CN109186034A CN201811113701.0A CN201811113701A CN109186034A CN 109186034 A CN109186034 A CN 109186034A CN 201811113701 A CN201811113701 A CN 201811113701A CN 109186034 A CN109186034 A CN 109186034A
Authority
CN
China
Prior art keywords
concubine
gas
chemical experiment
pipeline
chamber system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811113701.0A
Other languages
Chinese (zh)
Inventor
王建祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Everest Laboratory System Engineering Co Ltd
Original Assignee
Suzhou Everest Laboratory System Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Everest Laboratory System Engineering Co Ltd filed Critical Suzhou Everest Laboratory System Engineering Co Ltd
Priority to CN201811113701.0A priority Critical patent/CN109186034A/en
Publication of CN109186034A publication Critical patent/CN109186034A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F7/00Ventilation
    • F24F7/04Ventilation with ducting systems, e.g. by double walls; with natural circulation
    • F24F7/06Ventilation with ducting systems, e.g. by double walls; with natural circulation with forced air circulation, e.g. by fan positioning of a ventilator in or against a conduit
    • F24F7/08Ventilation with ducting systems, e.g. by double walls; with natural circulation with forced air circulation, e.g. by fan positioning of a ventilator in or against a conduit with separate ducts for supplied and exhausted air with provisions for reversal of the input and output systems
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/12Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Ventilation (AREA)

Abstract

The present invention relates to a kind of chemical experiment chamber systems, chemical experiment chamber system includes the building structure body to form space, ceiling board of the tabula in the middle part of building structure body in above-below direction, installation space positioned at ceiling board top, it is used to carry out the laboratory of experimental implementation positioned at ceiling board lower part, laboratory includes main chamber and concubine, chemical experiment chamber system further includes air cleaning system, the gas extracting device for quickly extracting secondary indoor gas out being connected to concubine, chemical test chamber system further includes gas supplementary device, gas supplementary device includes supplementing pipeline and the first blower on supplement pipeline;The chemical experiment chamber system can be avoided air cleaning system (air-conditioning) and supplement a large amount of gas into main chamber, avoid air cleaning system highly energy-consuming, it substantially reduces laboratory electric energy and uses burden, it avoids high-power more air-conditioning equipments while using, to alleviate the expense expenditure of the setting of air-conditioning equipment.

Description

A kind of chemical experiment chamber system
Technical field
The present invention relates to laboratory overall construction design fields, and in particular to a kind of chemical experiment chamber system.
Background technique
Chemical laboratory is to provide chemical experiment condition and its carries out the important place of scientific exploration.There is a large amount of instrument in it Device: the experimental tools such as iron stand, asbestos gauge, chemicals cabinet, alcolhol burner.In chemical laboratory, experimental implementation can produce often Raw foul smell, moisture and the toxic and harmful gas such as inflammable, explosive, perishable prevent in experiment to protect the safety of user Toxic and harmful gas spread in experiment, it will usually laboratory is separated into the multiple regions including main chamber and concubine, it is main Room be detained for a long time with personnel and operate it is some without chemical test that is poisonous and harmful, thering is gas with foreign flavor to generate, it is then special in concubine It operates and places for be also easy to produce chemical test that is poisonous and harmful, having gas with foreign flavor and some be also easy to produce poisonous and harmful substance Experiment drug, tool, therefore concubine need to be provided with the extractor fan of the toxic and harmful gas quickly extracted, in order to Generate it is poisonous and harmful quickly draw it out (extraction amount need to reach 2000m3/h), and then avoid harm to the human body, existing skill It need to be supplemented from main chamber in art from the gas that concubine extracts, can also remain that the pressure of concubine is lower than the pressure of main chamber in this way Power, so that the toxic and harmful gas of concubine is avoided to flow in main chamber, however entire laboratory is closed space, is tested indoor Air is then entirely the purification that purification air-conditioning (and using high-power, more air-conditionings are just able to satisfy gas supplement demand) provides Air, a large amount of extract then need a large amount of gas supplement of air-conditioning, and whole system runs unusual power consumption, and energy waste is very tight Weight.The power load in city is especially even more seriously increased in summer.
Summary of the invention
The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and provide a kind of chemical experiment chamber system.
In order to solve the above technical problems, the technical solution adopted by the present invention is as follows:
A kind of chemical experiment chamber system, chemical experiment chamber system include the building structure body to form space, in above-below direction tabula Ceiling board in the middle part of building structure body, positioned at the installation space on ceiling board top, positioned at ceiling board lower part for being tested The laboratory of operation, laboratory include main chamber and concubine, and chemical experiment chamber system further includes empty for providing purification into main chamber The air cleaning system of gas, the gas extracting device for quickly extracting secondary indoor gas out being connected to concubine, chemical test Chamber system further includes the gas supplementary device for the make-up gas into concubine being connected to concubine, and gas supplementary device includes will The supplement pipeline and the first blower on supplement pipeline that outside air is connected to concubine.
Preferably, gas supplementary device further includes inside concubine for incuding the air pressure of concubine internal gas pressure Sensor, control the first blower driving motor revolving speed controller, baroceptor connect with controller signals, controller root The driving motor revolving speed of the first blower is controlled according to the induction information of baroceptor.
Preferably, the parameter value for the relative pressure being arranged in controller is -5pa, and the driving motor of the first blower is electrodeless Variable speed electric motors, particularly, when baroceptor senses secondary indoor relative pressure lower than -5pa, controller controls the drive of the first blower Dynamic motor accelerates rotation, and when baroceptor senses that secondary indoor relative pressure is equal to -5pa, controller controls the first wind The driving motor constant revolution of machine, when baroceptor senses that secondary indoor relative pressure is higher than -5pa, controller control The driving motor underdrive of first blower.By the intelligence cooperation between sensor and controller, when so that system starting, begin Keeping concubine eventually is in the state of tiny structure, so that secondary indoor toxic and harmful gas be avoided to flow backward in main chamber, avoids safe thing Part occurs.
Preferably, there are two concubine settings, two concubines are located at the two sides of main chamber.Convenient for carrying out a variety of generations simultaneously The experimental implementation of poisonous and harmful substance discharge, applicability are stronger.
Preferably, supplement pipeline includes the first main pipeline, is respectively communicated between the first main pipeline and the concubine of two sides First subtube and the second subtube;First main pipeline is located in installation space, and the entrance of the first main pipeline is provided with house In the one side wall of structural body, the first blower is set on the first main pipeline, the first subtube and the second subtube from installation space to Under extend across ceiling board respectively to two sides concubine top.(the first main pipeline and the first subtube and the second subtube Junction connected by triple valve threeway, and synchronized in gas through the first main pipeline and be passed through the first subtube and the second subtube When middle, triple valve can guarantee that the gas flow being passed through in the first subtube and the second subtube is equal.
Preferably, gas extracting device includes extracting pipeline and the second blower on extraction pipeline out, extracts pipeline packet out The third subtube and the 4th subtube for including the second main pipeline, being respectively communicated between the second main pipeline and the concubine of two sides;The Two main pipelines are located in installation space, and the outlet of the second main pipeline is provided on another side wall of building structure body, the second wind Machine is set on the second main pipeline, and third subtube and the 4th subtube extend downward and through ceiling board respectively extremely by installation space The top of the concubine of two sides.Supplement pipeline and each pipeline extracted out in pipeline are reasonably spaced apart mounting hole is interior.
Preferably, ceiling board hangs the inside for being located at building structure body by the more full thread sunpenders vertically extended In the middle part of space, supplement pipeline and extraction pipeline, which pass through full thread sunpender and hang, to be located in installation space.Full thread sunpender is not only right Ceiling board is lifted, and can also hang set each main pipeline and subtube in above-below direction.So that structure design is more reasonable, take It is more convenient to build work.
Preferably, air cleaning system includes being set to the airhandling equipment outside building structure body, being set on ceiling board Ventilation opening, the purge pipe that is connected between airhandling equipment and ventilation opening, purge pipe penetrates installation space by outside It is connected to afterwards with ventilation opening.
Preferably, air cleaning system include VRV air-conditioner outdoor unit outside the building structure body and with the air conditioning chamber VRV It is that outer machine is connected to by connecting pipe and be located at main indoor VRV air conditioner indoor unit.
Preferably, ceiling board hangs the inside for being located at building structure body by the more full thread sunpenders vertically extended In the middle part of space, purge pipe, connecting pipe pass through full thread sunpender and are lifted in installation space.
Due to the implementation of above technical scheme, the invention has the following advantages over the prior art:
Chemical experiment chamber system of the invention carries out having poisonous and harmful generation in concubine by the way that gas supplementary device is arranged When test operation, when gas collection apparatus extracts toxic and harmful gas out, which can be quickly from the external world by gas Body fills into concubine, to avoid concubine extraction gas by leading indoor gas come the case where supplement;To avoid air Purification system (air-conditioning) supplements a large amount of gas into main chamber, avoids air cleaning system highly energy-consuming, substantially reduces experiment Room electric energy is also avoided high-power more air-conditioning equipments while being used using burden, thus alleviate the setting of air-conditioning equipment Expense expenditure.
Detailed description of the invention
Fig. 1 is the main view of chemical laboratory overall system architecture of the invention;
Wherein: 100, building structure body;10, the first blower;11, the first main pipeline;12, the first subtube;13, second is in charge of Road;20, the second blower;21, the second main pipeline;22, third subtube;23, the 4th subtube;30, airhandling equipment;31, Purge pipe;32, ventilation opening;33, VRV air-conditioner outdoor unit;34, connecting pipe;35, VRV air conditioner indoor unit;S1, installation space; S2, main chamber;S3, concubine;A1, ceiling board;A2, full thread sunpender;A3, fixed link;A4, pendant.
Specific embodiment
The present invention will be further described in detail with specific embodiment with reference to the accompanying drawing.
As shown in Figure 1, a kind of chemical experiment chamber system, chemical experiment chamber system includes the building structure body to form space 100, in above-below direction ceiling board a1 of the tabula at the middle part of building structure body 100, the installation space s1 positioned at the top ceiling board a1, It is used to carry out the laboratory of experimental implementation positioned at the lower part ceiling board a1, laboratory includes main chamber s2 and concubine s3, chemical laboratory System further include for providing the air cleaning system of purification air into main chamber s2, being used for concubine s3 of being connected to concubine s3 The gas extracting device that interior gas is quickly extracted out, chemical test chamber system further include being connected to concubine s3 for into concubine s3 The gas supplementary device of make-up gas, gas supplementary device include by supplement pipeline that outside air is connected to concubine s3 and being set to Supplement the first blower 10 on pipeline.
In this example, air cleaning system includes the airhandling equipment 30 being set to outside building structure body 100, is set to furred ceiling Ventilation opening 32 on plate a1, the purge pipe 31 being connected between airhandling equipment 30 and ventilation opening 32, purge pipe 31 by Outside is connected to after penetrating installation space s1 with ventilation opening 32.Air cleaning system includes the VRV outside building structure body 100 Air-conditioner outdoor unit 33 and the air conditioning chamber VRV that is being connected to VRV air-conditioner outdoor unit 33 by connecting pipe 34 and being located in main chamber s2 Interior machine 35.
Further, gas supplementary device further includes inside concubine s3 for incuding concubine s3 internal gas pressure Baroceptor, control the first blower 10 driving motor revolving speed controller, baroceptor connect with controller signals, Controller controls the driving motor revolving speed of the first blower 10 according to the induction information of baroceptor.In this example, set in controller The parameter value for the relative pressure set is -5pa, and the driving motor of the first blower 10 is electrodeless variable-speed motor, when baroceptor sense When should arrive relative pressure in concubine s3 lower than -5pa, the driving motor that controller controls the first blower 10 accelerates to rotate so that the One blower 10 accelerates make-up gas, when baroceptor senses that the relative pressure in concubine s3 is equal to -5pa, controller control The driving motor constant revolution for making the first blower 10, when baroceptor senses that the relative pressure in concubine s3 is higher than -5pa When, controller controls the driving motor underdrive of the first blower 10 so that 10 deceleration make-up gas of the first blower.Pass through sensing Intelligence cooperation between device and controller when so that system starting, remains that concubine s3 is in the state of tiny structure, to avoid Toxic and harmful gas in concubine s3 flows backward in main chamber s2, avoids security incident.In addition, by air cleaning system to Be passed through clean gas in main chamber s2, and the relative pressure in main chamber s2 be maintained at 5pa, that is, remain in main chamber s2 in it is micro- just Pressure condition can also be flow backwards even if there is of short duration micro-positive pressure in concubine s3 in this way to avoid toxic and harmful gas in concubine s3 To main chamber s2, so that the toxic and harmful gas further effectivelying prevent in concubine s3 flows backward in main chamber s2.
In this example, there are two concubine s3 settings, two concubine s3 are located at the two sides of main chamber s2.Convenient for carrying out simultaneously A variety of experimental implementations for generating poisonous and harmful substance discharge, applicability are stronger.Supplement pipeline in this example includes the first main pipeline 11, the first subtube and the second subtube being respectively communicated between the first main pipeline 11 and the concubine s3 of two sides;First supervisor Road 11 is located in installation space s1, and the entrance of the first main pipeline 11 is provided in the one side wall of building structure body 100, the first wind Machine 10 is set on the first main pipeline 11, and the first subtube and the second subtube extend downward and through ceiling board by installation space s1 A1 respectively to two sides concubine s3 top.The junction of first main pipeline 11 and the first subtube and the second subtube passes through three Port valve threeway connection, and when gas is synchronized through the first main pipeline 11 and is passed through in the first subtube and the second subtube, triple valve It can guarantee that the gas flow being passed through in the first subtube and the second subtube is equal.
In addition, gas extracting device includes extracting pipeline and the second blower 20 on extraction pipeline out, pipeline packet is extracted out Include the second main pipeline 21, the third subtube 22 that is respectively communicated between the second main pipeline 21 and the concubine s3 of two sides and the 4th point Pipeline 23;Second main pipeline 21 is located in installation space s1, and the outlet of the second main pipeline 21 is provided with building structure body 100 (it is corresponding that the outlet of the entrance of the first main pipeline 11 and the second main pipeline 21 is opened in building structure body 100 respectively on another side wall Two sidewalls on), the second blower 20 be set to the second main pipeline 21 on, third subtube 22 and the 4th subtube 23 are by installation space S1 extend downward and through ceiling board a1 respectively to two sides concubine s3 top.It supplements pipeline and extracts each pipeline in pipeline out It is reasonably spaced apart mounting hole is interior.
Further, ceiling board a1 is that the full thread sunpender a2 vertically extended by more hangs and is located at building structure (bottom of full thread sunpender a2, which is hung, sets fixed link a3, and fixed link a3 passes through pendant a4 and ceiling board in the middle part of the inner space of body 100 A1 connection, so realize ceiling board a1 hanging), the first main pipeline 11, the first subtube, the second subtube, the second main pipeline 21, Third subtube 22, the 4th subtube 23, purge pipe 31, connecting pipe 34 etc. are lifted on installation by full thread sunpender a2 In the s1 of space.Full thread sunpender a2 not only lifts ceiling board a1, but also can also hang set each pipeline in above-below direction.So that Structure design is more reasonable, and building is more convenient.
In conclusion chemical experiment chamber system of the invention is carried out by the way that gas supplementary device is arranged in concubine When malicious harmful test operation generated, when gas collection apparatus extracts toxic and harmful gas out, which can be fast Speed fills into gas in concubine from the external world, to avoid concubine extraction gas by leading indoor gas come the case where supplement; To avoid air cleaning system (air-conditioning) from supplementing a large amount of gas into main chamber, air cleaning system highly energy-consuming is avoided, Laboratory electric energy is substantially reduced using burden, high-power more air-conditioning equipments is also avoided while using, to alleviate air-conditioning The expense of the setting of equipment is paid.
The present invention is described in detail above, its object is to allow the personage for being familiar with this field technology that can understand this The content of invention is simultaneously implemented, and it is not intended to limit the scope of the present invention, all Spirit Essence institutes according to the present invention The equivalent change or modification of work, should be covered by the scope of protection of the present invention.

Claims (10)

1. a kind of chemical experiment chamber system, the chemical experiment chamber system includes the building structure body to form space, in upper and lower To ceiling board of the tabula in the middle part of the building structure body, positioned at the ceiling board top installation space, be located under ceiling board Portion is used to carry out the laboratory of experimental implementation, and the laboratory includes main chamber and concubine, and the chemical experiment chamber system further includes For the air cleaning system of purification air is provided into the main chamber, be connected to the concubine be used for secondary indoor gas is fast The gas extracting device of speed extraction, it is characterised in that: the chemical test chamber system further includes being used for what the concubine was connected to The gas supplementary device of make-up gas into the concubine, the gas supplementary device include connecting outside air and the concubine Logical supplement pipeline and the first blower on the supplement pipeline.
2. chemical experiment chamber system according to claim 1, it is characterised in that: the gas supplementary device further includes being set to The driving of the baroceptor for incuding the concubine internal gas pressure, control first blower inside the concubine The controller of motor speed, the baroceptor are connected with the controller in a signal way., and the controller is according to the air pressure transmission The induction information of sensor controls the driving motor revolving speed of first blower.
3. chemical experiment chamber system according to claim 2, it is characterised in that: the relative pressure being arranged in the controller Parameter value be -5pa, the driving motor of first blower is electrodeless variable-speed motor, when the baroceptor senses institute When stating secondary indoor relative pressure lower than -5pa, the driving motor that the controller controls first blower accelerates rotation, when When the baroceptor senses that the indoor relative pressure of pair is equal to -5pa, the controller controls first blower Driving motor constant revolution, when the baroceptor sense the indoor relative pressure of pair be higher than -5pa when, it is described Controller controls the driving motor underdrive of first blower.
4. chemical experiment chamber system according to claim 1, it is characterised in that: there are two the concubine settings, two institutes State the two sides that concubine is located at the main chamber.
5. chemical experiment chamber system according to claim 4, it is characterised in that: the supplement pipeline includes the first supervisor Road, the first subtube and the second subtube being respectively communicated between first main pipeline and the concubine of two sides;It is described First main pipeline is located in installation space, and the entrance of first main pipeline is provided with the one side wall of the building structure body On, first blower is set on first main pipeline, and first subtube and the second subtube are by the installation space Extend downward and through the ceiling board respectively to two sides the concubine top.
6. chemical experiment chamber system according to claim 5, it is characterised in that: the gas extracting device includes extraction pipe Road and the second blower on the extraction pipeline, the extraction pipeline including the second main pipeline, be respectively communicated with described the Third subtube and the 4th subtube between two main pipelines and the concubine of two sides;Second main pipeline is located at the peace It fills in space, and the outlet of second main pipeline is provided on another side wall of the building structure body, second blower On second main pipeline, the third subtube and the 4th subtube extend downward and through institute by the installation space State ceiling board respectively to two sides the concubine top.
7. chemical experiment chamber system according to claim 6, it is characterised in that: the ceiling board is vertically square by more It hangs and is located in the middle part of the inner space of the building structure body to the full thread sunpender of extension, the supplement pipeline and extraction pipe Road, which passes through the full thread sunpender and hangs, to be located in the installation space.
8. chemical experiment chamber system according to claim 1, it is characterised in that: the air cleaning system includes being set to institute It states the airhandling equipment outside building structure body, the ventilation oral area on the ceiling board, be connected to the air-treatment Purge pipe between equipment and the ventilation opening, the purge pipe by outside penetrate after the installation space with the ventilation Oral area connection.
9. chemical experiment chamber system according to claim 8, it is characterised in that: the air cleaning system includes being set to institute State the VRV air-conditioner outdoor unit outside building structure body and be connected to the VRV air-conditioner outdoor unit by connecting pipe and be located at The indoor VRV air conditioner indoor unit of master.
10. chemical experiment chamber system according to claim 9, it is characterised in that: the ceiling board passes through more vertically The full thread sunpender that direction extends, which is hung, to be located in the middle part of the inner space of the building structure body, the purge pipe, the connection Pipeline passes through the full thread sunpender and is lifted in the installation space.
CN201811113701.0A 2018-09-25 2018-09-25 A kind of chemical experiment chamber system Pending CN109186034A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811113701.0A CN109186034A (en) 2018-09-25 2018-09-25 A kind of chemical experiment chamber system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811113701.0A CN109186034A (en) 2018-09-25 2018-09-25 A kind of chemical experiment chamber system

Publications (1)

Publication Number Publication Date
CN109186034A true CN109186034A (en) 2019-01-11

Family

ID=64909592

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811113701.0A Pending CN109186034A (en) 2018-09-25 2018-09-25 A kind of chemical experiment chamber system

Country Status (1)

Country Link
CN (1) CN109186034A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113125653A (en) * 2021-04-21 2021-07-16 林国伟 Indoor air detection device
WO2021207995A1 (en) * 2020-04-16 2021-10-21 上海易托邦建筑科技有限公司 Virus detection laboratory with inflatable membrane structure, biosafety laboratory, and virus detection laboratory with earth-sheltered structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07260222A (en) * 1994-03-25 1995-10-13 Kajima Corp Combined air-conditioning and ventilating system for laboratory and fume hood
CN203972435U (en) * 2014-03-06 2014-12-03 中石化上海工程有限公司 A kind of air-replenishing type ventilating cabinet
JP3205519U (en) * 2016-03-17 2016-07-28 台灣尖端先進生技醫藥股▲分▼有限公司Taiwan Advance Bio−Pharm Inc Laboratory environment control system
CN207350692U (en) * 2017-04-19 2018-05-11 重庆哥尔摩科技有限公司 Based on the intelligent ventilating system in scientific experiment room
CN207372010U (en) * 2017-08-15 2018-05-18 江西金域医学检验所有限公司 Draught cupboard and draught cupboard ventilating system
CN208936419U (en) * 2018-09-25 2019-06-04 苏州珠峰实验室系统工程有限公司 A kind of chemical experiment chamber system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07260222A (en) * 1994-03-25 1995-10-13 Kajima Corp Combined air-conditioning and ventilating system for laboratory and fume hood
CN203972435U (en) * 2014-03-06 2014-12-03 中石化上海工程有限公司 A kind of air-replenishing type ventilating cabinet
JP3205519U (en) * 2016-03-17 2016-07-28 台灣尖端先進生技醫藥股▲分▼有限公司Taiwan Advance Bio−Pharm Inc Laboratory environment control system
CN207350692U (en) * 2017-04-19 2018-05-11 重庆哥尔摩科技有限公司 Based on the intelligent ventilating system in scientific experiment room
CN207372010U (en) * 2017-08-15 2018-05-18 江西金域医学检验所有限公司 Draught cupboard and draught cupboard ventilating system
CN208936419U (en) * 2018-09-25 2019-06-04 苏州珠峰实验室系统工程有限公司 A kind of chemical experiment chamber system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王建群: "洁净负压实验室彩钢夹心板围护结构安装技术", 建筑技术, no. 09, pages 674 - 676 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021207995A1 (en) * 2020-04-16 2021-10-21 上海易托邦建筑科技有限公司 Virus detection laboratory with inflatable membrane structure, biosafety laboratory, and virus detection laboratory with earth-sheltered structure
CN113125653A (en) * 2021-04-21 2021-07-16 林国伟 Indoor air detection device
CN113125653B (en) * 2021-04-21 2023-08-15 林国伟 Indoor air detection device

Similar Documents

Publication Publication Date Title
CN202419845U (en) Window type indoor fresh air supply device
CN109186034A (en) A kind of chemical experiment chamber system
CN208936419U (en) A kind of chemical experiment chamber system
CN219693510U (en) Exhaust system of refrigerator room
CN110107980A (en) A kind of anti-exhaust ventilation device in kitchen
CN209197075U (en) A kind of fire engineering automatic smoke exhausting system
CN105990796B (en) A kind of damp-proof moisture removing apparatus of switch cabinet of converting station
CN202094499U (en) Intelligent adjusting device for fresh air and cold air
CN208238170U (en) Insect-and mouse-preventing device and air conditioner indoor unit with it
CN203201826U (en) Intelligent inducing fan
CN206361852U (en) A kind of Classroom air purifier
CN205248668U (en) A remove condensation device for cubical switchboard
CN204214093U (en) Transformer station's indoor environment intelligent controlling device
CN107218690A (en) A kind of solar energy VMC
CN207872190U (en) Mobile Laboratory Module
CN205897439U (en) Laboratory inverter type ventilation control system
CN207455838U (en) A kind of door socket forced draft device
CN203501395U (en) Air inlet and outlet pipeline of fresh air machine
CN104089340A (en) Air purifier with fresh air exhausting function
CN107741067B (en) Integrated high-energy active oxygen ion air purification device
CN211503049U (en) Ceiling type fresh air dehumidifier
CN103162371A (en) Intelligent fresh air ventilator for dust-haze prevention
CN207939003U (en) A kind of industrial automatic control electric control cabinet
CN207050174U (en) A kind of fresh air dehumidification autonomous control system
CN102526914A (en) Fire fighting device and fire fighting method for electrical control room

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination