CN109149442A - A kind of hanging wire clamp connection lifting arm - Google Patents

A kind of hanging wire clamp connection lifting arm Download PDF

Info

Publication number
CN109149442A
CN109149442A CN201811138313.8A CN201811138313A CN109149442A CN 109149442 A CN109149442 A CN 109149442A CN 201811138313 A CN201811138313 A CN 201811138313A CN 109149442 A CN109149442 A CN 109149442A
Authority
CN
China
Prior art keywords
lifting arm
wire clamp
hanging wire
clamp connection
support rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811138313.8A
Other languages
Chinese (zh)
Other versions
CN109149442B (en
Inventor
宋云海
邢建平
徐文建
王立忠
高旭平
乔荣
马玉晖
杨雨欣
陈冠兴
杨国林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Weifang Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Weifang Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Weifang Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201811138313.8A priority Critical patent/CN109149442B/en
Publication of CN109149442A publication Critical patent/CN109149442A/en
Application granted granted Critical
Publication of CN109149442B publication Critical patent/CN109149442B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/04Protective tubing or conduits, e.g. cable ladders or cable troughs
    • H02G3/0456Ladders or other supports

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Clamps And Clips (AREA)
  • Electric Cable Installation (AREA)

Abstract

A kind of hanging wire clamp connection lifting arm, is related to lifting device technical field, including support rod;There are two the moving jaws for making opposite and reverse motions for the one end installation of support rod, and form clip attachment area domain by the region between two moving jaws, and the other end of support rod is equipped with flexible pipe fitting.Single terrestrial operation is realized, the technical effect of labour is saved.

Description

A kind of hanging wire clamp connection lifting arm
Technical field
The present invention relates to lifting device technical fields, and in particular to a kind of hanging wire clamp connection lifting arm.
Background technique
Frequently encounter the phenomenon various electric wires hung on wall in more old cell or workshop, because electric wire is long The phenomenon that phase is exposed in the environment of exposing to the weather, is just easy to happen aging over time, there are security risks, often this when It waits, the maintenance personnel of Utilities Electric Co. is just needed to repair and replace route, in the prior art, generally pass through clip for route Be suspended on the support rod to support route, but due to safety for the sake of, it is general to hang over route apart from 3 meters of ground or more On the wall of safe altitude, clip is mounted on support rod due to facilitating in the prior art without a kind of device, this just makes It needs to lodge ladder during hanging route and carries out assisted suspension, but which, appropriation of labour power is bigger, needs to take Band ladder, also tends to need people's staircase, and another person is responsible for climbing installment work and maintenance personnel in the process of climbing In be easy slide, influence life security.
Therefore, a kind of hanging wire clamp connection lifting arm is developed regarding to the issue above, and not only there is urgent researching value, Also with good economic efficiency and commercial application potentiality, where this power exactly of the invention being accomplished and basis.
Summary of the invention
For the defects in the prior art, the present invention provides a kind of hanging wire clamp connection lifting arm, to realize one The technical effect of labour is saved in terrestrial operation.
To achieve the above object, the invention provides the following technical scheme:
A kind of hanging wire clamp connection lifting arm, including support rod;There are two make phase for the one end installation of the support rod To and reverse motions moving jaws, and clip attachment area domain is formed by the region between two moving jaws, the support rod The other end is equipped with flexible pipe fitting.
As an improvement scheme, the one end of the support rod is equipped with fixing seat, and two moving jaws are opposite It is articulated in the fixing seat side by side, and the upper end of two moving jaws is equipped with a bending section in opposite directions respectively, and described curved The end of tune, which is equipped with, clamps pawl, and clamps by the way that both ends work of two clamping pawls to clip is opposite, two shiftings Linkage part is also installed jointly in pawl.
As an improvement scheme, the linkage part includes two linkage boards hinged in X-shaped, two linkages Plate is articulated in fixing seat, and the lower end of two moving jaws respectively corresponds the upper end for being slidably mounted on two linkage boards In portion, the lower end of two linkage boards is also equipped with power part.
As an improvement scheme, the power part includes power plate, and the power plate moves back and forth up and down, two The lower end of the linkage board offers sliding groove along the extending direction of the linkage board respectively, is slidably installed in the sliding groove There is the first slide protrusion portion, opens up that there are two the first slidings on the power plate side by side along the extending direction of the power plate respectively Hole, two linkage boards are utilized respectively first slide protrusion portion correspondence and are slidably mounted on two first sliding eyes It is interior.
As an improvement scheme, the upper end of two linkage boards offers the second sliding eye, two institutes respectively The lower end for stating moving jaws is connected with the second slide protrusion portion respectively, and second slide protrusion portion is slidably mounted on described second In sliding eye.
As an improvement scheme, the fixing seat is equipped with support base, and the support base is located at clip attachment area In domain.
As an improvement scheme, the flexible pipe fitting includes stretched sheathed tube, and the stretched sheathed tube is set in the branch On strut, and enclose on the end wall of the one end being set with the support rod equipped with several clamping plates, the outer wall of several clamping plates The upper outer wall with the stretched sheathed tube is equipped with one section of screw thread jointly, and several clamping plates are threadedly coupled jointly using the screw thread There is gripping sleeve, the inner wall of the clamping plate is equipped with clamp clip, and the thickness of the clamp clip is gradually incremented by towards its other end.
As an improvement scheme, be connected with ring body on the power plate, pulling rope be connected in the ring body, it is described Winding roller is connected on stretched sheathed tube, the other end for pulling rope is wound on the winding roller.
As an improvement scheme, be also equipped with pulling ring on pulling rope, be connected on the pulling peripheral wall Pulling thread base, the pulling rope pass through the pulling thread base, stop knob are also threaded on the pulling thread base, the stop knob End offsets with the pulling rope in the pulling thread base.
As an improvement scheme, be also equipped with stretching reset spring between the upper end of two linkage boards, two Hanging hole is offered on a linkage board respectively, the both ends for stretching reset spring correspond to hooking in the hanging hole.
Compared with prior art, the beneficial effects of the present invention are:
Hanging wire clamp connection lifting arm, including support rod;The one end installation of support rod is opposite and opposite there are two making The moving jaws of movement, and clip attachment area domain, the other end installation of support rod are formed by the region between two moving jaws There is flexible pipe fitting, be based on the above structure, clip is fixed in installation region in advance, the route hung will be needed to be previously positioned at In clip, then by single hand-held supports bar by after clip and route lifting, being moved toward one another by two moving jaws can be with After doing opposite clamp to the both ends of clip, clip is hung in the support line bar in building, then done by two moving jaws Reverse motions realize that moving jaws are separated with clip, complete the operation for installing clip, flexible pipe fitting is wherein equipped on support rod, The flexible of support rod can be realized by the pipe fitting that stretches, be convenient for carrying lifting arm, design rationally, saves labour, realizes One man operation realizes single terrestrial operation, saves the technical effect of labour.
To sum up, the present invention realizes single terrestrial operation, saves the technical effect of labour, operation control letter Just, it is easy to manufacture and install on a large scale, has a wide range of application.
Detailed description of the invention
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art Embodiment or attached drawing needed to be used in the description of the prior art are briefly described.In all the appended drawings, similar element Or part is generally identified by similar appended drawing reference.In attached drawing, each element or part might not be drawn according to actual ratio.
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the structural schematic diagram that the present invention stretches reset spring;
Fig. 3 is the structural schematic diagram that the present invention clamps pawl;
Fig. 4 is the structural schematic diagram that the present invention pulls ring;
In figure: 1- stretched sheathed tube;2- support rod;3- pulls rope;4- non-slip rubber set;5- pulls ring;6- gripping sleeve;7- folder Tight piece;8- clamping plate;9- conductor loop;10- fixing seat;11- moving jaws;12- clamps pawl;13- linkage board;14- power plate;15- Second slide protrusion portion;The second sliding eye of 16-;17- sliding groove;The first slide protrusion of 18- portion;The second sliding eye of 19-;20- is drawn Stretch reset spring;21- ring body;22- convex block;23- support base;24- card holding trough;25- winding roller;26- pulling thread base;27- stop rotation Button.
Specific embodiment
It is described in detail below in conjunction with embodiment of the attached drawing to technical solution of the present invention.Following embodiment is only used for Clearly illustrate technical solution of the present invention, therefore be only used as example, and cannot be used as a limitation and limit protection model of the invention It encloses.
As shown in Figures 1 to 4, hanging wire clamp connection lifting arm, including support rod 2;The one end of support rod 2 is equipped with Two are made opposite and reverse motions moving jaws 11, and form clip attachment area domain by the region between two moving jaws 11, The other end of support rod 2 is equipped with flexible pipe fitting.
Clip is fixed in installation region in advance, the route hung will be needed to be previously positioned in clip, then passed through For single hand-held supports bar 2 by after clip and route lifting, being moved toward one another by two moving jaws 11 can be to the both ends of clip After opposite clamping is done in portion, clip is hung in the support line bar in building, then does reverse motions by two moving jaws 11, it is real Existing moving jaws 11 are separated with clip, are completed the operation of installation clip, are wherein equipped with flexible pipe fitting on support rod 2, can pass through Flexible pipe fitting realizes the flexible of support rod 2, is convenient for carrying lifting arm, and design rationally, saves labour, realizes single behaviour Make, realizes single terrestrial operation, save the technical effect of labour.
The one end of support rod 2 is equipped with fixing seat 10, and two moving jaws 11 are articulated in fixing seat 10 side by side in opposite directions, and The upper end of two moving jaws 11 is equipped with a bending section in opposite directions respectively, and the end of bending section is equipped with and clamps pawl 12, and passes through two A pawl 12 that clamps clamps the both ends work of clip in opposite directions, linkage part is also equipped with jointly on two moving jaws 11, wherein solid It is additionally provided with two convex blocks 22 in reservation 10, using the convenient hinged installation moving jaws 11 of the convex block 22, it is convenient to be provided with bending section The power for realizing that moving jaws 11 export is turned to, and wherein bending section, which is equipped with, clamps pawl 12, wherein clamping pawl 12 is C-shaped setting Plate body, the end of clip be installed in C-shaped setting plate body cladding region in, using clamp pawl 12 can play to card The fixed effect in position is bound round, second is that realizing during moving jaws 11 are mobile, guarantees the stability between clip, wherein It may be implemented to drive two moving jaws 11 mobile simultaneously equipped with linkage part, ensure that stability.
Linkage part includes two linkage boards 13 hinged in X-shaped, and two linkage boards 13 are articulated in fixing seat 10, and two The lower end of moving jaws 11, which respectively corresponds, to be slidably mounted on the upper end of two linkage boards 13, the lower end of two linkage boards 13 It is also equipped with power part, using realizing in two hinged linkage boards 13 of X-shaped while driving two swings of moving jaws 11 It acts on, power part is installed between two of them linkage board 13, realize and realized to two linkage boards 13 in fact using power part Existing power drive, is easy to use.
Flexible pipe fitting includes stretched sheathed tube 1, and stretched sheathed tube 1 is set on support rod 2, and the one end being set with support rod 2 End wall on enclose equipped with several clamping plates 8, be equipped with one section of spiral shell jointly with the outer wall of stretched sheathed tube 1 on the outer wall of several clamping plates 8 Line, several clamping plates 8 are threaded with gripping sleeve 6 using screw thread jointly, and the inner wall of clamping plate 8 is equipped with clamp clip 7, clamp clip 7 thickness is gradually incremented by towards its other end, according to actual use adjust collapsing length, using gripping sleeve 6 realize stretched sheathed tube 1 with Position between support rod 2 is fixed, and wherein the bottom end of stretched sheathed tube 1 is further sleeved with non-slip rubber set 4, is guaranteed in operating process Stability has wherein also been respectively and fixedly connected with conductor loop 9 on support rod 2 and stretched sheathed tube 1, wherein rope 3 is pulled to run through conductor loop 9, benefit Play the role of fair line conducting wire with conductor loop 9, facilitates operation.
Ring 5 is pulled as shown in figure 4, pulling and being also equipped on rope 3, pulls and is connected with pulling thread base 26 on 5 peripheral wall of ring, pull rope 3 run through pulling thread base 26, are also threaded with stop knob 27 on pulling thread base 26, in the end of stop knob 27 and pulling thread base 26 It pulls rope 3 to offset, installation on rope 3 is pulled to pull ring 5, can use and pull ring 5 convenient to pulling rope 3 to drop, wherein working as support When the collapsing length of bar 2 is adjusted, by unclamping stop knob 27, it is corresponding adjust the position for pulling ring 5 after, by stop knob 27 Stop is screwed, is easy to use.
As shown in Fig. 2, power part includes power plate 14, power plate 14 is moved back and forth up and down, under two linkage boards 13 End offers sliding groove 17 along the extending direction of linkage board 13 respectively, and the first slide protrusion portion is slidably fitted in sliding groove 17 18, it is opened up side by side along the extending direction of power plate 14 there are two the first sliding eye on power plate 14 respectively, two linkage boards 13 divide It is not slidably mounted in two the first sliding eyes using the first slide protrusion portion 18 correspondence, the upper end difference of two linkage boards 13 The second sliding eye is offered, the lower end of two moving jaws 11 is connected with the second slide protrusion portion 15, the second slide protrusion respectively Portion 15 is slidably mounted in the second sliding eye, and ring body 21 is connected on power plate 14, and pulling rope 3 is connected in ring body 21, is extended It is connected with winding roller 25 on casing 1, pulls the other end of rope 3 to be wound on winding roller 25, may be implemented to work as using winding roller 25 Pulling rope 3 can be wound and be unreeled by winding roller 25 when the length of support rod 2 changes, winding additional length is played and draws The effect of running rope 3 pulls running rope 3 under and realizes that power plate 14 moves down, utilizes the first slide protrusion portion 18 and the first sliding eye Realization is mobile in two hinged 13 bifurcateds of linkage board of X-shaped, recycles the second slide protrusion portion 15 and the realization pair of the second sliding eye The driving of two moving jaws 11 realizes that two moving jaws 11 move toward one another, facilitates operation.
Fixing seat 10 is equipped with support base 23, and support base 23 is located in clip attachment area domain, equipped with support base 23 first is that The support to clip bottom is realized, the route of suspension is supported second is that realizing.
As shown in figure 3, two of them moving jaws 11 are hinged on convex block 22 by the different shaft realization of length respectively, benefit Mutual dislocation between two moving jaws 11 is realized with the different shaft of length, is guaranteed when the both ends of clip are swung in opposite directions not by shadow It rings.
It wherein is also provided with card holding trough 24 on support base 23, wherein card holding trough 24 is solid in order to carry out position to clip bottom surface It is fixed, prevent clip from shifting.
It is also equipped between the upper end of two linkage boards 13 and stretches reset spring 20, opened up respectively on two linkage boards 13 There is hanging hole, the both ends for stretching reset spring 20 correspond to hooking in hanging hole, are equipped with and stretch reset spring 20, play to two The effect that linkage board 13 resets, realizes two moving jaws 11 and makees opposite direction swing, rapid operation.
Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;To the greatest extent Pipe present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: its according to So be possible to modify the technical solutions described in the foregoing embodiments, or to some or all of the technical features into Row equivalent replacement;And these are modified or replaceed, various embodiments of the present invention technology that it does not separate the essence of the corresponding technical solution The range of scheme should all cover within the scope of the claims and the description of the invention.

Claims (10)

1. a kind of hanging wire clamp connection lifting arm, it is characterised in that: including support rod;The one end of the support rod is equipped with Two are made opposite and reverse motions moving jaws, and form clip attachment area domain by the region between two moving jaws, described The other end of support rod is equipped with flexible pipe fitting.
2. a kind of hanging wire clamp connection lifting arm according to claim 1, it is characterised in that: one end of the support rod Portion is equipped with fixing seat, and two moving jaws are articulated in the fixing seat side by side in opposite directions, and two moving jaws is upper End is equipped with a bending section in opposite directions respectively, and the end of the bending section is equipped with and clamps pawl, and passes through two clamping pawls pair Opposite clamping is made at the both ends of clip, is also equipped with linkage part jointly on two moving jaws.
3. a kind of hanging wire clamp connection lifting arm according to claim 2, it is characterised in that: the linkage part includes In two hinged linkage boards of X-shaped, two linkage boards are articulated in fixing seat, the lower end difference of two moving jaws Correspondence is slidably mounted on the upper end of two linkage boards, and the lower end of two linkage boards is also equipped with power part Part.
4. a kind of hanging wire clamp connection lifting arm according to claim 3, it is characterised in that: the power part includes Power plate, the power plate move back and forth up and down, and the lower end of two linkage boards is respectively along the extension side of the linkage board To sliding groove is offered, it is slidably fitted with the first slide protrusion portion in the sliding groove, is moved respectively along described on the power plate The extending direction of power plate is opened up side by side there are two the first sliding eye, and two linkage boards are utilized respectively first slide protrusion Portion's correspondence is slidably mounted in two first sliding eyes.
5. a kind of hanging wire clamp connection lifting arm according to claim 3, it is characterised in that: two linkage boards Upper end offers the second sliding eye respectively, and the lower end of two moving jaws is connected with the second slide protrusion portion, institute respectively The second slide protrusion portion is stated to be slidably mounted in second sliding eye.
6. a kind of hanging wire clamp connection lifting arm according to claim 2, it is characterised in that: the fixing seat is equipped with Support base, and the support base is located in clip attachment area domain.
7. a kind of hanging wire clamp connection lifting arm according to claim 1, it is characterised in that: the flexible pipe fitting includes Stretched sheathed tube, the stretched sheathed tube are set on the support rod, and are set with enclosing on the end wall of one end of support rod suit There are several clamping plates, is equipped with one section of screw thread jointly with the outer wall of the stretched sheathed tube on the outer wall of several clamping plates, it is several The clamping plate is threaded with gripping sleeve using the screw thread jointly, and the inner wall of the clamping plate is equipped with clamp clip, described The thickness of clamp clip is gradually incremented by towards its other end.
8. a kind of hanging wire clamp connection lifting arm according to claim 4, it is characterised in that: affixed on the power plate There is ring body, pulling rope is connected in the ring body, winding roller is connected on the stretched sheathed tube, the other end for pulling rope twines It is around on the winding roller.
9. a kind of hanging wire clamp connection lifting arm according to claim 8, it is characterised in that: also pacify on the pulling rope Equipped with ring is pulled, pulling thread base is connected on the pulling peripheral wall, the pulling rope passes through the pulling thread base, goes back on the pulling thread base It is threaded with stop knob, end and the pulling rope in the pulling thread base of the stop knob offset.
10. a kind of hanging wire clamp connection lifting arm according to claim 3, it is characterised in that: two linkage boards Upper end between be also equipped with stretching reset spring, offer hanging hole on two linkage boards respectively, the stretching resets The both ends of spring correspond to hooking in the hanging hole.
CN201811138313.8A 2018-09-28 2018-09-28 Clamp connection lifting rod for hanging wire Expired - Fee Related CN109149442B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811138313.8A CN109149442B (en) 2018-09-28 2018-09-28 Clamp connection lifting rod for hanging wire

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811138313.8A CN109149442B (en) 2018-09-28 2018-09-28 Clamp connection lifting rod for hanging wire

Publications (2)

Publication Number Publication Date
CN109149442A true CN109149442A (en) 2019-01-04
CN109149442B CN109149442B (en) 2020-10-16

Family

ID=64813144

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811138313.8A Expired - Fee Related CN109149442B (en) 2018-09-28 2018-09-28 Clamp connection lifting rod for hanging wire

Country Status (1)

Country Link
CN (1) CN109149442B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110556757A (en) * 2019-09-06 2019-12-10 国网山东省电力公司诸城市供电公司 Cable protection device in power construction
CN110581475A (en) * 2019-09-23 2019-12-17 赵琳萱 Cable suspension lock catch and hanger used with same
CN111541189A (en) * 2020-05-07 2020-08-14 广东电网有限责任公司 Device is demolishd in transmission line foreign matter insulation
CN111864630A (en) * 2020-08-11 2020-10-30 国网青海省电力公司海西供电公司 Telescopic insulating operating rod
CN112202131A (en) * 2020-09-28 2021-01-08 苏州市职业大学 Cable pendant
CN112271644A (en) * 2020-11-04 2021-01-26 国网山东省电力公司潍坊供电公司 Laying auxiliary device for low-voltage cable
CN112688232A (en) * 2020-11-24 2021-04-20 国网山东省电力公司郓城县供电公司 Cable lifting device for electric power overhaul
CN113711800A (en) * 2021-08-26 2021-11-30 坚果派农业有限公司 Carya illinoensis branch pulling set

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104396586A (en) * 2014-12-15 2015-03-11 广西大学 Safe clamp-type tree branch trimmer
CN107552424A (en) * 2017-10-13 2018-01-09 成都丝迈尔科技有限公司 A kind of power equipment cleaning plant
CN108271527A (en) * 2018-03-07 2018-07-13 宜春学院 A kind of envelop-type fruit picker
CN207757404U (en) * 2017-11-30 2018-08-24 潍坊创高信息科技有限公司 A kind of adjustable surface processing device based on mold manufacturing

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104396586A (en) * 2014-12-15 2015-03-11 广西大学 Safe clamp-type tree branch trimmer
CN107552424A (en) * 2017-10-13 2018-01-09 成都丝迈尔科技有限公司 A kind of power equipment cleaning plant
CN207757404U (en) * 2017-11-30 2018-08-24 潍坊创高信息科技有限公司 A kind of adjustable surface processing device based on mold manufacturing
CN108271527A (en) * 2018-03-07 2018-07-13 宜春学院 A kind of envelop-type fruit picker

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110556757A (en) * 2019-09-06 2019-12-10 国网山东省电力公司诸城市供电公司 Cable protection device in power construction
CN110581475A (en) * 2019-09-23 2019-12-17 赵琳萱 Cable suspension lock catch and hanger used with same
CN111541189A (en) * 2020-05-07 2020-08-14 广东电网有限责任公司 Device is demolishd in transmission line foreign matter insulation
CN111864630A (en) * 2020-08-11 2020-10-30 国网青海省电力公司海西供电公司 Telescopic insulating operating rod
CN112202131A (en) * 2020-09-28 2021-01-08 苏州市职业大学 Cable pendant
CN112202131B (en) * 2020-09-28 2021-12-17 苏州市职业大学 Cable pendant
CN112271644A (en) * 2020-11-04 2021-01-26 国网山东省电力公司潍坊供电公司 Laying auxiliary device for low-voltage cable
CN112688232A (en) * 2020-11-24 2021-04-20 国网山东省电力公司郓城县供电公司 Cable lifting device for electric power overhaul
CN113711800A (en) * 2021-08-26 2021-11-30 坚果派农业有限公司 Carya illinoensis branch pulling set

Also Published As

Publication number Publication date
CN109149442B (en) 2020-10-16

Similar Documents

Publication Publication Date Title
CN109149442A (en) A kind of hanging wire clamp connection lifting arm
KR101592964B1 (en) Method for hot line work of power distribution equipment
JP5268778B2 (en) Arm changer
CN207967780U (en) A kind of cable rigid support of auxiliary bypass operation
CN209807972U (en) Winding and unwinding devices of rainbow curtain cloth
CN111668757A (en) Convenient support is used in cable erection convenient to adjustment cable interval
CN216900638U (en) Current test fixture platform with anticreep protection architecture
US2269350A (en) Awning
CN204677095U (en) A kind of Cordless curtain
CN205442449U (en) Portable tower crane device
CN205846663U (en) A kind of height-adjustable overhead line structures
JP5660499B2 (en) Net or sheet suspension moving system using winch
CN205322574U (en) Collapsible recovered muscle ware of stretching of formula femur head necrosis of cutting
CN205530876U (en) A subassembly for stainless steel meshwork curtain is fixed
CN207061529U (en) A kind of electric pole framework of steel reinforcement stretching device
CN108033354B (en) Novel breakwater facing block removes device
CN211526534U (en) Hang adjustable electric heater
CN205733352U (en) A kind of welding pole bracket
CN213585037U (en) Building construction wiring arrangement with locate function
CN214365354U (en) Telescopic adjusting type iron net device
CN214062425U (en) Ancient building roofing suspension wire device
CN111972188B (en) Method for installing agricultural greenhouse sunshade net and installation fixer thereof
CN210380058U (en) Tower crane cable fixing device
CN220913871U (en) Conveniently fixed cloth mark for advertisement design
CN220283394U (en) Portable hoisting equipment for installation of power peripheral equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201016