of plastering bucket for building a wall of the invention is in use, only need to be in each hook of the double-layer cross frame 3 of suspender
The symmetrical lifting of hanging seat 4 plastering bucket, can meet lifting requirements, can once lift 2-8 plastering bucket according to actual needs.
The present invention has substantive distinguishing features and a significant technological progress, the suspender of the plastering bucket for building a wall of the invention and
Production method, suspender production is simple, easy to operate, greatly improves work efficiency, and has wide promotion prospect.
The suspender and production method of plastering bucket for building a wall of the invention are secondary in Yunnan Coca-Cola project management department civil engineering
It is used in structure masonry project, significant effect.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field
Member, without departing from the spirit and scope of the present invention, can also make various transformation or variation.Therefore, all equivalent
Technical solution also should belong to scope of the invention, should be limited by each claim.
Claims (6)
1. a kind of suspender of the plastering bucket for building a wall, including upright bar and double-layer cross frame, it is characterised in that:
The upright bar is diameter >=20mm, length >=957mm steel pipe (2), is equipped with suspension hook (1) on the top of steel pipe;
The double-layer cross frame (3) be the identical reinforcing bar cross brace of two structure and size sizes, four of reinforcing bar cross brace
Strut lengths are equal, and the upper layer cross of double-layer cross frame and lower layer's cross are arranged in parallel, are spaced 400mm;Reinforcing bar ten
Each strut ends of word bracket, which are equipped with, hooks seat (4), to hook plastering bucket lifting rope;
Wherein: lower layer's cross center and the bottom end of pole steel tube are welded and fixed, and are welded and fixed in the middle part of upper layer cross and upright bar,
Upright bar is vertical with reinforcing bar cross brace plane.
2. the suspender of the plastering bucket as described in claim 1 for building a wall, which is characterized in that the suspension hook is diameter 50mm circle
Ring.
3. the suspender of the plastering bucket as described in claim 1 for building a wall, which is characterized in that the cross is by diameter
12mm, long 400mm four struts be formed by welding.
4. the suspender of the plastering bucket as described in claim 1 for building a wall, which is characterized in that the hook seat is two parallel
Spaced reinforcing bar quarter butt, reinforcing bar quarter butt are perpendicularly fixed at strut ends, and two reinforcing bar quarter butts constitute hook open upwards
End.
5. a kind of suspender production method of the plastering bucket for building a wall, it is characterised in that the following steps are included:
A, upright bar and suspension hook production: a diameter 20mm, long 957mm steel pipe (2) is taken to make upright bar, steel pipe upper end is welded and fixed one
Diameter is that 50mm annulus is made suspension hook (1), and annulus is that 20mm round steel makes with diameter;
B, reinforcing bar cross brace makes: taking two diameters is 12mm, long 800mm reinforcing bar, it is made to be mutually perpendicular to weld with respective midpoint
It connects fixation and lower layer's cross is made;Lower layer's cross center is welded and fixed with steel pipe (2) lower end, and steel pipe and cross plane are hung down
Directly;Upper layer cross is made with same method, is welded and fixed in the middle part of upper layer cross center and steel pipe (2), makes upper layer cross
Spacing with lower layer cross is 400mm;
C, the reinforcing bar quarter butt of two parallel intervals setting, reinforcing bar quarter butt is respectively welded in eight strut ends of double-layer cross frame (3)
Strut ends are perpendicularly fixed at, two reinforcing bar quarter butts constitute hook seat (4) open upwards, to hook plastering bucket lifting rope.
6. the suspender production method of the plastering bucket as described in claim 1 for building a wall, which is characterized in that the reinforcing bar quarter butt
For diameter 8mm, long 50mm reinforcing bar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710543978.6A CN109205459A (en) | 2017-07-05 | 2017-07-05 | A kind of suspender and production method of the plastering bucket for building a wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710543978.6A CN109205459A (en) | 2017-07-05 | 2017-07-05 | A kind of suspender and production method of the plastering bucket for building a wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109205459A true CN109205459A (en) | 2019-01-15 |
Family
ID=64992237
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710543978.6A Pending CN109205459A (en) | 2017-07-05 | 2017-07-05 | A kind of suspender and production method of the plastering bucket for building a wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109205459A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2377845A (en) * | 1944-05-26 | 1945-06-05 | Robert W Westfall | Barrel tongs |
CN101323413A (en) * | 2008-07-16 | 2008-12-17 | 戴纪荣 | Pipe hanger and manufacturing method thereof |
CN201553530U (en) * | 2009-11-13 | 2010-08-18 | 周宏伟 | Hanging tool for processing surface |
CN201777786U (en) * | 2010-09-17 | 2011-03-30 | 天津灯塔涂料工业发展有限公司 | Hoisting group hook |
CN204096895U (en) * | 2014-09-25 | 2015-01-14 | 株洲市华晟实业有限公司 | A kind of two-layer equation shot-blasting machine suspender |
-
2017
- 2017-07-05 CN CN201710543978.6A patent/CN109205459A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2377845A (en) * | 1944-05-26 | 1945-06-05 | Robert W Westfall | Barrel tongs |
CN101323413A (en) * | 2008-07-16 | 2008-12-17 | 戴纪荣 | Pipe hanger and manufacturing method thereof |
CN201553530U (en) * | 2009-11-13 | 2010-08-18 | 周宏伟 | Hanging tool for processing surface |
CN201777786U (en) * | 2010-09-17 | 2011-03-30 | 天津灯塔涂料工业发展有限公司 | Hoisting group hook |
CN204096895U (en) * | 2014-09-25 | 2015-01-14 | 株洲市华晟实业有限公司 | A kind of two-layer equation shot-blasting machine suspender |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102864936B (en) | Combination lifting construction method for large-scale high hollow building roof of steel structure | |
CN105484502B (en) | A kind of industrial premises steel structural roof purlin and support bar combined installation method | |
CN105201195A (en) | Liftable supporting leg type elevator shaft construction platform and method | |
CN203794456U (en) | Cast-in-place concrete pile reinforcement cage lifting appliance | |
CN211736298U (en) | Double-rod diagonal cantilever scaffold | |
CN103643800A (en) | Lifting installation system for buckling restrained supporting member and construction method thereof | |
CN104295077A (en) | Annular hanging platform for mounting stove shell of hot-blast stove, and mounting and dismounting method thereof | |
CN107217836A (en) | A kind of construction hanging basket suspension arrangement for steel construction shelter bridge | |
CN217105096U (en) | Deep well support wall concrete pouring and distributing system | |
CN211689948U (en) | Suspension operation platform device for construction of suspension cable at tower part of cable-stayed bridge | |
CN109205459A (en) | A kind of suspender and production method of the plastering bucket for building a wall | |
CN209742389U (en) | Alignment positioning machine tool for casting ribs of prefabricated column | |
CN107201725A (en) | A kind of steel box-girder decoration hanging scaffold and its construction method | |
CN203877726U (en) | Multi-hoisting-point hoisting beam for turning over and hoisting equipment | |
CN207110442U (en) | The connector that a kind of scaffold uses | |
CN105350761A (en) | Installation method of I-steel cantilevered external scaffolding | |
CN210597326U (en) | Precast concrete bearing structure that can assemble | |
CN204282816U (en) | A kind of girder template | |
CN204510767U (en) | The basket operating platform of Novel hanging | |
CN203583484U (en) | Space moving hoist frame of light assembly type tube-following drilling drawbench | |
CN209556318U (en) | A bracket formula bearing structure for scaffold frame is set up | |
CN103643790B (en) | It is applicable to the self-crawling type operating platform of colossal column | |
CN207633773U (en) | A kind of glomeration building prefabricated construction reinforcing bar guiding tube dismounting system | |
CN207063488U (en) | A kind of construction hanging basket suspension arrangement for steel construction shelter bridge | |
CN206768858U (en) | Assembled external application construction elevator base steel plinth |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190115 |