CN109165412A - A kind of cable duct bank engineering design method and system based on GIS-Geographic Information System - Google Patents

A kind of cable duct bank engineering design method and system based on GIS-Geographic Information System Download PDF

Info

Publication number
CN109165412A
CN109165412A CN201810839628.9A CN201810839628A CN109165412A CN 109165412 A CN109165412 A CN 109165412A CN 201810839628 A CN201810839628 A CN 201810839628A CN 109165412 A CN109165412 A CN 109165412A
Authority
CN
China
Prior art keywords
design
engineering
cable
laying
cable duct
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810839628.9A
Other languages
Chinese (zh)
Inventor
白旭
周纬
费香泽
金欢
王剑
侯林波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
State Grid Shanghai Electric Power Co Ltd
Original Assignee
China Electric Power Research Institute Co Ltd CEPRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electric Power Research Institute Co Ltd CEPRI filed Critical China Electric Power Research Institute Co Ltd CEPRI
Priority to CN201810839628.9A priority Critical patent/CN109165412A/en
Publication of CN109165412A publication Critical patent/CN109165412A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/14Pipes

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

A kind of cable duct bank engineering design method and system based on GIS-Geographic Information System, comprising: laying route selection is carried out based on cable duct bank engineering project information combination Basic Geographic Information System, master pattern library and the zone digit model library obtained in advance;The electrical design for carrying out the cable duct bank engineering in conjunction with the cable duct bank engineering parameter information obtained in advance based on the laying route, obtains laying design;The comb engineering of the cable is carried out according to laying design.Technical solution of the present invention completes the digital coordination design of cable duct bank engineering, realizes design object standardization, design process visualization, the digitlization of design cycle collaborative, result of design and has many advantages, such as accurate convenient, technologically advanced.

Description

A kind of cable duct bank engineering design method and system based on GIS-Geographic Information System
Technical field
The invention belongs to cable work fields, and in particular to a kind of cable duct bank engineering design based on GIS-Geographic Information System Method and system.
Background technique
The design of cable work mainly uses the two-dimensional design method of AutoCAD at present, and the achievements exhibition of cable work is adopted It is the electronic document and drawing of DWG format.Although the accuracy and beauty of design can be increased using computer graphics Property, the portability of result of design carrying and repeated application is improved, but there is no change design in itself for this design method Process is only to eliminate tracing link;In the management of design finished product, electronic drawings and archives are only increased.Due to design drawing It is still isolated data, Various types of data does not do structuring processing, therefore extraction, statistics, inquiry, analysis of information etc. is grasped Make that difficulty is larger, the degree of tap value is relatively low in data, and most of designing units are still in the rank of computer graphics Section.
The design work of cable work is related to the multi-specialized cooperations such as exploration, communication, electrical, system, civil engineering, traditional In design method, this matching relationship is by mutually mentioning data process and realize between profession, and collaborative design work stops substantially It stays in the artificial collaboration level by means of computer platform, workflow generally uses sequential working mode, i.e. continuous productive process Task in one design process is divided into multinomial subtask, is designed according to the workflow pre-established, respectively by mode The work starting point of profession is the firsthand information input of preceding working procedure, and the data provided between profession is with two-dimentional drawing and text, number Word expression.In traditional cable work design, after design work starts, money is mutually proposed between profession, receives money, revisions on drawings, It after adjusted design, also to re-start and propose money, receive money, repeat the above steps, cause basic information interaction unsmooth, concertedness, Inheritance is insufficient, and designing quality and efficiency is caused to reduce.
Currently, the digital coordination design in relation to cable work is also in exploratory stage, and the basic data of cable work The case where in the presence of not being inconsistent with scene, the accuracy of subsurface investigation detection technique and accuracy also have certain gap, these situations Difficulty is increased to the Design of digital of cable work.
Summary of the invention
In order to solve the above-mentioned deficiency in the presence of the prior art, the present invention provides a kind of electricity based on GIS-Geographic Information System Cable comb engineering design method and system.
Present invention provide the technical scheme that
A kind of cable duct bank engineering design method based on GIS-Geographic Information System, comprising:
Based on obtain in advance cable duct bank engineering project information combination Basic Geographic Information System, master pattern library and Zone digit model library carries out laying route selection;
The cable duct bank work is carried out in conjunction with the cable duct bank engineering parameter information obtained in advance based on the laying route The electrical design of journey obtains laying design;
The comb engineering of the cable is carried out according to laying design.
Preferably, described based on the cable duct bank engineering project information combination Basic Geographic Information System obtained in advance, mark Quasi- model library and zone digit model library carry out laying route selection, comprising:
The Fundamental Geographic Information Data in cable work region is obtained based on Basic Geographic Information System;
Multi dimension information model is obtained according to master pattern library and zone digit model library;
According to Fundamental Geographic Information Data, multi dimension information model and in advance the cable duct bank engineering project information that obtains carries out Lay route selection;
Wherein, the java standard library includes: substation, tunnel, comb, cable duct, Gong Jing, shaft tower, basis and cable termination;
The zone digit model library includes: building, the title of device model, coordinate and elevation in partial region Information.
Preferably, described according to Fundamental Geographic Information Data, multi dimension information model and the cable duct bank engineering that obtains in advance Project information carries out laying route selection, comprising:
According to Fundamental Geographic Information Data, multi dimension information model and in advance the cable duct bank engineering relevant information that obtains carries out Line route selection, which generates, simplifies laying route;
Determining primary election is adjusted to the simplified route by the Basic Geographic Information System based on exploration situation to apply If route;
Route, which is laid, according to the primary election carries out collision detection and the determining final laying route selection of barrier evacuation inspection.
Preferably, it is described carried out based on the laying route in conjunction with the cable duct bank engineering parameter information that obtains in advance described in The electrical design of cable duct bank engineering, comprising:
Establish the engineering index of the cable duct bank engineering;
The structural parameters of cable duct bank engineering, overhead cabling method are determined based on the laying route and the engineering index The electrical design of the cable duct bank engineering is carried out with cable operating parameter, generates calculated description.
It is preferably, described to obtain laying design, comprising:
Based on final laying route and the electrical design, design key position work well and according to preset interval described Straight line work well is designed between key position work well, while explanation is transformed to active well;
Based on design comb and the cabling in the comb between the key position work well and the straight line work well;
Corresponding earthing mode is selected according to the actual situation and carries out the segment design of the cable, between every section of the cable It is connected by transition joint, the transition joint is placed in the active well;
The cable termination is selected according to default principle and is designed by the laying that actual requirement carries out terminal ground connection arrangement.
Preferably, the basis presets principle and selects the cable termination and carry out terminal ground connection arrangement by actual requirement After laying design, further includes:
It is generated based on GIS-Geographic Information System with numbered engineering drawing by laying design.
Preferably, the comb engineering that the cable is carried out according to laying design, comprising:
According to the engineering drawing and calculated description storage digitlization achievement after laying design;
The progress cable duct bank engineering design of digital information model is generated based on the digitlization achievement and transfers the number Word information model carries out the comb engineering of the cable;
Wherein, the digital information model includes: project data, geographic information data and documentation.
Another object of the present invention is to propose a kind of cable duct bank engineering design system based on GIS-Geographic Information System, packet It includes:
Route chooses module, collaborative design module and engineering design module,
The route chooses module, for based on the cable duct bank engineering project information combination fundamental geological letter obtained in advance Breath system, master pattern library and zone digit model library carry out laying route selection;
The collaborative design module, for combining the cable duct bank engineering parameter obtained in advance letter based on the laying route Breath carries out the electrical design of the cable duct bank engineering, obtains laying design;
The engineering design module, for carrying out the comb engineering of the cable according to laying design;
Wherein, the java standard library includes: substation, tunnel, comb, cable duct, Gong Jing, shaft tower, basis and cable termination;
The zone digit model library includes: building, the title of device model, coordinate and elevation letter in partial region Breath.
Preferably, the route chooses module, comprising: the first acquisition submodule, the second acquisition submodule and route are chosen Submodule;
First acquisition submodule, for obtaining the basis ground in cable work region based on Basic Geographic Information System Manage information data;
Described second obtains mould block, for obtaining multidimensional information mould according to master pattern library and zone digit model library Type;
The route chooses submodule, for obtaining according to Fundamental Geographic Information Data, multi dimension information model and in advance Cable duct bank engineering project information carries out laying route selection.
Preferably, the route chooses submodule, comprising: the first selection unit, the second selection unit and third are chosen single Member;
First selection unit, for according to Fundamental Geographic Information Data, multi dimension information model and the electricity that obtains in advance Cable comb engineering relevant information carries out line route selection and generates simplified laying route;
Second selection unit, for passing through the Basic Geographic Information System to the simplified road based on exploration situation Line is adjusted determining primary election laying route;
The third selection unit, for being laid according to the primary election, route carries out collision detection and barrier evacuation checks Determine final laying route selection.
Preferably, the collaborative design module, comprising: building index submodule, electrical design submodule and calculating inteilectual At submodule;
The building indexes submodule, for establishing the engineering index of the cable duct bank engineering;
The electrical design submodule, for determining cable duct bank engineering based on the laying route and the engineering index Structural parameters, overhead cabling method and cable operating parameter carry out the electrical design of the cable duct bank engineering;
The calculated description generates submodule, for generating calculated description.
Preferably, the collaborative design module, further includes: the first laying submodule, the second laying submodule, third laying Submodule and the 4th laying submodule;
The first laying submodule, for being based on the final laying route and the electrical design, design key Position work well simultaneously designs straight line work well according to preset interval between the key position work well, while being transformed to active well Explanation;
The second laying submodule designs comb between the key position work well and the straight line work well for being based on And the cabling in the comb;
The third lays submodule, for selecting corresponding earthing mode according to the actual situation and carrying out the cable Segment design, is connected by transition joint between every section of the cable, and the transition joint is placed in the active well;
The 4th laying submodule, for selecting the cable termination according to default principle and being carried out eventually by actual requirement End ground connection arrangement.
Preferably, the collaborative design module, further includes: drawing creation submodule;
The drawing creation submodule, for being generated based on GIS-Geographic Information System with numbered by laying design Engineering drawing.
Preferably, the engineering design module, comprising: sub-module stored and engineering design submodule;
The sub-module stored, for according to the engineering drawing and calculated description storage digitlization achievement after laying design;
The engineering design submodule carries out cable row for generating digital information model based on the digitlization achievement Pipe engineering design simultaneously transfers the comb engineering that the digital information model carries out the cable;
Wherein, the digital information model includes: project data, geographic information data and documentation.
Compared with the immediate prior art, technical solution provided by the invention is had the advantages that
Technical solution of the present invention is based on the cable duct bank engineering project information combination Fundamental Geographic Information System system obtained in advance System, master pattern library and zone digit model library carry out laying route selection;It is obtained in advance based on laying route combination Cable duct bank engineering parameter information carries out the electrical design of cable duct bank engineering, obtains laying design;It is carried out according to laying design The comb engineering of the cable.The digital coordination design for completing cable duct bank engineering, realizes design object standardization, design Process visualization, design cycle collaborative, result of design digitize and have many advantages, such as accurate convenient, technologically advanced.
Technical solution of the present invention realizes the fusion of each profession, realizes the collaborative work of the profession such as electrical, system, civil engineering, By integration realization information sharing, realize and draw, calculate integration, ensure that data in engineering design have " primary input, Repeatedly utilize " the characteristics of, and realize design information effectively transmitting, shared and feedback in real time in engineering overall process.
Technical solution of the present invention can effectively avoid collision the appearance of problem, reduce and avoid and is existing caused by design mistake Field change, is improved greatly the quality of result of design, guarantees engineering construction progress.
Detailed description of the invention
Fig. 1 is design method flow chart of the present invention;
Fig. 2 is cable duct bank engineering collaborative design method schematic diagram;
Fig. 3 is cable duct bank Engineering Digital Model of Collaborative Design figure.
Specific embodiment
For a better understanding of the present invention, following will be combined with the drawings in the embodiments of the present invention, in the embodiment of the present invention Technical solution be clearly and completely described, it is clear that described embodiments are some of the embodiments of the present invention, rather than Whole embodiments.
Embodiment 1
Such as Fig. 1, comprising:
S1, the cable duct bank engineering project information combination Basic Geographic Information System based on obtaining in advance, master pattern library And zone digit model library carries out laying route selection;
S2, the cable duct bank is carried out in conjunction with the cable duct bank engineering parameter information obtained in advance based on the laying route The electrical design of engineering obtains laying design;
S3, the comb engineering that the cable is carried out according to laying design.
It is specific as shown in Fig. 2,
S1 further comprises:
Step 1, newly-built cable duct bank engineering, the relevant data of assembled item, information, in digital coordination designing system In, it is managed collectively;It determines that each profession participates in the designer of this engineering, determines the power for the personnel at different levels that engineering participates in Limit;
Wherein, the data includes: general purpose discipline specification relevant to cable duct bank engineering, such as standardized designs, design Specification and designing technique regulation;Binding character material relevant to this engineering, such as project proposal.
The information includes: the start-stop point information and planning transmission capacity of cable duct bank engineering, start-stop substation are related Information (including substation's outgoing line interval, phase sequence etc.);
The permission of the personnel at different levels includes: reading permission, modification authority, audit permission etc..
Step 2 is based on GIS technology, obtains the Fundamental Geographic Information Data in this cable work region, including digital shadow Picture, digital elevation model, underground pipe line data, cable distribution and position data and power grid thematic data etc.;
Wherein, the GIS technology is the necessary carrier of cable work Design of digital, in the process of entire Design of digital In, GIS technology will play the role of uniform operational platform and overall process data medium.
The concrete application of GIS technology is as follows:
(1) digitization
Dynamic update is carried out to data using GPS technology and RS technology, guarantees the timeliness of GIS data, while utilizing GIS Platform organizes geographic information data, guarantees each stage continuous effective of cable work design.
(2) proceduring
Guarantee that GIS technology is applied to the feasibility study of cable work design, just sets, each stage of construction drawing design.
(3) collaborative
GIS technology is relied on, is transferred in cable work Path selection, electrical design, structure design, collaborative design and achievement Etc. realize synergistic application.
Step 3 obtains multi dimension information model from master pattern library and zone digit model library, comprising: builds, sets Standby, substation, Gong Jing, comb, cable duct, cable accessory etc.;
Wherein, the master pattern library includes substation, tunnel, comb, cable duct, Gong Jing, shaft tower, basis, cable end End etc.;
The zone digit model library includes title, coordinate and the elevation of the models such as building, equipment in partial region Information.
Step 4 is based on GIS technology, extracts Fundamental Geographic Information Data, is shown using two dimension or three dimensional pattern, and Display mode can be controlled by figure layer;
Wherein, the Fundamental Geographic Information Data includes topographic map, elevation information, satellite image and power grid special topic number According to etc..
Step 5 carries out line route based on GIS and automatically selects, using special to existing geographic information data and power grid The integrated of data is inscribed, relevant expert data is information-based so that cable duct bank engineering circuit designs, digitizes, and improves Path selection Quality and efficiency;
Wherein, the Path selection is simplified route scheme, the main area for considering to need to avoid in cabling process Domain and turning point are taken into account and consider built route and planning route.
Step 6, according to the route scheme automatically selected in above-mentioned steps, actual conditions of the designer according to field survey Path is manually adjusted, determines the route scheme of primary election;
Wherein, the exploration situation should be entered into Basic Geographic Information System, supplement perfect relevant information, and confession is subsequent Engineering uses.
Step 7, the path according to initial option, carry out collision detection and barrier evacuation checks, path optimizing scheme;
Collision detection described in step 7 is the cable duct bank path according to primary election, to heating power along the line, draining, combustion gas Bidirectional collision inspection is carried out Deng other municipal pipelines;
Wherein, it is cable trace according to primary election that the described barrier evacuation, which checks, to the buildings such as house along the line from Dynamic evacuation.
Step 8, Path selection and scheme optimization according to above-mentioned steps, determine final cable (optical cable) line route Figure;
Wherein, the optical cable path profile is determined according to the optical cable demand that communication speciality proposes.
Step 5, the selection process in cable duct bank path described in 6,7,8 can be indicated by figure.
S2 further comprises:
Step 9, on newly-built cable duct bank path, design key position Gong Jing first, including rotation angle well, three driftings, Four driftings, the case where being transformed to active well, should also illustrate;
Step 10, between key position work well, every 100-150 meters or so spaced design straight line work wells;
Wherein, step 9, the design of work well described in 10, are equidistantly pacified on fixed cable trace using automated manner Work well is put, is then adjusted manually;
The work well design should refer to modular design, in conjunction with the actual cable feeder number of this cable duct bank engineering, automatically Recommend the size of selection work well;
Cross-sectional design of the described work well design comprising work well, vertical alignment design include draining, reinforcing bar, built-in fitting Design.
Step 11 designs comb between the work well arranged;
Wherein, the design comb is divided into excavation and no-dig technique.Excavating comb design includes comb specification, section ruler The design such as very little, pitch-row, internal diameter, wall thickness;In special road section, river is such as passed through, comb uses no-dig technique, and design content includes comb Specification, aperture etc.;
The comb should refer to modular design, in conjunction with this engineering practice, according to the radical of cabling, cable trace Select comb without concrete pack, comb concrete pack, non-digging tube-pulling by location situation and cable penetration mode;According to Cable laying radical selects comb specification and internal diameter, system automatically generated cable duct bank cross-section diagram, this cross-section diagram is parametrization Model, designer can make corresponding modification according to the actual situation.
Step 12, the cabling in the comb of above-mentioned design.
Wherein, the cable design includes cable model, the cross-section of cable and Cable Bending Radius requirement.
Step 13, according to the actual situation, selects corresponding earthing mode and carries out cable segment design, between every section of cable It is connected using transition joint, transition joint should be placed in active well;
Wherein, for the cable segment design in such a way that automatic segmentation adds and manually adjusts, logic principle is as follows:
(1) distance in computer installation, in addition cable length, estimates total length;
(2) it determines every section of approximate length L, judges whether there is work well near the distance of L, if any being then divided into one section, and will Transition joint is placed in work well;
(3) after automatic segmentation, the drum length of cable, connector quantity and the connector place work well of every section of statistics;
(4) designer automatically generates the drum length of cable and connector statistics according to automatic segmentation as a result, be adjusted manually Table;
Whether the cable segment design should meet the requirements according to the induced voltage that every segment length verifies protective metal shell;
The transition joint should be required according to cable voltage class, type of insulation, installation environment, equipment dependability and economy Rational principle selects suitable model.
Step 14 requires and economical rationality is former according to cable voltage class, type of insulation, installation environment, equipment dependability Then, cable termination is selected, and carries out terminal ground connection arrangement by actual requirement.
Step 15 selects specification template from database, automatically generates specification, and designer is according to the actual situation again It makes an amendment.
Step 16, the drawing for selecting corresponding picture frame (can manual modification or autonomous Design), selection to need from database Classification, the drawing and automatic numbering of this engineering of system automatically generated.
2. the process of electrical design is as follows:
The electrical design of cable duct bank engineering mainly carries out cable electrical calculating, and output result includes current-carrying capacity, metal The input of the associated electrical parameters such as sheath induced voltage, cyclic impedance, tractive force, lateral pressure, output, the meter for calculating reference formula Calculate book.The electrical design of cable duct bank engineering mainly includes following steps:
Step 1 establishes engineering index.
It is the electrical calculating that index completes entire engineering with engineering, the essential information of engineering includes designing unit, engineering name Title, engineering code, design phase, calculating content, date etc..
Step 2 determines construction of cable parameter.
Select structural parameters used in this engineering as the basic parameter electrically calculated, including conductor layer, insulating layer, interior Each parameter of sheath, outer jacket.Conductor layer parameter includes comprising conductor material, conductor diameter, nominal area, core structure etc.;Absolutely Edge layer parameter mainly includes insulating materials, insulation thickness, insulation diameter etc.;Sheath parameter mainly includes sheath material, wrinkle Sheath, lining material, liner layer thickness etc.;Outer jacket parameter mainly includes armoring material, outer sheath material etc..
Step 3 determines overhead cabling method.
Overhead cabling method is selected, including is excavated, no-dig technique two ways.
Step 4 determines cable operating parameter.
Cable operating parameter includes operation conditions parameter and environmental conditions parameter.Wherein operation conditions parameter includes operation system System, feeder number, voltage rating, phase spacing, circuit spacing, working frequency etc..Environmental conditions parameter includes environment temperature, conductor Running temperature, protective metal shell running temperature.Environmental condition is related with overhead cabling method.
Step 5 is completed to calculate.
Selection calculates type and required parameter, in conjunction with calculation formula, completes current-carrying capacity of cable calculating, protective metal shell sense It answers voltage etc. to calculate, while generating calculated description.
Wherein, the carrying current calculation calculates two methods using look-up table and formula.
Look-up table: providing the numerical value of the current-carrying capacity under different condition in design platform, and designer can be according to voltage The conditions such as grade are screened, and lookup obtains the numerical value of current-carrying capacity;
Formula calculates: designer can select formula or base in code requirement IEC60287 according to the demand of Practical Project In the carrying current calculation method of finite element analysis;
The calculating of the protective metal shell induced voltage is according to GB50217 " Code for design of cables of electric works " according to feeder number And arrayed feature is calculated.
S3 further comprises:
3. the function that digital coordination design is realized mainly has:
(1) GIS platform integration
Using GIS technology as carrier, the Fundamental Geographic Information Data in this cable work region is obtained, including digitized video, Digital elevation model, underground pipe line data, cable distribution and position data and power grid thematic data etc., while to data Carry out dynamic update, guarantee design feasibility study, just set, the construction drawing stage can be applied.
(2) design object standardizes
In the design of cable work comb, design element includes comb, Gong Jing, cable accessory, fitting etc., in design process Reference cable engineering modular design is answered, parameterized model is established, while being considered as the requirement of defined in digitlization transfer standard, Standardize cable work design gradually.
(3) design process visualizes
The concept of the visual design is introduced using Design of digital simultaneously, by the design of cable work from traditional two dimension Design is gradually converted to Design of three-dimensional visualization, while realizing two three-dimensional linkage functions, designer can be made in three-dimensional environment Middle real-time simulation design.By the application to GIS technology, GIS-Geographic Information System can be showed in three-dimensional scenic, assists design The path design and optimization of cable duct bank engineering is better achieved in personnel.
(4) design cycle collaborative
Cable duct bank engineering effort is related to exploration, system, power transformation, electrical, structure, technical economy, geology, physical prospecting etc. specially Industry, each profession intersect.Digital coordination design can make the designer of different majors directly from Uniting platform Required parametric data is extracted in database to be designed, and is avoided the multiple typing of data, is eliminated traditional proposing and provided Journey;Meanwhile digital coordination design can make the designer of diverse geographic location that can realize that design data is total with Strange Place Design It enjoys, result of design intercommunication.
(5) result of design digitizes
The achievement that the digital coordination design of cable duct bank engineering generates is stored by database, is managed, and number is formed Word is melted into fruit, and comprising the categorical datas such as project data, geographic information data, documentation and threedimensional model, these data can be with It is applied in the life cycle management of cable work design, meets the needs of cable work design.
Embodiment 2
Based on unified inventive concept, a kind of cable duct bank engineering design system based on GIS-Geographic Information System proposed by the present invention It unites similar with a kind of cable duct bank engineering design method based on GIS-Geographic Information System, comprising:
Route chooses module, collaborative design module and engineering design module;
Above three module is described further below:
Route chooses module, for based on the cable duct bank engineering project information combination Fundamental Geographic Information System system obtained in advance System, master pattern library and zone digit model library carry out laying route selection;
Collaborative design module, for combining the cable duct bank engineering parameter information obtained in advance to carry out electricity based on laying route The electrical design of cable comb engineering obtains laying design;
Engineering design module, for designing the comb engineering for carrying out cable according to laying;
Wherein, java standard library includes: substation, tunnel, comb, cable duct, Gong Jing, shaft tower, basis and cable termination;
Zone digit model library includes: building, the title of device model, coordinate and elevation information in partial region.
Further, route chooses module, comprising: the first acquisition submodule, the second acquisition submodule and route choose son Module;
First acquisition submodule, for obtaining the fundamental geological letter in cable work region based on Basic Geographic Information System Cease data;
Second obtains mould block, for obtaining multi dimension information model according to master pattern library and zone digit model library;
Route chooses submodule, for according to Fundamental Geographic Information Data, multi dimension information model and the cable that obtains in advance Comb engineering project information carries out laying route selection.
Further, route chooses submodule, comprising: the first selection unit, the second selection unit and third selection unit;
First selection unit, for according to Fundamental Geographic Information Data, multi dimension information model and in advance the cable that obtains is arranged Plumber's journey relevant information carries out line route selection and generates simplified laying route;
Second selection unit, for being adjusted really by Basic Geographic Information System to route is simplified based on exploration situation Determine primary election laying route;
Third selection unit, for checking and determining finally according to primary election laying route progress collision detection and barrier evacuation Lay route selection.
Further, collaborative design module, comprising: building index submodule, electrical design submodule and calculated description generate Submodule;
Building index submodule, for establishing the engineering index of cable duct bank engineering;
Electrical design submodule, for determining that the structure of cable duct bank engineering is joined based on laying route and the engineering index Number, overhead cabling method and cable operating parameter carry out the electrical design of cable duct bank engineering;
Calculated description generates submodule, for generating calculated description.
Further, collaborative design module, further includes: the first laying submodule, the second laying submodule, third laying Module and the 4th laying submodule;
First laying submodule, for based on final laying route and the electrical design, design key position Gong Jing And straight line work well is designed between the key position work well according to preset interval, while explanation is transformed to active well;
Second laying submodule, for based on design comb between key position work well and the straight line work well and described Cabling in comb;
Third lays submodule, sets for selecting corresponding earthing mode according to the actual situation and carrying out the segmentation of cable It counts, is connected between every section of cable by transition joint, transition joint is placed in the active well;
4th laying submodule is grounded cloth for selecting cable termination according to default principle and carrying out terminal by actual requirement It sets.
Further, collaborative design module, further includes: drawing creation submodule;
Drawing creation submodule, for being generated based on GIS-Geographic Information System with numbered engineering drawing by laying design Paper.
Further, engineering design module, comprising: sub-module stored and engineering design submodule;
Sub-module stored, for according to the engineering drawing and calculated description storage digitlization achievement after laying design;
Engineering design submodule carries out cable duct bank work for generating digital information model based on the digitlization achievement Journey designs and transfers the comb engineering that the digital information model carries out the cable;
Wherein, digital information model includes: project data, geographic information data and documentation.
It should be understood by those skilled in the art that, embodiments herein can provide as method, system or computer program Product.Therefore, complete hardware embodiment, complete software embodiment or reality combining software and hardware aspects can be used in the application Apply the form of example.Moreover, it wherein includes the computer of computer usable program code that the application, which can be used in one or more, The computer program implemented in usable storage medium (including but not limited to magnetic disk storage, CD-ROM, optical memory etc.) produces The form of product.
The application is referring to method, the process of equipment (system) and computer program product according to the embodiment of the present application Figure and/or block diagram describe.It should be understood that every one stream in flowchart and/or the block diagram can be realized by computer program instructions The combination of process and/or box in journey and/or box and flowchart and/or the block diagram.It can provide these computer programs Instruct the processor of general purpose computer, special purpose computer, Embedded Processor or other programmable data processing devices to produce A raw machine, so that being generated by the instruction that computer or the processor of other programmable data processing devices execute for real The device for the function of being specified in present one or more flows of the flowchart and/or one or more blocks of the block diagram.
These computer program instructions, which may also be stored in, is able to guide computer or other programmable data processing devices with spy Determine in the computer-readable memory that mode works, so that it includes referring to that instruction stored in the computer readable memory, which generates, Enable the manufacture of device, the command device realize in one box of one or more flows of the flowchart and/or block diagram or The function of being specified in multiple boxes.
These computer program instructions also can be loaded onto a computer or other programmable data processing device, so that counting Series of operation steps are executed on calculation machine or other programmable devices to generate computer implemented processing, thus in computer or The instruction executed on other programmable devices is provided for realizing in one or more flows of the flowchart and/or block diagram one The step of function of being specified in a box or multiple boxes.
The above is only the embodiment of the present invention, are not intended to restrict the invention, all in the spirit and principles in the present invention Within, any modification, equivalent substitution, improvement and etc. done, be all contained in apply pending scope of the presently claimed invention it It is interior.

Claims (14)

1. a kind of cable duct bank engineering design method based on GIS-Geographic Information System characterized by comprising
Based on cable duct bank engineering project information combination Basic Geographic Information System, master pattern library and the region obtained in advance Digital model library carries out laying route selection;
The cable duct bank engineering is carried out in conjunction with the cable duct bank engineering parameter information obtained in advance based on the laying route Electrical design obtains laying design;
The comb engineering of the cable is carried out according to laying design.
2. the cable duct bank engineering design method based on GIS-Geographic Information System as described in claim 1, which is characterized in that described Based on cable duct bank engineering project information combination Basic Geographic Information System, master pattern library and the zone digit obtained in advance Change model library and carry out laying route selection, comprising:
The Fundamental Geographic Information Data in cable work region is obtained based on Basic Geographic Information System;
Multi dimension information model is obtained according to master pattern library and zone digit model library;
According to Fundamental Geographic Information Data, multi dimension information model and in advance the cable duct bank engineering project information that obtains is laid Route selection;
Wherein, the java standard library includes: substation, tunnel, comb, cable duct, Gong Jing, shaft tower, basis and cable termination;
The zone digit model library includes: building, the title of device model, coordinate and elevation letter in partial region Breath.
3. the cable duct bank engineering design method based on GIS-Geographic Information System as claimed in claim 2, which is characterized in that described According to Fundamental Geographic Information Data, multi dimension information model and in advance the cable duct bank engineering project information that obtains carries out laying route Selection, comprising:
According to Fundamental Geographic Information Data, multi dimension information model and in advance the cable duct bank engineering relevant information that obtains carries out route Path selection, which generates, simplifies laying route;
Determining primary election is adjusted to the simplified route by the Basic Geographic Information System based on exploration situation and lays road Line;
Route, which is laid, according to the primary election carries out collision detection and the determining final laying route selection of barrier evacuation inspection.
4. the cable duct bank engineering design method based on GIS-Geographic Information System as claimed in claim 2, which is characterized in that described The electrical of the cable duct bank engineering is carried out in conjunction with the cable duct bank engineering parameter information obtained in advance based on the laying route Design, comprising:
Establish the engineering index of the cable duct bank engineering;
The structural parameters, overhead cabling method and electricity of cable duct bank engineering are determined based on the laying route and the engineering index Cable operating parameter carries out the electrical design of the cable duct bank engineering, generates calculated description.
5. the cable duct bank engineering design method based on GIS-Geographic Information System as described in claim 1, described to obtain setting Meter, comprising:
Based on final laying route and the electrical design, design key position work well and according to preset interval in the key Straight line work well is designed between the work well of position, while explanation is transformed to active well;
Based on design comb and the cabling in the comb between the key position work well and the straight line work well;
Corresponding earthing mode is selected according to the actual situation and carries out the segment design of the cable, is passed through between every section of the cable Transition joint connection, the transition joint are placed in the active well;
The cable termination is selected according to default principle and is designed by the laying that actual requirement carries out terminal ground connection arrangement.
6. the cable duct bank engineering design method based on GIS-Geographic Information System as claimed in claim 5, which is characterized in that described After selecting the cable termination according to default principle and carrying out the laying design of terminal ground connection arrangement by actual requirement, further includes:
It is generated based on GIS-Geographic Information System with numbered engineering drawing by laying design.
7. the cable duct bank engineering design method based on GIS-Geographic Information System as claimed in claim 6, which is characterized in that described The comb engineering of the cable is carried out according to laying design, comprising:
According to the engineering drawing and calculated description storage digitlization achievement after laying design;
The progress cable duct bank engineering design of digital information model is generated based on the digitlization achievement and transfers the digitlization Information model carries out the comb engineering of the cable;
Wherein, the digital information model includes: project data, geographic information data and documentation.
8. a kind of cable duct bank engineering design system based on GIS-Geographic Information System characterized by comprising route chooses mould Block, collaborative design module and engineering design module,
The route chooses module, for based on the cable duct bank engineering project information combination Fundamental Geographic Information System system obtained in advance System, master pattern library and zone digit model library carry out laying route selection;
The collaborative design module, for based on the laying route combine the cable duct bank engineering parameter information that obtains in advance into The electrical design of the row cable duct bank engineering obtains laying design;
The engineering design module, for carrying out the comb engineering of the cable according to laying design;
Wherein, the java standard library includes: substation, tunnel, comb, cable duct, Gong Jing, shaft tower, basis and cable termination;
The zone digit model library includes: building, the title of device model, coordinate and elevation information in partial region.
9. the cable duct bank engineering design system based on GIS-Geographic Information System as claimed in claim 8, which is characterized in that described Route chooses module, comprising: the first acquisition submodule, the second acquisition submodule and route choose submodule;
First acquisition submodule, for obtaining the fundamental geological letter in cable work region based on Basic Geographic Information System Cease data;
Described second obtains mould block, for obtaining multi dimension information model according to master pattern library and zone digit model library;
The route chooses submodule, for according to Fundamental Geographic Information Data, multi dimension information model and the cable that obtains in advance Comb engineering project information carries out laying route selection.
10. the cable duct bank engineering design system based on GIS-Geographic Information System as claimed in claim 9, which is characterized in that institute It states route and chooses submodule, comprising: the first selection unit, the second selection unit and third selection unit;
First selection unit, for according to Fundamental Geographic Information Data, multi dimension information model and in advance the cable that obtains is arranged Plumber's journey relevant information carries out line route selection and generates simplified laying route;
Second selection unit, for based on exploration situation by the Basic Geographic Information System to the simplified route into Row, which adjusts, determines that route is laid in primary election;
The third selection unit, for being laid according to the primary election, route carries out collision detection and barrier evacuation is checked and determined Final laying route selection.
11. the cable duct bank engineering design system based on GIS-Geographic Information System as claimed in claim 8, which is characterized in that institute State collaborative design module, comprising: building index submodule, electrical design submodule and calculated description generate submodule;
The building indexes submodule, for establishing the engineering index of the cable duct bank engineering;
The electrical design submodule, for determining the knot of cable duct bank engineering based on the laying route and the engineering index Structure parameter, overhead cabling method and cable operating parameter carry out the electrical design of the cable duct bank engineering;
The calculated description generates submodule, for generating calculated description.
12. the cable duct bank engineering design system based on GIS-Geographic Information System as claimed in claim 8, which is characterized in that institute State collaborative design module, further includes: the first laying submodule, the second laying submodule, third laying submodule and the 4th laying Submodule;
The first laying submodule, for being based on the final laying route and the electrical design, design key position Work well simultaneously designs straight line work well according to preset interval between the key position work well, while being transformed to active well It is bright;
It is described second laying submodule, for based between the key position work well and the straight line work well design comb and Cabling in the comb;
The third lays submodule, for selecting corresponding earthing mode according to the actual situation and carrying out the segmentation of the cable It designs, is connected between every section of the cable by transition joint, the transition joint is placed in the active well;
The 4th laying submodule connects for selecting the cable termination according to default principle and carrying out terminal by actual requirement Ground arrangement.
13. the cable duct bank engineering design system based on GIS-Geographic Information System as claimed in claim 12, which is characterized in that institute State collaborative design module, further includes: drawing creation submodule;
The drawing creation submodule, for being generated based on GIS-Geographic Information System with numbered engineering by laying design Drawing.
14. the cable duct bank engineering design system based on GIS-Geographic Information System as claimed in claim 8, which is characterized in that institute State engineering design module, comprising: sub-module stored and engineering design submodule;
The sub-module stored, for according to the engineering drawing and calculated description storage digitlization achievement after laying design;
The engineering design submodule carries out cable duct bank work for generating digital information model based on the digitlization achievement Journey designs and transfers the comb engineering that the digital information model carries out the cable;
Wherein, the digital information model includes: project data, geographic information data and documentation.
CN201810839628.9A 2018-07-27 2018-07-27 A kind of cable duct bank engineering design method and system based on GIS-Geographic Information System Pending CN109165412A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810839628.9A CN109165412A (en) 2018-07-27 2018-07-27 A kind of cable duct bank engineering design method and system based on GIS-Geographic Information System

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810839628.9A CN109165412A (en) 2018-07-27 2018-07-27 A kind of cable duct bank engineering design method and system based on GIS-Geographic Information System

Publications (1)

Publication Number Publication Date
CN109165412A true CN109165412A (en) 2019-01-08

Family

ID=64898441

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810839628.9A Pending CN109165412A (en) 2018-07-27 2018-07-27 A kind of cable duct bank engineering design method and system based on GIS-Geographic Information System

Country Status (1)

Country Link
CN (1) CN109165412A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109948277A (en) * 2019-03-28 2019-06-28 盐城市科恒达材料有限公司 A kind of Design of Cable Layout method
CN110659831A (en) * 2019-09-25 2020-01-07 国网上海市电力公司 Urban substation channel laying planning method based on full-life management cycle
CN110889158A (en) * 2019-11-27 2020-03-17 国网冀北电力有限公司经济技术研究院 Method and device for determining external drainage system of substation area of transformer substation
CN112100272A (en) * 2020-09-09 2020-12-18 广联达科技股份有限公司 Data display method and device for drainage line, computer equipment and storage medium
CN112734078A (en) * 2020-12-04 2021-04-30 苏州热工研究院有限公司 Standard implementation method for engineering modification of nuclear power plant
CN112836324A (en) * 2021-02-02 2021-05-25 国网山东省电力公司聊城供电公司 Wiring design system and wiring design method for power grid
CN113128066A (en) * 2021-04-30 2021-07-16 广东电网有限责任公司 Modeling data processing method and device, electronic equipment and storage medium
CN113591174A (en) * 2021-08-24 2021-11-02 国网天津市电力公司 Cable channel information integration system and method based on CAD
CN113868820A (en) * 2021-10-19 2021-12-31 大连理工大学 Ocean cable multifunctional integrated software development platform, method and storage medium
CN114491895A (en) * 2022-04-01 2022-05-13 广东电网有限责任公司东莞供电局 Cable laying stress analysis method and device

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105005676A (en) * 2015-08-13 2015-10-28 国网上海市电力公司 Three-dimension design method based on cable engineering information model
CN106530391A (en) * 2016-10-11 2017-03-22 上海电力设计院有限公司 GIS-based urban underground cable three-dimensional design method
CN107153744A (en) * 2017-06-01 2017-09-12 杭州纵波科技有限公司 Subsurface three-dimensional pipeline decision system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105005676A (en) * 2015-08-13 2015-10-28 国网上海市电力公司 Three-dimension design method based on cable engineering information model
CN106530391A (en) * 2016-10-11 2017-03-22 上海电力设计院有限公司 GIS-based urban underground cable three-dimensional design method
CN107153744A (en) * 2017-06-01 2017-09-12 杭州纵波科技有限公司 Subsurface three-dimensional pipeline decision system

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109948277A (en) * 2019-03-28 2019-06-28 盐城市科恒达材料有限公司 A kind of Design of Cable Layout method
CN110659831A (en) * 2019-09-25 2020-01-07 国网上海市电力公司 Urban substation channel laying planning method based on full-life management cycle
CN110659831B (en) * 2019-09-25 2023-11-21 国网上海市电力公司 Urban substation channel laying planning method based on whole life management period
CN110889158A (en) * 2019-11-27 2020-03-17 国网冀北电力有限公司经济技术研究院 Method and device for determining external drainage system of substation area of transformer substation
CN110889158B (en) * 2019-11-27 2023-07-28 国网冀北电力有限公司经济技术研究院 Method and device for determining external drainage system of substation area
CN112100272A (en) * 2020-09-09 2020-12-18 广联达科技股份有限公司 Data display method and device for drainage line, computer equipment and storage medium
CN112100272B (en) * 2020-09-09 2024-04-12 广联达科技股份有限公司 Drainage line data display method and device, computer equipment and storage medium
CN112734078B (en) * 2020-12-04 2023-06-02 苏州热工研究院有限公司 Standardized implementation method for engineering transformation of nuclear power plant
CN112734078A (en) * 2020-12-04 2021-04-30 苏州热工研究院有限公司 Standard implementation method for engineering modification of nuclear power plant
CN112836324A (en) * 2021-02-02 2021-05-25 国网山东省电力公司聊城供电公司 Wiring design system and wiring design method for power grid
CN113128066A (en) * 2021-04-30 2021-07-16 广东电网有限责任公司 Modeling data processing method and device, electronic equipment and storage medium
CN113591174A (en) * 2021-08-24 2021-11-02 国网天津市电力公司 Cable channel information integration system and method based on CAD
CN113868820B (en) * 2021-10-19 2023-01-24 大连理工大学 Ocean cable multifunctional integrated software development platform, method and storage medium
CN113868820A (en) * 2021-10-19 2021-12-31 大连理工大学 Ocean cable multifunctional integrated software development platform, method and storage medium
CN114491895A (en) * 2022-04-01 2022-05-13 广东电网有限责任公司东莞供电局 Cable laying stress analysis method and device

Similar Documents

Publication Publication Date Title
CN109165412A (en) A kind of cable duct bank engineering design method and system based on GIS-Geographic Information System
CN105005676A (en) Three-dimension design method based on cable engineering information model
CN101630419B (en) Structuring method for three-dimensional visualizing system of urban synthesis pipeline network
CN104794755B (en) A kind of high-tension cable three-dimensional tube field of line scape construction method
KR100866830B1 (en) System and method for managing river using 3d based moving picture
CN102087753A (en) Rapid three-dimensional mapping moulding method for ground and underground pipe network
CN106557892A (en) City Buried Pipeline GIS-Geographic Information System
Song et al. Research on management and application of tunnel engineering based on BIM technology
CN105320811A (en) Method for establishing topological connected model of urban underground electricity pipe network
CN103093008A (en) System and method for power transmission and transformation project three-dimensional-aided preliminary design
CN102750618A (en) {0>Auxiliary management system for subway integrated pipeline construction and implementation method thereof
CN109245923B (en) Communication optical cable routing resource management method and system
CN110929363B (en) Communication line investigation design method and system
CN107153744B (en) Underground three-dimensional pipeline decision making system
CN106372309A (en) Electric power tunnel digital laying method and system based on GIS (geographic information system) and BIM (building information modeling)
CN113536421A (en) BIM-based port planning collaborative analysis method and system
Mao Development of coal geological information technologies in China
Bansal Use of geographic information systems in spatial planning: A case study of an institute campus
CN113536505A (en) Automatic collaborative design system for 10kV and below power distribution network engineering line
CN102411646B (en) Distribution data processing method and device
Lv et al. Three-dimensional design method of overhead transmission line based on BIM technology
CN201820263U (en) Field pipeline data acquisition and update system based on topological relation
CN113420359A (en) Method for automatically transmitting parameters to well placement based on REVIT (remote visual inspection) electric power engineering general diagram
KR100848820B1 (en) A presentation system and method for construction criterion with 3d mass
CN115577541A (en) Digital twin identification method and management system for hidden cable pipe network facilities

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190603

Address after: No. 15, Qinghe Xiaoying East Road, Haidian District, Beijing

Applicant after: China Electric Science Research Institute Co., Ltd.

Applicant after: State Grid Corporation of China

Applicant after: State Grid Shanghai Municipal Electric Power Company

Address before: No. 15, Qinghe Xiaoying East Road, Haidian District, Beijing

Applicant before: China Electric Science Research Institute Co., Ltd.

SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination